MALAYSIA (CIDB)
TINGKAT 10, MENARA DATO ONN, PUSAT
DAGANGAN DUNIA PUTRA (PWTC),
NO. 45, JLN TUN ISMAIL, 50480 KUALA LUMPUR
KERTAS TUGASAN
( ASSIGNMENT SHEET )
KOD DAN NAMA
PROGRAM /
PROGRAMS CODE &
NAME
BC-061-2:2015
BASIC SCAFFOLD ERECTION, ALTERATION AND
DISMANTLING
TAHAP / LEVEL
BC-061-1:2015-C04
TRUSS-OUT (SPUR) SCAFFOLD ERECTION,
ALTERATION AND DISMANTLING
BC-061-2:2015-C04/T(1/1)
TAJUK/TITLE:
TRUSS-OUT (SPUR) SCAFFOLD ERECTION, ALTERATION AND DISMANTLING G
TUJUAN/PURPOSE :
This Assignment Sheet is intended to assess understanding and knowledge of
trainees in the on tubular, modular and frame scaffold for Independent With Return
Scaffold erected, altered and dismantled.
BC-061-1:2015-C04/T(1/1)
ARAHAN / INSTRUCTION:
Trainees are required to answer all question with reference of Information Sheet BC061-1:2015-C04/P(1/1).
This paper consistes of four (4) questions:a. Part A : Multiple Choice Question
b. Part B : True or False Question
c. Part C : Matching/Fill in the Blank Question
d. Part D : Short Answer Question
1. Time allowed: 20 minutes
2. Not impersonate or imitate opportunities to other trainees.
SOALAN/QUESTION :
PART A: MULTIPLE CHOICE QUESTION
Arahan/Direction : Circle the correct answer.
BC-061-1:2015-C04/T(1/1)
(1 Mark)
3.
4.
5.
A. 3 M
B.
2.4 M
C.
1.5 M
D.
1.8 M
(1 Mark)
BC-061-1:2015-C04/T(1/1)
Scaffolder
must
always
erect
and
dismantle
scaffold
to
3.
manufacturers specifications.
Clusters should only be climbed where it is impracticable to use other
4.
5.
means of access
The maximum lift height is 3.0m.
Toe boards and guardrail should be fitted inside standards to prevent
6.
outward movement
For stationary towers, check that standards are fitted with base plates
and that base plates are securely fixed to prevent lateral movement
(5 Markah)
BC-061-1:2015-C04/T(1/1)
Building
Lifted
Granted
Hung
7.
8.
9.
10.
11.
BC-061-1:2015-C04/T(1/1)
13.
(2 Marks)
14.
BC-061-1:2015-C04/T(1/1)
....................................................................................................................
...................................................................................................................
ii) ....................................................................................................................
...................................................................................................................
(4 Marks)
15.
Give one (1) way inspection of TRUSS-OUT (SPUR) SCAFFOLD. for tubes
i)
....................................................................................................................
(1 Marks)
16.
....................................................................................................................
(1 Marks)
9. True
10. True
BC-061-1:2015-C04/T(1/1)
BC-061-1:2015-C04/T(1/1)
18. Identify two (2) ways inspection of TRUSS-OUT (SPUR) SCAFFOLD. for
standards.
i) Must be vertical and stable
ii) Joints should be made with sleeve couplers, or parallel couplers and
staggered.
19. Give one (1) way inspection of TRUSS-OUT (SPUR) SCAFFOLD. for tubes
i) Check all tubes of splits, flattened ends and corrosion
20. Identify one (1) way inspection of TRUSS-OUT (SPUR) SCAFFOLD. for
couplers
i) Check that only correct couplers are used and that they are fully
tightened