Contracts & Law in Construction

Term Project

[ C L A I M]
Student Name :-

Mohammed Rajab Massry


Mohammed Ahmed Youssif
Raslan samy Raslan
Mohammed Saeed Elfahl

Spring 2015 2016

Table of Contents
1- Summary 3
2- Introduction
1

2.1 Description of the project 4


2.2 Information of the project... 5
2.3 The parties to the project 5
3- Subject of the Claim. 6
4- Approach to the preparation of this claim 6
5- Sequence of events 7
6- Quantifications. 8
7- Entitlement .. 10
8- Conclusion 11
9- Attachments.. 12

Summary
Demand for housing complex project for the owner and the Ministry of
Housing, Utilities and Urban Development
It was agreed under the contract between the owner and the contractor on
the implementation of a housing project in Mahalla al-Kubra
It was a delay by the owner to pay one project abstracts, and it has resulted
in slow business Altnfve of the project, followed by stops business fully
because of lack of liquidity for financial contractor has been notified the
2

owner Palmstkhals then followed by the 56 day letter of notice to the owner
and a letter to the consultant to explain the reason for the delay
I received a letter from the advisory write to the owner and we have not any
reply stating our position and it is served this claim in order to speed
payment of the value extracted Late also call for compensation in view of the
harm Annex delay also demand compensation schedule for the
implementation of the project is fully.

Introduction
- Description of the project :
Work of construction and building the new Residential
Complexes that was located on land with dimensions ( 100
125 m ) , area 7350 m2 . It is working on a 30 Residential
Building, each building consists of 10 floors , and each floor
consists of 4 department .
3

Description of concrete and architecture works according to


specification and drawing in the tender

The parties to the project :Owner : The Ministry of Housing, Utilities and Urban Development
And his deputy : Eng. Mohammed saeed Elfahl
Consultant : consultant eng. Bureau
And his deputy : Eng. Mohammed Ahmaed youssif
Contractor : Rajab company for construction and building
And his deputy : Eng. Mohammed Rajab Massry
And: Eng. Raslan samy Raslan
Information of the project :Contract Price : 85,000,000 EGP
4

Signing Date : 17 May 2013


Beginning Date : 17 June 2013
Project Duration : 3 years (( 36 month ))
Finishing Date : 16 June 2016

Subject of the Claim


The preparation of this claim due to the impact of the delay in
the payment of the required dues Abstract No. Ar212-2016 and
on 21 Feb 2016 To obtain a delay in the project and request an

increase in the duration of the project with financial compensation also .

Approach to the preparation of this claim


The approach in the preparation of this claim It had been sent Invoice
No. Ar212-2016 dated 21 Feb 2016 has been disbursed delay
demodulator us thus delaying actions have been notified discourse No.
Se183-2016 on 28 March 2016 to let us know because the delay has not
been reply to us by you and send a letter to Eng. Advisory ( consultant
eng. Bureau ) No. Se253-2016 on 10 April 2016 the reply us a speech on
12 April 2016 he has been notified by the consultant , and resulted to
slow down the business , which is supported in the schedule

Sequence of events
- Invoice submitted by [Rajab company for construction and
building] on 21/02/2016 with an explanation of the amount of work
performed and costs in the period prior to him .
- It was sending a letter to the owner in order to clarify the reason
for the delay in disbursement Abstract sent by the contractor on
18/03/2016
- It has been sent a letter consultant engineer to explain the delay in
the work site with a request to inquire about the delay in
disbursement demodulator and so on 25/03/2016
-

The answer to the letter sent by the Contractor to the consultant


so that will be paid for yourselves at the earliest possible date a
speech 27 March 2016

Quantifications :- Time Impact Study


- The Following Time Schedule explain the subject of
the claim and
the current effect on the project works progress.

- From FIDIC :

Entitlement

Conclusion
9

Based on the above study attached to the schedule explain Th


impact of the delay in payment of the extract on 05/11/201
student at increasing the duration of the project And als
appropriate financial compensation because of the failures tha
have resulted from the delay in the extract , has shown that th
effects of time So we demand financial compensation of 500,00
EGP and 3% of the value of the extract , and also an increase o
70 days , and the new date to finish the project 22.08.201
instead of 16.06.201

Contractor
Mohammed Rajab Massry

Se183-2016 :

March 2016 28 :

10

: 2016

-:


Ar212-2016 : Feb 2016 21 :
.
,,,

Ar212-2016 :
Feb 2016 21 :

: 2016

11

-:

2016

.
,,,

Se253-2016 :
April 2016 10 :

12

-:


2016 /
.
,,,

13

14