HEAD
REGULATOR
500.00 m
350.00 m
500.00 m
1.00 m
2.20 m
1.50 m
Section A-A
Fig:2 Detail section of a single diversion wall
Now For the Long wall along the flow (considering the section A-A),
Total volume of earth filled gunny bags
So, no. of bags required per 850 m length of wall
[ it is assumed that 70% of the bags used for the 500 m long wall will be used for the adjacent wal
considering 850m wall length.]
Now For the Short walls perpendicular to the flow (considering the section B-B),
No. of intermediate walls per 500 m long wall
Total volume of earth filled gunny bags
So, no. of bags required per 850 m length of wall
So total no of gunny bags required per 850 m length of wall
Total Number of gunny bags required for full reach (0.00 -57.096 km)
Now total cost for Diversion Work involves the following phases1) Cost for supply, earth filling, sewing & laying for each bag
(As per Item No. 30, Chapter 21, Page No. 28, UPID SOR, Kanpur Commissionary)
So, total cost
(9.5*3647971)
2) Cost for shifting the previously placed bags by 2m - 3m at same chainage but changing the flow
( Here, only handling of earth filled bags are to be considered)
Let us assume, One person can handle and relay 40 bags per hour / 320 bags a day
As per SL. No.1, Chapter-1, Pg-3, UPID SOR, Kanpur Commissionary,
daily wages rate/labour
So rate for handling and laying bags in adjacent place for
Add 15% for contractor's profit
So, total cost =
(63.25*3647971)/100
3) Cost for moving 70% of reusable bags from the 500 m stretch to adjacent 350 m stretch by bull
It is assumed that 70% of Bags can be reused in next season and can be utilised in 70% * 500m le
As per Item. No.1, Chapter-2, Pg-5, UPID SOR, Kanpur Commissionary,
rate for carriage of materials by bullock cart /M.T
Vol. of one bag (1cft )
Density of earth
So, Weight of one bag
So the number of bags that can be moved @ rate Rs. 118/Total cost for moving 70% usuable bags
[The cost include loading, unloading and stacking.]
4) Cost for shifting the previously placed bags by 2m - 3m at same chainage but changing the flow
The rate for this item will be same as Item no. 2
So, Total cost for laying earth fill bags in
(70% of 34655724.5)*63.25/100
adjacent 350 m will be,
6) Cost for dewatering from local pockets after closing the gate
Power of Pump
Efficiency of pump set ()
Head against which mortor has to work (H)
Assuming losses in the conveyance system
So,effective head on the pump (H ef)
So, dischrge capacity of the pump,
= (735 )/(
_ ) ^2
= (735 )/(
Average bed width in this stretch
_ ) ^2
Length of the stretch
Assuming average depth of water inside the diversion wall
So,total volume of water to be displaced from local pockets after closing the gate as well
as the seeping water during construction
Assuming total number of 5HP pump provided
So required time for dewatering with 1Nos of 5HP pump
Hiring charges for 5HP Diesel Pump including P.O.L & Operator
(As per Lucknow Zonal Schudule of Rates, Irrigation Department UP)
So total cost of Dewatering
8) unlined canal excavation with cutting slope section must reach above water level in one period
of construction.
9) The work for IP and non-IP shall be second year of construction in that reach
10) In case of lining work shall be taken up with completion of earth work and to reach above wate
in the same working year. However proper compaction of side slope as bed of lining is essential.
11) The excavation work where necessary for widening shall be taken up with JCB or such excavato
shall be done with labours using section and level format.
12) The diversion wall considered here with construction with earth filled second hand gunny bags
job shall be done with unskilled and semiskilled labours.
13 ) Agency may choose diversion by sheet piles or any other suitable means as per his choice. In
estimate / tender the work has been considered with earth filled gunny bags but incase of otherv m
the agency shall make the rate with proper approval of the client's authority.
14) Diversion wall shall be completely removed at the end of work i.e., between october to decemb
in third working year to allow water to flow full section in third year and irrigation shall be available
early February in third working year.
1) Reconnaissance visit of contractor and finalising site offices, labours camp and yard, first aid cen
It should be completed in 7 days from 1st October.
be 5/6 labour camps from where the labours shall be transported every morning.
Cement and steel can be kept in contractors 3 stack yards and sand and stone chips can be dumpe
site.
2) construction of labour camps and first aid centres within next 10 days.
3) Removal of shrubs and bushes by Dozers along with motor graders both of which shall also be n
for approach roads. This work should start by 3rd week of October.
4) Arranging gunny bags and dumping at sites from 3rd week of Octoberber and to complete by 3r
week of November for 50% work
5) Mobilisation of machinary from 10 th October within 3 weeks
6) Mobilisation of Labour from !st week of November and to complete by end of November.
( This time availability of such huge labour to construct diversion bund may be difficult
paddy harvesting season).
(Availability of labour also may be difficult for NAREGA works.)
7) The Head Regulators at 0.00 shall be closed by 4th week of October
and remain closed up to end of November.
8) Sundrying of Canal Bed for 5 days including pumping local pockets to complete
9) The Template for canal profile and bed level with CBW ( 1:6 ) shall start from 1st wee
end of November for each 500 m but full section of canal at 30 m c/c and two levels at c
If work is done by full closure then only two levels at corners and only one at center.
10) Construction of Diversion Bund from 1st week of November and to complete by 3rd
at all 500 m locations.
( Time analysis given separately )
11) Machine excavation to start from 1st November
12) Optimum water is released on end of construction of Bund by end of 3rd wk. of Nov
13) Earthwork excavation and shaping by labours by mid november
14) Completing canal in design shape by mid February
15) HR closed for 7 days after one side construction complete
16) The same wall to be displaced by 3m and internal cross walls to be completed on ot
walls within 6 days ( Time analysis given separately )
17) Machime to work on other side after completion of the 1st side
18) Lbours to start work on other side from 3rd week of February and to complete by en
19) water will be released on 16 th June for full section the bags in position
20) IP work shall start from next year.
21) Lining to be completed with the completion of canal section after full compaction of
side slope including laying of Geotextiles and sand bed.
( Where lining necessary but not for 1st Tender of WAB).
22) Structure work to cvontinue with canal work and if necessary ring bund may be con
up to bearing level of pier & abutment .
23) Deck and other superstructure work to complete by next year.
WAB
0.00 to 57.096 km
3647971
57.096 to 113.632 Km
Length =
57 km
( Approx )
Av. BW =
31 m
FSD Av.
2.15 m
Number of Bags will be more or less same as 1st part of 1st reach
3647971
156.969 to 210.304 Km
Length =
Av. BW =
Av. FSD
53.335 km . Approx
19 m
1.8 m
524 m
2.2
m
C/S =
2.2
1.2
0.6
210.304 to 242 km
Length =
31.696 km
Av. BW
11.25 m
Av.FSD
1.45 m
Length of 500 m bund =
C/S
0.8
2
1.44 m
524 m
Int. Bund
0.6
1.8
0.8
Vol. of wall =
28816.69807 m3
1017229.44189176
No, of earth filled bags =
1017229
10980218
12078240
FBC
Length =
Av. BW =
Av. FSD
0 to 31
31 km
24.5 m
2.2 m
1
2.6
C/S =
1.6
Length of 500m bund =
3.38
526 m
Int. Bund
0.6
0.6
C/s
1817.57 M3
66287.84706 M3
2339961 nos.
0.36
2339961.00117647
31 to68.073
Length =
Av. BW
Av. FSD
37.1 m
28.6 m
2.3 m
1
2.7 C/S
1.6
3.51
Int. Bund
0.6
0.6
Volm. Of Bund =
83219 m3
Number of Bags =
2937626.43077647
2937626.431
68.073 to 116.667
Length =
Av. BW
FSD
48.7 km
17.4
1.93
1
2.3
C/S
2.875 m2
1.5
116.667 to 169.6
Length
Av. BW
FSD
52.9 km
12.6
1.6
1
2
C/S
Volm of Bund =
inclu. Internal bund
number of bags=
65372.6998 m3
2307656.302
10665865
11732451.0422447
WAB
Tender 1
3647971
Tender 2
3647971
Tender 3
2667047
Tender 4
1017229
1823985.5
A group of persons ( 1/3 person filling earth, 1/3 person stitching and one laying it ) in 3
In one day they can do
160
no. of persons engaged =
1.7
1.7 nos persons in one day lay
160
Deep Foundation
Construction of Bored Pile including initial load test
Pile Cap
Pier and Abutment up to Bearing Level
2nd Year
Time for rebuild the next 350 m Bund with same earth filled bags N
OLD WORK
STRUCTURES
Deck , Approach Slab etc to be completed
NEW WORK
for remaining 50% of the Tender ;
Same as earlier.
DIVERSION WORK
imate including Cost Analysis)
350.00 m
500.00 m
530.00 m
0.60 m
1.00 m
Section B-B
=
51449.75 cft
=
51450 no.s
wall will be used for the adjacent wall of 350 m. So no of bags are determined
9 no.s
2859.3 cft
2859 no.s
54309 no.s
3647971 no.s
ng phases-
pur Commissionary)
9.50
=
=
34,655,724.50
t same chainage but changing the flow from one side to other.
100 bags
dd 15% for contractor's profit
63.25*3647971)/100
175.00
=
=
=
55.00
63.25
2,307,341.66
350.00 m
118.00
0.028 cum
1800 kg/M3
51 kg
20 no.s
15,066,120.23
t same chainage but changing the flow from one side to other.
=
63.25
f 34655724.5)*63.25/100
en in Sl.No.-2(b), Chapter-3,
1,615,139.16
=
=
103341.954674221 m3
8,732,395.17
=
=
=
=
=
5 HP
70 %
5.00 m
20 %
0.044 m3/s
158.4 m3/hr
6.00 m
or
ent UP)
=
=
=
31.00 m
57.096 Km
0.200 m
353995.200 m3
=
=
1
2235 hrs
=
=
100 Rs/hr
223,500.00
M3
all be followed.
ext 10 days.
r graders both of which shall also be necessary
A works.)
week of October
by next year.
nos.
m2
53.335
1
cft
0.6
cft
nos
nos
m2
m2
cft
m2
cft
3080620.85021176 cft
m2
2307656.30169412 cft
23810691
6039120.03 nos.
der of WAB =
2006384.05 nos
1823985.5 bags =
mber of stretch =
d in 20 days
nstruction of 500m bund =
( Cost included in estimate )
1072932.6471
34
0 persons =
1 minute
4.7499622396
miscellaneous uncertainty
oundfation -
6 days
120 days
10 days
60 days
200 days
om cente.
AAAA
person days
nos
nos
one bag
HEAD
REGULATOR
500.00 m
350.00 m
500.00 m
1.00 m
2.50 m
1.50 m
Section A-A
Fig:2 Detail section of a single diversion wall
Now For the Long wall along the flow (considering the section A-A),
Total volume of earth filled gunny bags
So, no. of bags required per 850 m length of wall
[ it is assumed that 70% of the bags used for the 500 m long wall will be reused for the adjacent w
considering 850m wall length.]
Now For the Short walls perpendicular to the flow (considering the section B-B),
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
No. of intermediate walls per 500 m long wall
Total volume of earth filled cement bags
So, no. of bags required per 850 m length of wall
So total no of cement bags required per 850 m length of wall
Total Number of cement bags required for full reach
Now total cost for Diversion Work involves the following items of works1) Cost for supply, earth filling, sewing & laying for each bag
(As per Item No. 30, Chapter 21, Page No. 28, UPID SOR, Kanpur Commissionary)
So, total cost
(9.5*4170521)
2) Cost for shifting the previously placed bags by 2m to 3m (as necessary) at same chainage to al
( Here, only handling of earth filled bags are to be considered)
Assuming, One person can handle and relay 40 bags per hour /
As per SL. No.1, Chapter-1, Pg-3, UPID SOR, Kanpur Commissionary,
daily wages rate/labour
(175/320)*100
Adding 15% for contractor's profit
(63.25*4170521)/100
3) Cost for moving 70% of reusable bags from the 500m stretch to adjacent 350m stretch
by bullock cart It is assumed that 70% of Bags can be reused in
next season and can be utilised in 70% * 500m length
As per Item. No.1, Chapter-2, Pg-5, UPID SOR, Kanpur Commissionary,
rate for carriage of materials by bullock cart /M.T
Vol. of one bag (1cft )
Density of earth
So, Weight of one bag ,
So the number of bags that can be moved @ rate Rs. 118/Total cost for moving 70% usuable bags
[The cost include loading, unloading and stacking.]
4) Cost for shifting the previously placed bags by 2m - 3m at same chainage but changing the flow
The rate for this item will be same as Item no. 2
So, Total cost for laying earth fill bags in
(70% of 39619950)*63.25/100
adjacent 350 m will be,
6) Cost for dewatering from local pockets after closing the gate
Power of Pump
Efficiency of pump set ()
Head against which mortor has to work (H)
Assuming losses in the conveyance system
So,effective head on the pump (H ef)
So, dischrge capacity of the pump,
= (735 )/(
_ ) ^2
57.096 Km
38.00 m
2.215 m
350.00 m
500.00 m
530.00 m
0.60 m
1.00 m
Section B-B
single diversion wall
=
58465.625 cft
=
58466 no.s
g wall will be reused for the adjacent wall of 350 m. So no of bags are determined
=
=
=
9 no.s
3621.78 cft
3622 no.s
62087 no.s
4170521 no.s
g
npur Commissionary)
=
=
9.50
39,619,950.00
(as necessary) at same chainage to allow the flow from one side to other.
sionary,
175.00
(175/320)*100
55.00
=
=
63.25
2,637,855.00
issionary,
=
=
=
=
=
=
350.00 m
118.00
0.028 cum
1800 kg/M3
51 kg
20 no.s
17,224,252.00
at same chainage but changing the flow from one side to other.
=
63.25
of 39619950)*63.25/100
en in Sl.No.-2(b), Chapter-3,
or
ment UP)
1,846,499.00
=
=
118145.07082153 m3
9,983,259.00
=
=
=
=
=
5 HP
70 %
5.00 m
20 %
0.044 m3/s
=
=
=
=
158.4 m3/hr
38.00 m
57.096 Km
0.200 m
6.00 m
433929.600 m3
=
=
1
2740 hrs
=
=
100 Rs/hr
274,000.00
=
=
=
1900 m3
12 Nos/ Hour
475.2 m3/Hour
4 Hour
he dewatering process within 4 hr so that the canal bed can be allowed for sun drying
(57.096/0.85)
tal stretch
ate same as Sl. 6)
=
=
=
=
=
2.67 Pump-Hours/Day.
420 Days
68 Nos
76160 Pump-Hours
7,616,000.00
SL
No.
Description of Item
Ref. No.
Quantity
4170521
4170521
Analysed Rate
2919365
2919365
Analysed Rate
118146.00
Lucknow Zonal
SOR, UPID
2740
Lucknow Zonal
SOR, UPID
76160
Estimated Cost
Add Contigency Charge @ 3%
Total Estimated Cos
Unit
Rate
(Rs.)
Each
9.50
100
Bags
63.25
20
Bags
118.00
100
Bags
63.25
1,846,498.00
Cum
84.50
9,983,337.00
Per
Hour
100.00
274,000.00
Per
Hour
100.00
7,616,000.00
Estimated Cost =
ntigency Charge @ 3%=
Total Estimated Cost=
Amount
(Rs.)
39,619,950.00
2,637,855.00
17,224,254.00
79,201,894.00
2,376,057.00
81,577,951.00
HEAD
REGULATOR
500.00 m
350.00 m
500.00 m
1.00 m
2.20 m
1.50 m
Section A-A
Fig:2 Detail section of a single diversion wall
Now For the Long wall along the flow (considering the section A-A),
Total volume of earth filled gunny bags
So, no. of bags required per 850 m length of wall
[ it is assumed that 70% of the bags used for the 500 m long wall will be reused for the adjacent w
considering 850m wall length.]
Now For the Short walls perpendicular to the flow (considering the section B-B),
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
No. of intermediate walls per 500 m long wall
Total volume of earth filled cement bags
So, no. of bags required per 850 m length of wall
So total no of cement bags required per 850 m length of wall
Total Number of cement bags required for full reach
Now total cost for Diversion Work involves the following items of works1) Cost for supply, earth filling, sewing & laying for each bag
(As per Item No. 30, Chapter 21, Page No. 28, UPID SOR, Kanpur Commissionary)
So, total cost
(9.5*3646165)
2) Cost for shifting the previously placed bags by 2m to 3m (as necessary) at same chainage to al
( Here, only handling of earth filled bags are to be considered)
Assuming, One person can handle and relay 40 bags per hour /
As per SL. No.1, Chapter-1, Pg-3, UPID SOR, Kanpur Commissionary,
daily wages rate/labour
(175/320)*100
Adding 15% for contractor's profit
(63.25*3646165)/100
3) Cost for moving 70% of reusable bags from the 500m stretch to adjacent 350m stretch
by bullock cart It is assumed that 70% of Bags can be reused in
next season and can be utilised in 70% * 500m length
As per Item. No.1, Chapter-2, Pg-5, UPID SOR, Kanpur Commissionary,
rate for carriage of materials by bullock cart /M.T
Vol. of one bag (1cft )
Density of earth
So, Weight of one bag ,
So the number of bags that can be moved @ rate Rs. 118/Total cost for moving 70% usuable bags
[The cost include loading, unloading and stacking.]
4) Cost for shifting the previously placed bags by 2m - 3m at same chainage but changing the flow
The rate for this item will be same as Item no. 2
So, Total cost for laying earth fill bags in
(70% of 34638568)*63.25/100
adjacent 350 m will be,
6) Cost for dewatering from local pockets after closing the gate
Power of Pump
Efficiency of pump set ()
Head against which mortor has to work (H)
Assuming losses in the conveyance system
So,effective head on the pump (H ef)
So, dischrge capacity of the pump,
= (735 )/(
_ ) ^2
57.000 Km
30.67 m
2.140 m
350.00 m
500.00 m
530.00 m
0.60 m
1.00 m
Section B-B
single diversion wall
=
51449.75 cft
=
51450 no.s
g wall will be reused for the adjacent wall of 350 m. So no of bags are determined
=
=
=
9 no.s
2922.87 cft
2923 no.s
54373 no.s
3646165 no.s
g
npur Commissionary)
=
=
9.50
34,638,568.00
(as necessary) at same chainage to allow the flow from one side to other.
sionary,
175.00
(175/320)*100
55.00
=
=
63.25
2,306,200.00
issionary,
=
=
=
=
=
=
350.00 m
118.00
0.028 cum
1800 kg/M3
51 kg
20 no.s
15,058,662.00
at same chainage but changing the flow from one side to other.
=
63.25
of 34638568)*63.25/100
en in Sl.No.-2(b), Chapter-3,
or
ment UP)
1,614,340.00
=
=
103290.793201133 m3
8,728,073.00
=
=
=
=
=
5 HP
70 %
5.00 m
20 %
0.044 m3/s
=
=
=
=
158.4 m3/hr
30.67 m
57.096 Km
0.200 m
6.00 m
350192.606 m3
=
=
1
2211 hrs
=
=
100 Rs/hr
221,100.00
=
=
=
1533.35 m3
10 Nos/ Hour
475.2 m3/Hour
4 Hour
he dewatering process within 4 hr so that the canal bed can be allowed for sun drying
(57.096/0.85)
tal stretch
ate same as Sl. 6)
=
=
=
=
=
2.67 Pump-Hours/Day.
420 Days
68 Nos
76160 Pump-Hours
7,616,000.00
SL
No.
Description of Item
Ref. No.
Quantity
3646165
3646165
Analysed Rate
2552316
2552316
Analysed Rate
103291.00
Lucknow Zonal
SOR, UPID
2211
Lucknow Zonal
SOR, UPID
76160
Estimated Cost
Add Contigency Charge @ 3%
Total Estimated Cos
Unit
Rate
(Rs.)
Each
9.50
100
Bags
63.25
20
Bags
118.00
100
Bags
63.25
1,614,340.00
Cum
84.50
8,728,090.00
Per
Hour
100.00
221,100.00
Per
Hour
100.00
7,616,000.00
Estimated Cost =
ntigency Charge @ 3%=
Total Estimated Cost=
Amount
(Rs.)
34,638,568.00
2,306,199.00
15,058,664.00
70,182,961.00
2,105,489.00
72,288,450.00
HEAD
REGULATOR
500.00 m
350.00 m
500.00 m
0.80 m
2.20 m
1.20 m
Section A-A
Fig:2 Detail section of a single diversion wall
Now For the Long wall along the flow (considering the section A-A),
Total volume of earth filled gunny bags
So, no. of bags required per 850 m length of wall
[ it is assumed that 70% of the bags used for the 500 m long wall will be reused for the adjacent w
considering 850m wall length.]
Now For the Short walls perpendicular to the flow (considering the section B-B),
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
No. of intermediate walls per 500 m long wall
Total volume of earth filled cement bags
So, no. of bags required per 850 m length of wall
So total no of cement bags required per 850 m length of wall
Total Number of cement bags required for full reach
Now total cost for Diversion Work involves the following items of works1) Cost for supply, earth filling, sewing & laying for each bag
(As per Item No. 30, Chapter 21, Page No. 28, UPID SOR, Kanpur Commissionary)
So, total cost
(9.5*2667047)
2) Cost for shifting the previously placed bags by 2m to 3m (as necessary) at same chainage to al
( Here, only handling of earth filled bags are to be considered)
Assuming, One person can handle and relay 40 bags per hour /
As per SL. No.1, Chapter-1, Pg-3, UPID SOR, Kanpur Commissionary,
daily wages rate/labour
(175/320)*100
Adding 15% for contractor's profit
(63.25*2667047)/100
3) Cost for moving 70% of reusable bags from the 500m stretch to adjacent 350m stretch
by bullock cart It is assumed that 70% of Bags can be reused in
next season and can be utilised in 70% * 500m length
As per Item. No.1, Chapter-II, Pg-2, UPID SOR, Allahabad Commissionary,
basic rate for carriage of materials/M.T
Again this rate has to be increased by 15% for canal service roads as per Item. No.1,
Chapter-II, Pg-2, UPID SOR, Allahabad Commissionary, rate for carriage of materials/M.T.
So, increment of carriage rate for canal service road will be by,
Therefore, rate of Transporting and moving of the requisite reusable Cement Bags
Vol. of one bag (1cft )
Density of earth
So, Weight of one bag ,
So the number of bags that can be moved @ rate Rs. 118/Total cost for moving 70% usuable bags
[The cost include loading, unloading and stacking.]
4) Cost for shifting the previously placed bags by 2m - 3m at same chainage but changing the flow
The rate for this item will be same as Item no. 2
So, Total cost for laying earth fill bags in
(70% of 25336947)*63.25/100
adjacent 350 m will be,
6) Cost for dewatering from local pockets after closing the gate
Power of Pump
Efficiency of pump set ()
Head against which mortor has to work (H)
Assuming losses in the conveyance system
So,effective head on the pump (H ef)
So, dischrge capacity of the pump,
= (735 )/(
_ ) ^2
53.335 Km
19.00 m
1.800 m
350.00 m
500.00 m
524.00 m
0.60 m
1.00 m
Section B-B
single diversion wall
=
40693.84 cft
=
40694 no.s
g wall will be reused for the adjacent wall of 350 m. So no of bags are determined
=
=
=
9 no.s
1810.89 cft
1811 no.s
42505 no.s
2667047 no.s
g
npur Commissionary)
=
=
9.50
25,336,947.00
(as necessary) at same chainage to allow the flow from one side to other.
sionary,
175.00
(175/320)*100
55.00
=
=
63.25
1,686,908.00
mmissionary,
350.00 m
105.00
15.75
121.00
=
=
=
=
=
0.028 cum
1800 kg/M3
51 kg
20 no.s
11,294,945.00
at same chainage but changing the flow from one side to other.
=
63.25
of 25336947)*63.25/100
en in Sl.No.-2(b), Chapter-3,
1,180,836.00
=
=
75553.7393767706 m3
6,044,300.00
=
=
=
=
=
5 HP
70 %
5.00 m
20 %
0.044 m3/s
=
=
=
=
158.4 m3/hr
19.00 m
53.335 Km
0.200 m
6.00 m
202673.000 m3
or
ment UP)
=
=
1
1280 hrs
=
=
100 Rs/hr
128,000.00
=
=
=
950 m3
6 Nos/ Hour
475.2 m3/Hour
2 Hour
he dewatering process within 4 hr so that the canal bed can be allowed for sun drying
(53.335/0.85)
tal stretch
ate same as Sl. 6)
=
=
=
=
=
2.67 Pump-Hours/Day.
420 Days
63 Nos
70560 Pump-Hours
7,056,000.00
SL
No.
Description of Item
Ref. No.
Quantity
2667047
Analysed Rate
2667047
Analysed Rate
1866933
Analysed Rate
1866933
75554.00
Lucknow Zonal
SOR, UPID
1280
Lucknow Zonal
SOR, UPID
70560
Estimated Cost
Add Contigency Charge @ 3%
Total Estimated Cos
Unit
Rate
(Rs.)
Each
9.00
100
Bags
63.25
20
Bags
121.00
100
Bags
63.25
1,180,835.00
Cum
80.00
6,044,320.00
Per
Hour
100.00
128,000.00
Per
Hour
100.00
7,056,000.00
Estimated Cost =
ntigency Charge @ 3%=
Total Estimated Cost=
Amount
(Rs.)
24,003,423.00
1,686,907.00
11,294,945.00
51,394,430.00
1,541,833.00
52,936,263.00
HEAD
REGULATOR
500.00 m
350.00 m
500.00 m
0.80 m
1.80 m
0.80 m
Section A-A
Fig:2 Detail section of a single diversion wall
Now For the Long wall along the flow (considering the section A-A),
Total volume of earth filled gunny bags
So, no. of bags required per 850 m length of wall
[ it is assumed that 70% of the bags used for the 500 m long wall will be reused for the adjacent w
considering 850m wall length.]
Now For the Short walls perpendicular to the flow (considering the section B-B),
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
[Theses walls are provided as stifeneres as well as a safety measure to prevent the work zone from
long wall fails]
No. of intermediate walls per 500 m long wall
Total volume of earth filled cement bags
So, no. of bags required per 850 m length of wall
So total no of cement bags required per 850 m length of wall
Total Number of cement bags required for full reach
Now total cost for Diversion Work involves the following items of works1) Cost for supply, earth filling, sewing & laying for each bag
(As per Item No. 30, Chapter 21, Page No. 28, UPID SOR, Kanpur Commissionary)
So, total cost
(9.5*1017230)
2) Cost for shifting the previously placed bags by 2m to 3m (as necessary) at same chainage to al
( Here, only handling of earth filled bags are to be considered)
Assuming, One person can handle and relay 40 bags per hour /
As per SL. No.1, Chapter-1, Pg-3, UPID SOR, Kanpur Commissionary,
daily wages rate/labour
(175/320)*100
Adding 15% for contractor's profit
(63.25*1017230)/100
3) Cost for moving 70% of reusable bags from the 500m stretch to adjacent 350m stretch
by bullock cart It is assumed that 70% of Bags can be reused in
next season and can be utilised in 70% * 500m length
As per Item. No.1, Chapter-II, Pg-2, UPID SOR, Allahabad Commissionary,
basic rate for carriage of materials/M.T
Again this rate has to be increased by 15% for canal service roads as per Item. No.1,
Chapter-II, Pg-2, UPID SOR, Allahabad Commissionary, rate for carriage of materials/M.T.
So, increment of carriage rate for canal service road will be by,
Therefore, rate of Transporting and moving of the requisite reusable Cement Bags
Vol. of one bag (1cft )
Density of earth
So, Weight of one bag ,
So the number of bags that can be moved @ rate Rs. 118/Total cost for moving 70% usuable bags
[The cost include loading, unloading and stacking.]
4) Cost for shifting the previously placed bags by 2m - 3m at same chainage but changing the flow
The rate for this item will be same as Item no. 2
So, Total cost for laying earth fill bags in
(70% of 9663685)*63.25/100
adjacent 350 m will be,
6) Cost for dewatering from local pockets after closing the gate
Power of Pump
Efficiency of pump set ()
Head against which mortor has to work (H)
Assuming losses in the conveyance system
So,effective head on the pump (H ef)
So, dischrge capacity of the pump,
= (735 )/(
_ ) ^2
31.696 Km
11.25 m
1.450 m
350.00 m
500.00 m
524.00 m
0.60 m
0.60 m
Section B-B
single diversion wall
=
26635.968 cft
=
26636 no.s
g wall will be reused for the adjacent wall of 350 m. So no of bags are determined
=
=
=
9 no.s
643.34 cft
643 no.s
27279 no.s
1017230 no.s
g
npur Commissionary)
=
=
9.50
9,663,685.00
(as necessary) at same chainage to allow the flow from one side to other.
sionary,
175.00
(175/320)*100
55.00
=
=
63.25
643,398.00
mmissionary,
350.00 m
105.00
15.75
121.00
=
=
=
=
=
0.028 cum
1800 kg/M3
51 kg
20 no.s
4,307,970.00
at same chainage but changing the flow from one side to other.
=
63.25
% of 9663685)*63.25/100
en in Sl.No.-2(b), Chapter-3,
450,379.00
=
=
28816.7138810198 m3
2,435,013.00
=
=
=
=
=
5 HP
70 %
5.00 m
20 %
0.044 m3/s
=
=
=
=
158.4 m3/hr
11.25 m
31.696 Km
0.200 m
6.00 m
71316.000 m3
or
ment UP)
=
=
1
451 hrs
100 Rs/hr
45,100.00
=
=
=
562.5 m3
4 Nos/ Hour
475.2 m3/Hour
2 Hour
he dewatering process within 4 hr so that the canal bed can be allowed for sun drying
(31.696/0.85)
tal stretch
ate same as Sl. 6)
=
=
=
=
=
2.67 Pump-Hours/Day.
420 Days
38 Nos
42560 Pump-Hours
4,256,000.00
SL
No.
Description of Item
Ref. No.
Quantity
1017230
Analysed Rate
1017230
Analysed Rate
712061
Analysed Rate
712061
28817.00
Lucknow Zonal
SOR, UPID
451
Lucknow Zonal
SOR, UPID
42560
Estimated Cost
Add Contigency Charge @ 3%
Total Estimated Cos
Unit
Rate
(Rs.)
Amount
(Rs.)
Each
9.00
9,155,070.00
100
Bags
63.25
20
Bags
121.00
100
Bags
63.25
450,379.00
Cum
80.00
2,305,360.00
Per
Hour
100.00
45,100.00
Per
Hour
100.00
4,256,000.00
Estimated Cost =
ntigency Charge @ 3%=
Total Estimated Cost=
643,398.00
4,307,969.00
21,163,276.00
634,899.00
21,798,175.00