Vous êtes sur la page 1sur 33

Time Management

Part 3 Scheduling Fundamentals


Activity Definition and Sequencing

Richard Boser
Time Management
This knowledge area includes the project
management processes required to ensure
timely completion of all work activities
included in the project.

Project Management Training Group -- Illinois State University 2


Time Management:
Knowledge Process Areas
6.1 - Activity Definition Specific schedule activities
required to produce project deliverables.
6.2 - Activity Sequencing Documenting dependencies
among schedule activities.
6.3 Activity Resource Estimating Type & quantity of
resources required to perform each schedule activity.
6.4 Activity Duration Estimating Number of work
periods needed to perform schedule activities
6.5 - Schedule Development Analyzing the activity
sequences, durations, resource requirements and
constraints to create the project schedule
6.6 - Schedule Control Evaluating and controlling any
changes to the project schedule
Project Management Training Group -- Illinois State University 3
PMI-isms Related to Time Mgmt
Assume you have historical info (Organizational
process assets)
PM has authority and power.
PMs fault if project doesnt meet time and cost
goals.
Always follow Plan-Do-Check-Act cycle.
Scope change must be evaluated for impact to
time, cost, quality, risk & customer satisfaction.
(See Rita Mulcahy (2005) PMP Exam Prep p. 16)

Project Management Training Group -- Illinois State University 4


6.1 Activity Definition
Inputs Tools & Outputs
Techniques
Enterprise Decomposition Activity list
environmental Templates Activity
factors (PMO) Rolling Wave Attributes
Organizational Planning Milestone list
process assets Expert Judgment Requested
Scope Statement Planning changes
WBS component
WBS Dictionary (high-level schedule)
PM Plan

Project Management Training Group -- Illinois State University 5


Activity Definition Tool: Decomposition

Project Management Training Group -- Illinois State University 6


Activity List (Activity Definition Outcome)
Vendor Selection (Work Package)
Agenda for visits
Visit schedule
Evaluation criteria
Team prep and training
Report on visits
Finalists list

Project Management Training Group -- Illinois State University 7


Activity Attribute Matrix (PMBOK p. 130)
Activity: Report on visits
ID and/or Code:
Description:
Predecessor:
Successor:
Logic Relationships:
Lead or Lag:
Resource Requirements:
Assumptions/Constraints:
Imposed Dates:
Project Management Training Group -- Illinois State University 8
Milestones (Activity Definition Outcome)
Zero duration events that mark major progress in work.
Start Milestones
Finish Milestones (deliverables)
Many small milestones improve project control.
Use for high level schedule
Use for summary level reporting to senior management.

Project Management Training Group -- Illinois State University 9


6.2 Activity Sequencing (PMBOK)
Inputs Tools & Outputs
Techniques
Scope Statement Precedence (PDM) Project Schedule
Activity List Diagram Method Network Diagrams
Activity Attributes Arrow Diagram Activity List UP
Milestone List Method (ASM) Activity Attributes
Approved Change Schedule Network UP
Requests Templates Requested Changes
Dependency
Determination
Apply Lead & Lag
(GERT) Conditional

Project Management Training Group -- Illinois State University 10


Precedence Diagramming Method (PDM)
or
Activity-On-Node (AON)
Task A Task B Task D Task E Task G
1d 3d 2d 1d 2d
ES EF ES EF ES EF ES EF ES EF

Task C Task F
4d 4d
ES EF ES EF

Look carefully as you will create a PD very soon!

Project Management Training Group -- Illinois State University 11



Planning by Post-It
# ____

Verb Noun

Estimated Time: _____

Project Management Training Group -- Illinois State University 12


Activity: Sequencing with Sticky Notes
Develop a Precedent Diagram for a
surprise birthday party (or alternate).
At a minimum, include at least dozen
activities.
Use only Finish-Start relationships. Use
parallel activities when appropriate.
You have 15 minutes.

Project Management Training Group -- Illinois State University 13


Activity: Debrief Questions
How did you decompose the project activities?
Bottom-up? Or top-down?
How many parallel activities were used ?
Were there any bottlenecks in your operation? If
so, how resolved?
How would you shorten the project time?
Which activities were not in your control?
Challenge activity: Enter in MS Project

Project Management Training Group -- Illinois State University 14


Sequencing Tool
Precedence Diagramming Method (PDM)
Or Activity-On-Node (AON)

Task A Task B Task D Task E Task G


1d 3d 2d 1d 2d
ES EF ES EF ES EF ES EF ES EF

Task C Task F
4d 4d
ES EF ES EF

Project Management Training Group -- Illinois State University 15


Sequencing Tool

Activity on Node (AON)


Design
Formwork

Mobilize Install Forms & Erect


Foundation Concrete Steel

Procure
Steel

Four types of dependencies possible.


Where are the mandatory dependencies?
Are there any discretionary dependencies?

Project Management Training Group -- Illinois State University 16


Sequencing Tool
Activity on Arrow (AOA)
Design Formwork

Forms & Erect


Install
Concrete Steel
Mobilize Foundation
Excavate
Procure Steel

Only ONE activity can occur between the same pair of nodes.
All finish-start relationships.
Dummy activities take no time or effort AND maintain logic.
Nodes can serve as milestones.

Project Management Training Group -- Illinois State University 17


Sequencing Tool
Dependency Logic

Dependents Logical Relationships


Consecutive / Linear (Finish Start)
Concurrent / Parallel
D
3
A B C F
2 4 7 2

E
5

Project Management Training Group -- Illinois State University 18


Sequencing Tool

Types of Dependencies
Mandatory Dependencies
Hard logic cannot change
Discretionary Dependencies
Soft logic- discretion of project manager
External Dependencies
Supply Chain related outside YOUR
control (typically)

Project Management Training Group -- Illinois State University 19


Sequencing Tool
Dependency Relationships

Project Management Training Group -- Illinois State University 20


Sequencing Tool
Dependency Relationships
Examples:
FS Lots of examples.
FF (rare) B cant finish before A
e.g. Data entry (B) cant finish
until Data collection (A) is finished
SS Data entry (B) can start once
Data collection (A) starts (w/ lag).
SF (rare) B cant finish before A
e.g. Terminate legacy server
Old system discontinued (B) when
new system (A) operable.

Project Management Training Group -- Illinois State University 21


Test Yourself
A dependency requiring that design be
completed before manufacturing can begin is
an example of a _____________ dependency.
a. Discretionary
b. External
c. Mandatory
d. Scope

Project Management Training Group -- Illinois State University 22


Test Yourself
A dependency requiring that design be
completed before manufacturing can begin is
an example of a _____________ dependency.
a. Discretionary
b. External
c. Mandatory
d. Scope

C: Required or mandatory dependency

Project Management Training Group -- Illinois State University 23


Sequencing Tool

Lead (Accelerate) SS
A
10

5 B
7

Start Start with 5 days head start for A


When might lead be used?

Project Management Training Group -- Illinois State University 24


Sequencing Tool

Lead (Accelerate) FS
A
10

5 B
7

Finish Start with 5 days overlap from finish


When might lead be used?

Project Management Training Group -- Illinois State University 25


Sequencing Tool

Lag (Wait)
A
10
5
B
7
Finish Start with 5 days lag
When might lag be used?

Project Management Training Group -- Illinois State University 26


Lead & Lag in MS Project

Project Management Training Group -- Illinois State University 27


Technical Constraints that
Affect Sequencing
FS least risk-prone
Use FS if it fits project time frame
Discretionary constraints
Judgment calls by PM (e.g. SS vs. FS)
Unique Attributes
Resource availability, location, staffing,
etc

Project Management Training Group -- Illinois State University 28


Types of Constraints - MS Project
Imposed Dates Software Default
Start no earlier than As soon as possible
Start no later than
Finish no later than
Finish no earlier than
Other Types
Must start on
Must finish on
As late as possible

Project Management Training Group -- Illinois State University 29


Sequencing Tool

Activity: Dependencies in MS Project

Create in MS Project

Project Management Training Group -- Illinois State University 30


Network Diagram Applications
Show activity dependencies
Display workflow and activity sequence
Tool for planning, organizing & controlling
Determine progress for control & reporting
Justify time estimates
Plan schedule compression

Project Management Training Group -- Illinois State University 31


Quiz #3: Sequencing Activities
1. What is the difference between AOA & AON?
2. Provide examples of mandatory, discretionary,
and external dependencies.
3. Name the 4 types of dependency relationships?
4. How does lead differ from lag?
5. What is the default setting for software time
constraints?
6. When is a milestone used?

Project Management Training Group -- Illinois State University 32


End Activity Definition and Sequencing
Questions/Notes

Project Management Training Group -- Illinois State University 33

Vous aimerez peut-être aussi