PSF 4f

Defects Liability Certificate


Contractor

Contract Number

Address

Consultant File Number


/

Date

/
of

Separable Portion

Defects Liability Certificate for


Contract
1.

I hereby certify in accordance with Clause 11.3 of the Conditions of Contract for
Building and Civil Engineering Construction (NZS 3910:2003) that the Contractor has
remedied any minor omissions or minor defects under Clause 10.4.1 NZS
3910:2003 and that the Period of Defects Liability for the whole of the Contract
Works or Separable Portion as described and included in the above named contract
has expired on ....

2.

In accordance with Clause 12.4 of NZS 3910:2003 you are now required to submit to
the Engineer a final account of all the Contractors payment claims in relation to the
contract.

Signed

Received
Engineer to Contract

Date

Contractor
/

Date

(Please sign and Return Copy to Engineer)

Distribution (Indicate as Appropriate)


Contractor

Contractors Duplicate Copy


(for Signing and Return)

Principal

Engineer

Contract File

PSF 4f
Version 1, March 2009