Vous êtes sur la page 1sur 12

1243

Characteristics of wall deflections and ground


surface settlements in Shanghai
Zhong W. Wang, Charles W.W. Ng, and Guo B. Liu

Abstract: The characteristics of wall deflections and surface ground settlements at six deep multi-strutted excavations
in Shanghai soft soils were studied and compared with those of similar case histories reported worldwide, particularly
in Taipei and Singapore. The measured wall deflections at the six metro stations of the Pearl II Circle Line show a
typical bulging profile (or deep-seated shape) at the end of the excavation. The ratio between the measured maximum
wall deflection and the depth of the excavation (hm /H) in Shanghai was <0.007, which was similar to the ratio mea-
sured in Taipei, but it was substantially smaller than the Peck bounding limit of 0.01. At each station, the measured
maximum displacement was <0.45% of the final excavation depth. Because of the large aspect ratios of the under-
ground excavations, no significant three-dimensional effects or corner effects were observed. The measured maximum
settlements of the six metro excavations fell within zone I of the Peck classical normalized settlement-distance chart.
These small measured settlements were consistent with the small measured wall deflections. The observed relatively
small maximum wall deflections can likely be attributed to the use of prestressed struts, the constant adjustment of the
stresses to about 0.7 times the total vertical stress during the excavation, and the short horizontal span of the excava-
tion.
Key words: multi-strutted excavations, soft clay, Shanghai, metro stations, horizontal deflection, settlement.
Rsum : On a tudi les caractristiques de dflexions des murs et de tassements du terrain sur le site de six excava-
tions multitanonnes dans les sols mous de Shanghai et on les a compares avec des histoires de cas travers le
monde, et particulirement celles de Taipei et de Singapour. Les dflexions des murs mesures aux six stations de m-
tro du Pearl II Circle Line montrent un profil protubrant typique (ou un sige profond) la fin de lexcavation. Le
rapport entre la dflexion maximum mesure du mur et la profondeur de lexcavation (hm /H) Shanghai tait infrieur
0,007, qui tait semblable au rapport mesur Taipei, mais il tait substantiellement plus petit que la frontire limite
de 0,01 de Peck. chaque station, le dplacement maximum mesur tait infrieur 0,45 % de la profondeur finale
de lexcavation. cause des grands rapports de forme des excavations souterraines, on na observ aucun effet tridi-
mensionnel significatif ou effet de coin. Les tassements maximum mesurs dans les six excavations de mtro sont tom-
bs sous la zone I de la charte classique normalise tassement-distance de Peck. Ces faibles tassements mesurs taient
consistants avec les faibles dflexions du mur mesures. Les dflexions maximum relativement faibles des murs obser-
ves taient attribuables vraisemblablement lutilisation dtanons prcontraints dans lesquels les contraintes ont t
constamment ajustes environ 0,7 fois la contrainte verticale totale au cours de lexcavation, et la courte porte ho-
rizontale de lexcavation.

Mots cls : excavation multitanonne, argile molle, Shanghai, stations de mtro, dflexion horizontale, tassement.
[Traduit par la Rdaction] Wang et al. 1254

Introduction to reduce environmental impacts due to the construction of


transportation networks, Shanghai has developed extensive
Shanghai is the largest city in China and the countrys ma- underground metro stations in the last 10 years. Many of
jor financial and commercial center. To meet the increasing these metro stations were constructed very close to existing
demands of its rapid demographic and economic growth and buildings and services. To avoid damage to these sensitive
buildings and nearby services, three different protective
Received 5 January 2004. Accepted 13 April 2005. Published grades (Liu and Hou 1997) have been adopted for excava-
on the NRC Research Press Web site at http://cgj.nrc.ca on tions in Shanghai (Table 1); which grade is required depends
14 September 2005. on the distance of the foundation from the excavation, the
Z.W. Wang. Department of Geotechnical Engineering, potential for damage, and its consequences.
Nanjing University of Technology, Nanjing, P.R. China. Field monitoring has proved to be cost-effective for veri-
C.W.W. Ng.1 Department of Civil Engineering, Hong Kong fying design assumptions and providing immediate feedback
University of Science and Technology, Clear Water Bay, to designers. Many invaluable case histories associated with
Kowloon, Hong Kong. multi-strutted excavations have been reported (Peck 1969;
G. B. Liu. Department of Geotechnical Engineering, Tongji Mana and Clough 1981; Clough and ORourke 1990; Finno
University, Shanghai, P.R. China.
et al. 1989; Wallace et al. 1992; Ou et al. 1993; Whittle et al.
1
Corresponding author (e-mail: cecwwng@ust.hk). 1993; Hsieh and Ou 1998; Ng 1998, 1999; Long 2001; Liu

Can. Geotech. J. 42: 12431254 (2005) doi: 10.1139/T05-056 2005 NRC Canada
1244 Can. Geotech. J. Vol. 42, 2005

Table 1. Control criteria for protecting the environment (modified from Liu and Hou 1997).
Protection Maximum allowable settlement and maximum
grade deflection Environmental conditions
1 Maximum ground surface settlement 0.1%He; Within 10 m from the excavation, there are metro lines and
maximum wall deflection 0.14%He; FOS 2.2 important services, such as gas mains and water drains
2 Maximum ground surface settlement 0.2%He; Within He from the excavation, there are metro lines and
maximum wall deflection 0.30%He; FOS 2.0 important services, such as gas mains and water drains;
He 10 m
3 Maximum ground surface settlement 0.5%He; Within He from the excavation, there are no metro lines or
maximum wall deflection 0.70%He; FOS 1.5 important services, such as gas mains and water drains
Note: He, final excavation depth, is usually 10 m for metro excavations in Shanghai; FOS, factor of safety against base heave.

Fig. 1. Soil profile and geotechnical parameters.

et al. 2005). The measured performance reported in these soft plastic clay. This uppermost thin clay layer is lightly
cases is strongly governed by local geological and overconsolidated, perhaps as a result of desiccation. It has a
geotechnical conditions, construction methods, retaining sys- lower water content and void ratio but a higher shear
tems, and quality of work. In this paper, the performance of strength than the underlain marine deposits. The third layer
six multi-strutted deep excavations for underground metro in succession is a 5 m thick soft silty clay, which consists of
stations of the Pearl II Circle Line in Shanghai is described. mica and on occasion other organic matter. Beneath this is a
The characteristics of ground surface settlements and lateral 10 m layer of thick soft clay, which has the largest void ratio
wall deflections in Shanghai soft soils are identified and but the lowest stiffness (i.e., the highest compressibility) and
compared with those of the relevant case histories. shear strength among the 40 m of soil deposits in Shanghai.
This soft layer also contains mica and other organic matter,
Geological and geotechnical conditions at as a result of marine deposition. The fifth layer is medium-
Shanghai soft grey clay containing mica, oyster shells, and other or-
ganic material, whereas the sixth layer is medium silty clay
Shanghai located where the Yangtze River empties into and silt. The groundwater table is generally about 1 m below
the East China Sea. The top layers of soil in Shanghai with the ground surface. The saturated permeability of clay and
any engineering significance were deposited during the Qua- that of the silty clay are of the order of 109 and 108 m/s,
ternary period. Figure 1 shows a typical soil profile in respectively.
Shanghai and the geotechnical properties of the soil. It
should be noted that the compressibility modulus (E0.10.2) Construction sequence for the underground
was determined from oedometer tests of the soil at stresses metro stations
ranging from 100 to 200 kPa, and the undrained shear
strength (cu) profile was obtained from in situ vane shear All six case histories reported in this paper were obtained
tests. The ground is underlain by relatively soft to medium- from station excavations of the Pearl II Circle Line in the
soft sedimentary marine deposits, which generally consist of city center. Figure 2 shows the Circle Line and the locations
uniform bedding planes. The top layer is a thin, artificial fill, of the six stations. These underground station excavations
whereas the second soil layer is a brownish yellow, medium- were largely rectangular and approximately 1723 m wide

2005 NRC Canada


Wang et al. 1245

Fig. 2. Locations of metro stations of the Pearl II Circle Line. and strutting were carried out as fast as possible, to mini-
mize wall deflections and ground settlements. A summary of
the main stages of excavations at each station is given in Ta-
ble 4. To protect the environment against any possible ad-
verse effects caused by the metro excavations, all the
stations were designed according to protection grade 2 crite-
ria (see Table 1), except for the South Xizan Road station,
where protection grade 1 criteria were adopted.

Instrumentation
To measure rotations, and hence deflections, of the dia-
phragm wall at each station, inclinometer tubes were fixed to
the steel reinforcement cages and concreted in the wall. The
inclinometer tubes were installed in two long sides of the di-
aphragm walls at 1824 m intervals along the horizontal lon-
gitudinal axis of each rectangular box station, except at
Yanchang Road (Fig. 6). Casing was installed with a pair of
grooves oriented in the expected direction of movement; to
avoid twisting of the casing, the groove was checked before
(W1) and 169335 m long (L1), as illustrated schematically installation to ensure that its twist angle was no more than
in Fig. 3. The dimensions W2 and L2 at each station are ap- 0.1%. Then the casing was fixed tightly to the steel cage of a
proximately 15 and 25 m, respectively. Figure 4 shows a diaphragm wall. The groove direction was checked again af-
typical cross section of the excavations, whose depths ter the steel cage was lowered into the bentonite inside the
ranged from 15 to 23 m. In all cases, the excavations were diaphragm wall before concreting. The twist angle of the
multi-strutted and retained by concrete diaphragm walls 0.6 groove was measured after the concreting, and the twist an-
0.8 m thick and 2638 m deep. Station dimensions and strut- gle of the groove was kept at less than the allowable value of
ting arrangements for the excavations are given in Tables 2 0.2%, in most cases. If the casing was found to be twisted
and 3, respectively. beyond the allowable value after installation, measured data
After the installation of the diaphragm wall and prior to were corrected according to the results of a spiral survey
excavation, the soil at two stations, the Yishan Road station through a spiral sensor.
and the South Xizan Road station, was improved by com-
A measuring probe with a resolution of 0.02 mm/500 mm
paction grouting. The depths of the grouting are summarized
and temperature rating of 20 C to +50 C was used during
in Table 2. Each station excavation started simultaneously
the monitoring. Before the monitoring started, some essen-
from each end and proceeded toward the center of the sta-
tial preparatory works were systematically carried out; this
tion. Each diaphragm wall was supported by prestressed
included checking the probe and allowing 510 min for the
steel struts 16 mm thick and 609 mm in diameter (external),
probe to adjust its temperature inside the casing.
spaced at 3 m horizontally along the longitudinal direction
of the stations at each level (Figs. 35), with the exception The rotation (tilt) of the wall was measured at 1 m inter-
of level 1 of the Yishan Road station, at which concrete vals along its depth. The estimated overall accuracy of the
beams 1.2 m deep and 0.8 m wide were installed. The hori- inclinometer was about 5 mm/25 m. Readings of each incli-
zontal span of the excavation in the longitudinal direction nometer were taken twice a day during the excavation and
(i.e., each segment of L1 in Fig. 3) at every level was kept at strut installation and once a day during the rest periods. To
<6 m to reduce lateral wall deflections and ground move- determine the absolute displacements of the wall, movement
ments. The height between each level of the excavation typi- at the top of each wall was surveyed by using a theodolite,
cally ranged between 3 and 4 m (see Table 3 for details). together with a horizontal reference, which was located at a
Each prestressed strut was installed 0.3 m above each level distance from the wall equivalent to about five times the ex-
of the excavation, and the magnitude of the prestressing was cavation depth.
actively adjusted to maintain about 0.7 times the total verti- For monitoring the ground surface settlements, critical
cal stress (v) throughout each excavation stage. Specific settlement sections, perpendicular to the longitudinal axis of
procedures used at each level for the installation of struts the diaphragm wall, were identified and were surveyed by
and for prestressing are illustrated in Fig. 5. using surface markers. The markers were located about 2
After the final excavation level was reached, a 200 mm 30 m perpendicularly away from one of the two long sides
thick concrete binding layer was constructed within 24 h af- of the wall at each rectangular box station and were secured
ter the excavation. This binding layer was used to provide at 0.5 m below the ground surface. All settlement monitor-
temporary horizontal support for the diaphragm wall and to ing was carried out with a leveling instrument with a stated
provide a convenient working platform for various construc- accuracy of 0.5 mm/km. The leveling reference point was lo-
tion activities, such as assembling reinforcements for rein- cated at a distance of about five times the final excavation
forced structures at each station. The processes of excavation depth (He) from the excavation site.

2005 NRC Canada


1246 Can. Geotech. J. Vol. 42, 2005

Fig. 3. Plan view showing a typical station and arrangement of strutting system.

Fig. 4. Cross section of a typical excavation.

Table 2. Summary of construction details and geometrical properties of each excavation.


Thickness of Wall Wall Maximum Excavation Excavation Depth of
diaphragm stiffness, depth excavation length on plan, width on Aspect grouting in
Station wall (mm) EI (kN/m2) (m) depth (m) L1+L2 (m) plan, W1 (m) ratio passive zone (m)
Yishan Road 600 540 000 28.0 15.5 335.0 17.3 19.4 8.610.6
16.619.6
South Xizan Road 800 1 280 000 38.0 20.6 169.0 22.8 7.4 15.517.5
23.025.5
South Pudong Road 600 540 000 27.0 17.3 196.0 20.8 9.4 Nil
Pudongdadao Road 600 540 000 27.0 16.0 200.0 18.5 10.8 Nil
Pudian Road 600 540 000 26.5 16.5 194.0 20.4 9.5 Nil
Yanchang Road 600 540 000 27.0 15.2 226.0 18.1 12.5 Nil

Deflections of the diaphragm walls noted that there were two relatively long sides (called sides
1 and 2) of each rectangular excavation box (see Figs. 3 and
For ease of describing the geometries of each excavation 6). The side on which the largest wall deflections were mea-
and presenting measured results at each station, the symbols sured is designated as side 1. Because of the significant dif-
and notations adopted are defined in Fig. 7. The normalized ference in the dimensions L1 and L2 (see Fig. 3), corner
maximum deflections of the diaphragm wall at each excava- effects on the wall deflections at the middle section of each
tion site, based on the inclinometer readings at the middle station were believed to be negligible (i.e., a plane-strain
section of each station, are shown in Fig. 8. It should be condition). For consistency, only the measured deflections at

2005 NRC Canada


Wang et al. 1247

Table 3. Strutting arrangements for the excavations.


H (m)
Station Stage 1 Stage 2 Stage 3 Stage 4 Stage 5
Yishan Road 1.5 4.7 6.9 9.7 12.5
South Xizan Road 1.5 6.5 10.8 14.4 17.5
South Pudong Road 0.6 4.2 7.8 11.4 14.5
Pudongdadao Road 1.0 4.3 7.8 11.3 14.4
Pudian Road 1.0 4.2 7.2 11.1 14.2
Yanchang Road 2.0 6.0 9.8 12.8
Note: Hs = H + 0.3 m.

Fig. 5. Schematic diagram showing strut installation and prestressing process at each level.

the center point of side 1 at each station were selected for ranges of 0.33%0.87% reported for similar ground
comparison (when possible). Because the inclinometer be- excavations and retaining conditions (using diaphragm wall)
low the depth of the excavation at one of the two long sides in Taipei and Singapore (Ou et al. 1993, 1998; Long 2001).
at Yanchang Road was damaged, only one set of measure- The relatively small wall deflections observed can likely be
ments is presented in this paper. In Fig. 8, a positive value attributed to the use of prestressed struts, the constant adjust-
for the wall deflection ( h) means inward movement toward ment of the stresses to about 0.7v during the excavation,
the excavation. As expected, the measured wall deflections and the short horizontal span of the excavation. After the in-
increased as the excavation proceeded. The magnitudes of spection of the measured wall deflections, it might be de-
the measured lateral wall deflections were <0.45% of the fi- duced that the quality of the application of the prestresses to
nal excavation depth, and they fell at the lower end of the the struts varied from site to site. Evidently, accidental over-

2005 NRC Canada


1248 Can. Geotech. J. Vol. 42, 2005

Table 4. Main stages of excavation.


Day No.
Yishan South Xizan South Pudong Pudongdadao Pudian Yanchang
Stage Construction operation Road Road Road Road Road Road
1(a) Construction of diaphragm wall 1 1 1 1 1 1
1(b) Compaction grouting 5 5 NA NA NA NA
1(c) Excavation to level 1 11 21 21 21 21 21
1(d) Installation of level 1 struts (casting of 13 21 21 21 21 21
level 1 struts at Yishan Road)
2(a) Reduced level dig to level 2 31 26 26 26 26 30
2(b) Installation of level 2 struts 31 26 26 26 26 30
3(a) Reduced level dig to level 3 35 31 30 29 34 39
3(b) Installation of level 3 struts 35 31 30 29 34 39
4(a) Reduced level dig to level 4 50 36 39 39 41 48
4(b) Installation of level 4 struts 50 36 39 39 41 48
5(a) Reduced level dig to level 5 (dig to the 53 52 61 44 45 53
final level at Yanchang Road)
5(b) Installation of level 5 struts 53 52 61 44 45 NA
6 Reduced level dig to the final level 63 61 71 48 48
Note: NA, not available or not applicable.

Fig. 6. Schematic diagram showing the locations of inclinometers at each station.

Fig. 7. Definitions of excavation variables. stressing of struts resulted in negative wall deflections away
from the wall at three stations, South Pudong Road, Pudong-
dadao Road, and Yanchang Road, as shown in Figs. 8c, 8d,
and 8f, respectively. As the excavation continued, the wall at
each station gradually developed a clearly bulging profile.
When normalized wall displacements at the stations with
and without grouting were compared (see Table 2), the mag-
nitudes of wall deflections in the improved grounds (i.e.,
Figs. 8a and 8b) did not appear to be noticeably smaller than
those in the unimproved ground (i.e., Figs. 8c8f). At the
end of excavation, the depths at which the maximum mea-
sured wall deflections occurred at each station were not con-
sistent. Some of these maximum deflections appeared above
the final excavation level, whereas others occurred below it.
Relatively significant lateral movements were observed at
2005 NRC Canada
Wang et al. 1249

Fig. 8. Normalized wall deflections at various excavation stages: (a) Yishan Road; (b) South Xizan Road; (c) South Pudong Road;
(d) Pudongdadao Road; (e) Pudian Road; ( f ) Yanchang Road.

the toe of each wall at two stations (see Figs. 8e and 8f). At Fig. 9. Relationship between normalized maximum wall deflec-
Yanchang Road (Fig. 8f), large toe displacement took place tion and distance ratio.
at the last stage (stage 5(a)) of the excavation and was about
40% of the total wall deflection. Because Shanghai clays
were formed from marine deposits and were largely uniform
in the Shanghai area, this relatively large toe movement was
unlikely to have been caused by an unexpected weak clay
seam or weak spot at this particular site. According to the
experience gained from excavations for various Shanghai
metro projects in the last 10 years, there was no evidence to
suggest that this large toe movement should be attributed to
basal heave, as no correspondingly large ground settlement
was observed. Possibly, this large wall deflection at the last
stage of excavation was associated with the quality control
(e.g., the last strut may not have been properly installed be-
fore the commencement of the final stage of excavation),
coupled with overstressing of the upper struts, as revealed
by the negative wall deflections at the top.

Three-dimensional distributions of wall


deflections
During excavation, wall deflections were measured at var-
ious locations along the longitudinal axis of the two long wall deflection with longitudinal distance ratio was limited
sides of the box stations. This provided an opportunity to at all stations. The limited (or nearly uniform) variations of
study any spatial variation in the wall deflections. Some re- normalized maximum wall deflections with distance ratio re-
searchers have reported significant three-dimensional effects vealed that the excavations showed essentially plane-strain
on wall deformations (Bono et al. 1992; Dysli and Fontana behavior. This may be attributable to the long and narrow
1982; Ou et al. 1993; Lee et al. 1998). Many of these exca- rectangular shape of each excavation, as shown in Figs. 3
vations were carried out at sites where the aspect ratios on and 6. Using a short horizontal span for excavation from the
the plan were not as large as those of the metro stations. Fig- two ends toward the center of each station did not appear to
ure 9 shows the normalized relationship between the mea- result in severe three-dimensional effects or corner effects
sured maximum wall deflection and the distance ratio, which on the wall deflections.
is defined as the ratio of the distance of the inclinometer
away from one end of each excavation site to the total length Maximum wall deflections
of the excavation in the longitudinal direction. It is clear
from the figure that the variation of normalized maximum Figure 10 shows the relationship between measured maxi-
2005 NRC Canada
1250 Can. Geotech. J. Vol. 42, 2005

Table 5. Average index properties for clay at various sites.


Undrained Water Plasticity Order of Undrained
strength, content, index, PI permeability, Youngs modulus,
Site cu(kPa) w (%) (%) k (m/s) Eu (kPa)
Shanghai soft clay 4060 4060 20 109 600 cu
Taiwan silty clay 2570 4560 17 108 650 cu
Singapore marine clay 2030 5090 60 109 450 cu

Fig. 10. Relationship between maximum lateral wall deflection Fig. 11. Relationship between location of maximum lateral wall
and excavation depth on side 1. TNEC, Taipei National Enter- deflection and excavation depth on side 1.
prise Center.

the metro stations in Shanghai were generally below hm =


0.0070H. The largest average recorded wall deflections were
mum wall deflection on side 1 and excavation depth in measured in Singapore and were probably due to the ground
Shanghai; for comparison, some similar case histories from conditions at this location being the weakest among the
Taipei (Ou et al. 1993, 1998) and Singapore are also in- three city locations reported (see Table 5). The ground con-
cluded in the figure. The three excavations in Singapore, ditions in Shanghai were similar to those of Taipei, but the
that is, United Overseas Bank (UOB), Bugis, and Newton, average measured deflections in the former were smaller
were initially reported on by Wallace et al. (1992), Hulme et than in the latter, probably because of the use of prestressed
al. (1989), and Nicholson (1987), respectively, and were struts, short excavation spans, and a fast strutting sequence
subsequently summarized by Long (2001). For ease of com- in Shanghai. It is evident that the use of stiff diaphragm
parison, some soil indices and properties for these cases are walls, modern strutting methods (to increase retaining sys-
summarized in Table 5. It can be seen in Fig. 10 that the tem stiffness) (Clough et al. 1989), and rapid excavation in
measured maximum wall deflections in Shanghai lie below the three cities substantially reduced wall deflections in soft
the protection line for the grade 2 rating (see Table 1), hm = soils in comparison with the Peck (1969) limiting line (i.e.,
0.0030H, except for several measurements at the Pudian hm = 0.0100H), which is essentially based on excavations in
Road and Yanchang Road stations. The measurements from soft clays supported by sheet piles and soldier piles.
the two stations with ground improvements, Yishan Road As expected, the depth of the maximum wall deflection
(grade 2) and South Xizan Road (grade 1), fall below hm = increases with the depth of the excavation. Ou et al. (1993)
0.0030H (grade 2 requirement), but two measurements at collected eight case histories in Taipei and found that the
South Xizan Road were above the grade 1 limiting line of maximum lateral wall deflection (Hm) occurred near the ex-
hm = 0.0014H. The effect of the ground improvement (com- cavation surface, and hence the ratio of the depth of the
paction grouting) on the maximum wall deflection is not maximum wall deflection to the depth of the excavation (H)
demonstrated. was approximately equal to 1. Figure 11 shows the relation-
From the comparison of the excavations in Singapore, Tai- ship between Hm and H for the six stations in Shanghai.
pei, and Shanghai, it appears that the measured wall deflec- Apart from a few exceptions, the Hm /H ratios were gener-
tions in Singapore were between hm = 0.0030H and hm = ally bounded by two lines, Hm = H and Hm = H + 7 m. This
0.0100H, whereas those in Taipei fell between hm = implies that deep-seated wall deflections were generally ob-
0.0030H and hm = 0.0070H. The measured deflections at served, probably because of the use of stiffer supports (i.e.,

2005 NRC Canada


Wang et al. 1251

Fig. 12. Relationship between FOS against base heave and nor- Fig. 13. Relationship between normalized settlement and normal-
malized maximum wall deflection on side 1. TNEC, Taipei Na- ized distance from wall. TNEC, Taipei National Enterprise Center.
tional Enterprise Center.

prestressed struts) than in Taipei. However, the ground im- Fig. 14. Relationship between relative settlement and normalized
provements inside the excavation site at South Xizan Road distance from wall.
might have limited the development of deep-seated deflec-
tions of the wall and hence resulted in Hm /H ratios <1.0.
After analyzing the distributions of the maximum wall de-
flection and the factor of safety (FOS) against heave from
field records of excavations in clays in San Francisco, Oslo,
Boston, and Chicago, Mana and Clough (1981), reported
limiting relationships, as shown in Fig. 12. For comparison,
data points from the six metro stations in Shanghai and from
three of the eight case histories in Taipei (Ou et al. 1993,
1998) are also presented in the figure. According to the envi-
ronmental protection criteria established to avoid adverse ef-
fects caused by excavations in Shanghai (see Table 1), the
FOS against base heave used in the design was 2.2, whereas
the FOS against base heave adopted in Taipei ranged from
1.2 to 1.7 (Hsieh and Ou 1998). It is clear from the figure
that the measured values in Shanghai were close to the lower
limiting curve proposed by Mana and Clough (1981), proba-
bly because of the use of prestressed struts and the short
horizontal span of the excavations.

Surface ground settlements


Peck (1969) summarized field observations of surface
ground settlements around excavations and classified these
settlements as belonging to zone I (sand and soft to hard ing the use of stiff diaphragm walls, prestressed struts, a
clay), zone II (very soft to soft clay), or zone III (very soft to short horizontal span, and fast excavation and strutting se-
soft clay to a great depth) (Fig. 13). Many of these excava- quences.
tions were retained by sheet piles and soldier piles. For com- Figure 14 compares the relationships between the normal-
parison, the measured settlements from the six metro ized settlement ( v / vm) and the distance ratio (d/He) for the
stations are plotted in the same figure. It is clear that the Shanghai excavations with those of other case histories re-
data from Shanghai all fall within zone I of the chart, and ported in the literature. Clough and ORourke (1990) sug-
the measured settlements are substantially smaller than those gested that the maximum settlement usually occurs at some
observed in similar ground conditions by Peck (1969). The distance away from the wall, and they proposed a nondi-
small measured settlements are consistent with the measured mensional bilinear limiting settlement profile (ABC in Fig,
wall deflections shown in Figs. 10 and 12. It is evident that 14) for their excavations in soft to medium clays. Hsieh and
the relatively small settlements and deflections measured in Ou (1998) described a trilinear relationship (DEFG in
Shanghai could be attributed to a number of factors, includ- Fig. 14) between v / vm and d/He from average measure-

2005 NRC Canada


1252 Can. Geotech. J. Vol. 42, 2005

ments in soft soils in Taipei, and they divided their observa- Fig. 15. Relationship between normalized maximum ground sur-
tions into primary and secondary influence zones. face settlement and normalized maximum wall deflection on side
In Fig. 14, it can be seen that the measured settlements at 2. TNEC, Taipei National Enterprise Center.
Shanghai lie on both sides of the line proposed by Hsieh and
Ou (1998), and it appears that the average line for Shanghai
is consistent with the one from Taipei. A triangular limiting
line (ABC), with the same slope as the limiting line pro-
posed by Clough and ORourke (1990), has been drawn in
Fig. 14 for comparison. It appears that the measured settle-
ment distributions in Shanghai are wider and deeper than the
one obtained by Clough and ORourke (1990).

Relationship between maximum ground


settlements and maximum wall deflections
Figure 15 shows the relationship between measured maxi-
mum ground surface settlement ( vm) and maximum lateral
wall deflection ( hm) in the six Shanghai excavations. In
Fig. 15, some reported data from excavations in soft soils in
Singapore (Wallace et al. 1992) and Taipei (Ou et al. 1993,
1998) are also included for comparison. Apart from a single
data point from UOB, Singapore, all measurements fall be-
low the line vm = hm. This suggests that the maximum
ground surface settlement is generally smaller than the maxi-
mum lateral wall deflection in soft soils. With the exception
only of Pudian Road station, data from Shanghai lie between Conclusions
vm = 0.2 hm and vm = 0.6 hm. However, all three data On the basis of the field monitoring of wall deflections
points from Taipei fall above the line vm = 0.6, which is and ground surface settlements at six deep multistage exca-
close to the range of 0.51.0 hm reported by Mana and vations on the Pearl II Circle Line in Shanghai, the follow-
Clough (1981). The difference in the observed distributions ing conclusions may be drawn:
in Shanghai and Taipei may be attributed to the larger FOS (i) Generally, the measured wall deflections at the six sta-
against base heave adopted in Shanghai. tions show a typical bulging profile (or a deep-seated
shape) at the end of the excavation. The magnitudes of
Discussion of the mechanism of movement the measured maximum lateral wall deflections were
<0.45% of the final excavation depth, and they fell at
in Shanghai the lower bound of the reported range of 0.33%0.87%
Despite the relatively weak ground conditions in Shang- observed from similar excavations in fairly soft soils
hai, the measured wall deflections and settlements obtained worldwide. The observed relatively small maximum
from these excavations were generally smaller than the lim- wall deflections can likely be attributed to the use of
its proposed by Mana and Clough (1981) for maximum wall prestressed struts, the constant adjustment of stresses to
deflections (see Fig. 12) or the criteria in the normalized set- 0.7v during the excavation phases, and the short hori-
tlement charts proposed by Peck (1969) (refer to Fig. 13). zontal span of excavation.
This may seem rather surprising initially. However, given the (ii) As a result of the geometrical shape (rectangular box)
use of a short excavation section (on plan), very rapid exca- and large aspect ratio of the underground excavations,
vation and strut installation procedures, stiff diaphragm fairly uniform variations in the maximum wall deflec-
walls, and active and continuous prestressing measures in tions were observed along the longitudinal axis of each
Shanghai, the observed relatively small wall deflections and station excavation. In other words, no significant three-
surface settlements seem to be reasonable, compared with dimensional effects or corner effects were observed,
past excavations elsewhere with similar ground conditions. even though the excavation procedure involved a short
This is because many of the previous data collected, ana- horizontal span. Hence, the walls showed essentially
lyzed, and reported were obtained from excavations sup- plane-strain behavior. The effects of ground improve-
ported by sheet piles, soldier piles with lagging, and ments from compaction grouting inside the excavation
unsupported spans of sheet piles exceeding 1015 ft, and at two of the six locations were not obvious.
most of these excavations had relatively long construction (iii) Given the location of the maximum wall deflection (Hm)
periods. From the last 10 years of experience gained from as the depth of excavation (H) increased, apart from a
various underground excavation projects in Shanghai, it ap- few exceptions the Hm /H ratios were generally bounded
pears that the excavation procedures, the wall and strut sup- by two lines, Hm = H and Hm = H + 7 m. Based on the
port systems (see Fig. 5), and the movement control correlations between the measured maximum wall de-
measures (refer to Table 1) reported in this paper are effec- flection ( hm) and H, the measurements at the metro sta-
tive and appropriate for the ground conditions in Shanghai. tions in Shanghai generally fell below the line hm =

2005 NRC Canada


Wang et al. 1253

0.0070H and were similar to data from reported cases in Hsieh, P.G., and Ou, C.Y. 1998. Shape of ground surface settle-
Taipei but substantially smaller than the Peck (1969) ment profiles caused by excavation. Canadian Geotechnical
bounding limit of hm = 0.0100H. Journal, 35(6): 10041017.
(iv) After the relationship between the measured maximum Hulme, T.W., Potter, J., and Shirlaw, N. 1989. Singapore MRT sys-
settlements ( vm) and the distance from the diaphragm tem: construction. In Proceedings of the Institution of Civil En-
wall of the six metro excavations had been studied, it gineers, Vol 86, pp. 709770.
was clear that the data from Shanghai all fell within Lee, F.H., Yong, K.Y., Quan, K.C.N., and Chee, K.T. 1998. Effect
zone I of the Peck (1969) limits. These small measured of corners in strutted excavations: field monitoring and case his-
tories. Journal of Geotechnical and Geoenvironmental Engi-
settlements were consistent with the small measured
neering, ASCE, 124(4): 339349.
wall deflections observed.
Liu, G.B., Ng, C.W.W., and Wang, Z.W. 2005. Observed perfor-
(v) When the relationships of the normalized settlement to mance of a deep multistrutted excavation in Shanghai soft clays.
the maximum settlement and to normalized distance Journal of Geotechnical and Geoenvironmental Engineering,
from the wall had been investigated, it was found that ASCE, 131(8): 10041013.
the measured data from Shanghai were consistent with Liu, J.H., and Hou, X.Y. 1997. Excavation engineering handbook.
the average line proposed by Hsieh and Ou (1998). If Chinese Construction Industry Press, Beijing, P.R. China.
the same slope as the limiting line proposed by Clough Long, M. 2001. Database for retaining wall and ground movements
and ORourke (1990) is adopted, a triangular limiting due to deep excavations. Journal of Geotechnical and
line can also be drawn in the figure for comparison. The Geoenvironmental Engineering, ASCE, 127(3): 203224.
measured settlement distributions in Shanghai are wider Mana, A.I., and Clough, G.W. 1981. Prediction of movements for
and deeper than those reported by Clough and ORourke braced cuts in clay. Journal of the Geotechnical Engineering Di-
(1990). vision, ASCE, 107(8): 759777.
(vii) With the exception of UOB Singapore, the surface set- Ng, C.W.W. 1998. Observed performance of multi-propped excava-
tlement and deflection measurements in soft soils fell tion in stiff clay. Journal of Geotechnical and Geoenvironmental
below the line vm = hm. This suggests that the maxi- Engineering, ASCE, 124(9): 889905.
mum ground surface settlement is generally smaller Ng, C.W.W. 1999. Stress paths in relation to deep excavations.
than the maximum lateral wall deflection in soft soils. Journal of Geotechnical and Geoenvironmental Engineering,
With the exception at the Pudian Road station, settle- ASCE, 125(5): 357363.
ments from Shanghai fell between vm = 0.2 hm and Nicholson, D.P. 1987. The design and performance of the retaining
vm = 0.6 hm. walls at Newton Station. In Proceedings of the Singapore Mass
Rapid Transit Conference, Singapore. pp. 147154.
Ou, C.Y., Hsieh, P.G., and Chiou, D.C. 1993. Characteristics of
Acknowledgments ground surface settlement during excavation. Canadian
Geotechnical Journal, 30(5): 758767.
The authors thank the National Natural Science Founda-
Ou, C.Y., Liao, J.T., and Lin, H.D. 1998. Performance of dia-
tion of China (grant No. 10102015), the Research Grants phragm wall constructed using top-down method. Journal of
Council of the Hong Kong Special Administrative Region Geotechnical and Geoenvironmental Engineering, ASCE,
(grant No. HKUST6025/01E), and Hong Kong University of 124(9): 798808.
Science and Technology (grant No. DAG02/03.EG15) for Peck, R.B. 1969. Deep excavation and tunneling in soft ground. In
providing financial support for this research. Proceedings of the 7th International Conference on Soil Me-
chanics and Foundation Engineering, Mexico City. Vol. 1,
References pp. 225281.
Wallace, J.C., Ho, C.E., and Long, M. 1992. Retaining wall behav-
Bono, N.A., Liu, T.K., and Soydemir, C. 1992. Performance of an iour for a deep basement in Singapore marine clay. In Proceed-
internally braced slurrydiaphragm wall for excavation support. ings of the International Conference on Retaining Structures.
In Slurry wall: design, construction and quality control. Ameri- Thomas Telford, London, UK. pp. 195204.
can Society for Testing and Materials, Philadelphia, Pa. ASTM Whittle, A.J., Hashash, Y.M.A., and Whitman, R.V. 1993. Analysis
STP 1129, pp. 347360. of deep excavation in Boston. Journal of Geotechnical Engi-
Clough, R.W., and ORourke, T.D. 1990. Construction induced neering, ASCE, 119(1): 6990.
movements of in-situ walls. In Proceedings, Design and Perfor-
mance of Earth Retaining Structures, ASCE Special Conference,
Ithaca, N.Y. pp. 439470. List of symbols
Clough, G.W., Smith, E.M., and Sweeney, B.P. 1989. Movement
cu undrained shear strength of soil from field vane
control of excavation support systems by iterative design. In
Proceedings of Current Principles and Practices on Foundation d distance from the wall
and Engineering, ASCE, New York. Vol. 2, pp. 869884. D depth from the ground surface
Dysli, M., and Fontana, A. 1982. Deformations around the excava- e void ratio
tion in clayey soil. In Proceedings of the International Sympo- E Youngs modulus
sium on Numerical Models in Geomechanics. A.A. Balkema, E0.10.2 compressibility modulus determined by oedometer test
Rotterdam, The Netherlands. pp. 634642. at stresses of 100200 kPa
Finno, R.J., Atmatzidis, D.K., and Perkins, S.B. 1989. Observed EI wall stiffness
performance of a deep excavation in clay. Journal of the Eu undrained Youngs modulus
Geotechnical Engineering Division, ASCE, 115(GT8): 1045 FOS factor of safety against base heave
1064. H excavation depth

2005 NRC Canada


1254 Can. Geotech. J. Vol. 42, 2005

He final excavation depth W1, W2 width of excavation on plan as shown in Fig. 3


Hm location of maximum lateral deflection w water content
Hs strut level h magnitude of lateral wall deflection at any depth
I moment of inertia hm magnitude of maximum lateral wall deflection
k permeability coefficient v magnitude of ground surface settlement
L1, L2 length of excavation on plan as shown in Fig. 3 vm magnitude of maximum ground surface settlement
PI plasticity index unit weight of soil
qt measured cone penetration test end resistance v total vertical stress

2005 NRC Canada

Vous aimerez peut-être aussi