Académique Documents
Professionnel Documents
Culture Documents
Richard Boser
Time Management
This knowledge area includes the project
management processes required to ensure
timely completion of all work activities
included in the project.
Task C Task F
4d 4d
ES EF ES EF
Verb Noun
Task C Task F
4d 4d
ES EF ES EF
Procure
Steel
Only ONE activity can occur between the same pair of nodes.
All finish-start relationships.
Dummy activities take no time or effort AND maintain logic.
Nodes can serve as milestones.
E
5
Types of Dependencies
Mandatory Dependencies
Hard logic cannot change
Discretionary Dependencies
Soft logic- discretion of project manager
External Dependencies
Supply Chain related outside YOUR
control (typically)
Lead (Accelerate) SS
A
10
5 B
7
Lead (Accelerate) FS
A
10
5 B
7
Lag (Wait)
A
10
5
B
7
Finish Start with 5 days lag
When might lag be used?
Create in MS Project