TITULO DEL TRABAJO

EXAMEN FINAL DEL VI CURSO RECEPTOR


GEODSICO GPS SATELITAL

PROFESOR: RUDDY REZZA

AULA: IGN

INTEGRANTES:

1.-RICHARD POOL YAEZ ALBARRAN

LIMA, AGOSTO 2015

1 de 94

INDICE

HOJA DE REVISION ................................................................................................................................... 1


INDICE ........................................................................................................................................................ 2
1.

PLANNING TRIMBLE CAMPAA GEODESICA ................................................................................... 3

2.

RECEPTOR GEODESICO POSTPROCESAMIENTO .........................................................................20

3.

PROCESAMINETO DE INFORMACION CON SOFTWARE TBC ........................................................32

4.

CONCLUCIOSNES Y RECOMENDACIONES .....................................................................................94

2 de 94

1. EMPLEO DEL SOFTWARE PLANNIG TRIMBLE SIMILAR.

I.1.

UBICACIN DE LA ZONA DE TRABAJO


El Proyecto se encuentra ubicado en el Distrito de Huancabamba y Canchaque en la
provincia de Huancabamba , en el departamento de Piura.

I.2.

CONDICIONES EN LA ZONA DE TRABAJO


El clima que se tiene en la zona de trabajo es frio con una temperatura de 21C despejado
en el da y por momentos soleado con una sensacin trmica alta, no hubo precipitaciones,
se not por momentos presencia de viento.

3 de 94

I.3.

ALCANCES DEL TRABAJO


El trabajo consisti en la georreferenciacin de puntos de control mediante equipos GPS
de doble frecuencia, una vez obtenidas las coordenadas UTM en el post-proceso se realiza
el clculo de las coordenadas topogrficas correspondientes.

PROCEDIMIENTO Y EJECUCION
PLANEAMIENTO
Se eligi como base para el enlace a la red geodsica Nacional la estacin de rastreo
Permanente de Pasco que es de orden 0, (Ficha Tcnica y data cruda) con la ubicacin y
descripcin del mismo, el cual fue adquirido en el IGN (Instituto Geogrfico Nacional) y que
corresponde a la misma fecha en que se tomaron lecturas a los 3 puntos de control.

4 de 94

5 de 94

6 de 94

Se utilizaran puntos de ESTACION DE RASTREO PERMANENTE de Piura, Huancabamba y


Jaen.

Luego enlazarlos a la red geodsica existente de la zona.

7 de 94

Se tiene tres ERP para un punto inicio del proyecto en Canchaque.


Anticipadamente se tiene que observar los parmetros del equipo a utilizar en modo
esttico.

8 de 94

I.

ITERACCION PIURA-CANCHAQUE (color verde)


Estatico: Horizontal 3+0.001ppm RMS
3+0.1 X (DISTANCIA DIRECTA NO RECORRIDO=115Km aprox.)
Pero esta en PARTES POR MILLON 1Km 1millon de milmetros
3mm+0.1X(115mm)=14.5mm=0.145cm incertidumbre en la lectura
Cinemtico: Horizontal 8+0.001ppm RMS
3+0.1 X (DISTANCIA DIRECTA NO RECORRIDO=115Km aprox.)
Pero esta en PARTES POR MILLON 1Km 1millon de milmetros
8mm+1X(115mm)=123mm=1.23cm incertidumbre en la lectura

II.

ITERACCION JAEN-CANCHAQUE (color magenta)


Estatico: Horizontal 3+0.001ppm RMS
3+0.1 X (DISTANCIA DIRECTA NO RECORRIDO=115Km aprox.)
Pero esta en PARTES POR MILLON 1Km 1millon de milmetros
3mm+0.1X(95mm)=12.5mm=0.125cm incertidumbre en la lectura
Cinemtico: Horizontal 8+0.001ppm RMS
3+0.1 X (DISTANCIA DIRECTA NO RECORRIDO=115Km aprox.)
Pero esta en PARTES POR MILLON 1Km 1millon de milmetros
8mm+1X(95mm)=98mm=0.98cm incertidumbre en la lectura

9 de 94

III.

ITERACCION HUANCABAMBA-CANCHAQUE (color naranja)


Estatico: Horizontal 3+0.001ppm RMS
3+0.1 X (DISTANCIA DIRECTA NO RECORRIDO=115Km aprox.)
Pero esta en PARTES POR MILLON 1Km 1millon de milmetros
3mm+0.1X(23mm)=5.3mm=0.053cm incertidumbre en la lectura
Cinemtico: Horizontal 8+0.001ppm RMS
3+0.1 X (DISTANCIA DIRECTA NO RECORRIDO=115Km aprox.)
Pero esta en PARTES POR MILLON 1Km 1millon de milmetros
8mm+1X(23mm)=4.5mm=0.045cm incertidumbre en la lectura
PLANEAMIENTO CON PLANING DE TRIMBLE

10 de 94

11 de 94

PRIMER DIA 22-08-15

De acuerdo con la normativa, y posibles alcances de la seal GNSS para los


60km de carretera a ejecutar se necesitaran tener 12 implantados a los largo
de su recorrido.
Por lo tanto se espera que para los das 22 y 23 de setiembre se establezcan 6
puntos de control de orden c por cada da, siempre y cuando el DOP, las
interferencias fsicas de las montaas, elevacin sobre el nivel mar, sean
favorables. Para ello se analizar con trimble planning.

12 de 94

13 de 94

14 de 94

15 de 94

SEGUNDO DIA 23-08-15

16 de 94

17 de 94

El DOP para este da en los horas centrales al medio da y media noche no son favorables pero
se ubican en un rango a medio aceptable, permitiendo recibir la seal de los satlites a pesar
de tener una configuracin geomtrica mxima de 2.00 hacia 2.7 regular.

18 de 94

Se resume que la campaa para estos das se realizara con dos brigadas en
extremos diferentes y cada una de ella colocar tres puntos por da en un
intervalo de tiempo de horas con 15 minutos en la recepcin empezando las
labores a la 7:00 am y finalizando a las 17:00pm antes de empezar el da
juliano del da siguiente a las 7:00pm.

19 de 94

2. RECEPTOR GEODSICO GPS SATELITAL


POST PROCESAMIENTO

Se estableci un punto geodsico aplicando el mtodo Diferencial Esttico, para esto se utiliz un GPS
diferencia TRIMBLE R7 GNSS es un receptor GNSS

(Sistema de navegacin global por satlite) se

consider los siguientes parmetros:

Mascara 15

Sin modelo geoide

Intervalo de tiempo 5 seg.

Tiempo de toma 65 minutos.

Datos de la ubicacin del punto: Losa Deportiva del IGN LIMA

Nombre del punto: losa

Altura de antena (Zephyr Geodsica): 1.386 mt.

Nombre de la Carpeta: ign21ago2015

Hora de Inicio de la toma: 7:02pm

Fecha de la toma: 21/08/2015

Nombre de la data: 08592347.T01

COORDENADAS UTM WGS84 PREVIAS TOMADA EN CAMPO:


N= 8661249.025
E= 280507.094
Elevacin= 152.245 m.

COORDENADAS GEOGRFICAS PREVIAS TOMADA EN CAMPO:


LATITUD= 1206 10.71386S
LONGITUD= 770100.08959W
ALTURA (LOCAL)= 151.250 m.
2.- Vamos a comenzar con el post proceso y para esto trabajaremos con las pginas siguientes:
http://www.trimblertx.com/UploadForm.aspx (PPP TRIMBLE)
http://webapp.geod.nrcan.gc.ca/geod/tools-outils/ppp.php?locale=en (PPP CANADIENSE)
http://www.ppp.ibge.gov.br/ppp.htm (PPP BRASILEO)
3.- Enviaremos la data a la pgina de http://www.trimblertx.com, aqu enviaremos en formato TRIMBLE
08592347.T01 (llenamos los campos que nos pide la pgina).

20 de 94

DESCARGA DE LA DATA DE LA ESTACION PEMANENTE DE AREQUIPA

Instalado el programa, se procede a cargar el almanaque descargado de la fuente receptora cercana al


lugar donde se ejecutara la instalacin del equipo y su toma de datos.
-

Ejm: se utiliz el cdigo IP: 200.24.166.166:6500 Perteneciente a una base que utiliza equipo GPSD de
modo permanente, ubicado en la ciudad de Arequipa, utiliza la tecnologa TRIMBLE para los fines
correspondientes.

DATOS DE LA BASE RECEPTORA PERMANENTE


Mascara de elevacin:
0
Mscara PDOP.:
99
Precisin horizontal:
0.30 [m]
Precisin vertical:
0.30 [m]
Control de reloj:
Habilitado/a
Everest Mitigacin de trayectoria mltiple:
Habilitado/a
ID antena:
185
Tipo de antena:
Zephyr Geodetic 2
Mtodo de medicin de la antena:
Base del soporte de la antena
Altura antena:
0.158 [m]
1PPS S/No:
Habilitado/a
Evento 1 S/No:
Inhabilitado/a
Evento 1 pendiente:
Positivo/a
Frecuencia externa disponible:
No detectada
Modo RTK:
Latencia baja
Movimiento receptor:
Esttico
Movimiento motor RTK:
Esttico
Filtro entrada CMR:
Inhabilitado/a
Latitud de referencia:
1624'41.30968"S
Longitud de referencia:
7131'59.92692"O
Altura de referencia:
2374.591 [m]
ID RTCM 2.x:
0
ID RTCM 3.x:
0
ID CMR:
0
Nombre de estacin:
GEO2
IP Ethernet:
200.24.166.166
Nombre del sistema:
GEO2
Nombre DNS resuelto:
---Nmero de serie:
5306K50758
Versin de firmware:
5.01
Fecha firmware:
2015-04-07

21 de 94

Comparacion del sitio web como fuente.

22 de 94

IBGE BRASIL
www.ibge.gob.br

ryanez314@gmail.com

23 de 94

24 de 94

25 de 94

26 de 94

TRIMBRE RTX
www.trimblertx.com

ryanez314@gmail.com

27 de 94

28 de 94

COORDENADAS UTMWG8418S
POSTPROCESO

NORTE(Y)

ESTE(X)

IBGE BRASIL

8661249.0759

280506.3920

TRIMBLE RTX

8661248.8400

280506.3622

DIFERENCIAS
(m)
0.0298

0.2359

CANADA
webapp.geod.nrcan.gc.ca

ryanez314@gmail.com

~~~~~~~~~~~~~~~~~~~~~~~~~~ 08592347 ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


The estimated coordinates / standard deviations (95%) for the 08592347 RINEX file are as follow:
Latitude (ITRF08): -12 06 10.7237 (dms) / 0.030 (m)
Longitude (ITRF08): -77 01 00.1080 (dms) / 0.072 (m)
Ellipsoidal Height (ITRF08): 148.061 (m) / 0.108 (m)
UTM (South) Northing: 8661248.955m Easting: 280506.302m Zone: 18 Scale Factor: 1.00019608
(point) 1.00017284 (combined)
Orthometric Height CGVD2013: _NOT_DEFINED_
Cartesian coordinates (X Y Z in metres) 1401344.994, -6077972.292, -1328574.298

29 de 94

COMPARACIN 1

CUADRO COMPARATIVO
X
Y

TRIMBLE

1401345.058

-6077972.292

-1328574.416

BRASILEO

1401345.192

-6077972.734

-1328574.275

DELTAS

-0.134

-0.442

0.141

DELTAS2

0.017956

0.195364

0.019881

0.233201

SUMA DELTAS2

0.4829

RAIZ

30 de 94

COMPARACIN 2

CUADRO COMPARATIVO
Y

TRIMBLE

1401345.058

-6077972.292

-1328574.416

CANADA

1401344.994

-6077972.292

-1328574.298

DELTAS

-0.064

0.000

-0.118

DELTAS2

0.004096

0.000000

0.013924

SUMA DELTAS2
RAIZ

0.018020
0.134

31 de 94

3 PROCESAMIENTO TBC
Se establece los parmetros de acuerdo al sector donde se va a realizar la campaa geodsica.

32 de 94

33 de 94

34 de 94

35 de 94

36 de 94

37 de 94

38 de 94

39 de 94

40 de 94

41 de 94

42 de 94

43 de 94

REPORTE 1 LOSA HACIA (CHIMBOTE-ANCAHS)


Informacin del proyecto
Nombre:
Tamao:
Modificado/a:
Nmero de referencia:
Descripcin:

Sistema de coordenadas
Nombre:
UTM
Datum:
WGS 1984
Zona:
18 North
Geoide:
EGM96 (Global)
Datum vertical:

Informe de procesamiento de lneas base

Detalles de la sesin
AN02 - LI-LOSA (07:02:20 p.m.-08:32:25 p.m.) (S2)
Observacin de lneas base: AN02 --- LI-LOSA (B2)
Procesada:
Tipo de solucin:
Frecuencia de uso:
Precisin horizontal:
Precisin vertical:
RMS:
Razn:
Efemride utilizada:
Modelo de antena:
Procesando hora de inicio:
Procesando hora de trmino:
Procesando duracin:

26/08/2015 05:43:06 p.m.


Flotante
Mltiples frecuencias
0.102 m
0.068 m
0.020 m
?
Transmisin
Calibracin de Trimble
21/08/2015 07:02:20 p.m. (Local: UTC0hr)
21/08/2015 08:32:25 p.m. (Local: UTC0hr)
01:30:05

Componentes del vector (Marca a Marca)


De:

AN02
Cuadrcula

Este

111931.339 m

Valor norte -1010948.716 m

Local

Global

Latitud S907'42.32831"

Latitud S907'42.32831"

Longitud O7831'47.19220"

Longitud O7831'47.19220"

44 de 94

Elevacin

23.643 m

A:

LI-LOSA

Altura

Cuadrcula
Este

39.205 m

Altura

39.205 m

Local

280506.564 m

Valor norte -1338750.979 m


Elevacin 125.047 m

Global

Latitud S1206'10.72161"
Longitud O7701'00.09933"
Altura

148.250 m

Latitud S1206'10.72161"
Longitud O7701'00.09933"
Altura

148.250 m

Vector:
Este

168575.225 m

Acimut Adelante NS

15325'22"

X 148947.664 m

Dist. elip

368323.929

Y 94175.097 m

Altura

109.045

Z -323379.187 m

Valor norte -327802.263 m


Elevacin

101.403 m

Errores estndar
Errores del vector:
Este

0.034 m

Acimut Adelante NS

000'00"

X 0.034 m

Valor norte

0.015 m

Dist. elip

0.022 m

Y 0.026 m

Elevacin

0.026 m

Altura

0.026 m

Z 0.015 m

Matriz de covarianzas a posteriori (Metro2)


Y

X
0.0011469617

0.0000035777

0.0006945459

-0.0000893916

-0.0000303349

0.0002205789

Ocupaciones
De

AN02

LI-LOSA

Archivo de datos:

F:\TRABAJO
FINAL\AN02234aA.T01

F:\TRABAJO
FINAL\08592347.15o

Tipo de receptor:

4000A

R7 GNSS

ID de punto:

Nmero serial del


receptor:
Tipo de antena:
Nmero de serie de la

4740K30859
Zephyr Geodsica 2 w/Dome

Zephyr Geodetic

40925626

--------

45 de 94

antena:
Altura de la antena
(Medido):

0.120 m

1.386 m

Mtodo de antena:

Base del soporte de la antena

Base del soporte de la antena

Resumen de seguimiento
Residuales

46 de 94

47 de 94

48 de 94

49 de 94

50 de 94

51 de 94

52 de 94

53 de 94

54 de 94

55 de 94

56 de 94

57 de 94

58 de 94

Mensajes
Forced float.
Satellite G14 was below the elevation mask 48% of the time for the base receiver.
Satellite G18 was below the elevation mask 100% of the time for the base receiver.
Satellite G20 was below the elevation mask 47% of the time for the base receiver.
Satellite G21 was below the elevation mask 100% of the time for the base receiver.
Satellite G5 was below the elevation mask 95% of the time for the base receiver.
Satellite G6 was below the elevation mask 100% of the time for the base receiver.
Satellite R14 was below the elevation mask 100% of the time for the base receiver.
Satellite R16 was below the elevation mask 22% of the time for the base receiver.
Satellite R17 was below the elevation mask 66% of the time for the base receiver.
Satellite R20 was below the elevation mask 54% of the time for the base receiver.
Satellite R4 was below the elevation mask 92% of the time for the base receiver.

59 de 94

Satellite R5 was below the elevation mask 28% of the time for the base receiver.
Satellite R6 was below the elevation mask 37% of the time for the base receiver.

Procesando estilo
Mscara de elevacin:
Iniciar procesamiento automtico:
Iniciar numeracin de ID
automtica:
Vectores continuos:
Generar residuales:
Modelo de antena:
Tipo de efemride:
Frecuencia:
Forzar flotante:

15.0 grado
S
AUTO0001
No
S
Automtico
Automtico
Mltiples frecuencias
No

Criterios de aceptacin
Componente del vector

Indicador

Fallida

Precisin horizontal >

0.050 m + 1.000 ppm

0.100 m + 1.000 ppm

Precisin vertical >

0.100 m + 1.000 ppm

0.200 m + 1.000 ppm

Fecha:26/08/2015 05:48:27 p.m.

Proyecto:

60 de 94

Trimble Business Center

REPORTE 2 LOSA HACIA (IGN-LIMA)

Informacin del proyecto


Nombre:
Tamao:
Modificado/a:
Nmero de referencia:
Descripcin:

Sistema de coordenadas
Nombre:
UTM
Datum:
WGS 1984
Zona:
18 North
Geoide:
EGM96 (Global)
Datum vertical:

Informe de procesamiento de lneas base

Detalles de la sesin
LI01 - LI-LOSA (07:02:20 p.m.-08:32:25 p.m.) (S3)
Observacin de lneas base: LI01 --- LI-LOSA (B3)
Procesada:
Tipo de solucin:
Frecuencia de uso:
Precisin horizontal:
Precisin vertical:
RMS:
Razn:
Efemride utilizada:
Modelo de antena:
Procesando hora de inicio:
Procesando hora de trmino:
Procesando duracin:

26/08/2015 05:43:08 p.m.


Fijo
Mltiples frecuencias
0.004 m
0.008 m
0.014 m
2.225
Transmisin
Calibracin de Trimble
21/08/2015 07:02:20 p.m. (Local: UTC0hr)
21/08/2015 08:32:25 p.m. (Local: UTC0hr)
01:30:05

Componentes del vector (Marca a Marca)


De:

LI01
Cuadrcula

Este

280479.727 m

Local

Global

Latitud S1206'10.86386"

Latitud S1206'10.86386"

61 de 94

Valor norte -1338755.549 m


Elevacin

134.410 m

A:

LI-LOSA

Altura

Cuadrcula
280506.219 m
Este
Valor norte -1338751.115 m
Elevacin

Longitud O7701'00.98771"
157.609 m

Local
Latitud S1206'10.72596"
Longitud O7701'00.11075"

124.852 m

Altura

148.055 m

Longitud O7701'00.98771"
Altura

157.609 m

Global
Latitud S1206'10.72596"
Longitud O7701'00.11075"
Altura

148.055 m

Vector:
Este

26.492 m

Acimut Adelante NS

8055'17"

X 23.942 m

Valor norte

4.434 m

Dist. elip

26.855

Y 14.195 m

Elevacin

-9.558 m

Altura

-9.554

Z 6.147 m

Errores estndar
Errores del vector:
Este

0.001 m

Acimut Adelante NS

000'07"

X 0.001 m

Valor norte

0.001 m

Dist. elip

0.001 m

Y 0.003 m

Elevacin

0.003 m

Altura

0.003 m

Z 0.001 m

Matriz de covarianzas a posteriori (Metro2)


Y

X
0.0000014605

-0.0000007071

0.0000081921

-0.0000002097

0.0000018725

0.0000012087

Ocupaciones
De

LI01

LI-LOSA

Archivo de datos:

F:\TRABAJO
FINAL\LI01234aA.T01

F:\TRABAJO
FINAL\08592347.15o

Tipo de receptor:

NetR5

R7 GNSS

Nmero serial del


receptor:

4806K53394

4740K30859

Zephyr Geodetic 2

Zephyr Geodetic

ID de punto:

Tipo de antena:

62 de 94

Nmero de serie de la
antena:

30738913

--------

Altura de la antena
(Medido):

0.164 m

1.386 m

Mtodo de antena:

Base del soporte de la antena

Base del soporte de la antena

Resumen de seguimiento
Residuales

63 de 94

64 de 94

65 de 94

66 de 94

67 de 94

68 de 94

69 de 94

70 de 94

71 de 94

72 de 94

73 de 94

74 de 94

75 de 94

Mensajes
Satellite G13 was below the elevation mask 26% of the time for the base receiver.
Satellite G14 was below the elevation mask 46% of the time for the base receiver.
Satellite G18 was below the elevation mask 100% of the time for the base receiver.
Satellite G20 was below the elevation mask 87% of the time for the base receiver.
Satellite G21 was below the elevation mask 100% of the time for the base receiver.
Satellite G6 was below the elevation mask 66% of the time for the base receiver.
Satellite R14 was below the elevation mask 100% of the time for the base receiver.
Satellite R16 was below the elevation mask 7% of the time for the base receiver.
Satellite R17 was below the elevation mask 45% of the time for the base receiver.
Satellite R20 was below the elevation mask 79% of the time for the base receiver.
Satellite R4 was below the elevation mask 99% of the time for the base receiver.
Satellite R5 was below the elevation mask 42% of the time for the base receiver.

76 de 94

Satellite R6 was below the elevation mask 55% of the time for the base receiver.
Satellite R9 was below the elevation mask 100% of the time for the base receiver.

Procesando estilo
Mscara de elevacin:
Iniciar procesamiento automtico:
Iniciar numeracin de ID
automtica:
Vectores continuos:
Generar residuales:
Modelo de antena:
Tipo de efemride:
Frecuencia:
Forzar flotante:

15.0 grado
S
AUTO0001
No
S
Automtico
Automtico
Mltiples frecuencias
No

Criterios de aceptacin
Componente del vector

Indicador

Fallida

Precisin horizontal >

0.050 m + 1.000 ppm

0.100 m + 1.000 ppm

Precisin vertical >

0.100 m + 1.000 ppm

0.200 m + 1.000 ppm

Fecha:26/08/2015 05:48:27 p.m.

Proyecto:

77 de 94

Trimble Business Center

REPORTE 3 LOSA HACIA (IGN-LIMA)


informacin del proyecto
Nombre:
Tamao:
Modificado/a:
Nmero de referencia:
Descripcin:

Sistema de coordenadas
Nombre:
UTM
Datum:
WGS 1984
Zona:
18 North
Geoide:
EGM96 (Global)
Datum vertical:

Informe de procesamiento de lneas base

Detalles de la sesin
GEO2 - LI-LOSA (07:02:20 p.m.-08:32:25 p.m.) (S4)
Observacin de lneas base: GEO2 --- LI-LOSA (B4)
Procesada:
Tipo de solucin:
Frecuencia de uso:
Precisin horizontal:
Precisin vertical:
RMS:
Razn:
Efemride utilizada:
Modelo de antena:
Procesando hora de inicio:
Procesando hora de trmino:
Procesando duracin:

26/08/2015 05:43:09 p.m.


Flotante
Mltiples frecuencias
0.132 m
0.092 m
0.030 m
?
Transmisin
No se aplicaron correcciones a la tabla de fases.
21/08/2015 07:02:20 p.m. (Local: UTC0hr)
21/08/2015 08:32:25 p.m. (Local: UTC0hr)
01:30:05

Componentes del vector (Marca a Marca)


De:

LI-LOSA
Cuadrcula

Este

280506.564 m

Valor norte -1338750.979 m

Local

Global

Latitud S1206'10.72161"

Latitud S1206'10.72161"

Longitud O7701'00.09933"

Longitud O7701'00.09933"

78 de 94

Elevacin

125.047 m

Altura

148.250 m

Altura

148.250 m

GEO2

A:

Cuadrcula
Este

Local

870329.037 m

Valor norte -1817619.441 m


Elevacin 2332.838 m

Global

Latitud S1624'41.30985"
Longitud O7131'59.92202"
Altura

2374.646 m

Latitud S1624'41.30985"
Longitud O7131'59.92202"
Altura

2374.646 m

Vector:
Este

589822.473 m

Acimut Adelante NS

12930'11"

X 537877.792 m

Dist. elip

759718.566

Y 271027.837 m

Altura

2226.397

Z -462549.445 m

Valor norte -478868.462 m


Elevacin

2207.791 m

Errores estndar
Errores del vector:
Este

0.044 m

Acimut Adelante NS

000'00"

X 0.044 m

Valor norte

0.021 m

Dist. elip

0.039 m

Y 0.035 m

Elevacin

0.036 m

Altura

0.036 m

Z 0.020 m

Matriz de covarianzas a posteriori (Metro2)


Y

X
0.0019614606

-0.0000095876

0.0012572909

-0.0001857680

-0.0000276532

0.0004168464

Ocupaciones
De

LI-LOSA

GEO2

Archivo de datos:

F:\TRABAJO
FINAL\08592347.15o

F:\TRABAJO
FINAL\GEO2234aB.15O

Tipo de receptor:

R7 GNSS

4000A

Nmero serial del


receptor:

4740K30859

ID de punto:

Tipo de antena:
Nmero de serie de la

Zephyr Geodetic

Externa desconocida

--------

--------

79 de 94

antena:
Altura de la antena
(Medido):

1.386 m

0.158 m

Mtodo de antena:

Base del soporte de la antena

Base del soporte de la antena

Resumen de seguimiento
Residuales

80 de 94

81 de 94

82 de 94

83 de 94

84 de 94

85 de 94

86 de 94

87 de 94

88 de 94

89 de 94

90 de 94

91 de 94

Mensajes
Forced float.
Satellite G13 was below the elevation mask 30% of the time for the rover receiver.
Satellite G14 was below the elevation mask 52% of the time for the rover receiver.
Satellite G17 had missing broadcast ephemeris 100% of the time for the rover receiver.
Satellite G18 was below the elevation mask 100% of the time for the rover receiver.
Satellite G20 was below the elevation mask 100% of the time for the rover receiver.
Satellite G6 was below the elevation mask 16% of the time for the rover receiver.
Satellite R14 had missing broadcast ephemeris 12% of the time for the rover receiver.
Satellite R14 was below the elevation mask 45% of the time for the rover receiver.
Satellite R17 was below the elevation mask 28% of the time for the rover receiver.
Satellite R20 was below the elevation mask 100% of the time for the rover receiver.
Satellite R4 was below the elevation mask 97% of the time for the rover receiver.

92 de 94

Satellite R5 was below the elevation mask 62% of the time for the rover receiver.
Satellite R6 was below the elevation mask 100% of the time for the rover receiver.
Satellite R9 was below the elevation mask 100% of the time for the rover receiver.

Procesando estilo
Mscara de elevacin:
Iniciar procesamiento automtico:
Iniciar numeracin de ID
automtica:
Vectores continuos:
Generar residuales:
Modelo de antena:
Tipo de efemride:
Frecuencia:
Forzar flotante:

15.0 grado
S
AUTO0001
No
S
Automtico
Automtico
Mltiples frecuencias
No

Criterios de aceptacin
Componente del vector

Indicador

Fallida

Precisin horizontal >

0.050 m + 1.000 ppm

0.100 m + 1.000 ppm

Precisin vertical >

0.100 m + 1.000 ppm

0.200 m + 1.000 ppm

Fecha:26/08/2015 05:48:27 p.m.

Proyecto:

93 de 94

Trimble Business Center

CONCLUSIONES DE LA GEOREFERENCIACION

a)

El trabajo geodsico est referido al Marco de Referencia Terrestre Internacional 2000


(ITRF2000) del servicio Internacional de Rotacin de la Tierra (IERS) que es el Sistema
Geodsico de Referencia Oficial para el Per.

b)

El modelo geoide utilizado para el post-proceso es el EGM 96, la cota correspondiente


al punto de control LOSA es de 4305.048m.

c)

Se ha realizado el enlace a la Estacin de orden 0 del receptor base del IGN.

d)

Se han obtenido puntos de Orden C-1.

e)

La precisin obtenida en los puntos, sta por encima de 1/100 000. Lo cual garantiza la
confiabilidad de los puntos, para el desarrollo de proyectos de ingeniera.

f)

La zona levantada se encuentra enteramente en la Zona UTM 18 Sur.

g)

Los valores del PDOP en las mediciones tuvo una fluctuacin de entre 1 y 2.8 Lo cual
determin una buena geometra de los satlites en la toma de datos.

h)

Para el Post procesamiento se utilizaron satlites de la constelacin GPS y Glonass.


Teniendo en promedio seales de 15 satlites en las mediciones.
*Tener presente los tres pilares para las campaas geodsicas:

Respaldo. Contar con sistemas para respaldar los archivos frecuentemente (una vez
al da al menos).

Continuidad. Capturar datos en todo momento (incluso cuando se hagan


detenciones para comer).Por lo menos, mantener el receptor activo para que
mantenga un buen rastreo de las seales recibidas.

Visibilidad. Evitar las obstrucciones locales, especialmente las que provoca uno
mismo con el cuerpo, el vehculo u otro elemento que utilice en terreno (otros
equipos, mochilas, etc.)

94 de 94