Académique Documents
Professionnel Documents
Culture Documents
Sheetpiles
and
cofferdams
Q.1)Examine
the
statement 'types
of strata,
velocity
and
depth of water are the main
factors
which decide
the type of cofferdam.
Ans:-Cofferdams are temporary enclosures that keep away earth and water from the
construction area.The following are the types of cofferdams :(1)Plain earth banks:-These are the simplest type and are used for great heights.But the
essentiality of these types of cofferdams is good impermeable foundation and it
can impound water upto greater depths.
(2) Single wall sheet pile cofferdam:- These types are employed for small areas
and shallow depths. In this as the piles are driven the strata is partially firm and
hence this type of cofferdam is not suitable where the velocity of water is more.
(3)Braced sheet pile cofferdam:- The braced sheet pile cofferdams are used for
small areas to moderate depths. The braced sheet piles are susceptible to flood
damage because these sheet piles are supported by soldier beams wales and
struts.
(4) Double wall sheet pile cofferdam:- These types are suitable for moderate
heights and the space in between the sheet piles is filled with granular earth. Care
has to be taken in these types of cofferdams against blowingup. The excessive
velocity of water at the site may change the decision of use of this type of
cofferdam.
(5)Cellular cofferdams :- Cellular cofferdams are used where the depth of water is
great (exceeding 8 m). These are self supporting sheet pile enclosures and are
advantageous than braced cofferdams because the struts are eliminated. The
cofferdam may either rest on rock or soil. The cellular type of cofferdams are
economical in rivers and lakes.
The size of the plan area of the cofferdam is determined by the size of the
structure. The height of the cofferdam is governed by the level of water and the
potential boiling and heave at the bottom of excavation.
From the above explaination it is clear that the type of strata, velocity of water
and depth of water are the main factors that decide the type of cofferdam.
Q.2)State six different types of cofferdams, indicating
the circumstances under which each is most suitable.
Ans:-Following are some of the common types of cofferdams
(1) Earth fill cofferdam
(2) Rock fill cofferdam
(3) Rock fill crib cofferdam.
(4) Single wall cofferdam
(5) Double wall cofferdam.
(6) Cellular cofferdam.
Circumstances:- (1) Earth fill cofferdam:- The use of this variety is limited in
the vicinity where the impervious earth is available and the water depth is
shallow with low velocity of flow. This type is not used where there is danger of
overtopping of water.
(2)Rock fill cofferdam:- These are constructed by placing rock along stream.
They can be used for depths of water up to about 3 m and are suitable even in
swift waters. These are economical in places where rock is available in plenty.
(3) Rock fill crib cofferdam:- These type of cofferdams are suitable where working
space is limited, the depth of water is high,the current of water is swift and
where there is a danger of overtopping.
(4) Single wall cofferdam:- This type of cofferdam is suitable when available
working space is limited and area enclosed is small.It can be used upto a depth
of water equal to 25 m.
(5) Double wall cofferdam:- Double wall cofferdams are provided to enclose a
larger area. This type is useful where scour problems and space limitations are
prevalent.
(6) Cellular cofferdam:- These are suitable for dewatering large areas.
These can withstand overtopping of water. These type of cofferdams are used in
case of bridges with long spans.
Q.3)Compare
advantages
of
cellular
coffer
dam
with
respect to diaphragm type cofferdam.
Ans:-(1)The cellular cofferdam is stable as a single unit and can be filled as soon
as it is constructed.
(2)The cellular cofferdam will not collapse in the event of failure of adjoining cells.
(3)The cellular cofferdam can be filled with no regard to the progress of the other cells.
The cell may be filled immediately after completion of pile driving for each cell and the
construction equipment can be operated on top of it.
(4)It requires fewer number of piles per linear foot of cofferdam as compared with the
diaphragm type of an equal design.
(5)The diaphragm type cell will distort unless the various units are filled essentially
simultaneously with not over 1m or 2m of differential soil height in adjacent cells.
(6)The collapse of a diaphragm cell may fail the cofferdam whereas the collapse of a
cellular cofferdam is generally a local failure.
Q.4)Sandy strata exists below water.Depth of water is 2 m
and unit weight of saturated sand is 18 KN/m3.Excavation
between two rows of sheet piles driven through the sandy
strata is to be carried out upto a depth of 1.5m.The sheet
piles are driven to a depth of 2.5 m in the sandy strata.
To avoid blowing of sand. It is decided to flood area
between the sheet piles and carry out excavation.
2 m
of
water
d
4.5 m
1.5m
sandy
strata
2.5 m
1 m
( 2 + 2.5) x w = (1 x 18) + (d x w)
(F.S)
(2 + 2.5) x 10 = 18 + (d x 10)
1.2
d = 3.6 m.
It is very clear from the above calculations that
the depth of water to be maintained in between the
sheet piles will
be
10 cm more than the level of
water outside the sheet pile.
Therefore
depth
of
water
in
the
sheet
piles
is
minimum 3.6 m to avoid blowing up of sand.
Q.4)Compare
advantages
of
cellular
coffer
dam
with
respect to diaphragm type cofferdam.
Ans:(1)The cellular cofferdam is stable as a single unit and can be filled as soon as
it is constructed.
(2)The cellular cofferdam will not collapse in the event of failure of adjoining cells.
(3)The cellular cofferdam can be filled with no regard to the progress of the
other cells. The cell may be filled immediately after completion of pile driving
for each cell and the construction equipment can be operated on top of it.
(4)It requires fewer number of piles per linear foot of cofferdam as compared with
the diaphragm type of an equal design.
(5) The diaphragm type cell will distort unless the various units are filled essentially
simultaneously with not over 1 m or 2 m of differential soil height in adjacent cells.
(6) The collapse of a diaphragm cell may fail the cofferdam, whereas the collapse
of a cellular cofferdam is generally a local failure.
Q.6)Two rows of steel sheet piles are driven through 5 m
thick saturated clayey strata having unit weight of
18KN/m3.Below clayey strata sand layer exists.Excavation
in clayey strata upto 3m below ground level and between
the sheet piles is to be done.Determine the depth below
ground level,upto which excavation between the sheet piles
should be flooded to avoid blowing up of sand and to have
factor of safety of 1.2. Assume w as 10 KN/m3.
Ans:
Clay
3 m
2 m
sand
Assume depth of water equal to d.(See fig.above)
The depth of clayey strata below excavated part is 2 m.
5 x w = (2 x 18) + (d x 10)
(F.S)
5 x 10 = (2 x 18) + (d x 10)
1.2
d = 2.4 m.
It is very clear from the above calculations that the depth of water to be maintained
in between the sheet piles will be minimum 2.4 m to avoid blowing up of sand.
Q.7)Starting
with
single
sheet
pile
of
cantilever
type,
explain
with
sketches
how
would
you
prepare
to strengthen the same by four different methods.
Ans:
Tierod
Depth
of
Deadman
embedment
Fig.(I)
Fig.(II)
Fig.(I) Cantilever sheet pile deriving its support entirely by lateral resistance of soil
in which it is driven.
Fig.(II)Sheet pile supported by means of tie rods for additional stability
Struts.
Sheet pile.
Fig.(III)
Fig.(III)
Braced
cofferdam.
Sheet pile.
Granular fill.
Fig.(IV.a)
Plan
Fig.(IV.b)
Q.8Draw
cofferdam
functions
subjected
method
neat
and
and
to.
sketch
enlist
the
Fixed
earth
braced
systems
parts
with
of
component
forces
to
which
the
method
of
their
system
is
Soln
Struts.
Laggings
Soldier beam
are
by
excavation
hand
Soldier
from
the
the
case
as
the
horizontal
beams:- Vertical
planks
for
taking
beams
are
not
sheetpiling
placed
proceeds.(See fig.7.8)
beams
lagging.Soldier
where
timber
is
Struts:- These
are
compression
the
reactions
from
one
the
excavation.
side
reactions
required
in
used.
members
to
the
for
other
carrying
side
of
braced
external
cofferdam
forces
is
subjected
e.g. Forces
due
to
to
swift
unbalanced
current
of
water.
If
the
soft,
Q.9
soil
the
danger
Work
clayey
below
out
Cohesion
(ii)
Unit
(iii)
Stability
(iv)Depth
be
of
should
doubled
Soln
Factor
the
of
should
of
safety
following
excavation
be
for
investigated.
cutting
data:
number
cutting
be
done
under
as
0.17.
6.86 m.
if
above
the
factor
of
safety
conditions?
safety = Fc =
c
Sn..H
35
0.17 x 20 x 6.86
in
soil = 20 KN/m3
of
Fc =
Factor
is
35 KN/m2
weight
of
bottom
heaving
factor
soil. Use
(i)
What
of
the
safety
worked
out
is 1.50.
3 =
35
0.17 x 20 x H
H = 3.43 m
is to
Limit
of
the
safety
height
to
be
of
3.
cut
to 3.43 m
for
the
factor