Académique Documents
Professionnel Documents
Culture Documents
hema_bhit@hotmail.com
Project Performance
5
2. Planned % complete:
If the schedule says that your team should have done 300 hours of
work so far, and they will work a total of 1,000 hours on the project,
then your planned % complete is 30%.
BAC
Planned %
Complete
Planned
Value (PV)
hema_bhit@hotmail.com
Project Performance
6
BAC
Actual %
Complete
Earned
Value (EV)
hema_bhit@hotmail.com
Project Performance
7
hema_bhit@hotmail.com
Project Performance
8
SPI
Earned
Planned
/
Value (EV)
Value (PV)
hema_bhit@hotmail.com
Project Performance
9
Earned
Planned
Value (EV)
Value (PV)
If the variance is positive, it tells you exactly how many dollars youre
ahead. If its negative, it tells you how many dollars youre behind.
hema_bhit@hotmail.com
Project Performance
10
hema_bhit@hotmail.com
Project Performance
11
Earned
/
Value (EV)
Actual
Cost (AC)
hema_bhit@hotmail.com
Project Performance
12
CV
Earned
Value (EV)
Actual
Cost (AC)
If the variance is positive, it tells you exactly how many dollars youre
under. If its negative, it tells you how many dollars youre over.
hema_bhit@hotmail.com
Project Performance
13
Project Performance
14
Project Performance
15
hema_bhit@hotmail.com
Project Performance
16
SPI =
$175,000
PV = $300,000
EV = $300,000
50%
40%
= $150,000
= $120,000
SV = $120,000 -
$150,000
= $-30,000
CV = $120,000 -
$175,000
=$-55,000
CPI =
$120,000
$150,000
= 0.8
$120,000
= 0.68
$175,000
Schedule
Budget
Within
Ahead
Behind
Over
hema_bhit@hotmail.com
Project Performance
17
68%
= $442,000
SV = $442,000 -
$390,000
= $52,000
CV = $442,000 -
$400,000
=$42,000
Schedule
Ahead
Behind
Budget
Within
Over
hema_bhit@hotmail.com
Project Performance
18
hema_bhit@hotmail.com
Project Performance
19
Forecasting:
You can use CPI to predict what your project will actually cost when its
complete by calculating Estimate at completion or EAC.
hema_bhit@hotmail.com
Project Performance
20
Forecasting:
The three parameters of PV, EV, and AC can be monitored and reported
on both a period-by-period basis and on a cumulative basis.
S-curves
hema_bhit@hotmail.com
Project Performance
21
Forecasting:
The project managers bottom-up EAC method builds upon the
actual costs and experience incurred for the work completed, and
requires a new estimate to complete the remaining project work.
EAC = AC + Bottom-Up ETC
hema_bhit@hotmail.com
Project Performance
22
Forecasting:
Only three of the more common methods to calculate EAC are described as follows:
EAC = BAC
CPI
3. EAC forecast for ETC work considering both SPI and CPI factors:
The ETC that considers both the cost and schedule performance indices.
hema_bhit@hotmail.com
Project Performance
23
Forecasting:
1. Estimate To Complete (ETC):
2. Variance At Completion (VAC):
ETC = EAT
AC
VAC = BAC -
EAC
hema_bhit@hotmail.com
Project Performance
24
hema_bhit@hotmail.com
Project Performance
25
EAC Based
(BAC - EV)
TCPI =
(EAC - AC)
It is for when you are
trying to get your project
done within the EAC
youve determined from
earned value calculations.
hema_bhit@hotmail.com
Project Performance
26
hema_bhit@hotmail.com