Académique Documents
Professionnel Documents
Culture Documents
(DEFORMED BARS)
4.50
4.50
4.50
4.50
EXISTING
PAVEMENT
DETAIL "B"
CONCRETE PAVEMENT
3.05 m.
WIDENING
1.50 m.
0.50
0.50
0.50
1:24
SCALE
NTS
NATURAL GROUND
NATURAL GROUND
CONCRETE PAVEMENT
EXISTING
PAVEMENT
0.50
0.60 min.
0.60 min.
NATURAL GROUND
0.60 min.
1.00 m.
min.
B=0.57H
1.00 m.
min.
B=0.57H
0.50
0.50
B=0.57H
1.00
1.00
0.50
1.50 m.
3.05 m.
WIDENING
EXPANSION JOINT
1.60
0.50
0.30
0.50
0.50
SPACED @ 2.0m HOR.& 1.0m VERT.,
STAGGERED
"A"
W/ FILTER CLOTH
SPACED @ 2.0m HOR.
& 1.0m VERT., STAGGERED
0.50
0.30
"A"
0.50
SEE DETAILS OF
CONCRETE LINED CANAL
0.50
1.60
0.50
0.50
0.50
TOP OF SHOULDER
NTS
4.50
4.50
4.50
1000
4.50
PVC WEEPHOLES
(DEFORMED BARS)
500
(DEFORMED BARS)
2.0m
1.0m
1:24
1.0m
500
1000
300
500
0.57H
NTS
L = 600mm
EXISTING STONE MASONRY
300mm
3.05
PROPOSED
WIDENING
1.50
SHOULDER
3.05
PROPOSED
WIDENING
EXISTING PCCP
1.50
SHOULDER
T/2
50
150
50 100 50
150
50
METAL DOWEL CAP GAUGE No. 18
TO BE PLACED ON EACH DOWEL BAR
ON ALTERNATE END
(FOR EXPANSION JOINTS ONLY)
T/2
T = SLAB DEPTH
300mm
s%
s%
1.529%
SPACING
(mm)
280
300
290
295
300
274
310
255
320
238
330
223
340
209
PROJECT/LOCATION :
SCALE
SHEET CONTENTS :
DESIGNED:
REVIEWED:
NTS
SUBMITTED:
RECOMMENDING APPROVAL:
RECOMMENDING APPROVAL:
APPROVED:
SET NO.
ENGINEER II
ENGINEER II
ENGINEER II
ADRIANO M. DOROY
DRAWN:
CECIL M. SANTOS
ZOISIMO L. BALISI
ENGINEER III
DATE :
DATE :
DANILO L. BALISI
CHIEF, HIGHWAY DIVISION, BOD
DATE :
DIRECTOR III
OFFICER-IN-CHARGE
DATE :
(NOTE: SEE COVER SHEET FOR SIGNATURE)
WALTER R. OCAMPO
DIRECTOR IV
OFFICER-IN-CHARGE FOR TECHNICAL SERVICES
DATE :
PDD
ROGELIO L. SINGSON
SECRETARY
DATE :
ISABELA
HDS
SHT NO.
20m
width = 0.10 m.
WIDENING
width = 0.10 m.
WIDENING
3.05
spaced @ 6.0 m.
6.0 m
3.05
3.05
3.500
EXISTING
ROADWAY
EXISTING
ROADWAY
width = 0.15 m.
Length = 3.0m.
A'
3.000
A'
3.000
width = 0.15 m.
6.70
6.70
EXISTING
ROADWAY
spaced @ 6.0 m.
6.0 m
75
5
width = 0.15 m.
5
WIDENING
WIDENING
3.05
Length = 3.0m.
100
300
3.05
width = 0.10 m.
width = 0.10 m.
Edge of Pavement
2.00m
width = 0.10 m.
2.00m
1.50m
Edge of Pavement
30.0m
Rumble strips
(white)
0.10
0.10
0.10 m.
width = 0.15 m.
0.30m
width = 0.15 m.
width = 0.15 m.
(white)
0.15
0.15
0.150
Rumble strips
width = 0.15 m.
width = 0.10 m.
Edge of Pavement
0.10
(white)
30.0m
1.50m
2.00m
2.00m
Edge of Pavement
PROJECT/LOCATION :
SHEET CONTENTS :
DESIGNED:
REVIEWED:
SUBMITTED:
RECOMMENDING APPROVAL:
RECOMMENDING APPROVAL:
APPROVED:
SET NO.
ENGINEER II
ENGINEER II
ENGINEER II
ADRIANO M. DOROY
DRAWN:
K. R. LASQUERO D. B. CONAG
E-ASSISTANT
C.C. MALLILLIN
E-ASSISTANT
CHECKED:
EPIFANIO M. DE GUZMAN
ENGINEER III
E-ASSISTANT
CECIL M. SANTOS
ZOISIMO L. BALISI
ENGINEER III
DATE :
DATE :
DANILO L. BALISI
CHIEF, HIGHWAY DIVISION, BOD
DATE :
DIRECTOR III
OFFICER-IN-CHARGE
DATE :
(NOTE: SEE COVER SHEET FOR SIGNATURE)
WALTER R. OCAMPO
DIRECTOR IV
OFFICER-IN-CHARGE FOR TECHNICAL SERVICES
DATE :
PDD
ROGELIO L. SINGSON
SECRETARY
DATE :
ISABELA
HDS
SHT NO.
WHEEL GUARD
PAVED SHOULDER
SEE DETAILS OF
WHEEL GUARD WINDOW
600
EDGE OF SHOULDER
150
TOP OF SHOULDER
600
150
TOP OF SHOULDER
150
SUBGRADE LEVEL
150
200
100mm
200mm
50
100
800
WHEEL GUARD
3
650
100
1000
1000
800
600
600mm
INVERT ELEVATION
50
150
100
100
100
100
900
100
100
100
100
150
SCALE
NTS
NTS
TOP OF WHEELGUARD
TOP OF SHOULDER
200mm
80
3.00m
200mm
80
200mm
5mm
GROUT
150
BAR TYPE
730
120
490
600
30
50
TOTAL LENGTH
(m.)
UNIT
WEIGHT
(kg/m)
4.00
2300
9.200
0.617
5.676
2.00
1000
2.000
0.617
1.234
6.00
1000
6.000
0.617
3.702
10.612
TOTAL
500
TOTAL
WEIGHT
(kg)
150
LENGTH
(mm.)
2
3
25
50
NO. OF PIECES
120
400
BAR SIZE
100
FOUNDATION FILL, 0.10 m THICK
150
600
150
GROUT
5mm
900
ITEM
UNIT
QUANTITY
kg
10.612
NTS
NTS
0.345
REINFORCING STEEL
GRANULAR GRAVEL BASE
0.055
100
152
152
152
152
650
1000
1000
370
420
630
650
100
152
800
152
800
1000
BAR TYPE
800
600
150
150
600
150
50
100
600
600mm
INVERT
ELEVATION
BAR TYPE
BAR SIZE
LENGTH
(mm.)
NO. OF PIECES
TOTAL LENGTH
(m.)
UNIT
WEIGHT
(kg/m)
TOTAL
WEIGHT
(kg)
4.00
2300
9.200
0.617
5.676
2.00
1000
2.000
0.617
1.234
5.00
1000
5.000
0.617
BAR SIZE
NO. OF PIECES
LENGTH
(mm.)
TOTAL LENGTH
(m.)
UNIT
WEIGHT
(kg/m)
TOTAL
WEIGHT
(kg)
10
934
9.34
1.578
14.739
724
2.896
1.578
4.570
674
4.044
1.578
6.381
10
1000
10.00
0.888
8.880
2600
10.40
0.888
9.235
5
TOTAL
43.805
3.085
ITEM
UNIT
QUANTITY
kg
43.805
9.995
TOTAL
150
REINFORCING STEEL
ITEM
UNIT
QUANTITY
kg
0.345
9.995
NTS
PROJECT/LOCATION :
SHEET CONTENTS :
DESIGNED:
REVIEWED:
SUBMITTED:
RECOMMENDING APPROVAL:
RECOMMENDING APPROVAL:
APPROVED:
SET NO.
0.10
FOUNDATION FILL
50
900
0.454
ENGINEER II
ENGINEER II
ENGINEER II
ADRIANO M. DOROY
DRAWN:
K. R. LASQUERO D. B. CONAG
E-ASSISTANT
C.C. MALLILLIN
E-ASSISTANT
CHECKED:
EPIFANIO M. DE GUZMAN
ENGINEER III
E-ASSISTANT
CECIL M. SANTOS
ZOISIMO L. BALISI
ENGINEER III
DATE :
DATE :
DANILO L. BALISI
CHIEF, HIGHWAY DIVISION, BOD
DATE :
DIRECTOR III
OFFICER-IN-CHARGE
DATE :
(NOTE: SEE COVER SHEET FOR SIGNATURE)
WALTER R. OCAMPO
DIRECTOR IV
OFFICER-IN-CHARGE FOR TECHNICAL SERVICES
DATE :
PDD
ROGELIO L. SINGSON
SECRETARY
DATE :
ISABELA
HDS
SHT NO.
200
100
51
100
51
d
131
1700
50
1470
3810
1470
3810
1700
362
131
1000
230
50
10
230
10
230
700
200
GENERAL NOTES:
MATERIALS AND WORKMANSHIP SHALL COMPLY WITH STANDARD SPECIFICATIONS FOR HIGHWAYS AND
BRIDGES REVISED 2013.
159
318
200
509
100
59
50
76
262
254
200
200
100
262
200
WHEN CONCRETE POST ARE USED, IT SHALL CONFORM WITH THE REQUIREMENTS OF CLASS "C"
CONCRETE, ITEM NO. 405 (3) AND REINFORCING STEEL SHALL CONFORM WITH REQUIREMENTS OF
REINFORCING STEEL, ITEM NO. 404.
59
50
NTS
500mm
CONCRETE CURB
CONCRETE GUTTER
500mm
210mm
360mm
W4 - 1
150mm
360mm
100mm
300mm
100mm
150mm
150mm
100mm
100mm
100mm
170mm
CONCRETE CURB
W4 - 2
CONCRETE GUTTER
s=8%
WHITE BACKGROUND
RED CHEVRON SYMBOLS
210mm
600
600
360mm
150mm
670mm
670mm
NGL
170mm
25mm
s%
8%
210mm
NOTE:
1. MATERIAL AND CONSTRUCTION REQUIREMENTS SHALL CONFORM TO DPWH STANDARD
SPECIFICATION FOR HIGHWAYS AND BRIDGES (2013).
2. USE OF MONOFILAMENT POLYPROPYLENE SYNTHETIC FIBERS (D.O. 95, SERIES 2005) AS ADDITIVE TO
CONCRETE MIX.
3. CONCRETE CURB AND GUTTER SHALL BE CONSIDERED IN THE DESIGN OF PAVED ROADS IF THE
FUNCTION IS TO FACILITATE THE CHANNELING OF SURFACE WATER RUN-OFF THUS PREVENTING THE
EROSION OF SHOULDER AND SLOPE.
600
PIPE POST
PAINTED W/
REFLECTORIZED
SUNSHINE YELLOW
W/ RED LEAD
BASE PAINT
W4 - 1
PAINTED W/ REFLECTORIZED
SUNSHINE YELLOW W/ RED
LEAD BASE PAINT
360mm
100mm
150mm
100mm
250mm
NOTE :
CONCRETE CLASS "A"
PROJECT/LOCATION :
SHEET CONTENTS :
REVIEWED:
SUBMITTED:
RECOMMENDING APPROVAL:
RECOMMENDING APPROVAL:
APPROVED:
SET NO.
DESIGNED:
NTS
ENGINEER II
DETAILS OF GUARDRAIL
DETAIL OF ROAD SIGN
DETAIL OF CURB & GUTTER
ENGINEER II
ENGINEER II
ADRIANO M. DOROY
DRAWN:
K. R. LASQUERO D. B. CONAG
E-ASSISTANT
C.C. MALLILLIN
E-ASSISTANT
CHECKED:
EPIFANIO M. DE GUZMAN
ENGINEER III
E-ASSISTANT
CECIL M. SANTOS
ZOISIMO L. BALISI
ENGINEER III
DATE :
DATE :
DANILO L. BALISI
CHIEF, HIGHWAY DIVISION, BOD
DATE :
DIRECTOR III
OFFICER-IN-CHARGE
DATE :
(NOTE: SEE COVER SHEET FOR SIGNATURE)
WALTER R. OCAMPO
DIRECTOR IV
OFFICER-IN-CHARGE FOR TECHNICAL SERVICES
DATE :
PDD
ROGELIO L. SINGSON
SECRETARY
DATE :
ISABELA
HDS
SHT NO.
THICKNESS
CBR
THICKNESS
CBR
CBR
CBR
CBR
PROJECT/LOCATION :
SHEET CONTENTS :
DESIGNED:
REVIEWED:
SUBMITTED:
RECOMMENDING APPROVAL:
RECOMMENDING APPROVAL:
APPROVED:
SET NO.
ENGINEER II
ENGINEER II
ENGINEER II
ADRIANO M. DOROY
DRAWN:
BORELOG
PAVEMENT DESIGN PARAMETERS
K. R. LASQUERO D. B. CONAG
E-ASSISTANT
C.C. MALLILLIN
E-ASSISTANT
CHECKED:
EPIFANIO M. DE GUZMAN
ENGINEER III
E-ASSISTANT
CECIL M. SANTOS
ZOISIMO L. BALISI
ENGINEER III
DATE :
DATE :
DANILO L. BALISI
CHIEF, HIGHWAY DIVISION, BOD
DATE :
DIRECTOR III
OFFICER-IN-CHARGE
DATE :
(NOTE: SEE COVER SHEET FOR SIGNATURE)
WALTER R. OCAMPO
DIRECTOR IV
OFFICER-IN-CHARGE FOR TECHNICAL SERVICES
DATE :
PDD
ROGELIO L. SINGSON
SECRETARY
DATE :
ISABELA
HDS
SHT NO.