Académique Documents
Professionnel Documents
Culture Documents
Tanuj Chopra
Thapar University, Patiala
Tanuj Chopra
Thapar University Patiala
CONTRACT
Contract is an agreement between two or
more than two parties (enforceable at law) in
which one is agreed to provide goods and
services to other for which he will get the
return in the some form.
The contract is legal document and
binding on both the parties.
The form in which return for providing goods
and services is delivered, is called type of
Tanuj Chopra
contracts.
Thapar University Patiala
Letter of Intent
In a perfect world employers and contractors,
and contractors and subcontractors, would
finalize all aspects of their deal and record it in a
written, signed contract before any work was
performed or expenditure incurred.
In reality, however, the parties are often under
commercial pressure to commence works or
preparatory works as soon as possible and turn
to a 'letter of intent' while they continue to
negotiate the full contract
Tanuj Chopra
Thapar University Patiala
GACEPL / GMRACEPL
The project sponsors normally will form a Special
Purpose Vehicle (SPV) to act as
Chopra
the concessionaire ThaparTanuj
University Patiala
Tanuj Chopra
Thapar University Patiala
IMPORTANT DATES
16th Nov 2005
Signing of the Concession Agreement with NHAI
11th May 2006
Commencement of Construction
11th May 2006
Financial Closure of Project
November 2008
Completion of the Project
Negative Grant of 105.86 Crore
STATISTICS
Location
NH22-21, Haryana-Punjab
Project Distance
35 kms
Cost of Project
499.11 Crores
(including a cost overrun of 107.95 crores)
Contract Basis
Build, Own, and Transfer
Toll project
Concession Period
2 0 y e a r s Tanuj Chopra
Thapar University Patiala
C LIENT
National Highway Authority Of India (NHAI)
C O N C E S S I O N A I R E / S P V:
GMR Ambala Chandigarh Expressway Pvt . Ltd .
(GMRACEPL).
E P C C O N T R A C TO R :
GMR Projects Pvt. Ltd.(GPPL)
C O N S U LTA N T S :
S T U P C O N S U LTA N T S P v t . L t d .
INDEPENDENT E NGINEER:
M/S Sheladia Associates In.
C O N T R A C TO R :
ITD Cementation India Ltd
Tanuj Chopra
TYPICAL DRAWINGS
IN A CONTRACT
AGREEMENT
Tanuj Chopra
Thapar University Patiala
Tanuj Chopra
Thapar University Patiala
CONCESSION AGREEMENT
This Agreement is entered into on this the
. day of ., 2015 BETWEEN
NATIONAL HIGHWAYS AUTHORITY OF INDIA, a
statutory body constituted under the provisions of the
National Highways Authority of India Act, 1988, and
having its principal office at ______,New Delhi 110 065.
AND
[
LIMITED],
a
company
incorporated under the provisions of the Companies
Act, 1956 and having its registered office at
. (hereinafter referred to as the
Concessionaire or Company/SPV.
Tanuj Chopra
WHEREAS
Tanuj Chopra
Thapar University Patiala
Advance Payment
The Contractor may claim an advance
payment not exceeding 20% of the value
of the Contract, provided that it is covered by
an unconditional and irrevocable bank
guarantee from a bank. Such guarantee should
be valid for the entire contract implementation
period & will be recoverable in equal installment
in
the
succeeding
payment
Valuation
Certificates.
Tanuj Chopra
Thapar University Patiala
PERFORMANCE SECURITY
A contractor may cause a Performance bond to
be issued in favor of a client for whom the
contractor is constructing a building / project.
If the contractor fails to construct the project
according to the specifications laid out by
the
contract(most
often
due
to
the bankruptcy of the contractor), the client is
guaranteed compensation for any monetary
loss up to the amount of the performance
bond.
Tanuj Chopra
Tanuj Chopra
Thapar University Patiala
Monitoring of Construction
During the Construction Period, the
Concessionaire shall, no later than 7
(seven) days after the close of each month,
furnish to the Authority and the
Independent Engineer a monthly
report
on
progress
of
the
Construction Works
Tanuj Chopra
Thapar University Patiala
During
the
Construction
Period,
the
Independent Engineer shall inspect the
Project Highway at least once a month and
make a report of such inspection (the
"Inspection Report") stating in reasonable detail
the defects or deficiencies, if any, with particular
reference to the Scope of the Project and
Specifications and Standards. It shall send a copy
of the Inspection Report to the Authority and the
Concessionaire within 7 (seven) days of such
inspection and upon receipt thereof, the
Concessionaire shall rectify and remedy the
Tanuj in
Choprathe
defects or deficiencies, if any, stated
Inspection Report.
Thapar University Patiala
COMPLETION CERTIFICATE
At least 30 (thirty) days prior to the likely
completion of the Project Highway, the
Concessionaire shall notify the Independent
Engineer of its intent to subject the Project
Highway to Tests. The date and time of each of
the Tests shall be determined by the
Independent Engineer in consultation with the
Concessionaire, and notified to the Authority
who may designate its representative to witness
the Tests.
Tanuj Chopra
Thapar University Patiala
Provisional Certificate
The Independent Engineer may, at the
request of the Concessionaire, issue a
provisional certificate of completion the
"Provisional Certificate if the Tests are
successful and the Project Highway can be
safely and reliably placed in commercial
operation though certain works or things
forming part thereof are outstanding and
not yet complete.
Tanuj Chopra
Tanuj Chopra
Thapar University Patiala
Financial Closure
Financial Closure:- within 180 days of
signing the agreement.
Grace period of 90 days for financial
closure with fees of Rs. 1,00,000 per
week as Damage charges.
Maximum 270 days for Financial closure.
After this termination of contract. Client can
en-cash bid security or performance
security.
Tanuj Chopra
Thapar University Patiala
Tanuj Chopra
Thapar University Patiala
ESCROW
ACCOUNT
SPV within 60
days from date of
agreement open
and establish the
Escrow account
& all funds
constituting the
financing package
for meeting the TPC
shall be credited to
such escrow
account by F.C.
Tanuj Chopra
Thapar University Patiala
Arbitration
Every dispute, difference, or question
which may, at any time, arise between the
parties ,in respect of any clause of this
agreement or in respect of work done or
quality of materials used or in respect of any
delay in completion of works, it may give a
notice in writing to the other party that the
matter in dispute be referred to the
arbitration of an arbitrator to be agreed upon
and appointed by both the parties.
Tanuj Chopra
Major
Type
of
Contracts
Construction Industry
in
Tanuj Chopra
Thapar University Patiala
Tanuj Chopra
Thapar University Patiala
Turn-key Contract
A turn-key contract is an integrated
contract in which all works pertaining
to various disciplines such as civil,
electrical, mechanical are in the hands of a
single contractor called the main
contractor.
The main contractor can sublet the contact
to subcontractors who are specialists in
their respective fields.
Tanuj Chopra