NOMBRE :__________________________________
FECHA : _________________
10. Which organization publishes most of the inspection codes cited in API 1104?
A. API
B. ASNT
C. ASTM
D. AWS
E. NACE
11. Which organization publishes most of the filler metal specifications for this code?
A. AWS
B. ASNT
C. ASTM
D. BSI
E. NACE
12. Which organization publishes a document on personnel certification used by this code?
A. API
B. ASNT
C. AWS
D. BSI
E. NACE
13. The term that best describes an acceptable weld flaw is:
A.
Defect
B.
Imperfection
C.
Indication
D.
Concavity
E.
Ridge
14. API 1104 uses the definitions of welding terms published by witch organization?
A.
API
B.
ASNT
C.
AWS
D.
BSI
E.
NACE
15. What process uses equipment that controls only the filler metal feed?
A.
Roll welding
B.
Submerged arc welding
C.
Gas tungsten arc welding
D.
Semiautomatic welding
E.
Root bead welding
16. The process where the pipe remains stationary during welding is called:
A.Automatic welding
B.Position welding
C.
Roll welding
D.
Roll bead welding
E.Semiautomatic welding
17. API 1104 applies to pipe welding that conforms to which specifications?
A. AWS 5.28
B. BSI BS 7448
C. API Specification 5L
D. Applicable ASTM
E. Both C&D
18. Once opened, where shall SMAW filler metals ending with numbers 5, 6, 8 be stored?
A. In ambient air
B. Electrode oven
C. Shipping container
D. Old refrigerator with 200 watt ligth bulb
E. Special plastic bags
19. What determines the tip size for gas welding equipment?
A. A manufacturer instructions
B. Trial and error
C. Welding procedure
D. Engineering drawing
E. Pressure of the gas
20. Coated filler metals and fluxes are sensitive to:
A. Ambient humidity
B. Overheating
C. Hidrogen craking
D. Inert gases
E. Active gases
21. API 1104 has grouped base material into three distinct groups. In group b the specified
minimum yield strength is:
A.
Less than or equal to 42,000 (290 Mpa) pounds per square inch
B.
Greater than 42,000 PSI (290 Mpa) but less than 65,000 PSI (448 Mpa)
C.
Greater than 42,000 PSI (290 Mpa) but less than 68,000 PSI (469 Mpa)
D.
Greater than 289.58 Mpa but less than 448.16 Mpa
E.
Both B and D
22. When conducting a procedure qualification on materials with outside diameters
greater than 135 mm, the number of tensile test(s) required is/are?
A.
Two
B.
One
C.
None are required
D.
Four
E.
None of the above
23. When preparing a tensile specimen for testing:
A.
A notch approximately 1/8 shall be cut into each of the weld
B.
The specimen must be machined
C.
May the oxygen cut with no further preparation provided sides all parallel and
smooth
D.
Weld reinforcement should not be removed on either side
E.
Both C&D
24. AWS Specification A5.1 and A5.5 are used for welding:
A.
Using the SMAW process
B.
Pipe in 2G position only
C.
Root pass welding only
D.
Electrodes in groups 1-2-3
E.
Both A and D above
25. When performing a nick-break test, the exposed area of fracture shall show complete
penetration and fusion. The greatest dimension of any gas pocket shall not exceed?
A.
1/16 wide
B.
2% of the exposed surface area
C.
5/8 wide
D.
1/ 2 wide
E.
Both A & B are correct
26. API1 1104 groups base metals into three groups based on their minimum yield
Strength. Which of the following is defined Group A?
A.
Less than 42,000 psi
B.
Less than or equal to 42,000 psi
C.
Greater than 65,000 psi
D.
Greater than 42,000 psi and less than 65000 psi
E.
Greater than 85,000 psi
27. For metals with specified minimum yield strengths greater than 42000 psi, what is
the minimum number of tensile test required?
A.
None
B.
One
C.
Two
D.
Four
E.
More than four
28. When preparing a tensile specimen for testing:
A.
Cut a 1/8-in. notch into each side of the weld
B.
Machine or grind all reinforcements smooth
C.
Cut a transverse notch into the weld
D.
Weld reinforcement should not be removed on either side
E.
Bend the specimen in a guided bend jig
29. AWS Specification A 5.20 is used for welding:
A.
Pipe in both uphill and downhill positions
B.
Pipe in 2G position only
C.
Root pass welding only
D.
Electrodes in group 3
E.
Both A and B above are correct
30. When performing a nick-break test, the exposed area of fracture shall be at least how
wide?
A.
1/ 2 in.
B.
3/ 4 in.
C.
5/ 8 in.
D.
1-1/ 2 in.
E.
A dimension is not specified
31. When automatic or semiautomatic welding is used, filler wire protruding into
the inside of the pipe:
A.
Is not permitted
B.
Length of protrusion shall not exceed 1/16
C.
Length of protrusion shall not exceed 0.79 mm
D.
Shall be kept to a minimum
E.
Both B and C above
32. For welder qualification on pipe greater than 4 in diameter, but less than or equal
to 12-3/4 in diameter, the number of destructive test specimens required are?
A.
4
B.
6
C.
Same as procedure qualification
D.
16
E.
Depends on the wall thickness of the pipe
33. In branch-on-pipe connection qualification, the finished weld:
A.
B.
C.
D.
E.
NOMBRE : __________________________________
FECHA : ____________________
41.- How many root-bend specimens are required for 8-in. OD pipe with wall thicknesses <
12.7 mm according to data in Table 3?
A.
None
B.
1
C.
2
D.
3
E.
4
42.- What is the total number of test specimens required for 8-in. OD pipe with wall thicknesses
< 12.7 mm according to data in Table 3?
A.
2
B.
3
C.
4
D.
5
E.
6
43.- Pipe ends of the same thickness should not be offset by more than:
A.
1/16 in.
B.
1/32 in.
C.
1/8 in.
D.
1/4 in.
E.
No offset is permitted
44.- Who determines the type of inspection to be done ?
A.
The welder
B.
The inspector
C.
The QC Manager
D.
The owner/company
E.
None of the above
45.- Which of the following destructive or non-destructive testing methods may not be
used?
A.
Visual inspection
B.
Radiographic inspection
C.
Trepanning
D.
Penetrant Testing
E.
Bend specimens
46.- Nondestructive testing personnel, other than visual inspection personnel, shall be
Qualified in accordance with which of the following?
A.
ASNT SNT-TC-1A
B.
ASME Section V
C.
ASTM 265E
D.
ACCP
E.
A & D above
47.- How often must Level III nondestructive testing personnel be re-certified?
A.
Every year
B.
Every two years
C.
Every three years
D.
Every four years
E.
Every five years
NOMBRE: _____________________________________
FECHA: ___________________
10
11
86.- Which of the following is not an essential variable for flash butt welds?
A.
Welding position
B.
Axial speed tolerances
C.
Pipe material
D.
Pipe wall thickness
E.
Filler metal
87.- As a minimum al completed flash butt welds shall:
A.
Be heated above the Ac3 temperature
B.
Use controlled cooling
C.
Use strip recorder to document heat treating
D.
Be heat treated again if out of spec
E.
All of the above
88.- Which of the following methods is not specified in flash butt repair procedures:
A.
Grinding
B.
Chipping
C.
Gouging
D.
Surface etching
E.
Cleaning
89.- When should NDT be performed on a flash butt weld?
A.
Immediately after welding
B.
After flash removal and heat treatment
C.
Before final heat treatment
D.
After final heat treatment
E.
Not specified
12
Section 1
5.- E
6- C
7- E
8- A
Section 5
26.- B
27.- B
28.- D
29.- C
30.- B
Section 9
57 .- D
58.- E
59.- E
60.- D
61.- B
Section 2
9.- D
10.- B
11.- A
12.- B
Section 6
34.- E
35.- D
36 .- A,B
Section 10
64.- B
65.- A
66.- E
Section 3
13.- B
14.- C
15.- D
16.- B
Section 7
40.- B
41.- C
42.- E
43.- C
Section 11
72.- E
73.- E
74.- B
75.- D
76.- D
Section 4
17.- E
18.- B
19.- C
20.- A
Section 8
48.- D
49.- D
50.- E
51.- C
Section 12
79.- E
80.- C
81.- B
Section 13
87.- E
88.- E
89.- E
90.- D
91.- B
13
Module 1
1.- D
2.- C
3.- B
4.- D
Module 4
37.- C
38.- E
39.- E
Module 7
62.- E
63.- D
Module 2
21.- E
22.- A
23.- E
24.- E
25.- E
Module 5
44.- D
45.- C
46.- E
47.- E
Module 8
67.- C
68.- D
69.- C
70.- B
71.- A
Module 3
31.- D
32.- B
33.- E
Module 6
52.- B
53.- B
54.- E
55.- D
56.- A
Module 9
77.- D
78.- C
3.- B
Module 10
81.- D
82.- B
83.- E
84.- C
85.- E