/REF: SRTS-1:CAO:KNL:TLC:KT-1:13: /DATE : .01.2013.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
Thukonda Quarry, 1. Determination of particle size
1 Coarse Yagantipalli PG/KNL/TLC/ (Sieve analysis)
aggregates M/s. Sri Laksmi KT-1/40mm/
(40mm) Road Metal 2. Flakiness Index.
Industries crushers
3. Crushing value.
2 Coarse Tammaraju Palli
aggregates Quarry, PG/KNL/TLC/ 4. Presence of deleterious materials.
(40mm) M/s. KNR KT-1/40mm/
Constructions. 5. Hardness
(Abrasion value & Impact values)

6. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes - 40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 2 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:13: /DATE : .01.2013.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Ultra- PG/KNL/ 1.Fineness (sqm/kg).


Grade Tech TLC/KT-1/
Cement Cement Cement/ 2. Compressive Strength
Week 72 hrs, 168 hrs & 672 hrs.
3. Initial & Final setting time.
4. Soundness - (Le chattlier/ Autoclave).

You are requested to arrange for conducting the above tests with relevant IS codes/
specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:13: /DATE : +.01.2013.
To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) -Testing


of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Description Source Sample ID No. Tests to be conducted


No.

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River sand River KT-1/FA/ particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

4. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes -

Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:13: /DATE : 12.01.2013.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
Thukonda Quarry, 1. Determination of particle size
1 Coarse Yagantipalli PG/KNL/TLC/ (Sieve analysis)
aggregates M/s. Sri Laksmi KT-1/20mm/11
(20mm) Road Metal 2. Flakiness Index.
Industries crushers
3. Crushing value.
2 Coarse Tammaraju Palli PG/KNL/TLC/ 4. Presence of deleterious materials.
aggregates Quarry, KT-1/20mm/12
(20mm) M/s. KNR 5. Hardness
Constructions. (Abrasion value & Impact values)

6. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes - 40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 2 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:13: /DATE : 09.01.2013.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
1. Determination of particle size
1 Coarse Thukonda Quarry, PG/KNL/TLC/ (Sieve analysis)
aggregates Yagantipalli KT-1/40mm/11
(40mm) M/s. Sri Laksmi 2. Flakiness Index.
Road Metal
Industries crushers 3. Crushing value.

4. Presence of deleterious materials.

5. Hardness
(Abrasion value & Impact values)

6. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes - 40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:13: /DATE : 09.01.2013.
To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) -Testing


of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Description Source Sample ID No. Tests to be conducted


No.

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River sand River KT-1/FA/06 particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

4. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes -

Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 09.01.2013.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Dalmia PG/KNL/ 1.Fineness (sqm/kg).


Grade Cement TLC/KT-1/
Cement Cement/07 2. Compressive Strength
Week 01 72 hrs, 168 hrs & 672 hrs.
3. Initial & Final setting time.
4. Soundness - (Le chattlier/ Autoclave).

You are requested to arrange for conducting the above tests with relevant IS codes/
specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 29.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Dalmia PG/KNL/ 1.Fineness (sqm/kg).


Grade Cement TLC/KT-1/
Cement Cement/06 2. Compressive Strength
Week 52 72 hrs, 168 hrs & 672 hrs.
3. Initial & Final setting time.
4. Soundness - (Le chattlier/ Autoclave).

You are requested to arrange for conducting the above tests with relevant IS codes/
specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 27.12.2012.
To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) -Testing


of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Description Source Sample ID No. Tests to be conducted


No.

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River sand River KT-1/FA/05 particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

4. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes -

Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 29.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
Thukonda Quarry, 1. Determination of particle size
1 Coarse Yagantipalli PG/KNL/TLC/ (Sieve analysis)
aggregates M/s. Sri Laksmi KT-1/40mm/09
(40mm) Road Metal 2. Flakiness Index.
Industries crushers
3. Crushing value.
2 Coarse Tammaraju Palli
aggregates Quarry, PG/KNL/TLC/ 4. Presence of deleterious materials.
(40mm) M/s. KNR KT-1/40mm/10
Constructions. 5. Hardness
(Abrasion value & Impact values)

6. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes - 40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 2 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 22.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Dalmia PG/KNL/ 1.Fineness (sqm/kg).


Grade Cement TLC/KT-1/
Cement Cement/05 2. Compressive Strength
Week 51 72 hrs, 168 hrs & 672 hrs.
3. Initial & Final setting time.
4. Soundness - (Le chattlier/ Autoclave).

You are requested to arrange for conducting the above tests with relevant IS codes/
specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : ____________

To,
The Manager/Lab in charge
M/s. Jyothi Spectra Analysis Pvt. Ltd.
A-30, APIE, Balanagar,
Hyderabad 500037 (AP)

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Concrete cubes - reg.

Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) is under


progress. As per our Standard Field quality plan, concrete cubes collected during RCC work
shall be got tested. Accordingly we are sending here with the One (set) samples (3 cubes each
set) in sealed condition for conducting the tests at your lab as mentioned against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample
No. Description Casting for testing cubes conducted
identification no.
1. Weight of cubes
Concrete &
1 cubes of mix 3 2. Compressive
1:1.5:3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager,
CAO, POWERGRID, Proddatur.
Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 set sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile No. 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 22.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Concrete cubes - reg.

Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) is under


progress. As per our Standard Field quality plan, concrete cubes collected during RCC work
shall be got tested. Accordingly we are sending here with the One (set) samples (3 cubes each
set) in sealed condition for conducting the tests at your lab as mentioned against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample
No. Description Casting for testing cubes conducted
identification no.
1. Weight of cubes
Concrete &
1 cubes of mix 25.11.12 23.12.12 20/8 dt. 25.11.12 3 2. Compressive
1:1.5:3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager,
CAO, POWERGRID, Proddatur.
Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 set sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile No. 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 19.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
Thukonda Quarry, 1. Determination of particle size
1 Coarse Yagantipalli PG/KNL/TLC/ (Sieve analysis)
aggregates M/s. Sri Laksmi KT-1/40mm/07
(40mm) Road Metal 2. Flakiness Index.
Industries crushers
3. Crushing value.
2 Coarse Tammaraju Palli
aggregates Quarry, PG/KNL/TLC/ 4. Presence of deleterious materials.
(40mm) M/s. KNR KT-1/40mm/08
Constructions. 5. Hardness
(Abrasion value & Impact values)

6. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes - 40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 19.12.2012.
To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) -Testing


of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Description Source Sample ID No. Tests to be conducted


No.

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River sand River KT-1/FA/04 particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

4. Sp. Gravity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Results required for Sieve sizes -

Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 15.12.2012.

To,
To,
The Manager/Lab in charge
M/s. Jyothi Spectra Analysis Pvt. Ltd.
A-30, APIE, Balanagar,
Hyderabad 500037 (AP)
Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Dalmia PG/KNL/TLC/ 1.Fineness (sqm/kg).


Grade Cement KT-1/
Cement Cement/04 2. Compressive Strength
Week - 50 72 hrs, 168 hrs & 672 hrs.
3. Initial & Final setting time.

4. Soundness - (Le chattlier/ Autoclave).

You are requested to arrange for conducting the above tests with relevant IS codes/
specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 22.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Concrete cubes - reg.

Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) is under


progress. As per our Standard Field quality plan, concrete cubes collected during RCC work
shall be got tested. Accordingly we are sending here with the One (set) samples (3 cubes each
set) in sealed condition for conducting the tests at your lab as mentioned against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample
No. Description Casting for testing cubes conducted
identification no.
1. Weight of cubes
Concrete &
1 cubes of mix 25.11.12 23.12.12 20/8 dt. 25.11.12 3 2. Compressive
1:1.5:3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager,
CAO, POWERGRID, Proddatur.
Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 set sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 18.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Concrete cubes - reg.

Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) is under


progress. As per our Standard Field quality plan, concrete cubes collected during RCC work
shall be got tested. Accordingly we are sending here with the One (set) samples (3 cubes each
set) in sealed condition for conducting the tests at your lab as mentioned against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample
No. Description Casting for testing cubes conducted
identification no.
1. Weight of cubes
Concrete &
1 cubes of mix 20.11.12 18.12.12 20/5 dt. 20.11.12 3 2. Compressive
1:1.5:3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager,
CAO, POWERGRID, Proddatur.
Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 set sealed sample.

Manager
CAO, Kurnool
Mobile: 9490611066

/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 15.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Concrete cubes - reg.

Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) is under


progress. As per our Standard Field quality plan, concrete cubes collected during RCC work
shall be got tested. Accordingly we are sending here with the One (set) samples (3 cubes each
set) in sealed condition for conducting the tests at your lab as mentioned against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample
No. Description Casting for testing cubes conducted
identification no.
1. Weight of cubes
Concrete &
1 cubes of mix 17.11.12 15.12.12 20/4 dt. 17.11.12 3 2. Compressive
1:1.5:3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager,
CAO, POWERGRID, Proddatur.
Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 set sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 08.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River sand River KT-1/FA/03 particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 10.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description

1 Coarse Tammaraju Palli PG/KNL/TLC/ 1. Determination of


aggregates Quarry, KT-1/40mm/06 particle size
(40mm) M/s. KNR (Sieve analysis)
Constructions.
2. Flakiness Index.
3. Crushing value.
4. Presence of
deleterious materials.
5. Hardness
(Abrasion value &
Impact values)

Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 11.12.2012.

To,
The Manager/Lab in charge
M/s. Jyothi Spectra Analysis Pvt. Ltd.
A-30, APIE, Balanagar,
Hyderabad 500037 (AP)

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
1 Coarse aggregates Gollapalli PG/KNL/TLC/
(20mm) Quarry, KT-1/20mm/04 1. Determination of
M/s. Srinivasa particle size
Stone Crusher, (Sieve analysis)
Gollapalli.
2 Coarse aggregates Gollapalli PG/KNL/TLC/ 2. Flakiness Index.
(40mm) Quarry, KT-1/40mm/04
3. Crushing value.
M/s. Sri Sai
3 Coarse aggregates Rajeswari PG/KNL/TLC/
(20mm) KT-1/20mm/05 4. Presence of
Stone Crushers deleterious materials.
4 Coarse aggregates Gollapalli PG/KNL/TLC/
(40mm) Quarry, KT-1/40mm/05 5. Hardness
M/s. Om Sri (Abrasion value &
Venkateswara Impact values)
Stone Crushers
Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 4 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 11.12.2012.

To,
The Manager/Lab in charge
M/s. Jyothi Spectra Analysis Pvt. Ltd.
A-30, APIE, Balanagar,
Hyderabad 500037 (AP)

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 Fine aggregate PENNA River PG/KNL/TLC/ 1.Determination of


River sand Near KT-1/FA/02 particle size
Dharmapuram (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -

Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 05.12.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Concrete cubes - reg.

Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1) is under


progress. As per our Standard Field quality plan, concrete cubes collected during RCC work
shall be got tested. Accordingly we are sending here with the One (set) samples (3 cubes each
set) in sealed condition for conducting the tests at your lab as mentioned against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample
No. Description Casting for testing cubes conducted
identification no.
1. Weight of cube
Concrete &
1 cubes of mix 07.11.12 05.12.12 9/1 dt. 07.11.12 3 2. Compressive
1:1.5:3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager,
CAO, POWERGRID, Proddatur.
Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 set sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 12.11.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Dalmia PG/KNL/TLC/ 1.Fineness (sqm/kg).


Grade Cement KT-1/
Cement Cement/03 2. Compressive Strength
Week - 45 72 hrs, 168 hrs & 672 hrs.
3. Initial & Final setting time.

4. Soundness - (Le chattlier/ Autoclave).

You are requested to arrange for conducting the above tests with relevant IS codes/
specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 no. sealed sample.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 06.11.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line(Part-1)


-Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
PG/KNL/TLC/ 1.Fineness (sqm/kg).
1 OPC 43 Dalmia
KT-1/
Grade Cement
Cement/01 2. Compressive Strength
Cement
Week 38 72 hrs, 168 hrs & 672 hrs.
2
PG/KNL/TLC/ 3. Initial & Final setting time.
KT-1/
Cement/02 4. Soundness - (Le chattlier/ Autoclave).
Week 44

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General Manager, CAO,
POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd., Mumbai.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 2 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 19.10.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River KT-1/FA/01 particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 18.10.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No Description
1 Coarse aggregates Tammaraju PG/KNL/TLC/
(40mm) Palli Quarry, KT-1/40mm/01 1. Determination of
2 Coarse aggregates M/s. KNR PG/KNL/TLC/ particle size
(20mm) Constructions. KT-1/20mm/01 (Sieve analysis)
3 Coarse aggregates Tammaraju PG/KNL/TLC/ 2. Flakiness Index.
(40mm) Palli Quarry, KT-1/40mm/02
4 Coarse aggregates M/s. Sai Stone PG/KNL/TLC/ 3. Crushing value.
(20mm) Crushers KT-1/20mm/02
5 Coarse aggregates Yagantipalle PG/KNL/TLC/ 4. Presence of
(40mm) Quarry, KT-1/40mm/03 deleterious materials.
6 Coarse aggregates M/s. Sri PG/KNL/TLC/
5. Hardness
(20mm) Lakshmi Road KT-1/20mm/03
(Abrasion value &
Metal
Impact values)
Industries
Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


40mm & 20mm aggregates : 40mm, 20mm, 10mm, 4.75mm

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 6 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 18.10.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 Fine aggregate Tammaraju PG/KNL/TLC/
(Stone dust) Palli Quarry, KT-1/Stone 1.Determination of
M/s. Sai Stone Dust/01 particle size
Crushers (Sieve analysis).
2 Fine aggregate Yagantipalle PG/KNL/TLC/
(Stone dust) Quarry, KT-1/Stone 2. Silt Content.
M/s. Sri Dust/02
3. Presence of
Lakshmi Road
deleterious materials.
Metal
Industries,
Banaganapalle

Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 2 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:TLC:KT-1:12: /DATE : 19.10.2012.

To,
The Manager/Lab in charge
M/s. TESTWELL Pvt. Ltd.
Plot no. 16, Snehitha Hills, Peram Cheruvu
Near APPA, Rajendra Nagar(Mandal)
Hyderabad 500 008, AP.

Dear Sir,

SUB : Construction of 765 KV D/C Kurnool-Tiruvelam Transmission


line(Part-1) -Testing of Construction materials Aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be
got tested. Accordingly we are sending here with the following samples (in sealed
condition) of aggregates for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 Fine aggregate Tungabhadra PG/KNL/TLC/ 1.Determination of


River KT-1/FA/01 particle size
Near Nidzur (Sieve analysis).
village
2. Silt Content.

3. Presence of
deleterious materials.

Contd..
--2--

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Dy. General
Manager, CAO, POWERGRID, Proddatur.

Applicable test charges will be paid by our contractor M/s. Bajaj Electricals Ltd.,
Mumbai.

Results required for Sieve sizes -


Fine aggregate: 10mm, 4.75mm, 2.36mm, 1.18mm, 600 microns, 300 micr, 150 micr.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 1 nos. sealed samples.

(TRC Murty)
Manager
CAO, Kurnool
Mobile: 9490611066
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 27.08.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1 30.07.12 27.08.12 R-Clm-30.07.12 3 1. Weight of
2 cube
Concrete
&
cubes of mix
31.07.12 28.08.12 Clm-31.07.12 3 2. Compressive
1:1.5:3
strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 24.08.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Soil samples for compaction test - reg.

As per our Standard Field Quality Plan, the back filled soil shall be got tested
compaction (Percentage Maximum Dry Density). Accordingly we are sending here with the
following samples (in sealed condition) of aggregates for conducting the tests at your lab as
mentioned against each sample.

Sl. Material Source/Area Sample ID No. Tests to be conducted


No. Description
B/Wall BC PG/KNL/ BW/
1 Soil Sample Soil/01, 02 & 03 Compaction Test
B/Wall CD PG/KNL/ BW/ (Percentage of
Soil/04, 05 & 06
B/Wall DE PG/KNL/ BW/ Maximum Dry
Soil/07, 08 & 09 Density)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : 3 sets (9 nos. sealed samples).

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 20.08.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1. Weight of
1 23.07.12 20.08.12 PB-23.07.12 3 cube
Concrete
&
2 cubes of mix
2. Compressive
1:1.5:3 24.07.12 21.08.12 R-Clm-24.07.12 3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 16.08.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1. Weight of
1 19.07.12 16.08.12 PB-Clm-19.07.12 3 cube
Concrete
&
2 cubes of mix
2. Compressive
1:1.5:3 20.07.12 17.08.12 Clm-20.07.12 3 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 11.08.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the One (set)
sample (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1. Weight of
cube
Concrete
&
1 cubes of mix 14.07.12 11.08.12 R-CLM-14.07.12 3
2. Compressive
1:1.5:3
strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 06.08.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1 08.07.12 05.08.12 R-08.07.12 3 1. Weight of
2 3 cube
Concrete 09.07.12 06.08.12 R-09-07-12
&
3 cubes of mix 11.07.12 08.08.12 R-CLM-11.07.12 3 2. Compressive
4 1:1.5:3
3 strength for 28
12.07.12 09.08.12 R-CLM-12.07.12 days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 01.08.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample
No. Description Casting for testing cubes conducted
identification no.
1 3 1. Weight of
04.07.12 01.08.12 R - 04.07.12 cube
2 Concrete
3 &
cubes of 05.07.12 02.08.12 R - 05.07.12 2. Compressive
3 mix 1:1.5:3
3 strength for 28
06.07.12 03.08.12 R - 06.07.12 days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 31.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1 27.06.12 25.07.12 Clm - 27.06.12 3 1. Weight of
2 3 cube
Concrete 28.06.12 26.07.12 Clm - 28.06.12
&
3 cubes of mix 29.06.12 27.07.12 Clm - 29.06.12 3 2. Compressive
4 1:1.5:3
3 strength for 28
30.06.12 28.07.12 R - 30.06.12 days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 23.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.

1 22.06.12 20.07.12 Clm-22.06.12 3 1. Weight of


cube
2 Concrete 23.06.12 21.07.12 Clm - 23.06.12
3 &
cubes of mix
25.06.12 23.07.12 Clm - 25.06.12
2. Compressive
3 1:1.5:3 3 strength for 28
4 26.06.12 24.07.12 Clm - 26.06.12 days.
3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 13.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.

1 12.06.12 10.07.12 PB-clm-12.06.12 3 1. Weight of


cube
Concrete
2 16.06.12 14.07.12 PB-16.06.12 &
cubes of mix 3 2. Compressive
1:1.5:3
3 strength for 28
4 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 11.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 1. Fineness - (in m2/kg)


Cement Cement Cement/15 2. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
3. Initial & final setting time
Cements & Week -27
4. Soundness
Minerals July/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 06.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1. Weight of
1 08.06.12 06.07.12 PB-Clm-08.06.12 3 cube
Concrete
&
2 cubes of
2. Compressive
mix 1:1.5:3 3
09.06.12 07.07.12 Clm-09.06.12 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 03.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 4. Fineness - (in m2/kg)


Cement Cement Cement/14 5. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
6. Initial & final setting time
Cements & Week -26
4. Soundness
Minerals June/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 03.07.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1. Weight of
1 04.06.12 02.07.12 Clm-04.06.12 3 cube
Concrete
&
2 cubes of
2. Compressive
mix 1:1.5:3 3
05.06.12 03.07.12 PB-Clm-05.06.12 strength for 28
days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 30.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.

1 Coarse Tammaraju PG/KNL/ 1. Determination of particle


aggregates Palli Quarry, BW/CA/13 size (Sieve analysis)
20mm M/s. KNR 2. Flakiness Index.
nominal size Constructions. 3. Crushing value.
4. Presence of deleterious materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 30.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 8 mm Dia. PG/KNL/
RINL Through
TMT bar BW/RS/15 1.Tensile Test
M/s. Swasthik
2 10 mm Dia. PG/KNL/ 2. Yield stress/Proof stress
Visakha Steels Pvt.
TMT bar BW/RS/16 3. Percentage elongation.
Ltd., Auth. Dealer,
3 12 mm Dia. PG/KNL/ 4. Bend/ Re-bend test.
Secunderabad
TMT bar BW/RS/17

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed sample.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:74 /DATE : 28.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Six (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification
No. Description Casting for testing cubes conducted
no.
1 28.05.12 25.06.12 R-CLM/28.05.12 3
1. Weight of
2 29.05.12 26.06.12 R-29.05.12 3 cube
3 Concrete 30.05.12 27.06.12 Clm-30.05.12 3 &
cubes of
4 31.05.12 28.06.12 Clm-31.05.12 2. Compressive
mix 1:1.5:3
5 01.06.12 29.06.12 Clm-01.06.12 strength for 28
6 days.
02.06.12 30.06.12 PB-Clm-02.06.12

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Six sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:74 /DATE : 21.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
23.05.12 20.06.12 PB/23.05.12 3
Concrete
2 Compressive
cubes of
24.05.12 21.06.12 PB-CLM/24.05.12 3 strength for
mix 1:1.5:3
3 28 days.
25.05.12 22.06.12 PB/25.05.12 3
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 13.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 7. Fineness - (in m2/kg)


Cement Cement Cement/13 8. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
9. Initial & final setting time
Cements & Week -23
4. Soundness
Minerals June/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:74 /DATE : 09.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the One (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
Concrete Compressive
CLM/12.05.12
1 cubes of 12.05.12 09.06.12 3 strength for
mix 1:1.5:3 28 days.
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

For Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:74 /DATE : 13.06.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
16.05.12 13.06.12 CLM/16.05.12 3
Concrete
2 Compressive
cubes of
17.05.12 14.06.12 CLM/17.05.12 3 strength for
mix 1:1.5:3
3 28 days.
18.05.12 15.06.12 CLM/18.05.12 3
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:74 /DATE : 31.05.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
02.05.12 29.05.12 PB-CLM/02.05.12 3
2
Concrete
03.05.12 30.05.12 PB-CLM/03.05.12 3 Compressive
cubes of
3 strength for
mix 1:1.5:3
05.05.12 31.05.12 R/05.05.12 3 28 days.
4
07.05.12 02.06.12 R-CLM/07.05.12 3
You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.
(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 30.05.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.

1 Coarse Tammaraju PG/KNL/ 1. Determination of particle


aggregates Palli Quarry, BW/CA/12 size (Sieve analysis)
20mm M/s. KNR 2. Flakiness Index.
nominal size Constructions. 3. Crushing value.
4. Presence of deleterious materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 28.05.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.

1 Fine Tadakanpalli Quarry, PG/KNL/ 1.Gradation/Determination of


aggregates Sri Sai BW/ FA/10 Particle size (Sieve analysis).
(Crushed Venkateswara Stone 2. Bulking.
stone) Crushers, Birapuram 3. Silt Content.
4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:70 /DATE : 25.05.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
28.04.12 25.05.12 CLM/28.04.12 3
2
Concrete
29.04.12 26.05.12 CLM/29.04.12 3 Compressive
cubes of
3 strength for
mix 1:1.5:3
30.04.12 27.05.12 R/30.04.12 3 28 days.
4
01.05.12 28.05.12 R/01.05.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:70 /DATE : 21.05.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
23.04.12 20.05.12 PB/23.04.12 3
2
Concrete
25.04.12 22.05.12 R/25.04.12 3 Compressive
cubes of
3 strength for
mix 1:1.5:3
26.04.12 23.05.12 PB/26.04.12 3 28 days.
4
27.04.12 24.05.12 R/27.04.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 11.05.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.

1 Fine Tadakanpalli Quarry, PG/KNL/


aggregates Sri Sai BW/ FA/08 1.Gradation/Determination of
(Crushed Venkateswara Stone Particle size (Sieve analysis).
stone) Crushers, Birapuram 2. Bulking.
3. Silt Content.
2 Fine Tadakanpalli Quarry, 4. Presence of deleterious
aggregates Sri Lakshmi PG/KNL/ materials.
(Crushed Venkateswara Stone BW/FA/09
stone) Crushers, Birapuram

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two nos. sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 08.05.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 10. Fineness - (in m2/kg)


Cement Cement Cement/12 11. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
12. Initial & final setting time
Cements & Week -19
4. Soundness
Minerals May/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 05.05.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the One (set)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
Concrete Compressive
1 cubes of 07.04.12 05.05.12 CLM/07.04.12 strength for
mix 1:1.5:3 3 28 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 30.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
02.04.12 30.04.12 CLM/02.04.12 3
2
Concrete
03.04.12 01.05.12 CLM/03.04.12 3 Compressive
cubes of
3 strength for
mix 1:1.5:3
04.04.12 02.05.12 CLM/04.04.12 3 28 days.
4
05.04.12 03.05.12 CLM/05.04.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:64 /DATE : 27.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete
30.03.12 27.04.12 PB&CLM/30.03.12 3 Compressive
cubes of
2 strength for
mix 1:1.5:3
31.03.12 28.04.12 R/31.03.12 3 28 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 26.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 13. Fineness - (in m2/kg)


Cement Cement Cement/11 14. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
15. Initial & final setting time
Cements & Week -17
4. Soundness
Minerals April/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 23.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 8 mm Dia. PG/KNL/
SAIL Through
TMT bar BW/RS/12 1.Tensile Test
M/s. Somani Ispat
2. Yield stress/Proof stress
2 12 mm Dia. Pvt. Ltd., Auth. PG/KNL/ 3. Percentage elongation.
TMT bar Dealer for Medchal BW/RS/13 4. Bend/ Re-bend test.
3 10 mm Dia. RINL, Vizag steel PG/KNL/
TMT bar M/s. Somani Ispat BW/RS/14
Pvt. Ltd.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed sample.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 23.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four (sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1
26.03.12 23.04.12 PB/26.03.12 3
2 Concrete
27.03.12 24.04.12 R/27.03.12 3 Compressive
cubes of
3 strength for
mix 1:1.5:3
28.03.12 25.04.12 RCLM/28.03.12 3 28 days.
4
29.03.12 26.04.12 PBR/29.03.12

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 16.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1 20.03.12 16.04.12 PB/20.03.12 3
Concrete Compressive
2 cubes of strength for 28
21.03.12 17.04.12 PB/21.03.12 3
mix 1:1.5:3 days.
3
22.03.12 18.04.12 PBR/22.03.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 12.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
1 16.03.12 12.04.12 PBC/16.03.12 3
2 Concrete
17.03.12 13.04.12 PB/17.03.12 3 Compressive
cubes of strength for 28
3 mix 1:1.5:3 days.
18.03.12 14.04.12 RC/18.03.12 3
4
19.03.12 15.04.12 RC/19.03.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:58 /DATE : 07.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Five(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
10.03.12 07.04.12 RC/10.03.12 3
1
2 11.03.12 08.04.12 Colm/11.03.12 3
Concrete Compressive
3 cubes of 12.03.12 09.04.12 Colm/12.03.12 3 strength for 28
mix 1:1.5:3 days.
4 14.03.12 10.04.12 PBC/14.03.12 3

5 15.03.12 11.04.12 PBC/15.03.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Five sealed samples.

For Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:57 /DATE : 02.04.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Five(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.
Sl. Material Date of Due date No. of Tests to be
Sample identification no.
No. Description Casting for testing cubes conducted
05.03.12 02.04.12 Raft/05.03.12 3
1
2 06.03.12 03.04.12 PB/06.03.12 3
Concrete Compressive
3 cubes of 07.03.12 04.03.12 Colm/07.03.12 3 strength for 28
mix 1:1.5:3 days.
4 08.03.12 05.04.12 Raft/08.03.12 3

5 09.03.12 06.04.12 Raft/09.03.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Five sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 29.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.
1.Gradation/Determination of
1 Fine aggregates Handri River, PG/KNL/ Particle size (Sieve analysis).
Near village BW/ FA/07 2. Bulking.
Lakshmipuram 3. Silt Content.
4. Presence of deleterious materials.
2 Coarse Tammaraju
aggregates Palli Quarry, PG/KNL/ 1. Determination of particle
20mm M/s. KNR BW/CA/10 size (Sieve analysis)
nominal size Constructions. 2. Flakiness Index.
3 40mm PG/KNL/ 3. Crushing value.
nominal size BW/CA/11 4. Presence of deleterious materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three nos. sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 29.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 16. Fineness - (in m2/kg)


Cement Cement Cement/10 17. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
18. Initial & final setting time
Cements & Week -12
4. Soundness
Minerals March/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 27.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
3
1 28.02.12
27.03.12 PB/28.02.12
Concrete Compressive
2 cubes of 29.02.12 3 strength for 28
28.03.12 Clm/29.02.12
mix 1:1.5:3 days.
3 01.03.12 3
29.03.12 Clm/01.03.12

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 26.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 19. Fineness - (in m2/kg)


Cement Cement Cement/09 20. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
21. Initial & final setting time
Cements & Week -11
4. Soundness
Minerals March/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:51 /DATE : 19.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1
20.02.12 19.03.12 PB/20.02.12 3
Concrete Compressive
2 cubes of 22.02.12 21.03.12 PB/22.02.12 3 strength for 28
mix 1:1.5:3 days.
3 25.02.12 24.03.12 Raft/25.02.12

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:51 /DATE : 16.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD
Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 17.02.12 16.03.12 RAFT/17.02.12 3 Compressive
cubes of strength for 28
2 mix 1:1.5:3 18.02.12 17.03.12 Colm/18.02.12 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 14.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 22. Fineness - (in m2/kg)


Cement Cement Cement/08 23. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
24. Initial & final setting time
Cements & Week -10
4. Soundness
Minerals March/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 05.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 8 mm Dia. PG/KNL/
SAIL
TMT bar BW/RS/09 1.Tensile Test
Through
2 10 mm Dia. PG/KNL/ 2. Yield stress/Proof stress
M/s. Sojiram Ispat
TMT bar BW/RS/10 3. Percentage elongation.
Pvt. Ltd., Auth.
3 12 mm Dia. PG/KNL/ 4. Bend/ Re-bend test.
Dealer for Medak
TMT bar BW/RS/11

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed sample.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 05.03.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 25. Fineness - (in m2/kg)


Cement Cement Cement/07 26. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
27. Initial & final setting time
Cements & Week -8
4. Soundness
Minerals Feb/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12:47 /DATE : 05.03.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1
04.02.12 03.03.12 R/04.02.12 3
Concrete Compressive
2 cubes of 06.02.12 05.03.12 Clm/06.02.12 3 strength for 28
mix 1:1.5:3 days.
3 08.02.12 07.03.12 Clm/08.02.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 27.02.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1
30.01.12 27.02.12 Colm/ 30.01.12 3
Concrete Compressive
2 cubes of 01.02.12 29.02.12 PBR/ 01.02.12 3 strength for 28
mix 1:1.5:3 days.
3 02.02.12 01.03.12 Colm/02.02.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 21.02.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.
1.Gradation/Determination of
1 Fine Handri River, PG/KNL/ Particle size (Sieve analysis).
aggregates Near village BW/ FA/06 2. Bulking.
Lakshmipuram 3. Silt Content.
4. Presence of deleterious materials.
2 Coarse Tammaraju 1. Determination of particle
aggregates Palli Quarry, PG/KNL/ size (Sieve analysis)
20mm M/s. KNR BW/CA/09 2. Flakiness Index.
nominal Constructions. 3. Crushing value.
size 4. Presence of deleterious materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.
Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.
Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two nos. sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 21.02.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1
Concrete 24.01.12 21.02.12 PBC/ 24.01.12 3 Compressive
cubes of strength for 28
2 mix 1:1.5:3 25.01.12 22.02.12 Colm/ 25.01.12 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 18.02.2012.

To,
The Executive Director
M/s. S.M. Consultants
Plot no. 58, Chandragiri Colony
Thirumalagiri, Secunderabad

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 28. Fineness - (in m2/kg)


Cement Cement Cement/06 29. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
30. Initial & final setting time
Cements & Week -6
4. Soundness
Minerals Feb/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 16.02.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1
Concrete 19.01.12 16.02.12 PB/ 19.01.12 3 Compressive
cubes of strength for 28
2 mix 1:1.5:3 21.01.12 18.02.12 Colm/ 21.01.12 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 06.02.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Five(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 09.01.12 06.02.12 PB/ 09.01.12 3
2 Concrete 10.01.12 07.02.12 PBC/ 10.01.12 3
Compressive
3 cubes of 11.01.12 08.02.12 RC/ 11.01.12 3 strength for 28
4 mix 1:1.5:3 12.01.12 09.02.12 Clm/12.01.12 3 days.
5 13.01.12 10.02.12 PBC/13.01.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Five sealed samples.

(P. Nageswara Rao)


Engineer
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 03.02.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Water - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following sample (in sealed condition) of Water
for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
Chemical & Physical
1 Water Bore well in PG/KNL/ properties of water for
Sample ORVAKAL BW/W/02 checking its suitability
village for construction purpose.
(As per IS 456, IS 3025)

You are requested to conduct the above tests with relevant IS codes/specifications and furnish
the results to the Engineer in charge Chief Manager, I/C, CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of water.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 12: /DATE : 02.02.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1.Gradation/Determination of
1 Fine Handri River, PG/KNL/ BW/ Particle size (Sieve analysis).
aggregates Near village FA/05 2. Bulking.
Lakshmipuram 3. Silt Content.
4. Presence of deleterious
Materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 02.02.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 05.01.12 02.02.12 PB/ 05.01.12 3 Compressive
2 cubes of 06.01.12 03.02.12 PB/ 06.01.12 3 strength for 28
3 mix 1:1.5:3 07.01.12 04.02.12 PBC/ 07.01.12 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 27.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 29.12.11 26.01.12 PB/ 29.12.11 3 Compressive
2 cubes of 30.12.11 27.01.12 PBC/ 30.12.11 3 strength for 28
3 mix 1:1.5:3 31.12.11 28.01.12 PB/ 31.12.11 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 23.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 26.12.11 23.01.12 PB/ 26.12.11 3 Compressive
2 cubes of 27.12.11 24.01.12 PB/ 27.12.11 3 strength for 28
3 mix 1:1.5:3 28.12.11 25.01.12 Clm/ 28.12.11 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 19.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 31. Fineness - (in m2/kg)


Cement Cement Cement/05 32. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
33. Initial & final setting time
Cements & Week -2
4. Soundness
Minerals Jan/2012 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 17.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 20.12.11 17.01.12 RC/ 20.12.11 3
Concrete 21.12.11 18.01.12 PB/ 21.12.11 3 Compressive
2
cubes of strength for 28
3 22.12.11 19.01.12 PB/ 22.12.11 3
mix 1:1.5:3 days.
4 23.12.11 20.01.12 PB/ 23.12.11 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 13.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
JNTU COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 16.12.11 13.01.12 RC/ 16.12.11 3 Compressive
2 cubes of 17.12.11 14.01.12 RC/ 17.12.11 3 strength for 28
3 mix 1:1.5:3 19.12.11 16.01.12 PBC/19.12.11 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 09.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
G. PULLA REDDY ENGINEERING COLLEGE
KURNOOL

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 12.12.11 09.01.12 Colmn/ 12.12.11 3 Compressive
2 cubes of 13.12.11 10.01.12 Colmn/ 13.12.11 3 strength for 28
3 mix 1:1.5:3 15.12.11 12.01.12 Colmn/15.12.11 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 06.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 34. Fineness - (in m2/kg)


Cement Cement Cement/04 35. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
36. Initial & final setting time
Cements & Week -52
4. Soundness
Minerals Dec/2011 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:12: /DATE : 05.01.2012.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1. Determination of particle
1 Coarse Tammaraju Palli PG/KNL/ size (Sieve analysis)
aggregates Quarry, BW/CA/08 2. Flakiness Index.
20mm nominal M/s. KNR 3. Crushing value.
size Constructions. 4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 30.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 8 mm Dia. SAIL PG/KNL/ 1.Tensile Test
TMT bar Through BW/RS/08 2. Yield stress/Proof stress
M/s. Noor Steel 3. Percentage elongation.
Traders, Kurnool 4. Bend/ Re-bend test.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 29.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
G. PULLA REDDY ENGINEERING COLLEGE
KURNOOL

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 1.12.11 29.12.11 Colmn/ 01.12.11 3
Concrete 2.12.11 30.12.11 Colmn/ 02.12.11 3 Compressive
2
cubes of strength for 28
3 3.12.11 31.12.11 Colmn/03.12.11 3
mix 1:1.5:3 days.
4 5.12.11 02.01.12 Colmn/02.01.12 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 24.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 10 mm Dia. SAIL PG/KNL/
TMT bar Through BW/RS/06 1.Tensile Test
M/s. Sojiram Ispat 2. Yield stress/Proof stress
2 12 mm Dia. Pvt. Ltd., Auth. PG/KNL/ 3. Percentage elongation.
TMT bar Dealer for Medak BW/RS/07 4. Bend/ Re-bend test.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed sample.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 23.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 37. Fineness - (in m2/kg)


Cement Cement Cement/03 38. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
39. Initial & final setting time
Cements & Week -51
4. Soundness
Minerals Dec/2011 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 21.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
G. PULLA REDDY ENGINEERING COLLEGE
KURNOOL

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Five(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 24.11.11 21.12.11 PB/ 24.11.11 3
2 Concrete 26.11.11 23.12.11 PB/ 26.11.11 3
Compressive
3 cubes of 28.11.11 25.12.11 Raft/28.11.11 3 strength for 28
4 mix 1:1.5:3 29.11.11 26.11.11 PB/29.11.11 3 days.
5 30.11.11 27.11.11 PBC/30.11.11 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Five sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 13.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Four(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 15.11.11 13.12.11 Column/ 15.11.11 3
Concrete 16.11.11 14.12.11 C&R/ 16.11.11 3 Compressive
2
cubes of strength for 28
3 17.11.11 15.12.11 Column/17.11.11 3
mix 1:1.5:3 days.
4 18.11.11 16.11.11 P. B/18.11.11 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Four sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 06.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 08.11.11 06.12.11 Column/ 08.11.11 3 Compressive
2 cubes of 12.11.11 10.12.11 RAFT/ 12.11.11 3 strength for 28
mix 1:1.5:3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 11: /DATE : 26.11.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials RR Stone - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
Random Rubble Stone for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
a) Compressive strength
1 Random Bukkapuram PG/KNL/
Rubble Stone Quarry BW/RRS/02 b) Water absorption
Samples (a,b,c)
Suitability as per CPWD
specifications for RR masonry.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three nos. sealed samples of RR Stones.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 26.11.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 40. Fineness - (in m2/kg)


Cement Cement Cement/02 41. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
42. Initial & final setting time
Cements & Week -47
4. Soundness
Minerals Nov/2011 (Le chatelier Method)

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 12.12.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1 12 mm Dia SAIL PG/KNL/ 1. Tensile Test
TMT bar Through BW/RS/05 2. Yield stress/Proof stress
M/s. Noor Steel 3. Percentage elongation.
Traders, Kurnool 4.Bend/ Rebend test.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 26.11.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Three(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 29.10.11 26.11.11 RAFT/ 29.10.11 3 Compressive
2 cubes of 31.10.11 28.11.11 RAFT/ 31.10.11 3 strength for 28
3 mix 1:1.5:3 01.11.11 29.11.11 RAFT/01.11.11 3 days.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C)
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 12.11.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Concrete cubes - reg.

Construction of Boundary wall at proposed 765/400KV Substation of at POWERGRID,


Kurnool is under progress. As per our Standard Field quality plan, concrete cubes collected
during RCC work shall be got tested. Accordingly we are sending here with the Two(sets)
samples (3 cubes each set) in sealed condition for conducting the tests at your lab as mentioned
against each sample.

Sl. Material Date of Due date No. of Tests to be


Sample identification no.
No. Description Casting for testing cubes conducted
1 Concrete 15.10.11 12.11.11 RAFT/ 15.10.11 3 Compressive
cubes of strength for 28
mix 1:1.5:3 days.
2 17.10.11 14.11.11 COLM/ 17.10.11 3

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Two sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 10.10.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Reinforcement steel - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
Reinforcement steel for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
8 mm Dia SAIL PG/KNL/ 1. Tensile Test
1 TMT bar Through BW/RS/01 2. Yield stress/Proof stress
2 10 mm Dia M/s. Noor Steel PG/KNL/ 3. Percentage elongation.
TMT bar Traders, Kurnool BW/RS/02 4.Bend/ Rebend test.
3 12 mm Dia PG/KNL/
TMT bar BW/RS/03

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.:11: /DATE : 19.09.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1. Determination of particle
1 Coarse Tammaraju Palli PG/KNL/ size (Sieve analysis)
aggregates Quarry, BW/CA/05 2. Flakiness Index.
20mm nominal M/s. KNR 3. Crushing value.
size Constructions. 4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 11: /DATE : 14.09.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Cement - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of Cement
(one bag) for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description

1 OPC 43 Gr Super Panyam PG/KNL/ BW/ 43. Fineness


Cement Cement Cement/01 44. Compressive strength
M/s. Panyam (for 3 days, 7 days & 28 days)
45. Initial & final setting time
Cements & Week -37
4. Soundness
Minerals Sept/2011

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of cement bag.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 11: /DATE : 14.09.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
Coarse Tammaraju Palli 1. Determination of particle
1 aggregates Quarry, PG/KNL/ BW/ size (Sieve analysis)
40mm nominal M/s. KNR CA(40mm)/06 2. Flakiness Index.
size Constructions. 3. Crushing value.
4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: SRTS-1:CAO:KNL:SSC:Civil:B.W.: 11: /DATE : 14.08.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
1.Gradation/Determination of
1 Fine Handri River, PG/KNL/ BW/ particle size (Sieve analysis).
aggregates Near village FA/04 2. Bulking.
Lakshmipuram 3. Silt Content.
4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 04.08.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
Coarse Tammaraju Palli 1. Determination of particle
1 aggregates Quarry, PG/KNL/ size (Sieve analysis)
20mm nominal M/s. KNR BW/CA/04 2. Flakiness Index.
size Constructions. 3. Crushing value.
4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 05.08.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
Fine Handri River, 1.Gradation/Determin
1 aggregates Near village PG/KNL/ BW/ ation of particle size
Lakshmipuram FA/03 (Sieve analysis).
2. Bulking.
3. Silt Content.
4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 04.08.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials RR Stone - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
Random Rubble Stone for conducting the tests at your lab as mentioned against each
sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
a) Compressive strength
1 Random Tadakanapalli PG/KNL/
Rubble Stone Quarry BW/RRS/01 b) Water absorption
Samples
Suitability as per CPWD
speicifications for RR masonry.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Three nos. sealed samples of RR Stones.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 04.08.2011.

To,
The Principal/ Head of Civil Engg. Dept.
J.N.T.U. COLLEGE OF ENGINEERING
HYDERABAD

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got
tested. Accordingly we are sending here with the following samples (in sealed condition) of
aggregates for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
Coarse aggregates Tammaraju Palli 1. Determination of particle
1 40mm nominal Quarry, PG/KNL/ BW/ size (Sieve analysis)
size M/s. KNR CA(40mm)/05 2. Flakiness Index.
Constructions. 3. Crushing value.
4. Presence of deleterious
materials.

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 30.07.2011.

To,
The Principal/ Head of Civil Engg. Dept.
G. PULLA REDDY ENGG. COLLEGE
KURNOOL

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Soil for Safe Bearing Capacity - reg.

To finalise the foundation for construction of Boundary of 765/400 KV Substation the


soil samples at various depths is to be tested. Accordingly we are sending here with the
following samples (in sealed condition) of Soil for conducting the tests at your lab as
mentioned against each sample.

Sl. Material Sample Depth Sample ID No. Tests to be


No. Description conducted
UDS & DS 1.0 to 1.3 PG/KNL/SOIL/01
1 Soil UDS & DS 1.5 to 1.8 PG/KNL/SOIL/02 Safe Bearing
Samples UDS & DS 2.7 to 3.0 PG/KNL/SOIL/03 Capacity

You are requested to arrange for conducting the above tests with relevant IS
codes/specifications and furnish the results to the Engineer in charge Chief Manager, I/C,
CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by us to your accounts Dept.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Each Three nos. UDS & DS
sealed samples of soils.
(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 20.07.2011.

To,
The Principal/ Head of Civil Engg. Dept.
G. PULLA REDDY ENGG. COLLEGE
KURNOOL

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Water - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following sample (in sealed condition) of Water
for conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID No. Tests to be conducted


No. Description
Kalva Bugga PG/KNL/ Chemical & Physical
1 Water Near Kalva Bugga BW/W/01 properties of water for
Sample vill. checking its suitability
for construction purpose.
(As per IS 456, IS 3025)

You are requested to conduct the above tests with relevant IS codes/specifications and furnish
the results to the Engineer in charge Chief Manager, I/C, CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,

Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : One sealed sample of water.

(TRC Murty)
Manager(C )
CAO, Kurnool
/REF: -1:
: : :..: 11: /DATE : 20.07.2011.

To,
The Principal/ Head of Civil Engg. Dept.
G. PULLA REDDY ENGG. COLLEGE
KURNOOL

Dear Sir,

SUB : Construction of Boundary wall and Security Room at 765KV Kurnool Substation
Testing of Construction materials Coarse & Fine aggregates - reg.

As per our Standard Field Quality Plan, all material used for above work shall be got tested.
Accordingly we are sending here with the following samples (in sealed condition) of aggregates for
conducting the tests at your lab as mentioned against each sample.

Sl. Material Source Sample ID Tests to be conducted


No. Description No.
Coarse aggregates a) Gaddenakonda Quarry, 1. Determination of
1 20mm nominal M/s. Sri Mahalakshmi Stone PG/KNL/ particle size (Sieve
size Crushers, Near Tamma BW/CA/01 analysis)
Rajupalle vill. 2. Flakiness Index.
2 Coarse aggregates b) Venkatapuram Quarry, M/s. 3. Crushing value.
20mm nominal Sri Madhava Stone Crushers, PG/KNL/ 4. Presence of
size Near Venkatapuram vill BW/CA/01 deleterious materials.
3 Coarse aggregates a) Gaddenakonda Quarry, M/s. PG/KNL/
40mm nominal Raja Rajeswari Stone Crushers, BW/CA
size Near Tamma Rajupalle vill. (40mm)/01
Fine aggregate Tungabhadra River PG/KNL/ 1.Gradation/Determin
4 Near Munagalapadu vill BW/FA/01 ation of particle size
(Sieve analysis).
5 Fine aggregate Handri River PG/KNL/ 2. Bulking.
Near Venkannabavi vill BW/FA/02 3. Silt Content.
4. Presence of
deleterious materials.

You are requested to conduct the above tests with relevant IS codes/specifications and furnish the
results to the Engineer in charge Chief Manager, I/C, CAO, POWERGRID, Kurnool.

Applicable test charges will be paid by our contractor M/s. Saiteja Constructions, Hyderabad.

Thanking you,
Yours faithfully,
for and on behalf of POWERGRID
Enclrs. : Five sealed samples.

(TRC Murty)
Manager(C )
CAO, Kurnool
Sieve Analysis:

PERCENTAGE PASSING FOR GRADED


IS SIEVE AGGREGATE OF NOMINAL SIZE
DESIGNATION 40 mm 20 mm

40 mm 95 to 100 100

20 mm 30 to 70 95 to 100

10 mm 10 to 35 25 to 55

4.75 mm 0 to 5 0 to 10

PERCENTAGE PASSING FOR GRADED


IS SIEVE AGGREGATE OF NOMINAL SIZE
DESIGNATION 40 mm 20 mm

40 mm 95 to 100 100

20 mm 30 to 70 95 to 100

10 mm 10 to 35 25 to 55

4.75 mm 0 to 5 0 to 10