Vous êtes sur la page 1sur 17

UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

ANALISIS DE COSTOS UNITARIOS DE ENCOFRADO Y

DESENCOFRADO

1. ZAPATA.

a) METRADO DE MADERA
TABLAS DE 1 X 8 X 3.28
1 X 8 X 3.28
A. 7 .5 X 2 X ( )=32.8pie2
12
1 X 8 X 3.28
5 .5 X 2 X ( ) =24.05pie2
B. 12
ARRIOSTRES HORIZONTALES O BARROTE S
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

2 X 2 X 4.8
C. 2 X 2X ( )=6.4pie2
12
2 X 2 X 3.6
D. 2 X 2X ( )=4.8
12
ARRIOSTRES INCLINADO S
2 X 3 X 3.28
E. 2 X 2X ( )=6.56pie2
12
2 X 3 X 3.28
F. 2 X 2X ( )= 6.56pie2
12
MADERA EN PIES CUADRADOS=81.17 pie 2

b) METRADO DEL ELEMENTO EST RUCTURAL EN ARE A


P=5 m

h=0.50
A=5x0.50=2.5m2

2.5m2 81.17pie2
1m2 x

X=32.47pie2

c) NUMERO DE USOS
Para 5 usos
32.47
=6.49
1m2= 5

1m2=6.49pie2

UNIDAD METRADO CU PARCIAL


ENCOFRADO Y
DESENCOFRADO M2 0

ANALISIS DE COSTOS UNITARIOS

RENDIMIENT 14 M2/DIA
O
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

JORNADA 8 HORAS/DIA

CUADRILL
RECURSOS UNIDAD A CANTIDAD PRECIO PARCIAL
0.57142857
OPERARIO HH 1 1 10 5.714285714
0.57142857
OFICIAL HH 1 1 8.4 4.8
0.57142857
PEON HH 1 1 7.6 4.342857143
ALAMBRE NEGRO N8 kg 0.21 3.81 0.8001
CLAVOS kg 0.12 3.81 0.4572
MADERA PARA
ENCOFRADO p2 6.49 3.75 24.3375
PETROLEO gln 0.15 12.71 1.9065
HERRAMIENTAS 0.74285714
MANUALES %MO 5 3 3.714285714

2. CIMIENTO CORRIDO PARA UNA DISTANCIA DE 3 METROS

METRADO DE MADERA
TABLAS DE 1 X 8 X 10
1 X 8 X 10
3X2X ( )=40pie2
12
ARRIOSTRES VERTICALES O BARROTE S
2 X 2 X 3.28
4 X 2X ( )=8.75pie2
12
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

ARRIOSTRES INCLINADO S
2 X 3 X 3.28
8X2X ( )=26.24pie2
12
MADERA EN PIES CUADRADOS=74.99 pie2

METRADO DEL ELEMENTO ESTRUCTURAL EN ARE A


P=6 m

h=0.50
A=5x0.50=3m2

3m2 74.99pie2
1m2 x

X=24.99pie2

NUMERO DE USOS
Para 5 usos
24.99
=4.99
1m2= 5

1m2=4.99pie2

UNIDAD METRADO CU PARCIAL


ENCOFRADO Y
DESENCOFRADO M2 0

ANALISIS DE COSTOS UNITARIOS

RENDIMIENT
O 24 M2/DIA
JORNADA 8 HORAS/DIA

CUADRILL
RECURSOS UNIDAD A CANTIDAD PRECIO PARCIAL
0.33333333
OPERARIO HH 1 3 10 3.333333333
0.33333333
OFICIAL HH 1 3 8.4 2.8
PEON HH 1 0.33333333 7.6 2.533333333
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

3
ALAMBRE NEGRO N8 kg 0.21 3.81 0.8001
CLAVOS kg 0.12 3.81 0.4572
MADERA PARA
ENCOFRADO p2 4.99 3.75 18.7125
PETROLEO gln 0.15 12.71 1.9065
HERRAMIENTAS 0.43333333
MANUALES %MO 5 3 2.166666667

3. SOBRECIMIENTO DE 3 METROS DE LONGITUD


UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

METRADO DE MADERA
TABLAS DE 1 X 8 X 10
1 X 8 X 10
3X2X ( )=40pie2
12
ARRIOSTRES VERTICALES O BARROTE S
2 X 2 X 3.28
4 X 2X ( )=8.75pie2
12
ARRIOSTRES INCLINADO S
2 X 3 X 3.28
8X2X ( )=26.24pie2
12
MADERA EN PIES CUADRADOS=74.99 pie2

METRADO DEL ELEMENTO ESTRUCTURAL EN ARE A


P=6 m

h=0.50
A=5x0.50=3m2
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

3m2 74.99pie2
1m2 x

X=24.99pie2

NUMERO DE USOS
Para 5 usos
24.99
=4.99
1m2= 5

1m2=4.99pie2

UNIDAD METRADO CU PARCIAL


ENCOFRADO Y
DESENCOFRADO M2 0

ANALISIS DE COSTOS UNITARIOS

RENDIMIENT
O 28 M2/DIA
JORNADA 8 HORAS/DIA

CUADRILL
RECURSOS UNIDAD A CANTIDAD PRECIO PARCIAL
0.28571428
OPERARIO HH 1 6 10 2.857142857
0.28571428
OFICIAL HH 1 6 8.4 2.4
0.28571428
PEON HH 1 6 7.6 2.171428571
ALAMBRE NEGRO N8 kg 0.21 3.81 0.8001
CLAVOS kg 0.12 3.81 0.4572
MADERA PARA
ENCOFRADO p2 4.99 3.75 18.7125
PETROLEO gln 0.15 12.71 1.9065
HERRAMIENTAS 0.37142857
MANUALES %MO 5 1 1.857142857
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

4. COLUMNA H=3.30m
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

METRADO DE MADERA
TABLAS DE 1 X 8 X 11
1 X 8 X 11
G. 1.5 X 2 X ( )=22pie2
12
1 X 8 X 11
1. 2 5 X 2 X ( ) =18.33pie2
H. 12
ARRIOSTRES HORIZONTALES O BARROTE S
2 X 2 X 4.92
I. 8X2X ( )=26.24pie2
12
2 X 2 X 4.1
J. 8X2X ( )=21.87pie2
12
ARRIOSTRES INCLINADO S
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

2 X 3 X 13.13
K. 2 X 2X ( )=26.26pie2
12
2 X 3 X 6.56
L. 2 X 2X ( )= 13.12pie2
12
MADERA EN PIES CUADRADOS=127.82 pie 2

METRADO DEL ELEMENTO ESTRUCTURAL EN ARE A


P=1 m
h=3.30
A=1x3.30=3.3m2

3.3m2 127.82pie2
1m2 x

X=38.73pie2

NUMERO DE USOS
Para 5 usos
38.73
=7.75
1m2= 5
1m2=7.75pie2

UNIDAD METRADO CU PARCIAL


ENCOFRADO Y
DESENCOFRADO M2 0

ANALISIS DE COSTOS UNITARIOS

RENDIMIENT 12 M2/DIA
O
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

JORNADA 8 HORAS/DIA

CUADRILL
RECURSOS UNIDAD A CANTIDAD PRECIO PARCIAL
0.66666666
OPERARIO HH 1 7 10 6.666666667
0.66666666
OFICIAL HH 1 7 8.4 5.6
0.66666666
PEON HH 1 7 7.6 5.066666667
ALAMBRE NEGRO N8 kg 0.21 3.81 0.8001
CLAVOS kg 0.12 3.81 0.4572
MADERA PARA
ENCOFRADO p2 7.75 3.75 29.0625
PETROLEO gln 0.15 12.71 1.9065
HERRAMIENTAS 0.86666666
MANUALES %MO 5 7 4.333333333

5. VIGA
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

METRADO DE MADERA
TABLAS DE 1 X 8 X 15.43
1 X 8 X 15.43
M. 1.5 X 1 X ( )=15.43pie2
12
1 X 8 X 15.43
2 X 2X ( ) =41.15pie2
N. 12
ARRIOSTRES VERTICALES O BARROTE S
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

2 X 2 X 1.31
O. 8X1X ( )=3.49pie2
12
2 X 2 X 1.31
P. 8X2X ( )=6.97pie2
12
ARRIOSTRES INCLINADO S
2 X 3 X 1.31
Q. 8X2X ( )=10.48pie2
12

PIE DERECH O

2 X 4 X 10
R. 3X1X ( )=20pie2
12

MADERA EN PIES CUADRADOS=97.52 pie2

METRADO DEL ELEMENTO ESTRUCTURAL EN ARE A


P=1.05 m
l=3m
A=1.05x3=3.15m2

3.15m2 97.52pie2
1m2 x

X=30.96pie2

NUMERO DE USOS
Para 5 usos
30.96
=6.1 9
1m2= 5
1m2=6.19pie2

UNIDAD METRADO CU PARCIAL


UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

ENCOFRADO Y
DESENCOFRADO M2 0

ANALISIS DE COSTOS UNITARIOS

RENDIMIENT
O 10 M2/DIA
HORAS/DI
JORNADA 8 A

CUADRILL
RECURSOS UNIDAD A CANTIDAD PRECIO PARCIAL
OPERARIO HH 1 0.8 10 8
OFICIAL HH 1 0.8 8.4 6.72
PEON HH 1 0.8 7.6 6.08
ALAMBRE NEGRO N8 kg 0.21 3.81 0.8001
CLAVOS kg 0.12 3.81 0.4572
MADERA PARA
ENCOFRADO p2 6.19 3.75 23.2125
PETROLEO gln 0.15 12.71 1.9065
HERRAMIENTAS
MANUALES %MO 5 1.04 5.2

6. TECHO ALIGERADO
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

METRADO DE MADERA
TABLAS DE 1 X 8 X 10 EN LAS 13 VIGUETAS
1 X 8 X 10
S. 13 X 4 X ( )=346.67pie2
12
TABLAS EN EL PERIMETR O
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

1 X 8 X 10
T. 10 X ( )=66.67pie2
12

ARRIOSTRES VERTICALES O BARROTE S


2 X 2 X 1.31
U. 6X2X ( )=5.24pie2
12
2 X 2 X 1.31
V. 9X2X ( )=7.86pie2
12
ARRIOSTRES INCLINADO S
2 X 3 X 1.31
W. 6X2X ( )=7.86pie2
12
1 X 8 X 1.31
X. 9X2X ( )=15.72pie2
12

PI E DERECH O

3 X 4 X 10
Y. 9X4 X ( )=360pie2
12

MADERA EN PIES CUADRADOS=810.02 pie2

METRADO DEL ELEMENTO ESTRUCTURAL EN ARE A


P=29.42 m

l=0.20m
A=29.42x0.20+49.23m2=55.12m2

55.12m2 810.02pie2
1m2 x

X=14.69pie2
UNIVERSIDAD NACIONAL DE HUANCAVELICA

FACULTAD DE INGENIERIA CIVIL

NUMERO DE USOS
Para 5 usos
14.69
=2.94
1m2= 5

1m2=2.94pie2

UNIDAD METRADO CU PARCIAL


ENCOFRADO Y
DESENCOFRADO M2 0

ANALISIS DE COSTOS UNITARIOS

RENDIMIENT
O 12 M2/DIA
JORNADA 8 HORAS/DIA

CUADRILL
RECURSOS UNIDAD A CANTIDAD PRECIO PARCIAL
0.66666666
OPERARIO HH 1 7 10 6.666666667
0.66666666
OFICIAL HH 1 7 8.4 5.6
0.66666666
PEON HH 1 7 7.6 5.066666667
ALAMBRE NEGRO N8 kg 0.21 3.81 0.8001
CLAVOS kg 0.12 3.81 0.4572
MADERA PARA
ENCOFRADO p2 2.94 3.75 11.025
PETROLEO gln 0.15 12.71 1.9065
HERRAMIENTAS 0.86666666
MANUALES %MO 5 7 4.333333333

7. LOSA DE CONCRETO (PAVIMENTO)


8. BUZON DE DESAGUE

Vous aimerez peut-être aussi