CASE STUDY

Proactive well integrity


management
Pulsed eddy current (PEC) technology helps to improve well integrity

the age of the well or factors such as


operating temperature or communication
with seawater.
During the D-PEC survey, we found that
some D annuli were blocked by debris
or corrosion deposits, and could not be
inspected, explains Taylor. This prompted
us to develop C-PEC inspection equipment
for accessing wells via the C annulus
valve that could negotiate obstructions.
C-PEC technology gave us an option for
inspecting wells that could otherwise not
be inspected through the D annulus.
An umbrella-like construction was

T
he North Sea is a mature basin difficulties of access and of working on designed for negotiating the obstructions and
with a well-established infrastructure. producing wells. positioning the miniaturised probe on the
Consequently, significant investment Together, Shell Global Solutions and steel surface. Closed, it is lowered into the C
is necessary to maximise the economic Shell UK E&P developed the D-PEC annular space and past any obstruction. A
recovery of oil and gas. The hundreds of well inspection method. This is based miniature chemical timer, inspired by a British
wells across the North Sea are among the on PEC technology in which a pulsed pencil detonator of World War II design,
extensive assets and facilities that require magnetic field induces eddy currents in then opens the device. An international
a focus on asset integrity and that must the steel being examined. PEC technology patent application has been filed for PEC
be maintained for safety, protection of the determines the wall thickness of the pipe inspection of well casings.
environment and continuing production. by sensing the decay of the eddy currents. The PEC technologies offer field
For example, wellhead support casings The D-PEC tool more than meets the operators simple ways to monitor for
can deteriorate over long periods of time requirements for the casing inspection, progressive corrosion and can have
through corrosion, and, in a worst-case says Ian Taylor, Principal Production commercial benefits. Knowledge of
scenario, this may lead to structural failure Technologist, Well Integrity and Well well integrity enables better planning of
unless integrity management programmes Completions, Shell U.K. Exploration and production deferment and more accurate
are followed. Production Limited. The method can production forecasting.
Shell Global Solutions has worked measure wall thickness through deposits Regular health checks of the corrosion
closely with Shell U.K. Exploration and without contact between the sensor and status of wells help us to plan more
Production Limiteds upstream business the steel surface. A two-man crew performs targeted and cost-effective workover
(Shell UK E&P) over the last few years a D-PEC survey using a portable unit while programmes and to focus on those wells
on an inspection campaign to assess the the well remains in production. that require urgent attention and remedial
integrity of its wells. This was a major The inspection campaign identified action, concludes Taylor.
technical challenge, as corrosion in clearly where remedial action was
offshore wells occurs predominantly at sea necessary and where it was not. The
level in the space (the D annulus) between survey also indicated that it was impossible
two concentric, vertical tubular conduits: to predict which wells were at risk from For more information contact:
the surface casing and the outer conductor. corrosion and which were not. Corrosion Diederick Bax
Email: diederick.bax@shell.com
A method was needed to overcome the did not seem to correlate directly with

16 impact Issue 1, 2010 www.shell.com/globalsolutions