Problem Solving. Analyze the following data and answer the
following questions below.

Activity Duration Job Description


(Days)

a 1-2 1 Relocation of boundaries-cleaning


b 2-3 2 Construction of field office
c 2-4 5 Delivery of materials
d 2-5 2 Staking and batter boards
e 3-5 6 Digging/excavation
f 4-5 10 Cutting and assembling of steel reinforcements
g 4-7 0 Dummy
h 3-6 12 Making of forms and door jambs
i 5-6 9 Positioning of steel reinforcement
j 5-7 5 Forms and scaffolding
k 5-8 8 Electrical, plumbing and water pipe connections
l 6-8 0 Dummy
m 6-9 2 Pouring of footings and columns
n 7-8 1 Removal of forms
o 7-10 12 CHB laying and backfilling

p 8-10 7 Beams and slab forms, reinforcement and various piping


installations
q 8-9 0 Dummy
r 8-11 8 Roof framing and roofing sheet
s 9-11 4 Pouring of beams and slabs
t 10-11 2 Construction of stairways
u 10-13 12 Plastering and tileworks
v 11-12 2 Installation of doors and windows
w 9-14 3 Plumbing and drainage system
x 12-14 2 Installation of plumbing fixtures
y 12-13 3 Install electrical wiring and fixtures
z 13-15 8 Painting and varnishing
aa 14-15 2 Final work and cleaning

1. Draw the network diagram for the activities listed. Indicate the alphabetical designation and the
corresponding duration of each activity.
2. Compute the total duration of the project in days.
3. Determine the Critical Path.
4. Solve for the Slack or Float for each activity.

Prepared by:
JOENIFER L. MONTEBON JR., RCE
Instructor

Recommending Approval:
AL EMMANUEL L. CABALLES, IE, MSME ENGR. MA. CARLA Y.
ABAQUITA, CHE, Dev. Ed. D
Chairperson, College of Engineering Director, College of
Engineering

Vous aimerez peut-être aussi