Alcatel lucent bts offline & commissioning

1. 1. Presented by ENG: Ahmed Mohammed NabiehSupervised by ENG : Amr Abd


ElkreemAlcatel Lucent BTSOffline & Commissioning
2. 2. Introduction
3. 3. The BTS commissioning & SW files are stored on the station unit
module(SUMA)The Station unit module is the core of the BTS ,it is responsible for
The O&M Functions such as Alarms reporting ,BTS Configuration,internal Power
Supply control & clock generation and distribution Transmission functions by
connecting the BTS to the BSC through theABIS cable.The ABIS can carry up to 32
time slots 0 to 30 are assigned to the TRES for normal traffic(voice and
Dataservices) 31 : is assigned to the OMU in the SUMA card for signaling
(Controlinformation) between BSC & BTS such as Alarm reporting ,BTSMaster file
Download, configuration files etc..
4. 4. LED Color Status DescriptionOML Yellow On BTS is supervised and connected to
the BSCBlinking BTS & BSC link is being establishedOff Link disconnected.ABIS
Yellow On Abis 1 is connected and can serve TCH/SignalingBlinking There are
Alarms on the ABISOff Not configured or not used.O&M Yellow On SUMA master file
& configuration are present in theEPROMBlinking In a transient state, SUMA is
loading the BTS MSF &Configuration file from the BSCOff Not used.FAULTRED On
Fatal alarm on BTS Module (ANC,TRE etc ..)Blinking Non-fatal alarm. Such as Faulty
Fan unitOff No alarm.SUMAcard led statusindication
5. 5. Offline
6. 6. Switch the BTS off by pushing down its DC C/BS
7. 7. Unscrew the ABIS Cable
8. 8. Open BTS SW and TypeUser Name : commtePassword : bts2site
9. 9. Go to Configuration Click On BTS Software Download
10. 10. Press the folder icon to start choosing the BTS Files
11. 11. Select Master File from the BTS SW folder
12. 12. Select 0CPF File from the BTS SW folder
13. 13. Wait for the BTS to download all the files ,During the SWDownload the Suma
LED Status will be :OML ,ABIS & O&M Flashinglast file to be downloaded is the
OCPF 002 file after that the O&Mwill be solid
14. 14. Commissioning
15. 15. From Configuration choose BTS Commissioning
16. 16. Click on Start Commissioning
17. 17. Notice that the status of the commissioning changed from notrunning to running
18. 18. Edit Q1 address by clicking its start button
19. 19. Edit Remote Inventory by clicking its start button and pressYES : if the update is
already done in the Remote InventorypanelsNO : if the update is not done in the
Remote Inventory panels
20. 20. Edit Sector Mapping by clicking its start buttonAssign sector-ID to each
combiner and then press ok
21. 21. Edit Twin-Settings by clicking its start buttonChoose the mode of each Twin-TRE
, usually in our networkwe leave at the default which is Dual TRE
22. 22. Hardware check by clicking its start buttonthe Suma card will start to check the
HW available insidethe BTS through the RI-Cable
23. 23. INIT _ALL_SECT by clicking its start buttonthe SUMA card will power on all the
combiners and TRES tocheck their operation
24. 24. Choose End commissioning ,Stop commissioning window will appearchoose ok
after moving all the modules in the selected module windowWait for the BTS to
restart itself SW and then connect the Abis cable.
25. 25. Finally restart the BTS HWthe SUMA led status should be as following :Abis &
OML are solidO&M Flashing as the BTS loading its data and RSLs from the BSC
26. 26. The loading process will take 15 to 20 Minutes ,after that theO&M Led will be
solid and the SUMA will initialize theBTS sectors (Combiners & TRES)
27. 27. The BTS Terminal program will start to load the BTS DataTake snapshots and
check with OMC