DATE:-13/05/2011
DAY-1
BUTT JOINTS (II) T JOINTS (III) LAP JOINTS (IV) CORNER JOINTS (V)OPEN
CORNER JOINTS
CLOSED CORNER JOINTS (VII) EDGE JOINTS.
1-3
WELDING INSPECTION
WELDING INSPECTOR SHOULD BE: ---------(1)FAMILIAR WITH THE STANDARDS, RULES AND SPECIFICATION RELEVANT FOR THE
FABRICATION WORK BEING UNDERTAKEN. (THIS MAY INCLUDE NATIONAL
STDS.CLIENT SPECIFICATION/STANDARDS AND THE COMPANY S OWN IN HOUSE
STANDARDS, INTERNATIONAL STDS.).
(2) FAMILIAR ABOUT THE WELDING PROCESSES/PROCEDURES TO BE USED IN
PRODUCTION.
(3)OF HIGH NEAR VISUAL ACUITY, PROFESSIONAL ATTITUDE, IMPARTIAL AND
CONSISTENCE.
(4)GOOD VISION, ABILITY TO MAINTAIN RECORD, KNOWLEDGE OF TESTING
METHODS.
IMPORTANT QUALITIES AND CHARACTERISTICS OF WELDING INSPECTOR:
------------------(1)HONESTY.
(2) A GOOD STANDARD OF LITERACY AND NUMERACY.
(3)A GOOD LEVEL OF GENERAL FITNESS.
(4) SHOULD BE HIGHEST LEVEL OF INTEGRITY, PROFESSIONALISM, COMPETENCE,
CONFIDENCE AND COMMITMENT.
(5) SHOULD BE PRACTICAL EXPERIENCE OF WELDING INSPECTION.
(6)COMMUNICATION SKILLS, RECORD KEEPING SKILLS, SHOULD BE ANALYTICAL,
DEDICATED, RESPECTED, SAFETY CONSCIOUS, DECISIVE, INQUISITIVE.
DUTIES OF WELDING INSPECTOR: ---(1)BEFORE WELDING
(2)DURING WELDING
(3)AFTER WELDING(INCLUDING REPAIR)
(1)BEFORE WELDING:--------------(I)SAFETY (II) DOCUMENTATION:--MATTERIAL TEST CERTIFICATE, DRAWINGS,
SPECIFICATION/REV- DATE, WELDER APPROVALS CERTIFICATES, PROCEDURES, WPS,
CONSUMABLE CERTIFICATES.
(III)CHECK WELDING EQUIPMENT AND ALL RELATED ANCILLARIES, (CABLE,
REGULATORS, OVANS ECT.)
(IV)CHECK PIPE/PLATE/COILS MATTERIALS /STORAGE, WELDING CONSUMABLES FOR
SIZE, CHECK ELECTRODS AND FLUX BATCHE NUMBER, HEAT NO. AND COIL NO. OF
MATTERIALS FOR PIPE.
2-3
(2)DURING WELDING:--------------(I)WEATHER CONDITIONS (MAINLY FOR SITE WORK)
(II)PRE-HEAT VALUE-HEATING METHOD, LOCATION AND CONTROL METHOD.
(III)IN PROCESS DISTORTION CONTROL (SEQUENCE OR BALANCED WELDING).
(IV)CONSUMABLE CONTROL (SPECIFICATION, SIZE, CONDITION, AND ANY SPECIAL
TREATMENTS).
(V)WELDING VARIABLE PARAMETERS (TRAVEL SPEED, VOLTAGE, CURRENT,
AMPERAGE ETC.)
(VI)WELDING GASES/PURGING GASES (PRESSURE FLOW AND CONTROL METHOD)
(VII)WELDING CONDITION FOR ROOT RUN/HOT PASS AND ALL SUBSEQUENT RUN
AND INTER-RUN CLEANING.
(XI)MINIMUM AND MAXIMUM INTER-PASS TEMPERATURE (TEMPERATURE AND
CONTROL METHOD).
(X) FULL COMPLIENCE WILL ALL ELEMENTS GIVEN ON THE WPS.
(3)AFTER WELDING: --------------------(I)PRIMARY VISUAL INSPECTION/VISUAL INSPECTION.
(II)NONDESTRUCTIVE TESTING/MANUAL UT/RADIOGRAPHIC TESTING.
(III)REPAIRS/REPAIRS PROCEDURES (NDT, WELDING, WELDER APPROVAL)
(IV)PWHT, HYDRO-FOR SAW PIPES.
(V)OFFLINE ULTRASONIC TESTING-FOR SAW PIPES.
(VI)ENDS BEVEL/ROOT FACINGFOR SAW PIPES.
(VII)RE-INSPECTION OF REPAIR AREA/FINAL VISUAL INSPECTION.
(VII)SUBMISSION ALL INSPECTION REPORT TO QC DEPARTMENT.
Inspector
Responsibilities of a Welding
TO OBSERVE---TO RECORD-----TO
COMPARE
TO OBSERVE ALL RELEVANT ACTIVITIES/ACTIONS RELATED TO WELD QUALITY
THROUGHOUT PRODUCTION
PRODUCTION TO
-------------------------------------------------------------------------------------------FINAL V
STATION
TO RECORD ALL PRODUCTION POINTS RELEVANT TO QUALITY, INCLUDING A FINAL
MAP AND REPORT SHEET SHOWING ALL IDENTIFIED WELDING IMPERFECTIONS,
ETC.
PRODUCTION TO
-------------------------------------------------------------------------------------------FINAL V
STATION
TO COMPARE ALL INSPECTION REPORTED INFORMATION WITH THE ACCEPTACE
LEVELS/CRITERIA AND CLAUSES WITH IN THE APPLIED APPLICATION STANDARD.
SUBMIT A FINAL INSPECTION REPORT OF YOUR FINDINGS TO THE QA/QC
DEPARTMENT FOR ANALYSIS AND ANY REMEDIAL ACTION.
3-3