Académique Documents
Professionnel Documents
Culture Documents
I. INTRODUCTION
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING
participation of generators/sources, not only depend on their relative sensitivity, but also on their bid price for up/down regulation to alleviate congestion. The most sensitive zones have been
identified as the union of most sensitive zones obtained on the
basis of real and reactive line flow sensitivity indexes separately.
The impact of optimal rescheduling of generators and capacitors
has been demonstrated in congestion management. The effectiveness of the proposed method has been tested on 39-bus New
England system and a 75-bus Indian system.
555
(15)
(16)
(1)
For determination of TCDFs, the following Jacobian relationship has been used:
(2)
(17)
Neglecting
as:
and
(3)
(23)
Similarly, the QTCDFs are defined as the change in the reactive power flow
in a transmission line- connected between bus- and bus- due to unit change in the reactive power
injection
at bus- and can be written as
(4)
(5)
(26)
(6)
(27)
Equations (5) and (6) can be rewritten as
or
(7)
(8)
(28)
556
(29)
Equations (28) and (29) can be rewritten as
(30)
(31)
where
Minimize
(32)
subject to
(33)
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING
and
(38)
557
(39)
where
is the number of generators participating in conis the MVA flow limit of a line
gestion management,
and
are the total
connected between bus- and bus- ,
real and reactive power loss, which have been expressed using
is the set of capacitors and
are
exact loss formula [14].
and
are the origthe number of buses in the system.
inal real and reactive power flow in line- (between bus- and
bus- ) caused by all of the transactions requesting the transmisis the real power adjustment of generator at
sion service.
is the change in the voltage due to
bus- .
change in the reactive power injection.
is the incremental or
decremental price bids submitted by generator- . These are the
prices at which generators are willing to adjust their real power
outputs. The second term in the objective function is the opportunity cost of the generator defined as [15]
(40)
where
is the cost of active power generation and is modeled
by a quadratic function as
(41)
where
The second and third terms in (38) and (39) incorporate the
change in the losses in the system occurring due to redispatch
of the generators and capacitors.
558
Fig. 1. Congestion zones based on PTCDF for 39-bus New England system.
TABLE I
ZONES (BUS NO., PTCDF) FOR 39-BUS NEW ENGLAND SYSTEM
Fig. 2. Congestion zones based on QTCDF for the 39-bus New England
system.
TABLE II
ZONES (BUS NO., QTCDF) FOR THE 39-BUS NEW ENGLAND SYSTEM
gested line, are shown in Fig. 1. The congestion zones are decided on the basis of PTCDFs and accordingly the SO selects
most sensitive congestion zones for managing congestion. The
PTCDFs for the congested line 34-14 corresponding to each bus
are given in Table I for the four different zones.
The zone 1 is the most sensitive zone with larger magnitude
and strongest nonuniform distribution of PTCDFs. The magnitudes of PTCDFs in zone 4 are higher than zone 2 and zone 3
but due to uniform distribution of PTCDFs, the zone 4 is considered as the least sensitive zone. Fig. 2 shows the zones based on
the QTCDFs for the congested line 34-14. The reactive power
flow indexes are given in Table II. The combined zones based on
both real and reactive power flow sensitivity indexes are shown
in Fig. 3. The most sensitive combined zone (zone-1) has been
taken as the union of the most sensitive zones obtained from the
real and reactive power flow sensitivity indexes, separately.
The next sensitive zones (zones 2, 3, and higher) have been
formed, in sequence, by taking union of the remaining buses in
the respective zones obtained from the real and reactive power
flow sensitivity indexes. Since the sensitivity of both real and reactive power sources is with respect to the flow in the congested
line, the zones (clusters of buses) formed are almost overlapping.
Different combinations of market structures comprising pool
model and mix of pool plus bilateral and multilateral contracts
taken for study are
P:
pool model without bilateral and multilateral contracts;
C1: pool model with one bilateral contract between buses
335;
C2: pool model with two bilateral contracts between buses
335 and 821;
C3: pool model with one multilateral contract between
buses 335, 36;
Fig. 3. New combined congestion zones for the 39-bus New England system.
C4:
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING
559
TABLE III
CONGESTION COSTS (DOLLARS PER HOUR) FOR 39-BUS NEW ENGLAND
SYSTEM FOR DIFFERENT CASES
Fig. 5.
560
TABLE IV
REACTIVE POWER RESCHEDULING (IN PER UNIT) FOR CASES 2 AND 3
TABLE V
REACTIVE POWER RESCHEDULING (IN PER UNIT) FOR CASE 4
Fig. 10.
Fig. 11.
Fig. 12.
power support from capacitor and change in reactive power outputs of generators for the case 4 are given in Table V.
From Tables IV and V, it is observed that capacitors are required to generate less MVAR when generators are also providing additional reactive support in the system. The generators
are subjected to lower reschedule of reactive power generation
when the capacitor is supporting the reactive power requirement
in the system.
B. Seventy-Five-Bus Indian System
For this system, the combined congestion zones based on the
real and reactive power flow sensitivity indexes for a line of interest 2641 are shown in Fig. 9. The system has been divided
into three zones with zone 1 as the most sensitive zone. It has
been assumed that SO selects generators G3, G12, and G13 from
the most sensitive zone 1 to participate in the congestion management based on their qualifying bids in an open market.
Different combinations taken for the study are:
P:
pool model without bilateral and multilateral contracts;
C1: pool model with one bilateral contract between buses
327;
C2: pool model with three bilateral contracts between
buses 327, 1224, and 1355;
C3:
KUMAR et al.: A ZONAL CONGESTION MANAGEMENT APPROACH USING REAL AND REACTIVE POWER RESCHEDULING
561
TABLE VI
CHANGE IN REACTIVE GENERATION (IN PER UNIT) (CASE 2)
Fig. 13.
Fig. 14.
Fig. 15.
system.
From Fig. 10, it is found that the congestion cost is less for
case 2 compared with case 1 and the congestion costs are quite
less as compared to those obtained from dc model [11]. From
Figs. 11 and 12, it is observed that the generators are subjected
to lower real power rescheduling in the presence of reactive support from the generators. The change in reactive power output
of generators for all of the transactions for case 2 is given in
Table VI.
TABLE VII
CPU TIMES IN SECONDS
C. Multicongestion Case
In a power system network, there may be more than one
line getting congested simultaneously. The studies for the multicongestion cases were carried out for both 39-bus and 75-bus
system. However, the results for only 39-bus system are being
presented. For the simulation of a multicongestion case (case
mc), it is assumed that two lines 3414 and 3621 are congested
simultaneously. The combined zones based on real and reactive
TCDFs are shown in Fig. 13. The zone 1 and the zone 2 are
the most sensitive zones. For managing the congestion, generators 3, 8, 10 were selected from zone 1 and generators 4 and 6
were selected from zone 2, based on their qualifying bids in the
market. The congestion costs for the multicongestion case along
with those for case 1 are shown in Fig. 14 for the transactions P,
C1 to C5. It is observed that the congestion cost is significantly
high for the multicongestion case. The change in optimal real
power generation of the generators participating in the congestion management is shown in Fig. 15.
D. Computational Time
In order to compare the computational time taken by the proposed ac distribution factors-based method with the dc distribution factors based method, CPU times were computed on a
Pentium IV, 1.9-GHz, 512-RAM computer. The CPU time for
calculation of TCDFs (only real power TCDF in the dc method
562
The reactive power support utilized from an optimally located capacitor in the system is more effective in reducing
congestion cost as compared to additional reactive power
support taken from the generators.
The amount of rescheduling of real power transactions is
reduced in the presence of reactive support considered in
the system for congestion management.
The proposed approach is computationally efficient and
simple as it utilizes the sensitivity factors, which can be easily
updated.
REFERENCES
[1] Federal Energy Regulatory Commission (FERC), Regional Transmission Organizations, Washington, DC, Dec. 20, 1999.
[2] W. W. Hogan, Contract networks for electric power transmission, J.
Regul. Econ., vol. 4, pp. 211242, Sept. 1992.
[3] F. C. Schweppe, M. C. Caramanis, R. D. Tabors, and R. E. Bohn, Spot
Pricing of Electricity. Norwell, MA: Kluwer, 1988.
[4] H. Chao and S. Peck, A market mechanism for electric power transmission, J. Regu. Econ., vol. 10, pp. 2529, July 1996.
[5] F. D. Galiana and M. Ilic, A mathematical framework for the analysis
and management of power transactions under open access, IEEE Trans.
Power Syst., vol. 13, pp. 681687, May 1998.
[6] R. S. Fang and A. K. David, Transmission congestion management in
an electricity market, IEEE Trans. Power Syst., vol. 4, pp. 877883,
Aug. 1999.
[7] H. Glavisch and F. Alvarado, Management of multiple congested conditions in unbundled operation of power systems, IEEE Trans. Power
Syst., vol. 13, pp. 10131019, Aug. 1998.
[8] H. Singh, S. Hao, and A. Papalexopoulos, Transmission congestion
management in competitive electricity markets, IEEE Trans. Power
Syst., vol. 13, pp. 672680, May 1998.
[9] S. C. Srivastava and P.Perveen Kumar, Optimal power dispatch in
deregulated market considering congestion management, in Proc.
Int. Conf. Electric Utility Deregulation and Restructuring and Power
Technologies, vol. 47. London, U.K., Apr. 2000, pp. 5359.
[10] S. N. Singh and A. K. David, Optimal location of FACTS devices for
congestion management, Int. J. Elect. Power Syst. Res., vol. 58, pp.
7179, 2001.
[11] C.-N.Chien-Ning Yu and M. Ilic, Congestion clusters-based markets
for transmission management, in Proc. 1999 IEEE Power Eng. Soc.
Winter Meeting , New York, Jan. 1999, pp. 111.
[12] N. G. Hingorani and L. Gyugi, Understanding FACTS: Concepts and
Technology of Flexible AC Transmission Systems. Piscataway, NJ:
IEEE Press, 2000.
[13] A Users Guide, GAMS Development Corp., 1999.
[14] A. J. Wood and B. F. Wollenberg, Power Generation, Operation and
Control. New York: Wiley, 1996.
[15] Y. Dai and Y. X. Ni et al., A study of reactive power marginal price in
electricity market, Elect. Power Syst. Res., vol. 57, pp. 4148, 2001.