Académique Documents
Professionnel Documents
Culture Documents
PILING WORKS
METHOD STATEMENT OF PILING WORKS BY JACKED-IN PILE METHOD
1.0 Scope of Work
The works will consist of the whole process of piling including setting out of pile points,
welding of joints for extension piles, sequence of piling, piling procedure, termination
criteria and loading tests.
Immediately before
installation of each pile, the pile position will be marked with suitable identifiable pegs or
markers (e.g. steel rod).
A pile is then
pitched with the help of the service crane and fed into the helmet attached at the
upper drive head. The pile is next checked for its verticality by using a spirit ruler.
Further adjustment to obtain verticality of the pitched pile is done by moving the
stabilizer jacks.
The delivered piles will be stacked at a location which will not hamper the
installation of piles. The body of each pile is marked with lines at 1m intervals to
indicate the penetration depth. The sequence of pile installation will be from one
end to the other in order to avoid the machine from disturbing those piles earlier
installed. The sequence is to minimize the detrimental effects of heave and lateral
displacement of the ground. The installation of one length of pile is completed by
two strokes: first using the upper drive head, and then followed by the lower drive
head. The force is exerted onto the pile head by upper drive head which pushes
half the length of the pile into the soil upon full extension of the two main jacks.
The jacks are next retracted to allow the lower drive head to close up.The next
half of the pile is pushed into the soil by the lower drive head upon full extension
of the main jacks. An extension pile is pitched and the process is repeated. Upon
completion of pile installation, the protruded portion