Vous êtes sur la page 1sur 9

DOCUMENT NO.

:
XXX-P-PR-001

DOCUMENT TITLE :

PIPING INSPECTION PROCEDURE

REV.

EFFECTIVE DATE
05/09/2009

CONTENTS
1. Purpose

2/9

2. Scope

2/9

3. Responsibility

2/9

4. Applicable Document and References

2/9

5. Definition

3/9

6. Piping Inspection Work

3/9

6.1. Piping Material Receiving and Storage

3/9

6.2. Piping Spool Shop Fabrication

4/9

6.3. Field Installation of Shop Fabricated Piping Spool

7/9

6.4. Piping System Flushing and Cleaning

9/9

7. Piping as Built Data

9/9

8. Inspection Record Form

9/9

REVISION RECORDS
REV.

DATE

DESCRIPTION

Originator
by

Original

Issued for Approval

DISTRIBUTION
1.
2.
3.
4.

All Manager Department


Project Manager
Site Manager
File ( DCC )

OWNER

CONTRACTOR

CHECKED

REVIEWED APPROVED
BY
BY

ARS

REMARKS

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 2 of 9

PIPING INSPECTION PROCEDURE

PURPOSE
This procedure provide guidelines for the inspection works that shall be performed by QA /
QC Inspector for piping work on Building Piping Process as such to achieve the final
product conforming to Owner requirement.
2.1.1.1.1.1.1.1.1.

SCOPE

This guide covers quality assurance and control of piping work activity from receiving of
material, storage, shop fabrication / testing and field installation / testing.
2.1.1.1.1.1.1.1.2.

RESPONSIB
ILITY

The QA / QC Mechanical & Piping shall be responsible for the performance of quality
assurance in piping work.
2.1.1.1.1.1.1.1.3.

APLICABL
E
DOCUMEN
TS

and

REFERENC
ES
The following documents / references out lines the inspection requirements for piping and
shall be implemented as applicable to the project work:
-

ASME B 31.1.

Power Piping

ASME B31.3

Process Piping

ASME Sec. IX

Welding and Brazing Qualification

ASME B31.9

Building Piping

ASME/ANSI B1.20.1 Pipe Threads, General Purpose (Inch)

ASME/ANSI B 16.5. Pipe Flange and Flange Fittings

The inspector shall ensure the above corresponding references are available / handy anytime
during the performance of the piping work, including this procedure.

02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 3 of 9

PIPING INSPECTION PROCEDURE

2.1.1.1.1.1.1.1.4.

DEFINITIO
N

Contractor
Owner
MIGAS

:
:
:
2.1.1.1.1.1.1.1.5.

PIPING
INSPECTIO
N WORK

The following paragraph outlines inspection works / items that shall be done by the inspector
for piping works as a minimum.
2.2. Piping Material Receiving and Storage
2.2.1. Piping material receiving.
Prior to material arrival at site, the inspector shall carry out the following work.
-

Obtain pipe material Purchase Order (P.O.), packing list and shop
inspection mill certificates.
The inspector shall identify the quantity, type and size of the piping as a
reference to inspect the storage area to be provided and the storage method /
requirement.

Prepare the receiving inspection record forms. Project specific forms are
recommended.

Upon arrival of the piping material at site the following inspection shall be
done:
-

Inspect the pipe material for damages that may occur during shipping /
handling.
Damage report shall be prepared and submitted to Contractor/Owner. The
damage report shall contain damage type and identification of rejected and
accepted material.
The damage report of rejected material shall quote the appropriate
specification as reason for rejection.

Identify the material of pipe shall conform to the purchase order.

Check sizes, type of pipe fittings, flanges etc. to conform to P.O.


02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 4 of 9

PIPING INSPECTION PROCEDURE

Verify the mill certificates :

Ladle analysis (chemical composition) shall conform to tabulated composition


in the standards & specification.
Tensile strength and ultimate strength value shall conform to strengths as
tabulated in the standards & specification.
Other specific certificates (valves, flame arrestors etc.).
Any discrepancy shall be reported in non- conformance report and be
submitted to Contractor/Owner and copied to the vendor and purchaser.
2.2.2.

Piping Material Storage Inspection.


Inspection to ensure the piping material is placed in the storage area properly:
-

Pipe or fitting stainless steel shall be separated with carbon steel /


galvanized material

Protected against weather or corrosion, refer to project specific requirement.

Each piping component or group shall have material identification tag.

Surface of plunges shall be protected with wood or rubber / plastic.

Rejected material shall be stored separately to avoid misuse and shall have
special identification (e.g. rejected, do not use etc.).

2.3. Piping Spool Shop Fabrication.


a) Construction Drawings
-

The inspector shall check the isometric drawings had been checked and
approved for construction.

The isometric drawings to be used for fabrication were marked at shop for
spool number, welds number and WPS number.

Spool drawings were checked by Piping Construction Group (by project


engineer) for correct dimension, identification of pipe cutting length, fittings
and flanges.
Selection of the correct fittings and flange (shall be in accordance with
isometric drawings) will be by the Construction Group but the inspector shall
inspect and notify them if any discrepancy occur.

02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 5 of 9

PIPING INSPECTION PROCEDURE

b.

Check Welders certifications


-

The welders certification of the welders shall be checked that they have
certificate copy handy.
Identify the certificates corresponds to which WPS. This avoids misuse of
welder.

Ensure that the welders use welder badge identifying their qualification.

c. Welding Facility.
-

Inspect to ensure the welding machines have proper amperage capacity (WPS
requirement), stable voltage etc.

Inspect that welding holder in good order.

Inspect space for welding to ensure welder free movement as required during
welding. This will avoid weld defects.

Inspect whether welding tents is needed to avoid winds during welding. Strong
wind may cause blowhole or porosity on welds.

Inspect the welding electrode heater for storage and heating of welding
electrode for immediate use. Heating temperature as per manufacturer
recommendation shall be checked.

Inspect size of grinder and grinding wheel to match the need for weld joints.

d. Welding of Pipe Spools


-

Inspect to ensure fit ups work utilizes proper method as usually in


construction practice (use of angle, level, clamp etc.).

Inspect to ensue that fit up tack welding is done by qualified welder. Check
the welding electrodes used conform to WPS.

Inspect randomly that weld bevel angle and gap are correct in accordance with
WPS.

Inspect to ensure that each welded spool is marked to identify the isometric
drawing & mark number, each weld with welder number, welding date and
radiography number / date shot.

Refer to project specification procedure for further requirements of inspection.

02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 6 of 9

PIPING INSPECTION PROCEDURE

e.

Radiography of welds.
-

Inspect the Radiography ray equipment must have the valid permit; proper
radiation power, etc. refer to Project (Specific) requirements.

Interpretation of Radiography film shall be done by inspector having


Contractor/Owner acceptance of interpretation is required.

The inspector shall prepare the weld Defect Report indicating type of defect,
location etc., refer to Project Specific requirement.
The report should clearly indicate the acceptability (rejected or accepted) of the
weld.
The rejection must indicate type of repair (local or overall cut and re weld).

The welds on the spool shall be marked with Radiography result (accepted,
rejected / repair or cut / re weld. The Radiography film of weld to be repaired
shall be given to the welding Supervisor.
The repaired weld shall be marked and radiographed.

f. Pressure Test of shop fabricated Spools :


-

The inspector shall review the project (specific) requirements for pressure
testing of the shop-fabricated spools which normally should be pressure tested
at shop yard.
The pressure test circuit design shall be prepared by the chief project engineer.
Typical test circuit is displayed in the exhibit 1.
The isometric drawing shall be reviewed to identify pressure test type (hydro
test with pressurized water or by pneumatic / air pressure or by hydraulic oil),
test pressure, test temperature etc.

The Inspector shall ensure all radiography films of weld joint at the spool were
interpreted, inspected acceptable to Contractor/Owner prior to hydrotest.

The spools shall be checked against P & ID prior to test.

The inspector shall ensure the pressure test is carried out in accordance with the
project (specific) procedure.

The pressure test assembly shall be inspected for:

02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 7 of 9

PIPING INSPECTION PROCEDURE

a. The facilities for pressuring water/other medium inlet, depressurizing after


hydrotest, air bubble vent with valve, calibrated pressure gauge or recorder,
etc.
b. The appurtenance piping for the pressure test (vent valves, supply block
valve depressurizing block valves etc.) shall have line class pressure rating
as the spool being hydrotested, as a minimum.
c. Ensure the pressure test assembly sketch and pressure testing procedure
(prepared by chief project engineer) is approved by Contractor/Owner.
d. Ensure Contractor/Owner and / or third party agent witnesses, as required.
-

The hydrostatic tested and acceptable spools shall be marked accordingly and
stored properly.

g. Storage of shop fabricated piping.


Inspector shall check that the fabricated spool is laid in the storage area in the
proper way as follows:

Open-end pipe shall be covered with wood or steel / plate.

Spools area laid with wooden support or equivalent, no contact to earth soil
(avoid corrosion).

Spools are separated in line class group or line size group, refer to project
(specific) requirement.

Stainless steel spools shall be laid in location separated form carbon steel /
spools.

2.4. Field installation of shop fabricated piping spools.


-

Prior to field welding, the inspector has to carry out similar inspection as outlined
in paragraph 6.2. (As applicable).

Inspect that field welds are marked with welding number, welder identification and
welding date.

The inspector shall carry out the work similar to paragraph 6.2.e.

Where field pressure test is required, the inspector shall carry out inspection works
similar with paragraph 6.2.f.

Special notes for piping field installation / test:


a) Valves

02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 8 of 9

PIPING INSPECTION PROCEDURE

All valves installed in the piping system and included in the hydrotest circuit
shall be opened (inspector shall check).

The inspector shall check against project or manufacturers specification if the


valve is to be included in hydrotest (as reference inspector should check the
standard used in manufacturing the valve).

The inspector shall check that the valves are installed in correct flow direction,
and orientation in accordance with construction drawing (hand wheel position,
angle of incline etc.)

During testing, the valves that are not to be included in hydrotest shall be
isolated or replace by flange spool.
Control valves, flow orifices, relief valves, strainers / filters shall not be
included in pressure testing. Inspector shall further verify with project
specification all limitation and requirement.

All instruments shall be isolated during pressure testing.

b) Blind Flanges
The blind flanges or spades installed to isolate valves and instrument shall not be
dismantled, as they are required for protection during flushing. Blind list shall be
prepared to easily control during removal for re-commissioning of the piping
system.
c) Bolts / Studs and Gaskets
-

Prior to field pressure testing, all bolting of flanges shall be inspected for
correct size / dimension, material and well tightened. The inspector shall check
and record.

Similar for gaskets shall be inspected

All dismantled gaskets used for pressure testing spools / flanges shall not be re
used for permanent installation. Similar with spades.

d) Spring Supports and Temporary Supports


-

Prior to pressure testing, the inspector shall inspect the required temporary
additional supports for pressure testing due to additional weight of piping due
water or gases fill of the piping system.
02/01/17lh\

Doc. No.
Date

INSTRUCTION GUIDE OF QA/QC


: XXX-P-PR-001
Revise
:0
: 04 05 2009
Page
: 9 of 9

PIPING INSPECTION PROCEDURE

Spring support normally shall be in stop position during testing to avoid


overload of the spring or affect the pipe alignment to the equipment it
connected to. Spring support status list shall be prepared, needed for precommissioning.

2.5. Piping System Flushing and Cleaning


-

After pressure testing, the piping system shall be cleaned with air blowing.
Hydraulic oil piping and tubing shall not be flushed with water but with air or
hydraulic coil.

The inspector shall witness the air outlet to verify that piping system is clean
already. Contractor/Owner witness is required.

The inspector shall verify and perform other flushing requirement in the project
(specific) procedure.
2.5.1.1.1.1.1.1.1.

PIPING

AS

BUILT
DATA
The inspector shall ensure that the as built data were marked by the project engineer in the
isometric drawings, P & ID and piping plan drawings. This will facilitate next preparation of
back up documents of mechanical completion acceptance request to the Contractor/Owner.
2.5.1.1.1.1.1.1.2.

INSPECTIO
N RECORD
FORM

The inspection from samples in the appendix I are recommended formats to be used to
record the result of inspection. Other format may be utilized, provided that the inspection
item shall completely cover the inspection requirements.

02/01/17lh\

Vous aimerez peut-être aussi