HIGHWAY & TRAFFIC ENGINEERING LABORAT0RY JOURNAL

RING AND BALL TEST (SOFTENING POINT TEST)


Muhammad Farhan Bin Ibrahim, Muhammad Efendi Bin Asmat, Mohamad Adlan Bin Zamri,
Muhammad Afif Rusydi Bin Md Khalil, Nur Izzati Emalia Bt Azhar, Erin Marissa Bt Ramlan ,
Maizatul Aqmar Bt Yusup, Zaila Maizuroh Bt Abd Muin

Abstract

The morphology of this test is that softening point is the temperature at which the
substance achieve a specific degree of softening under specified condition of the
test.The Softening Point of bitumen is the temperature at which the substance achieve
specific of softening. When heated under water at specified condition and specific
temperature in C at which a standard ball passes through a sample of mould and falls
through a height of 2.5 cm. The purpose of softening point helps to know the
temperature up to which a bituminous binder should be heated for different road use
application.The ring and ball apparatus determine the softening point .

Keywords:softening point,temperature,bitumen,degree of softening,ring and balls

INTRODUCTION

The ring and ball test is for determining


the softening point of bitumen. The temperature at which each ball
Softening point can be defined as the touches a bar near the bottom is called
temperature at which a substance the softening point. A high softening
achieve a specific degree of softness point is preferable to a low one. In
under specified condition test. The addition, if the two balls drop at
softening point is useful in the temperatures more than 2 degrees apart,
classification of bitumen. the test is invalidated and must be
repeated.The ring and ball test is
The ring and ball softening point test important for testing the bitumen
involve heating two small samples of the material for road/highway project.Being
bitumen in a container of water.The ring very simple in concept and equipment
is immersed to a depth such that its the ring and bell has remained a valuable
bottom is exactly 25mm(1in) above the consistency test for control in refining
bottom of the bath. The temperature of operations particularly in the production
the bath is then gradually of air blown bitumen. It is also an
increased,causing the bitumen to soften indirect measure of viscosity is evident.
and permitting the ball to sink The softening point value has particular
eventually to the bottom of the bath. A significance for materials which are to
metal ball is placed on top of each ring be used as thick films such as joint and
sample. crack filters and roofing material. A high
softening point ensures that they will not
flow in services. For bitumen of a given
penetration determined at 25C the
higher the softening point the lower the
temperature sensitivity.
HIGHWAY & TRAFFIC ENGINEERING LABORAT0RY JOURNAL

OBJECTIVE

To determine the Softening Point of


Bitumen by ring and ball method.
The temperature which the bitumen
achieve consistent under the specified
condition of the test is called softening
point of bitumen.At give the temperature PROCEDURE
at which the bitumen plastic state to
liquid state.
1. The sample has to be heated at a
temperature between 75C and
Apparatus 100C, until its stir to a completely
fluid and free from air bubbles.
1. Standard ring-and-ball test 2. Poured the asphalt into the ring and
apparatus cooled at room temperature for
approximately 30 minutes,to level
the temperatures.
2. Thermometer
3. To place the ring on the ring holder.
3. Bath Maintain the temperature in the
water bath to 5 1C for 40 minutes
and keep the sample in the water
4. Bath liquid (water) bath and a level of not less than 102
mm and not more than 108mm from
the bottom of the bath
5. Stirrer
4. Forceps are used to place the ball in
6. Heater each ball-centering plate guide.
Heat is applied at a rate 5C per
minute to ensure the uniformly its
7. Stopwatch increase

5. Each ring and ball temperature


shown by the thermometer is
recorded when the specimen
surrounding the ball touches the
bottom plate

6. The mean of the temperatures


recorded is determined as the
softening point.

RESULT

The result which obtained from the test


is as follow:For bitumen grade 80/100

Instant Softening
Ring No. Temperature, Point,
C Average C
Figure 1:Ring and Ball softening point A 60
apparatus
B 52 56

2
Example calculation =60C + 52C
2
Average = ball 1 + ball 2 =56 C
HIGHWAY & TRAFFIC ENGINEERING LABORAT0RY JOURNAL

we can see that the ball pass the bitmen


DISCUSSION at the difference time and temperature of
56C.This may result from mistake from
From the observation/result, which was human error .
done, we found that the value for the
ring and ball test is 56C .In this RECOMMENDATION
experiment the bitumen samples are
ready at the temperature of 30C to Softening point indicates the
100C, and the bitumen is ready pour at temperatures at which binders posses the
a pair of the brass ring. After this, the same viscosity. Bituminious materials do
ring is suspended in breaker filled with not have a melting point. Rather, the
distilled water at 5C and this change of state from solid to liquid is
temperature is maintained for 5 minutes. gradual over a wide range of
temperature. Softening point has
This is important to obtain an accurate particular signifacance for materials to
penetration result. The steel ball were be used as joint and crack fillers. Higher
place not carefully at the center of the softening point ensures that they will not
brass ring, precaution does not taken flow during service. The higher the
such as the steel ball are not been softening point , the lesser the
screwed tightly at the center of the ring. temperature susceptibility. Bitumen with
After that,the water will heated and higher softening point is preferred in
stirred at a controlled rate of 5C per warmer places .
minute and the temperature will record
at every minute.
CONCLUSION
The temperature of the bath will
gradually increase , causing the bitumen From the experiment above , after
to soften and permitting the ball to sink performing the ring and ball test on the
eventually to the bottom of the beaker, bitumen sample given, it is found that
the temperature which the softened the softening point of the bitumen is at
bitumen sinks will be recorded. But the 56C . Its mean that , the bitumen
there is some mistake with placing the when pour at site for the roadway
bitumen on the brass ring .Hence, the construction will behave softly at that
difference temperature for both bitumen temperature and before design for road
is exceed 1C. The result of the ring and pavement, the softening point must take
ball test will compare with the result of into account so that will reduce the
the penetration test to get the properties maintainance for the road. We didnt
of Asphalt according to PI value . have any problem while doing this test;
We have tried our best to achieve the
To get more accurate and valid result objective of the test. Avoid bringing in
ensures that the water bath temperature and bringing out the standard ring-and
is maintained at 5 1C. -ball test holder to being used and the
progress running smoothly. We are
Temperature is the main factors that success to maintain the temperature in
control the sample result. To get an the water bath at 5 1C for 5 minutes.
accurate result the water temperature is Temperatures is important while paving
increased using a heater. If the sample the road .It can cause settlement of the
heated with a high temperature, the vehicle wheel. So this experiment is
bitumen will melts and the balls can pass necessary to be done for knowing that
through. Compare to ball 1 and ball 2,
HIGHWAY & TRAFFIC ENGINEERING LABORAT0RY JOURNAL

what is the temperature applicable to


determine the softening of bitumen.
Penetration is related to viscosity and
empirical relationship have been developed
REFERENCE for Newtonian materials. If penetration is
B.L. Pearce, Comparison of measured over a range of temperatures, the
Temperature Variations For temperature susceptibility of the bitumen can
Softening Point Apparatus With be established. The nomograph as given in
Varying Filler: Binder Ratio, Cape Table 1 enables the PI to be deduced
Technikon, Department of Civil approximately from the penetration at 25C
Engineering PO Box 652, Cape and the softening point temperature. Typical
Town,8000 values of PI are

Bitumen Type PI
ASTM(1998).D26-95 Standard test
method for softening point of Blown Bitumen >2
bitumen(Ring-and-Ball Apparatus) Conventional Paving Bitumen -2 to +2
1998 Annual Books of ASTM Temperature Susceptible Bitumen <-2
Standards, Volume V04.04, Table 1
American Society for Testing and
Materials, Philadelphia, PA 19103- PI values can be used to determine the
1187. stiffness (modulus) of bitumen at any
temperature and loading time. It can also, to a
ASTM (1978): Standard Tests limited extent, be used to identify a particular
Method for Resistance to Plastic type of bituminous material. One drawback
Flow of Bituminous Mixtures using of the PI system is that it uses the change in
Marshall Apparatus. Annual Book bitumen properties over a relatively small
of ASTM Standards, Part 15, pp.425 range of temperatures to charactize bitumen;
-433. extrapolations to extreme of the behavior can
be sometimes be misleading.
As we have done the both test, When the ring
and ball test is compared to the penetration
test, the value of penetration index (PI) is
almost zero (refer to appendix) it means
-2<PI<+2. So from the Table 1 we can say
that the bitumen will classify as Conventional
Paving Bitumen .