Vous êtes sur la page 1sur 2

Commissioning Service Department

Commissioning Standard Test Formats


Description : AC Distribution Panel
Equip. No.
Drawing ref.:
Contractor :
Contract no.:
1.

Record No. :
Sheet : Page 1 of 2
Substation No :

General data & information:


Serial no
Panel no
Panel designation
Make
Circuit reference

2.
2.1.

Electrical test: As per TCS P 105, Rev 01, Item no 3.34.2


Insulation resistance Test:
Applied voltage: 1000V
Connection

Duration: 1min.
Measured insulation value

Remarks

Criteria:
2.2.

Main Circuit Resistance Test:


Circuit Reference
From

To

2.3.

Measured
Resistance ()

V
A.C.
Ammeter
Test:

Secondary injection test:


Tested by
Name:
Signature:
Date:

Witnessed by

Commissioning Service Department


Commissioning Standard Test Formats
Description : AC Distribution Panel
Equip. No.
Drawing ref.:
Contractor :
Contract no.:

Injected
secondary AC
Current (A)

Observed meter
reading (A)

Record No. :
Sheet : Page 2 of 2
Substation No :

Calculated meter
reading

% Error (At Full


scales)

% Error = (Observed meter reading-Calculated meter reading)/Full scale


reading x 100

3. Test Equipment Used


Item

Test Equipment

Freja 300

Serial Number

Tested by
Name:
Signature:
Date:

Calibration
Date

Calibration
Due Date

Witnessed by

Remarks

Vous aimerez peut-être aussi