Planning Calendar Calculation Rule detail

information
Hello Every one,
I prepared this document to understand the detail information of the calculation rule of Planning Calendar.
Planning calendar define flexible periods for a period lot-sizing procedure in master production
scheduling (MPS) and in Material Requirement planning (MRP).
System group to gather the entire requirement which fall with in period which mention in planning
calendar from a lot.
Planning calendar depend on the factory calendar, so whenever changes happens in factory
calendar, we need to update the planning calendar
Pre-Requisite
Planning calendar assign to the material in material master MRP view 2.
Lot size assign In MRP Material master view 1 as PK (Period lot size acc. to plng calendar)
For creation/Change/Display of the planning calendar go to T: code, MD25/MD26/MD27
Create Planning calendar with respect to the Plant

Generated by Jive on 2015-01-28+01:00


1

Planning Calendar Calculation Rule detail information

Planning calendar Calculation Rule


With help of the calculation rule, we can achieve planning calendar requirement.
1. Weeks ( Week Days)
This calculation rule for create requirement for per week.
We can create requirement for any day of week, suppose if we select the 1,2,3 in below calculation
rule system create requirement for Every week Monday, Tuesday, Wednesday.
Using this calculation rule you can create the requirement for any day of week.
Please check below snap shot of Period and calendar

Generated by Jive on 2015-01-28+01:00


2

Planning Calendar Calculation Rule detail information

Generated by Jive on 2015-01-28+01:00


3

Planning Calendar Calculation Rule detail information

2. Months ( Week Days)


This calculation rule for create requirement for per Month.
We can create requirement for any counter week of week day, suppose if we select the 2 as counter
week day and select week day as 5 (Friday) system calculated and create requirement for every
month second week of Friday.
Using this calculation rule you can create the requirement for any day of week in particular month.
Please check below snap shot of Period and calendar

Generated by Jive on 2015-01-28+01:00


4

Planning Calendar Calculation Rule detail information

Generated by Jive on 2015-01-28+01:00


5

Planning Calendar Calculation Rule detail information

3. Months ( WorkDays)
This calculation rule for create requirement for per Month workdays .
Suppose if we select the 1, 5, 10 Working days of per month, in that case system create
requirement for every month 1 , 5 , and 10 working days. With help of this rule you can create
requirement of any day of the month.
In planning calendar system not count the Non-working days as per respective factory
calendar.
Please check below snap shot of Period and calendar
st

th

th

Generated by Jive on 2015-01-28+01:00


6

Planning Calendar Calculation Rule detail information

Generated by Jive on 2015-01-28+01:00


7

Planning Calendar Calculation Rule detail information

4. Years ( WorkDays)
This calculation rules similar to the above calculation rule Month ( Workdays)
We can define the work Day/Days for year in planning calendar according to factory calendar.
5. Workdays
This calculation rule for create requirement for work days.
Suppose if we create the requirement for 10 work days, in that case system create requirement after
every 10 working days
We have to mention calculation start date.
system not count the Non Working days as per Factory calendar changes

Generated by Jive on 2015-01-28+01:00


8

Planning Calendar Calculation Rule detail information

Generated by Jive on 2015-01-28+01:00


9

Planning Calendar Calculation Rule detail information

6. Weekdays
This calculation helpful to create the requirement for any week of workdays.
We create the requirement for every alternate week 2of Thursday 4. We can create
requirement for any week work days
We have to mention calculation start date.
In planning calendar system not count the Non-working days as per respective factory
calendar.

Generated by Jive on 2015-01-28+01:00


10

Planning Calendar Calculation Rule detail information

Generated by Jive on 2015-01-28+01:00


11

Planning Calendar Calculation Rule detail information

Planning calendar additional future.


Planning calendar depend on the factory calendar, but in factory calendar some days are mention as nonworking days. Suppose on this particular day requirement fall in that case system follow the below rules. Before
calculation rule apply we need to select the one of the rules.
1. Do not Displace :
04/14/2014, set as Holiday in Factory calendar and suppose period start falls on Same day
In this case a system not displaced but calculates and creates the demand on Same period date
Every week Tuesday working days calculation rule use in planning calendar

Generated by Jive on 2015-01-28+01:00


12

Planning Calendar Calculation Rule detail information

2. Following Working Day:

14/04/2014, set as Holiday in Factory calendar and suppose staring period falls on Same day
In this case a system select the next working day.
Here Next working day is 15/04/2014,
Every week Tuesday working days calculation rule use in planning calendar

Generated by Jive on 2015-01-28+01:00


13

Planning Calendar Calculation Rule detail information

3. Previous Working Day:

14/04/2014, set as Holiday in Factory calendar and suppose starting period falls on Same day
In this case a system select the previous working day.
Here Previous working day is 13/04/2014,
Every week Tuesday working days calculation rule use in planning calendar

Generated by Jive on 2015-01-28+01:00


14

Planning Calendar Calculation Rule detail information

4. No new Period:
14/04/2014, set as Holiday in Factory calendar and suppose starting period falls on Same day
In this case a system not creates any period.
Every week Tuesday working days calculation rule use in planning calendar

Generated by Jive on 2015-01-28+01:00


15

Planning Calendar Calculation Rule detail information

I hope this detail document helpful to every one to understand the Planning calendar Calculation rule.
Request to all expert to suggest and guide if any thing missing in this document
Thanks & Regrads
Umesh Mali

Generated by Jive on 2015-01-28+01:00