DECEMBER 2016- KPC / NJD EXCELLIUM START UP PENDING ISSUES -

ITEM
1

DESCRIPTION
Ensure as a minimum all containers are fabricated as per
approved drawing These are confined spaces Golden
Rule number 8- entry requires extra caution as discussed
with staff on site. There is no ventilation provided to allow
continuous dissipation of product fumes to ensure the HC
content is below LEL and cannot cause suffocation to any
one accessing the unit.

RESPONSIBILITY
James/ CALVIN OCHIENG

DUE DATE
15-12-2016

REMARKS/STATUS
PRIORITY.
Convert a container in NLW to
replace PS 25 and replicate for the
other KPC PS 27 and 28 using PS
using kisumu depot as the working
site.

Hose reel supports ( Kisumu and Nakuru)- All are loose


and swinging dangerously urgently have the contractor on
site to correct.

James. OUMA

13-12-2016

PRIORITY.
Instructions give works to
commence immediately.

Safety Equipments- Provide ERP equipment urgently, Spill


kits, Fire Extinguishers etc.

James . OUMA

16-12-2016

PS 25 NAKURU Depot- Forklift access- The containers are


too high for safe access and positioning of IBCs. Provide a
landing ramp.

James OUMA/CALVIN

JAN 2017

PRIORITY.
Consolidate the needs for the KPC
facilities and have an order to the
service provider.
URGENT.
Do a platform at install on site.

ALL SITES including NJD and MJT- Safety Gloves urgent


supply of EN 388 & EN 374 class Nitrile gloves availed as
consumable to all the sites, Initial estimates is about 2
pairs per staff at site/week ( 4 pairs /week per depot)

John Mikisi.

16-12-2016

PRIORITY.

ALL SITES including NJD and MJT -Breathing masks from


EN 136 full Mask most appropriate, or EN 141 Half Mask
FRPM 3M preferred; Filters to meet spec EN 141 type
A2B2E2K1.

John Mikisi.

16-12-2016

PRIORITY

ALL SITES including NJD and MJT -Working Table and


chairs for the staff at the site.

J OUMA/DDM

16-12-2016

PRIORITY- Pending Eldoret and


Kisumu.

Page | 1 OF 3
2016 OPERATIONS DEPARTMENT

DECEMBER 2016- KPC / NJD EXCELLIUM START UP PENDING ISSUES 8

ALL SITES including NJD and MJT -Cotton waste for all
sites.

J. MIKISI/DDM

13-12-2016

Can Secure contractors provide?

ALL SITES including NJD and MJT -Communication Radios


between for the staff in the operation.

J. OUMA/DDM

Jan 2017

CAPEX

ALL SITES including NJD and MJT -Provide drain pots x 2


pcs for all sites including MJT and NJD ( currently we are
using Sampling cans)

J. OUMA/DDM

16-12-2016

URGENT- Sampling cans will do.

10

ALL SITES including NJD and MJT -Provide leak proof 5L


aluminum and Brass containers. The ones supplied are
leaking at the top.

J.OUMA/C. OCHIENG

16-12-2016

URGENT- Focus on KPC depots

11

ALL SITES including NJD and MJT -Provide aluminum and


brass Jars (with handle and spout) for collecting product
from pump to measuring cylinders.
ALL SITES including NJD and MJT -Replace the Hand pump
hose with a 2 Metres stronger but more flexible chemical
resistant pipe.
Kisumu PS 28.
1. Register the Forklift and provide insurance cover
for at least 1 to be used in KPC depot
2. Power supply to the container an issue.
3. Monitor PS 28 KRA reaction on product Name
change.
Nakuru PS 25.
1. Firm a contract with a reliable forklift service
provider only one contractor available Mr john.
2. Provide a safe platform over the drain, relocate
the container to the originally agreed position
away from the drain and provide an all weather
access road for placement of the IBCs.
3. Discuss with Network to allow storage of Empty
and full IBCs at the Free Area TSS. Construct a
storage shed.

J.OUMA/C. OCHIENG

16-12-2016

J.OUMA/C. OCHIENG

Jan 2017

Send the sample from Eldoret for


replacement.

P.KAMAU

Jan 2017

HR to register the Forklift

12

13

14

J
OUMA/CALVIN/OPM/DDM

Page | 2 OF 3
2016 OPERATIONS DEPARTMENT

13-12-2016
and on
Jan 2017

Jan 2017

Immediate

Extend SK Ngangas contract to


cover other areas.

DECEMBER 2016- KPC / NJD EXCELLIUM START UP PENDING ISSUES 4. Relocate the injection to Free area station due to
congestion.
15

16

17

Eldoret PS 27.
1. Provide an all weather access road to the
container for placement of the IBCs.
2. Construct/Allow a storage Shed for additives in
the New LPG common User storage Area west of
the New BLF at PS 27.
3. Firm a contract with a reliable forklift service
provider
Disposal of IBCs /Navi cubes.
Identify contractors for safe disposal of IBCs at sitecontainers can not be re-used for lubes activity.
Provide second set of plastic measuring cylinders. 5L

review

J.OUMA/CALVIN/DDM
Jan 2017

ENGG to visit site and define the


needs.
As above

TBA
JAN 2017
HSSEQ

J.Ouma/DDM

Page | 3 OF 3
2016 OPERATIONS DEPARTMENT

Jan 2017

Extend SKs contract to cover


Eldoret
Incinerate the IBCs after use.

Replace as required