Académique Documents
Professionnel Documents
Culture Documents
2013 FAA Design Competition for Universities by GT Aircraft, Inc consisting of seven graduate
students, two of whom were distance learning, and four undergraduate students from the Georgia
Institute of Technology. The Next Generation Air Transportation System provides a driving
force for the development of new aircraft requiring technology infusion to address green
aviations reduced emissions and energy consumption objectives; offering a feasible and viable
solution in closing the gap between current aviation operations and NextGen 2025 goals. The
Georgia Tech Integrated Product and Process Development decision-making process and a
alternatives and obtain the optimum-compromised design solution, as well as allow for the
inclusion of abstract design disciplines, such as safety and risk management. The final
architecture, the NXG-50, is a 50 passenger, short to medium range regional transport, powered
by a hybrid-electric propulsion system. Balancing the benefits of conventional fuel and high
energy density batteries, the aircraft provides an environmentally feasible solution while still
meeting cruise speed and balanced field length requirements. Through more reliable electric
systems and decreased fuel burn, the NXG-50 reduces life cycle cost by 4.2% in comparison to a
baseline CRJ200 regional jet. Turnaround time, airport electric demand, airport infrastructure,
and personnel skills and training are minimally impacted through the integration of more electric
components requiring less maintenance and servicing. The innovative technology suite
implemented on the NXG-50 provides a future regional jet with expected reductions of 15% for
life-cycle energy consumption, 13 EPNL reduction for aircraft noise certification levels, and
21% reduction for life-cycle greenhouse gas emissions compared to the baseline.
i
Table of Contents
List of Figures ............................................................................................................................... iii
List of Tables ................................................................................................................................ iv
Nomenclature ................................................................................................................................ v
Problem Statement and Background .......................................................................................... 1
PROBLEM STATEMENT ................................................................................................................. 1
BACKGROUND AND CURRENT CONDITIONS ................................................................................. 1
DESIGN ISSUES ............................................................................................................................. 2
STATE OF THE ART APPROACHES ................................................................................................. 3
Literature Review and Problem Solving Approach .................................................................. 4
CURRENT MARKET OUTLOOK AND FUTURE SCENARIO ............................................................... 4
TECHNOLOGY FORECAST ............................................................................................................. 5
PROBLEM SOLVING APPROACH.................................................................................................... 6
ENVIRONMENTAL BENEFITS ...................................................................................................... 25
Safety Risk Assessment............................................................................................................... 31
AIRPORT INFRASTRUCTURE IMPACT ASSESSMENT..................................................................... 32
REQUIRED SKILLS AND TRAINING .............................................................................................. 34
Implementation and Financial Analysis ................................................................................... 36
IMPLEMENTATION ...................................................................................................................... 36
BUSINESS SCENARIO .................................................................................................................. 37
Conclusion ................................................................................................................................... 39
Appendix A List of Complete Contact Information ........................................................... A-1
Appendix B Georgia Institute of Technology ...................................................................... B-1
Appendix C Non-University Partners .................................................................................. C-1
Appendix D Design Submission Form ................................................................................. D-1
Appendix E Educational Evaluation .................................................................................... E-1
Appendix F References ...........................................................................................................F-1
Appendix G Additional Documentation .............................................................................. G-1
ii
List of Figures
Figure 1: Airline Industry Dynamics [14] ...................................................................................... 5
Figure 2: Problem Solving Approach ............................................................................................. 7
Figure 3: IRMA and Morphological Matrix (Red=Incompatible) ................................................ 11
Figure 4: Selected Aircraft Architectures ..................................................................................... 12
Figure 5: Selected Propulsion Architectures................................................................................. 12
Figure 6: Primary and Secondary Constraint Diagrams ............................................................... 16
Figure 7: Shifting Design Space ................................................................................................... 17
Figure 8: Design Mission Profile [27] .......................................................................................... 17
Figure 9: Final Concept Architecture ........................................................................................... 18
Figure 10: Top and Front View of Cabin Layout ......................................................................... 19
Figure 11: Propulsion Integration System .................................................................................... 21
Figure 12: Battery Technology Chart [96].................................................................................... 22
Figure 13: Empennage Configuration ........................................................................................... 23
Figure 14: Electrical Sub System Schematic ................................................................................ 24
Figure 15: Different Mission Segment Electrical Load Profiles .................................................. 24
Figure 16: Noise Contour Plot for NXG-50 Aircraft .................................................................... 28
Figure 17: Mission Lifecycle GHG Emissions Trade Study ........................................................ 30
Figure 18: Airline vs. Manufacturer ROI ..................................................................................... 39
Figure 19: Compliance Matrix ...................................................................................................... 40
Figure 20: Georgia Tech [95] ..................................................................................................... B-1
Figure 21: Top Level Requirement Flowdown ........................................................................... G-2
Figure 22: Notional IRMA With Compatibility (Red=Incompatible) ........................................ G-3
Figure 23: Physical vs Functional Decomposition ..................................................................... G-3
Figure 24: Bombardier CRJ200 [90] .......................................................................................... G-4
Figure 25: Design Exploration and Modeling and Simulation Architecture .............................. G-5
Figure 26: Scatterplot Matrix (Visual Analytics) ....................................................................... G-5
Figure 27: Detailed Mission Profile ............................................................................................ G-6
Figure 28: Energy Weight Trade Study ...................................................................................... G-6
Figure 29: V-n Diagram .............................................................................................................. G-7
Figure 30: NXG-50 Weight Breakdown ..................................................................................... G-8
Figure 31: Center of Gravity Excursion Diagram....................................................................... G-8
iii
Figure 32: Component and Total Drag Breakdown .................................................................... G-9
Figure 33: Theoretical Cruise Drag Polar ................................................................................... G-9
Figure 34: Payload/Range Capability ....................................................................................... G-10
Figure 35: Subsystem Layout ................................................................................................... G-11
Figure 36: Lifecycle GHG Emissions per Unit of Energy [39] ................................................ G-14
Figure 37: Manufacture Return on Investment and Breakeven Unit Number .......................... G-15
Figure 38: Operating Cost Breakdown ..................................................................................... G-15
Figure 39: Airline Return on Investment .................................................................................. G-16
List of Tables
Table I: Metrics of Interest ............................................................................................................. 8
Table II: Steps for Creating an IRMA ............................................................................................ 9
Table III: TOPSIS Weighting Breakdown .................................................................................... 13
Table IV: Aircraft Architecture TOPSIS Results ......................................................................... 13
Table V: Propulsion TOPSIS Results ........................................................................................... 13
Table VI: Final Architectures ....................................................................................................... 14
Table VII: Wing Geometry ........................................................................................................... 20
Table VIII: Empennage Geometry................................................................................................ 23
Table IX: Single Aircraft Environmental Benefits Summary....................................................... 27
Table X: Fleet Environmental Analysis Summary ....................................................................... 29
Table XI: SRM Five Phase Approach to Safety Mitigation ......................................................... 32
Table XII: Calculated Energy per NXG-50 (60% Discharge) ...................................................... 32
Table XIII: Aircraft Acquistion Price ........................................................................................... 37
Table XIV: Direct, Indirect & Total Operating Cost ($ 2012 / Trip) ........................................... 38
Table XV: Industry Experts ........................................................................................................ G-1
Table XVI: Technology Readiness Levels ................................................................................. G-1
Table XVII: Aircraft and Propulsion Architecture Concepts ..................................................... G-4
Table XVIII: Fuselage Trade Study............................................................................................ G-7
Table XIX: Regional Jet Best In Class ....................................................................................... G-7
Table XX: Flying Quality Assessment ..................................................................................... G-10
Table XXI: Operating Cost Breakdown Per Trip ..................................................................... G-17
Table XXII: Evaluation Criteria Compliance Matrix ............................................................... G-19
iv
Nomenclature
Acronyms
ALCCA Aircraft Life Cycle Cost Analysis TOFL Takeoff Field Length
ANOPP Aircraft Noise Prediction Program TOGW Takeoff Gross Weight
APU Auxiliary Power Unit TOPSISTechnique for Ordered Preference
CAEP Committee on Aviation by Similarity to Ideal Solutions
Environmental Protection RDT&E Research, Development, Testing
CFD Computation Fluid Dynamics and Evaluation
CLEEN Continuous Lower Energy, RFP Request for Proposal
Emissions, and Noise RoI Return on Investment
e-fan Electric Fan RPM Revenue Passenger Mile
FAA Federal Aviation Administration USAF United States Air Force
FAR Federal Aviation Regulations VSP Vehicle Sketch Pad
FLOPS Flight Optimization System
GHG Greenhouse Gas Regular Symbols
GREAT Global and Regional Aspect Ratio
Environmental Aviation Trade-off cg Center of Gravity
GREET Greenhouse Gases, Regulated Aircraft Zero Lift Drag Coefficient
Emissions, and Energy Use in Compressibility Drag Coefficient
Transportation Model Induced Drag Coefficient
HEV Hybrid-Electric Air Vehicle
Pressure Lift Drag Coefficient
HTS High Temperature
Superconducting Aircraft Drag Coefficient
ICAO International Civil Aviation Aircraft Lift Coefficient
Organization Ci Closeness to Ideal
INM Integrated Noise Model kVA Kilo Volt-Amps
IRMA Interactive Reconfigurable Matrix kW Kilowatt
of Alternatives kWh Kilowatt-Hour
LE Leading Edge L/D Lift to Drag Ratio
LTO Landing and Takeoff MJ Mega Joule
MAC Mean Aerodynamic Chord MW Megawatt
MADM Multi-Attribute Decision Making N Load Factor
P/W Power Loading
MOI Metric of Interest S* Ideal Positive Separation
MSL Mean Sea Level S- Ideal Negative Separation
MTOW Maximum Takeoff Weight Time to double amplitude (sec)
NASA National Aeronautics and Space Equivalent Velocity (knots)
Administration Take-off Weight (lbs)
NextGen Next Generation Air W/S Wing Loading (lbs/ft)
Transportation System Greek
NPIAS National Plan of Integrated Airport Time to half amplitude (sec)
Systems Damping Ratio
R&D Research and Development
v
Problem Statement and Background
Problem Statement
In an effort to reduce carbon emissions, energy consumption, and noise to meet the goals
of the Next Generation Air Transportation System (NextGen), this particular design challenge
requires the design of a 25-50 passenger regional aircraft using electric or hybrid-electric
propulsion with a cruise Mach regime of 0.72-0.8, at least a 500 nautical mile range, and service
entry by 2025 [1]. Current regional aircraft are capable of ranges on the order of 1,500 nautical
miles and are comprised of turbo propeller aircraft capable of carrying 9-78 passengers and jet
In addition to the passenger, speed, and range requirements defined by the Request for
Proposal (RFP), assumptions for technology readiness and timeframes as well as estimates of
production, operation, and maintenance costs are required [1]. Road blocks to implementation
regarding power generation and power management will require assessment [1]. Furthermore, a
multitude of specialists, from the Federal Aviation Administration (FAA) including inspectors,
trainers, and certifiers, as well as airport operators, service and, maintenance personnel will need
training on this new system [1]. Life-cycle emissions and environmental impacts including noise,
particulate emissions, and fuel burn at the single level and fleet level will be estimated assuming
total replacement of existing same-class aircraft by 2025 [1]. Finally, the metrics for comparison
to existing aircraft must be based on energy consumption and lifecycle greenhouse gas emissions
excessive delays, adverse environmental impacts, and safety risks [3]. The changes associated
with NextGen provide an opportunity to improve the nations economy and reduce overall
1
carbon footprint [3]. These changes are achieved through better use of the national airspace,
airports and the integration of more environmentally responsible aircraft [3]. NextGen is driving
the advancement of the airspace infrastructure which includes: positively impacting overall
economic health and the global environment, restoring flexibility to the system for future growth,
and enhancing airspace safety [3]. Despite its many expected benefits, NextGen is not without
future growth. The FAAs Continuous Lower Energy, Emissions, and Noise (CLEEN) goals of
reducing fuel burn by 33% and oxides of nitrogen by 60% impose environmental design
constraints for competitive NextGen systems [3]. The environmental goals outlined by CLEEN
cannot be achieved by existing conventional aircraft, making new technology such as electric or
Design Issues
Currently, no electric or hybrid-electric aircraft exist to service the US regional passenger
transport market, presenting a variety of design issues [2]. GT Aircraft, Inc recognizes that the
propulsion system is the source of many of these issues. The design of the propulsion system
must decrease noise, energy consumption, and greenhouse gas emissions while still providing a
cost-effective solution for service entry in 2025 [4]. Thus, the aircraft design becomes a balance
between new system technology integration for efficiency, as well as minimizing complexity and
weight associated with respective new technologies. For example, using batteries and/or fuel
cells may increase efficiency and reduce fuel burn, but have prohibitive characteristics such as
One of the biggest technical hurdles for new aircraft is energy storage (energy density) in
the form of batteries for an aircrafts electrical needs [6]. Recent studies indicate the maturation
2
of energy storage methods could accelerate based on demand from commercial electronics and
automobiles [7]. Despite the expected energy storage technology maturation, little is known
about future capabilities and expected timelines; therefore, the inclusion of advanced energy
storage options in the aircraft design must rely on appropriate predictions and expert opinions.
GT Aircraft, Inc understands that one of the more important challenges in this design is
into NextGen and to inspire interest from airlines; resulting in a successful and profitable modern
aircraft [3]. To accurately assess these issues, industry experts and airline operators
professional judgments (as catalogued in Appendix G, Table XV) and safety issues will be
considered.
requirements. In conjunction with new technology, new design practices must be implemented to
provide more efficient aircraft. Currently, regional passenger transports are designed for long
ranges to enable more capability; however, these aircraft rarely fly distances greater than 1000
nautical miles [8]. The one size fits all design approach has shown inferior environmental
performance and from an energy consumption perspective designing the aircraft for the
reviewed. The Georgia Tech Integrated Product and Process Development (IPPD) design
systematic approach to the early integration and concurrent application of all the disciplines that
3
play a part throughout a systems life cycle[10]. This approach ensures maximum flexibility for
systematic, structured decision matrix used to integrate objective and implicit knowledge into the
concept selection process [11]. The use of compatibility matrices ensure that interrelationships
between concept options are captured and displayed [11]. Due to the interdependencies of
[12]. Current sizing methods assume coupling between propulsion system sizing and aircraft
sizing, are limited to certain types of fuel, and assume a decrease in weight of the aircraft during
flight proportional to fuel flow [12]. Nams method addresses these shortcomings through a
generalized propulsion system model, the concept of multiple power paths, use of multiple
airline industry to help define future design decisions. The airline operating environment is
driven by challenging, hard to predict pressures including volatile fuel prices, a continually
shifting world economy, regulatory policies, large scale events such as the attacks on September
11th, 2001, changing traffic growth, and environmental pressures [13]. Global economic growth
drives air travel and in turn airline fleet growth which can be seen in Figure 1 [14].
4
The 2011 FAA Aerospace Forecast
growth and the need for improved airspace FIGURE 1: AIRLINE INDUSTRY DYNAMICS [14]
utilization and reduced aviation environmental impact, approximately 34,000 airplanes are
forecasted to replace older, less efficient models, stimulating innovation in airline business [13].
Specifically, significant 50-seat jet retirements and a regional jet growth rate of 2% annually
through 2031 are expected in the domestic market [15]. These expectations result in the need for
One way in meeting passenger needs is improving airline commercial service access
because only 63% of the population is conveniently located near commercial service airports
even though 98% of the US population is within 20 miles of the 3,330 existing National Plan of
Integrated Airport Systems (NPIAS) airports [16]. By increasing flight frequency to these under-
utilized airports through affordable, regional aircraft the supply-demand gap is bridged,
through a balance of point-to-point and hub-to-point services. This scenario imposes design
constraints, such as reduced field length, increased emission concerns, and airline load factor.
Technology Forecast
In order to address imposed design constraints and ensure a feasible design space, a
specific set of technologies are required. There exist fundamental requirements for any
technology used in aircraft applications, namely high reliability, high availability and high power
5
density, while reducing weight, complexity, fuel consumption, operational costs, and
environmental impact [17]. Although there exist airframe technologies that address design goals,
as seen in Cal Polys AMELIA report, other studies including the Boeing SUGAR report place
importance on propulsion technologies which is in alignment with this design challenge[14] [18].
One such potential enabling technology is High Temperature Superconducting (HTS) Electric
Motors due to their high specific power. However, high operating temperatures and immaturity
in cryogenic cooling systems exclude HTS technology from the design study [19]. Another
significant limiting factor regarding electric propulsion is energy density, which currently is an
order of magnitude lower than existing fossil fuels [20]. Currently lithium air (Li-Air) batteries
hold the key to bridging the gap between fossil fuels and batteries [21]. For the timeframe of this
design challenge Li-Air batteries will not be deemed an enabling technology due to the infancy
of the associated programs [21]. The exclusion of these enabling technologies renders purely
electric propulsion infeasible, requiring a hybrid-electric propulsion architecture. For this design
challenge, GT Aircraft, Inc identified all technologies possessing technology readiness levels
Tech Integrated Product and Process Development (IPPD) design decision support process in
order to address the broad scope of this design challenge. Following the IPPD process, a Concept
Development and Systems Engineering (CDSE) approach was taken to enable full exploration of
the problem definition, concept development, and concept selection prior to system definition
and design. This approach provided the ability to determine the best design through a process
6
that trades requirements, technologies, and
approach.
Requirement Analysis
In order to fully define the design
miles and a cruise speed of 0.72-0.80 Mach. FIGURE 2: PROBLEM SOLVING APPROACH
and objectives, and federal regulations. Based on the FAA CLEEN initiative the environmental
requirements are: a cumulative noise reduction of -32 EPNL below Stage IV, LTO NOx
emissions reduction of 60% below CAEP 6, and a 33% reduction in energy consumption relative
to 2005 best in class [19]. In order to operate at a majority of the NPIAS airports the design will
require a balanced field length of 5,400 feet. A summary of requirements can be found in
Appendix G, Figure 21, and were mapped to a set of metrics in order to establish value in the
Establish Value
Based on the design challenge requirements and motivation, and in alignment with the
NextGen initiatives [22], a set of Metrics of Interest (MOIs) were chosen and weighted, shown
in Table I, in order to evaluate the goodness of each the alternative solutions. These drivers
simplified decisions that had inherent bias and assisted in the resolution of conflicts during the
Improvement upon energy consumption and emissions prevents the aircraft from
Energy
being a constraint to the airspace systems growth. Energy consumption and
Consumption/ 35%
emissions were incorporated into one MoI to avoid biasing the design due to the
Emissions
existence of a strong correlation.
Not only must this aircraft be designed to certification requirements to join the
Safety 15%
airspace system, but it must also be deemed safe and reliable for public acceptance.
components [14]. The NXG-50 concept selection used the Interactive Reconfigurable Matrix of
Alternatives (IRMA) developed by the Georgia Tech Aerospace Systems Design Lab (ASDL)
which uses the Morphological Matrix of Alternatives [23]. Due to the complexity of advanced
systems, the IRMA captures the entire design space where there may be upwards of billions of
possible solutions and outputs concept architectures (alternatives) through a manageable design
describe whether one morphological matrix component alternative is compatible with another
matrix component alternative. This can be seen in the notional IRMA in Appendix G, Figure 22
when the selection of an electric energy source removes the ability to select Brayton cycle,
8
piston, and fuel cell power generation. These compatibility relationships drive the down-
selection and output an architecture upon completion. Before selecting a set of architectures to be
considered, several steps in the creation of the IRMA were performed. With the help of technical
advisors, the following steps described below (Table II) were completed to construct the notional
In reference to Step III above, the IRMA can use a strictly functional or physical
taxonomy. An example of functional vs. physical decomposition can be seen through an analogy
in Appendix G, Figure 23. The analogy selects a reference design and shows that through a
physical decomposition the output designs are relatively similar to traditional designs, but in
changes to the propulsion architecture due to timeframe viability and associated risk. Because of
this, a physical taxonomy was used for the airframe architecture decomposition and a functional
taxonomy was used for the propulsion architecture decomposition which can be seen in Figure 3.
Step VII requires the establishment of a baseline aircraft. The Bombardier CRJ200 was
chosen by GT Aircraft, Inc as a frame of reference and for benchmarking purposes. The CRJ200
is a 50 passenger aircraft that can fly more than 500 nautical miles and operates in the 0.72-0.8
9
Mach regime [24]. The CRJ200 not only aligns perfectly with this design challenge, but it also
accounts for 33% of the US regional jet market and over 55% of 50 passenger regional jet
operations [2]. The CRJ200 is shown in Appendix G, Figure 24. It should be noted that analysis
methods used by GT Aircraft, Inc produce a model of the Bombardier CRJ200, but not the actual
aircraft. The modeled aircraft will be referred to as the baseline aircraft and offers a departure
Upon creation of the IRMA, concept alternatives were generated following the steps
outlined below:
IRMA Step 1 - Metric Impact and Order Selection: The first step was to map the impact of each
matrix component (None-Low-Med-High scale) to each metric of interest. This was done
through a review of literature and with the expertise of technical advisors. Once each component
was mapped to each metric, the order of selection was determined logically beginning with the
high impact components as to allow compatibility effects of the most important components to
IRMA Step 2 - Score Matrix of Alternatives: GT Aircraft, Inc investigated each Metric of
Interest and scored the matrix alternatives within each taxonomical component (row) based on
their value to the specific metric where 1 was very low, 3 was low, 5 was average, 7 was high,
and 9 was very high. This was completed for each MOI. An example can be seen in Figure 3
where a single fuselage scored a 5 whereas a two fuselage configuration scored a 3 due to the
associated increase in weight and drag having a detrimental effect on energy consumption.
10
FIGURE 3: IRMA AND MORPHOLOGICAL MATRIX (RED=INCOMPATIBLE)
IRMA Step 3 - Down-Select Group Concepts: GT Aircraft, Inc began selecting alternatives with
respect to each metric of interest following the order of selection based on the highest scored
option. However, the highest scored option was not always the selection due to mission
capabilities and matrix compatibility effects. Upon completion, a set of architectures would be
down-selected. Figure 3 displays a mapping of a notional concept through the IRMA and its
11
IRMA Step 4 - Sketch Selected Architectures: Based on the aircraft architecture selections,
sketches for the aircraft system were created in Vehicle Sketch Pad (VSP) [25]. Similarly,
propulsion architecture sketches were created for the propulsion architecture selections.
established for further investigation which can be seen in Appendix G, Table XVII, respectively.
The set of airframe and propulsion architectures from the IRMA process are shown in Figure 4
and Figure 5.
The physical decomposition of the airframe architecture resulted in a set of evolutionary down-
12
propulsion architecture resulted in a set of revolutionary down-selected concepts depicted in
Figure 5.
Evaluate Alternatives
A Multi-Attribute Decision Making (MADM) method, Technique for Ordered Preference
by Similarity to Ideal Solutions (TOPSIS) was used to rank concept alternatives through the use
qualitative trade study effects such as wing mounted engine vs. fuselage mounted engine or
speed regime effects on open rotors. These types of effects are taken into account in the
alternative scoring. By investigating a range of weightings (Table III), GT Aircraft, Inc was able
to establish the sensitivity of the changes due to weighting bias. The final configuration was
shown to be the most robust solution for the weighted metric ranges.
Weighting Ranges
Energy
TOFL Noise Cost Safety
Consumption
Weighting 15% 35% 25% 10% 15%
Valid Range 0% - 25% 0% - 50% 25% - 50% 0% - 20% 10% - 50%
This MADM process of establishing the closeness to the ideal solution through the weighting of
normalized raw scores ensured the selection of the optimal-compromise solution. The summary
of airframe and propulsion architectures TOPSIS results are shown in Table IV and Table V
respectively.
13
Based on GT Aircraft, Incs process, airframe architecture Concept 3 and propulsion system
were selected as the final architectures (Table IV) due to their closeness to the ideal solution.
Sizing and further analysis was performed using an integrated modeling and simulation
environment.
poses unique challenges. The most significant challenge is the introduction of an additional
degree of freedom(s) and the alternate fuel source(s). Traditional formulations assume a single,
homogeneous fuel source that reduces in weight when consumed. This may not hold true for the
fuel source(s) of a HEV. Existing legacy tools incorporate traditional sizing approaches in their
design routines.
To address this concern, a generalized sizing method outlined in Nam [12], was
implemented to allow for the use of multiple power paths within a HEV. This allowed for the
integration of multiple fuel sources, whose weight(s) may or may not change as a function of
time. Similar to a traditional sizing and synthesis formulation, constraint analysis was performed
to ensure the HEV met the mission performance requirements. Due to the existence of multiple
power paths, multiple constraint plots were constructed, each unique to a specific power path.
There exists no closed form solution to finding the optimum power mix (portion of primary
14
power), and thus the objective of the modeling and simulation environment, in addition to sizing
the aircraft, was to determine the optimum power mix between turboelectric generators and
System Simulation (NPSS) analysis code, both developed by NASA, were used to form the
foundation of the modeling and simulation environment [26]. A synthesis tool was then
developed, encompassing the formulations outlined in Nam [12], to augment the mission
analysis and performance calculations. Due to the conventional aircraft airframe, modification to
the weight and aerodynamic modules of FLOPS was not required. Using the calibrated baseline
model as a departure point, the aircraft underwent preliminary sizing by FLOPS and the primary
and secondary power path efficiency maps were determined using NPSS, and passed to the
synthesis code. The synthesis code, using Nam's formulation, determined the design point based
on constraint analysis and performed the mission analysis for a preselected power mix. The
sizing loop was then closed by feeding back the post mission analysis sized aircraft and
comparing it with the post FLOPS sized aircraft. If the comparison was not equivalent within
specified tolerances the propulsion size and required energy data was updated within FLOPS and
another sizing iteration performed. The described method illustrates the sizing routine for a
single power mix case. In order to establish a design space in which to investigate, the above
process was run for multiple power mixes, which was determined using the design of
of each of the limiting mission requirements, shown in Figure 6. These requirements were both
15
derived and defined, and include requirements stated in the RFP, in conjunction with Federal
wing loading configurations at which to evaluate. These correspond to minimum primary power
loading, minimum secondary power loading and maximum wing loading. Through the use of the
established integrated design environment and visual analytic methods, shown in Appendix G,
Figure 25 and Figure 26, it was determined that maximizing the wing loading was preferable to
minimizing power loading, in order to obtain the most robust design. Ensuring a large feasible
design space is paramount allowing for growth or deviation from the selected design point, while
still being able to satisfy the design requirements. The feasible space is depicted as the white
region in Figure 7.
16
Power Mix @ Climb
The design mission profile depicted in Figure 8 is a forecasted NextGen regional aircraft
mission profile and is detailed in Appendix G, Figure 27. A traditional mission profile for this
class of aircraft consists of a takeoff, climb, step cruise, descent, loiter, and divert segment. This
traditional profile was augmented for use in a future environment, and takes into account
improved airway management and spacing. These modifications include an optimized climb
Using the integrated design environment, the power mix of the primary and secondary
power paths were explored, shown in Figure 7. Through the use of the above described physics
17
based sizing and synthesis environment and visual analytics techniques, the optimum mission
profile and power mix schedule was determined, see Figure 8, the primary and secondary power
paths were appropriately sized and the required wing loading determined.
The environment was then used to perform multivariate trade studies to ensure an
optimum wing and empennage configuration. This was achieved by performing sensitivity
studies to determine key design variables. Once the key variables were identified, trade studies
were performed to establish the optimal compromised solution. An example of this process can
motor fan with a generator. The combined architectures, the NXG-50, are shown in Figure 9.
Vehicle Definition
Once the NXG-50 concept architecture was selected and conceptual sizing performed, the
preliminary vehicle was defined. The preliminary design phase focused on important commercial
aircraft components such as fuselage, propulsion system, wing, and aircraft subsystems.
Fuselage
The fuselage must not only meet the design challenge requirement of 25-50 passengers,
but also support cabin pressurization and all subsystems, while concurrently abiding by Part 25
and Part 121 of the FARs [27]. A circular cross section fuselage was chosen as it provides a
18
strong pressure vessel that is easy to manufacture while minimizing drag and weight and
To provide the end user (the passenger) with a higher level of comfort, the seating
arrangement was designed not only to meet FAR minimums, but to exceed all competitive
aircraft in todays regional jet fleet as shown in Appendix G, Table XIX, with an additional 3
inches in seat pitch, an additional 1.2 inches in seat width, and an additional 2 inches for aisle
outlined in FAR Part 25 were met. Figure 29 in Appendix G depicts the required maximum
design load factor of 2.58. In addition to structural constraints, component weights were
calculated as seen in Appendix G, Figure 30 where fuselage and hydraulics weights were
reduced. Using information provided in Figure 30 and component locations, a center of gravity
excursion diagram (Appendix G, Figure 31) shows a 0.6% change in mean aerodynamic chord
Wing
From the initial airframe selection a cantilevered, low wing was selected due to
space for passenger comfort, and incorporating dihedral to increase stability [29]. Due to the
19
airframes conventional design the wing layout was based on the CRJ200 wing and
optimized using FLOPS for the NXG-50 nominal mission, the wing geometry can be seen in
Table VII. Based on this geometry the NASA supercritical airfoil series was selected for its
In addition to selecting the airfoil shape and determining the wing configuration, drag
calculations were performed to ensure optimum cruise efficiency, seen in Figure 32 and Figure
33 in Appendix G. With this optimum cruise efficiency, the NXG-50 meets the 500 nautical mile
range requirement as depicted in the payload-range diagram (Appendix G, Figure 34), satisfying
point-to-point and hub-to-point capabilities with a design range of 1,000 nautical miles.
propulsions main turboelectric generators drive the e-fan motors to generate the required thrust.
However, these generators also recharge the high density batteries of the aircraft and generate
power for the subsystems. The e-fan units are connected to the aircraft main body through pylon
structures as is standard in the industry. In this case however, the pylon only needs to allow
space for a high energy density cables instead of the bleeding ports and fuel pipes that are
traditionally hosted. The pylon is structurally optimized without the piping restriction and
20
considering the reduced weight of the e-fan
Aircraft
engines, the propulsion integration saves weight
Batteries >
Aircraft
with respect to traditional propulsion systems. This Subsystems
Power
integration is shown in Figure 11. Management
simulations are 8,200 horsepower per generator FIGURE 11: PROPULSION INTEGRATION
SYSTEM
excluding efficiency losses. A typical turboelectric
generator is comprised of a compact gas turbine that powers a set of generators. Modern
Auxiliary Power Units (APUs) found in the civil aviation industry fulfill current electric
generator requirements for aircraft. They generate electricity from jet fuel in an efficient manner
with variable generators that adapt to the power demands. They also have reduced levels of noise
and emissions. A modern APU normally generates between 670 and 1340 horsepower [31]. For
our application a new 8,200 horsepower turboelectric unit is required for the NXG-50.
[14]. The power required per electric motor is 9,300 horsepower at maximum power (8,200
horsepower from turboelectric generator and 1,100 horsepower from batteries). The electric
motor is required to provide the desired power for a wide range of shaft speeds within efficiency
limits. The electric motor will be required to meet all FAA certification requirements such as fan
blade off, water ingestion, and extreme weather conditions. There is no precedent for commercial
e-fans in the aviation industry; therefore, an e-fan type electric motor will need to be developed
21
for this specific application. The electric motor technology is well understood; however, an
Battery
The battery selection considered several types of battery technologies. One of the main
key metrics for battery selection was energy density since it had an important influence on the
performance of the aircraft. The chart presented in Figure 12 considers different battery
specific energy for jet fuel is approximately 18,550 British thermal unit per pound (44 MJ/kg)
[32]. It is clear that jet fuel presents a specific performance advantage; however, the use of power
The safety and reliability of the battery is crucial for a robust design. Lithium batteries
based on cobalt oxide (LiCoO2) offer higher energy density; however, are less thermally robust
than other lithium battery types. The Boeing 787 battery incident has set the precedent on battery
certification, in particular for lithium batteries based on cobalt oxide. Although thermal related
concerns exist regarding battery usage, Boeings solution, based on the redesign of the batterys
internal components, proves that this type of battery is feasible within the aviation industry [33].
For these reasons and the great scope of future evolution of this technology, the cobalt oxide
requirements of the NXG-50 as well as attenuate noise emissions associated with e-fans [28].
The empennage geometry provided in Table VIII meet the static stability requirements as well as
the dynamic stability requirements. With GT Aircraft, Incs design, the resulting static margin is
10% which is above the value of 5% suggested by Roskam [30] for longitudinal static stability.
Additionally, the directional static stability meets the minimum requirement of 0.001 per degree
suggested by Roskam [30]. A complete flying quality assessment can be found in Appendix G
Table XX.
subsystems to result in a more efficient and environmentally friendly regional jet. The NXG-50
subsystem layout is shown in Appendix G, Figure 35, and in comparison to a traditional regional
jet in Figure 14, all power for the subsystems is provided by the electric generators. The removal
of all hydraulic systems was found to reduce weight, operating cost, maintenance, and eliminate
contamination problems [34]. Similarly, the removal of engine bleed, as already proven in the
B787, improved engine efficiency, fuel consumption, reliability, and reduce maintenance costs
[34][35].
23
FIGURE 14: ELECTRICAL SUB SYSTEM SCHEMATIC
The expected power load for the subsystems at various flight conditions was based on a
study completed for an all-electric aircraft concept for approximately 130 passengers [36]. This
study used a statistical approach with current referenced subsystem voltage requirements to
calculate expected power required for the electric subsystems [36]. Figure 15 shows the expected
power load for various electric subsystems at different conditions in the mission profile.
Actuation
Landing Gear
Total Power
External Lighting Condition
Load (kW)
Starter & Fuel Pump Ground Ground 195
Cabin Equipment Takeoff Takeoff 90
Climb 224
Avionics Cruise
Cruise 276
Ice Protection Descent 234
Environmental Control Loiter 231
Landing 96
0 50 100 150
Power (kW)
24
Environmental Benefits
Four metrics were used to track the environmental impact of the NXG-50: energy
consumption, noise, landing-takeoff (LTO) cycle nitric oxides (NOx) emissions and life cycle
greenhouse gas (GHG) emissions. These metrics were used to compare between the baseline
benchmark aircraft (CRJ200-based model) and the NXG-50. Several software tools, described in
the following sections, were used to model the environmental impacts of the baseline aircraft and
the NXG-50.
baseline and NXG-50 aircraft [37]. The baseline aircraft was modified from a model calibrated
to the Bombardier CRJ200. The calibration of the baseline aircraft is explained in Appendix G in
the Acoustics section (G-11). The baseline model was then modified to the NXG-50 aircraft.
Suppression factors were used in ANOPP to appropriately model the reduction in core due to the
use of the electric propulsion system. The results (in dB below Stage IV) of the noise assessment
sizing and mission analyses. The analysis is based on the rated output thrust at sea level static
and four operating points defined in the International Civil Aviation Organization (ICAO)
Emissions Databank [38]. The NXG-50 electric contribution to the propulsion system did not
contribute to the LTO NOx analysis. Table IX shows the results of the LTO NOx analysis with a
reduction of 71% over the baseline and 58.2% below CAEP 6. Details of the analysis are found
in Appendix G (G-12).
25
Life Cycle GHG Emissions
Well-to-wake GHG emissions (including the emissions from energy production and
transportation) from fuel burn and electricity used for charging were determined using Argonne
National Laboratorys GREET 1 (Greenhouse Gases, Regulated Emissions, and Energy Use in
Transportation Model) Excel-based software (2012 rev2) [39]. Life cycle GHG emissions for the
battery only were estimated using the GREET 2 (2012) vehicle cycle model. Unless specified,
default inputs were not changed. These emissions results required fuel burn, distance travelled,
weight/energy use metric for a specified type of aviation fuel. A hypothetical future US
electricity generation mix in 2025, based on the 2013 U.S. Energy Information Administrations
Outlook (0.83% Oil, 37.61% Coal, 19.88% Nuclear, 14.39% Renewables, and 27.28% Natural
Gas) was input to determine emissions due to electricity generation at the wall outlet, assuming a
6.5% transmission loss [39] [40]. This electricity mix represents the U.S. electricity generation
on the average and does not take into account regional generation biases. Finally, life-cycle
emissions due to the manufacture and recycling of Li-Ion batteries were determined from the
battery weight and assuming typical Li-Ion chemistry, as well as 48% emissions from original
manufacture to recycle and reconstruct the battery [41][42]. Estimating the number of battery
packs over the life of an aircraft, and then applying that to each mission give the share of battery
GHG emissions per mission. The total emissions from these three processes are added together
for the total lifecycle GHG emissions of the NXG-50. GHG emissions due to manufacture and
disposal of the actual aircraft were neglected and assumed similar to baseline for comparison
purposes. The results from this process are in Table IX where the reduction over the baseline
aircraft with a US mix is 10.24% and 21% for a clean energy mix.
26
Energy Consumption
NASAs FLOPS was used for the baseline aircraft mission analysis. The FLOPS baseline
model was calibrated to Bombardier CRJ200 data [24]. The geometry and design mission were
used to calibrate to the design maximum weights and then to the fuel required to make the design
range. The calibration details are shown in Appendix G in the baseline aircraft calibration energy
consumption section. The aircraft was then flown with the NXG-50 mission. The fuel required
for the mission excluding the reserves is called the block fuel and is typically used to assess the
fuel burn efficiency. The block fuel burn for the baseline aircraft is 2,922 pounds for a 500
nautical mile mission. FLOPS mission analysis was supplemented with energy analysis for a
hybrid-electric propulsion system to analyze the NXG-50. The NXG-50 block fuel burn is 2,296
lbs for the 500 nautical mile mission, with a supplemental requirement of 930 kWh electric
energy from Lithium-Ion batteries. The batteries can be fully charged on the ground from an
outside source and are discharged to 40% capacity to improve battery lifespan [43]. Given the
mission, GREET is able to determine the required well to wake energy used for each aircraft.
Using conventional Jet A as a basis of comparison for each aircraft with an assumed lower
heating value (LHV) of 43.2 MJ/kg [39], additional energy from the battery was added to the
fuel energy (assuming 90% charging efficiency [44]) to determine the overall energy required.
The results of the single mission energy analysis in Table IX show a reduction in energy
27
Fleet Level Aircraft Assessment
Acoustics
Integrated Noise Model (INM) software was
operations for this analysis. That data along with the aircraft noise results from ANOPP were
input to INM. The resulting contours for the baseline and NXG-50 appear identical due to the
small difference in noise applied over many operations in a given day. Figure 16 shows a sample
noise contour plot for the aircraft. The contours show that the light blue area (55 dB DNL)
extends slightly outside 2 miles from the center of the airport area. Each ring in the figure
performance, and then comparing the concept to the baseline as in the single aircraft analysis. As
a result, relative performance improvements are the same, but now a tangible performance metric
is realized. Significant reduction in the 25-59 passenger class (assumed 25-50 passenger) global
fleet size is expected, from 3,600 aircraft in 2011 to 1920 aircraft (est.) in 2025 [46].
Assumptions included both aircraft would be used at the same average rate as a CRJ200 (2096
28
flight cycles/year [47]), the average mission was the design mission, and comparisons were made
for a notional total fleet replacement in 2025 at the projected fleet size, the results of which are in
Table X. GHG reduction was on the order of several million tons of CO2e per year for the fleet,
Energy Consumption
Fleet energy consumption was calculated similarly to the fleet GHG emissions, with the
same assumptions for fleet size. Energy consumption was compared for the baseline aircraft and
the NXG-50 with similarly sized 2025 fleets. Results are in Table X, and show nearly a 15%
A trade study was performed to determine the trade-off between increased power plant
emissions due to recharging the battery at the airport compared with emissions from aviation
fuel, as shown in Figure 17. Six different energy sources were compared to the baseline design
and represented as a percent change relative to the baseline. In general, electricity generated from
oil, coal, or natural gas, to include the US average energy mix (projected in 2025) led to higher
GHG emissions overall as the share of energy from the battery increased. However, generating
decrease in GHG emissions (reference Figure 36 for the actual emission per unit of energy). GT
Aircraft, Incs current design point is shown as well, overlaid on the various sources. No attempt
29
was made during this trade study to adjust the different energy required due to changing energy
weights, although this may yield a specific optimal design point with respect to greenhouse gas
emissions that considered the rapidly increasing weight and increased energy required of more
battery. The energy density of the battery was assumed to be 0.07 kWh/lb, (which incorporates a
minimum energy depletion of 40%), and that of Jet A to be 5.45 kWh/lb. That is a significant
difference that cannot be ignored, and is depicted on the right axis in Figure 17. There exists a
point where the percentage of energy supplied by a battery/fuel combination will not overcome
the energy required by the mission, which was not explored. Until energy storage approaches the
energy density of jet fuel, it should be noted that the battery energy weight would be significant
in comparison to pure jet fuel, and that unless the electricity that goes to recharging the batteries
comes from clean sources, no real GHG emission benefit would materialize with increased
emphasis on batteries.
Natural Gas
250% 5000%
Coal
200% 4000%
Biomass
Nuclear/Clean
50% 1000%
Energy Weight
0%
100%
0%
7.82% Energy Weight
0% 20% 40% 60% 80% 100%
Baseline
Percent Energy from Battery
30
Safety Risk Assessment
The incorporation of any new aircraft into the national airspace is a delicate balance
between production and safety [48]. The FAA Safety Management System Manual introduces
Safety Management Systems (SMS) for airport operators to manage and mitigate safety risks
through the implementation of policy, architecture, assurance, and the promotion of safety
[48][49]. One of the key processes incorporated in SMS is Safety Risk Management (SRM)
The safety risk factors of interest for SRM include the type of aircraft and performance
characteristics, systems and/or subsystems intended to function in flight or on the ground; traffic
density and distribution; airspace complexity and classification; airport layout; type of air-ground
communication; type and capability of surveillance and automation system; human factors; and
local or regional weather phenomena [49]. Using the FAA Advisory Circular 150/5200-37, SRM
was applied to the NXG-50 design and the five phase analysis is outlined below in Table XI [48].
Two risk areas were identified that are unique to the NXG-50 design. These include: (1) the
failure of the battery responsible for providing power to the electric subsystems and the hybrid-
electric propulsion system, and (2) the high electric loads to be delivered to the airport apron for
31
TABLE XI: SRM FIVE PHASE APPROACH TO SAFETY MITIGATION
By service entry in 2025, it is assumed that NXG-50 will incorporate advanced batteries
that more closely reflect the successful Chevy Volt battery which has experienced no undetected
or catastrophic failure [50]. Analysis of risk associated with airport operators responsible for
handling high electric loads was derived from injuries of electrical workers which remained less
than 0.003% from 2003 2010; making the injury of airport operators for the NXG-50 extremely
improbably [51]. Table XI shows the inclusion of the NXG-50 design into the national airspace
in 2025 will include minimal risk provided that risk is treated as outlined in Phase 5 (Table XI).
was calculated based on a maximum 60% discharge of the battery, similar to the Chevy Volt
battery which is designed to improve battery life [43]. Using the energy density and weight of
the battery, the energy required to charge the batteries for one NXG-50 was calculated to be 940
32
Assuming a supply of 180 kVA of apparent power which is currently used to support the
Airbus A380 while on the apron, the expected time required to charge the batteries for one NXG-
published in the Advanced Energy Materials Journal by Dr. Harold Kung, rechargeable batteries
with new electrodes could charge up to 10 times faster than current batteries [54][55]. As this
technology is expected to reach the marketplace in three to five years, the battery charge time for
the NXG-50 could be as low as 30-40 minutes by 2025 [54][56]. The rapid charge rates will
allow the NXG-50 to be charged at the apron by simply plugging the aircraft into ground power
units or the airport electric grid. Due to rapid charging, the turnaround time for the NXG-50 will
be approximately 40 minutes, only modestly higher than the average 25 minutes [57].
The daily power requirements will be different for small, medium, and large size airports
where the arrival rate can vary from 1 180 aircraft per hour [58]. Assuming the number of
NXG-50 hybrid-electric aircraft is only 30% of the arriving aircraft (most constraining case) in
2025, the daily electrical demand could vary from 6,800 1.2 million kWh [59]. To determine
the impact on the electric grid, the maximum daily electricity for the busiest airport, Atlantas
Hartsfield-Jackson International Airport was used as a sample case. Introducing the NXG-50 to
Hartsfield-Jackson would result in an additional annual energy requirement of 445 GWh, only
1.3% of the City of Atlantas electricity in 2007 [60]. This implies that introducing the NXG-50
would have a feasible impact on the electric grid and local community life; similar minimal
impacts on the electric grid have been projected for electric cars [59]. As the batteries for the
NXG-50 will require a significant amount of energy while parked at the apron, improvements in
the airport power management system will likely need to occur. These improvements should
prevent stringent surge requirements from being enforced. Unlike the potential surge hazards
33
with electric cars where the majority of the vehicles will be charged in the evening, the power
Using a projected electricity cost of $0.08/kWh and the daily airport cost for an airport
could range from $740 - $170,000 which is less than the displaced fuel ranging from $2,000 -
$8.7 million per day (2013 jet fuel prices)[62][63]. As the NXG-50 is a hybrid-electric aircraft,
all current airport infrastructure would have to remain with the addition of a battery maintenance
facility and an upgrade to the apron power supply for rapid battery charging. After speaking with
industry expert Dr. John Joyner from Delta Airport Consultants, it was concluded that an
additional off-site facility would be required for battery handling and maintenance [64]. The
expected cost for the additional battery related improvements would vary based on airport size,
but could be as high as $600,000 based on functional space requirements for an electro-
environment shop of 12,500 square feet and an average warehouse construction cost of $48.35/sq
ft [65][66]. The average time to build a warehouse in the U.S. is a mere 30 days, making the time
architecture, the necessity for increased skills and training for personnel in the aircraft industry
must increase alongside technology. Complementary to this will be the requirement of skills and
training to be tailored to the specific aircraft that select personnel will be required to interact
with. Based on the NXG-50 all-electric subsystems and hybrid-propulsion system the only
changes in operations, maintenance and servicing are intended to occur at the terminal apron and
any airline offsite maintenance facilities. While GT Aircraft, Incs design is essentially
conventional to todays regional jets it does have three large differences which include the
34
enhanced electronic network, more batteries, and a hybrid-electric propulsion system. In these
FAA Personnel
Part of the responsibility for successful implementation of new aircraft into NextGen is
handled by FAA personnel. With a new aircraft, inspectors, trainers, and certifiers must all gain
additional skills and knowledge specific to the aircraft. The NXG-50 is essentially an advanced
derivative aircraft where specific skills and knowledge of electric subsystems, electric power
management, thermal management, electric motors, and the interaction of fuel and electric power
generation systems will be necessary. Inspectors, trainers, and certifiers will require proficient
knowledge and experience in these areas in order to fulfill their required duties. The timeframe
for these skills and training objectives will be determined by a safety system analysis plan that
will occur in concurrence with the certification of this design to 2025 and after in order to
Airport Personnel
Airport personnel are expected to grow to over 600,000 technicians worldwide by 2029
[68] which are why it is important to understand the required skills and training for these
technicians. Airport personnel that do not directly interact with the aircraft will not require any
additional skill sets or training as the differences associated with the NXG-50 are all internal.
Airport operators will require additional knowledge and training of the airport electrical grid in
order to be able to provide power to the NXG-50 when necessary. With the help of John Greaud,
Vice President of Operations at Memphis International Airport, it was determined that personnel
requiring additional skills and training will be Aircraft Electronics Technicians (AETs) and
Aircraft Mechanics. AETs currently receive approximately 1,000 hours in classroom training
specifically for avionics and electric system operations and maintenance as well as additional
35
refresher courses and aircraft specific courses as required by manufacturers and airport
administration. It is reasonable to assume that training hours will increase minimally as the
training content changes to meet the additional NXG-50 design needs. Also, Aircraft Mechanics
currently receive approximately 3,000 hours of training and similar to the AETs, will only
require a minimal increase in time in the classroom to adhere to the enhanced systems of the
NXG-50. The actual skill sets, training requirements, and timeframes are under constant state of
fluctuation and depending on a more in depth analysis beyond the timeframe of this design
challenge and the future state of the aviation industry the requirements for personnel will adapt
implementation into an ever changing environment. Many performance benefits come at a great
price and it requires a balance of performance and affordability to ensure a successful aircraft.
Acquisition cost and operating cost are two important cost metrics. Acquisition cost is important
to both aircraft manufacturers and airline operators, and directly affects the return on investment
(RoI) of both sectors; whereas the operating cost directly affects only the airline operators. Using
the Aircraft Life Cycle Cost Analysis program (ALCCA) acquisition cost and operating costs
were determined for both the baseline CRJ200 type aircraft and the NXG-50.
Implementation
Effective implementation of the NXG-50 was an integral part of the design process. It
had a large impact on the selection of the metrics of interest, which included noise and GHG
readiness levels. As identified early the NXG-50 caters for a niche market, operating into smaller
airports that are closely surrounded by urban dwellings. Thus noise and emissions are important,
36
as they are stringently enforced to ensure continued operations at these smaller regional airports
[69]. To ensure maximum noise and emission mitigation within the airport airspace, all ground
operations with the exception of takeoff utilizes only power provided from the batteries, as well
as descent and approach maximize battery use, enabling one of the turboelectric generators to be
implementation and commercial activities must be undertaken. These activities include, but are
not limited to: maturation of the required technologies, establishment of an aircraft certification
manufacturers, airlines, and the FAA for required skills and training to operate aircraft.
Business Scenario
The aircraft weight breakdown in Appendix G, Figure 30, along with aircraft dimensions
and propulsion architecture were used to determine the acquisition cost of the NXG-50. The
NXG-50 acquisition cost was compared to the baseline aircraft (Table XIII). As expected there
was an increase in cost due to an increased takeoff gross weight as well as implementation of
new materials and technology, driving research, development, testing and evaluation (RDT&E)
costs. A plot depicting the acquisition cost as a function of manufacturer RoI can be found in
The operating cost analysis (Table XIV) takes into account a large number of sub-costs,
including maintenance, passenger service, crew salaries, etc. A detailed breakdown of the
37
operating costs can be found in Appendix G, Table XXI. Due to the implementation of batteries,
enabling the use of alternate forms of energy, the direct operating cost was greatly reduced,
Appendix G, Figure 38. It should be noted, although there was a decrease in fuel cost, an
additional operating cost had to be included for the NXG-50. This being the cost to charge the
batteries, as well as the amortized cost of replacing the batteries every year or 4,000 charge
cycles. The Chevy Volt was used to determine the cost amortization. The Volt Li-Ion battery has
a maximum number of charge cycles of 4000, weighs 435 pounds and costs approximately
TABLE XIV: DIRECT, INDIRECT & TOTAL OPERATING COST ($ 2012 / TRIP)
DOC IOC TOC
CRJ200 Type $7,661 $2,580 $10,241
NXG-500 $7,118 $2,617 $9,814
(%) Change -6.1% 1.4% -4.2%
Due to the improved operating cost of the NXG-50, even with a larger acquisition cost, airline
operators will be able to operate at a lower revenue passenger mile ($/RPM) and still experience
a favorable return on investment. A figure depicting the airline operators RoI as function of
It can be seen in Figure 18 that even though the NXG-50 has a higher acquisition cost, by
reducing the direct operating cost the airlines can still offer competitive airfares and obtain an
38
Airline Manufacturer Return on Investment (RoI)
0 2 4 6 8 10
120
Aircraft Price (M$ 2012) 110
100
90
80
70
$/RPM = 0.435
60
$/RPM = 0.435 $/RPM = 0.395
50
40
0 2 4 6 8 10 12 14
Airline Operator Return on Investment (RoI)
In addition to aircraft related costs, there exist additional infrastructure and training costs
due to the implementation of the NXG-50. Based on electric motor vehicle charge station
projects and in consulting with Steve Debban from the FAA, it was estimated that an investment
training of ground staff and flight crew, including new safety protocols, will require a budget
increase of $13,704 per technician required for hybrid-electric aircraft [75]. This additional
training cost was amortized and included under indirect maintenance operating cost detailed in
Table XXI.
Conclusion
Utilization of hybrid-electric propulsion coupled with all electric subsystems, the NXG-
50 provides enhanced environmental benefits and more reliable technology leads to savings in
operating costs. The infrastructure required to support the NXG-50 is minimal and only requires
additional battery maintenance facilities and easily modified aprons for battery charging. The
39
skills and training required to integrate, operate, and maintain the NXG-50 are minimal. The
unique design of the NXG-50 addresses all requirements imposed by the NextGen initiative and
this design challenge as seen in Figure 19, and helps the aircraft industry strive for a much
40
Appendix A List of Complete Contact Information
Advisors
Academic Advisor
Dr. Dimitri N. Mavris
Boeing Professor of Advanced Aerospace Systems Analysis, School
of Aerospace Engineering
Director, Aerospace Systems Design Laboratory
275 Ferst Drive NW
Atlanta, GA 30332-0150
404.894.1557
dimitri.mavris@aerospace.gatech.edu
Technical Advisors
Dr. Jimmy Tai
Senior Research Engineer
Aerospace Systems Design Laboratory
School of Aerospace Engineering, Georgia Institute of Technology
275 Ferst Drive NW
Atlanta, GA 30332-0150
404.894.0197
jimmy.tai@aerospace.gatech.edu
Chris Perullo
Research Engineer II
Aerospace Systems Design Laboratory
School of Aerospace Engineering, Georgia Institute of Technology
275 Ferst Drive NW
Atlanta, GA 30332-0150
404.894.5404
christopher.perullo@ae.gatech.edu
A-1
Graduate Team Members
Timothy Banning Grant Bristow
Project Manager Chief Engineer
10672 Creeknoll Ct. 1820 Peachtree Rd #1103
Montgomery, OH 45242 Atlanta, GA 30309
770.862.6220 512.473.9040
tcbanning@gmail.com bristow.g@gatech.edu
Jorge Calderon-Fernandez
Propulsion Lead
c\Bolivia, 4, 6D
Valladolid 47014
Spain
770.309.9736
jorgecalderon@gatech.edu
A-2
Undergraduate Team Members
Nicole Davis
207 Mill Pond Chase
Warner Robins, GA 31088
937.367.6224
nydavis56@gmail.com
Sudhanshu Ambadpudi
3437 E Glacier Pl
Chandler AZ 85249
602.881.9623
sudhanshu.ambadipudi@gmail.com
Clarence Du
75-08 Utopia Pky
Fresh Meadows, NY 11366
347.341.3015
cdu35@gatech.edu
Jacob Paulson
121 Merilyn Dr.
Ringgold, GA 30736
706.618.1357
jpaulson3@gatech.edu
A-3
Appendix B Georgia Institute of Technology
The Georgia Institute of Technology is consistently
Georgia Techs campus includes over 400 acres in the heart of Atlanta, Georgia, but is
well known for its welcoming campus with substantial greenery [77]. Georgia Tech is home to
more than 20,000 undergraduate and graduate students, all studying technology focused fields
[77]. Georgia Tech is regularly ranked in U.S. News & World Reports top ten public universities
in the United States [77]. Georgia Techs College of Engineering is currently 5th for both
undergraduate and graduate programs according to U.S. News & World Report [78]. Georgia
Techs Daniel Guggenheim School of Aerospace Engineering was established in 1930 and is
ranked 2nd for Aerospace Engineering Undergraduate Programs and 4th for Graduate Aerospace
Programs in the nation by U.S. News & World Report [79][80]. The School of Aerospace
Engineering receives annually research funding from NASA, the FAA, NSF, and the U.S. Air
Force, Navy, and Army; totaling over $32 million [79][81]. The School of Aerospace
Engineering has approximately 750 undergraduate students and 550 graduate students with 36
academic faculty and 80 research faculty [81]. Georgia Tech continues to grow as one of the top
B-1
Appendix C Non-University Partners
guidance on this design challenge allowed GT Aircraft, Inc to gain a better understanding of
airport personnel and airport operations, including: airport apron challenges with respect to
electric/hybrid-electric aircraft and battery charging. His assistance and experience was
Environmental Design (LEED). Mr. Debban shared his professional experience with GT
Aircraft, Inc to help establish a first approximation of the expenses necessary to make aprons
sources to estimate the cost of additional training required for ground staff and crew of hybrid-
electric aircraft.
Joyner provided advice for the battery design and location inside the aircraft as well as the
integration of the hybrid-electric aircraft into a traditional airport. He also suggested research
topics and areas of interest to modern/advanced batteries. The advice provided by Dr. Joyner
was essential to generating a design that could be reasonably integrated into current airports.
C-1
Appendix D Design Submission Form
D-1
Appendix E Educational Evaluation
Student Evaluation
1. Did the FAA Design Competition provide a meaningful learning experience for you?
The competition provided each team member a unique learning experience by: providing
a true, meaningful test as project manager or chief engineer of a team, applying newly gained
knowledge as a graduate and undergraduate student, and learning to work as a diverse, multi-
every level throughout the project. Ultimately, this competition provided each member of the
team a great conduit for applying their skills in a real world project.
2. What challenges did you and/or your team encounter in undertaking the Competition?
One of the biggest challenges that the team encountered was the composition of the team
itself. The team was challenged by two members (not included in final team) that held the
progress of the team back by not upholding their responsibilities and withdrew from the team
part way through the competition. In addition, two additional members joined the team with only
several months left in the competition that provided the challenge of acquainting themselves to
the project. The four undergrads on the team had little knowledge and experience in aircraft
design. In addition, two of the graduate students were distance learning and provided the
additional challenge of no face to face participation. Finally, while the team diversity was a large
challenge the project approach and design environment provided a difficult obstacle due to the
uniqueness of the design competition. Despite the many challenges, the resulting team of
graduate and undergraduate students was able to bond over the difficulties and found the unique
E-1
perspectives from each student to be essential to the final success of the project.
3. Describe the process you or your team used for developing your hypothesis.
GT Aircraft, Inc used the top-down design decision making process known as the
Georgia Tech Integrated Product and Process Development (IPPD) decision-making process, a
thorough literature review process, and industry experts for developing the hypothesis. The IPPD
process used systems engineering methods for concept selection, and a computer-integrated
environment for sizing and synthesis of the aircraft. The environmental assessment was
developed using a combination of tools including: GREET, INM, ANOPP, FLOPS, and
4. Was participation by industry in the project appropriate, meaningful and useful? Why
or why not?
Participation by industry was extremely meaningful for this project. This design
challenge was unique in the fact that it is based on future technology and future scenarios which
make industry information invaluable for estimates on its future state due to inherent uncertainty.
In addition, industry experts were important for providing information in areas where detailed
analysis could not be performed based on the scope and time of this design challenge.
5. What did you learn? Did this project help you with skills and knowledge you need to be
successful for entry in the workforce or to pursue further study? Why or why not?
Each member viewed this project as a great learning opportunity for applying new design
processes for the first time and learning aspects from all of the aircraft design disciplines. Not
only were technical skills developed, but time management, team participation, and problem
solving were also honed. Skills taught in the classroom were heavily emphasized and application
E-2
of these skills gave invaluable experience for future endeavors. Not only does the applicability of
this design challenge provide an opportunity to discover ground breaking technology in the
aerospace industry, but it also helped prepare team members for future study and entry in the
workforce.
Faculty Evaluation
1. Describe the value of the educational experience for your student(s) participating in this
Competition submission.
This competition forced the students to extend their conventional knowledge of aircraft
and sizing by applying it to a relatively new problem in aerospace. The use of batteries in a
hybrid-electric configuration expands the number of degrees of freedom greatly, both from an
operational and sizing perspective. This forced the team to discover, possibly modify, and
implement methods applicable for the problem at hand. From an academic perspective, this
taught them how to do research, filter large amounts of information, and be creative enough to
2. Was the learning experience appropriate to the course level or context in which the
Yes. The project required synthesis of existing sizing methods along with developing
new models, simulation environments, and algorithms. This goes beyond the level of many
projects where only a cursory analysis is paid to generating detailed performance information.
4. Would you use this Competition as an educational vehicle in the future? Why or why
not?
Yes, it is an open ended problem currently missing a well-established design process and
solution. The students were unbiased in their approach and often provide new insight into the
problem. This is also a good learning experience for graduate and undergraduate level students
since one primary purpose of a university academic program is to teach students how to solve
problems independently.
5. Are there changes to the Competition that you would suggest for future years?
The scope might be reduced. Given the time available it was hard to fully assess the
aircraft design, environmental impacts (fuel burn, noise, and emissions), infrastructure and
training implications. Future competitions could exclude the requirements that training and
E-4
Appendix F References
[1] FAA, FAA Design Competition for Universities, V. Electric/Hybrid-Electric Aircraft
Technology, Federal Aviation Administration, 2012.
[2] RAA, 2012 Annual Report, Regional Aircraft Association, 2012.
[3] FAA, NextGen: Implementation Plan, U.S. Department of Transportation, Washington,
D.C., 2012.
[4] I. Kroo, Aircraft Design: Synthesis and Analysis [Online], Chapter 12.1, Desktop
Aeronautics, May 2004. [Online]. Available:
http://adg.stanford.edu/aa241/AircraftDesign.html.
[5] S. Bruner, S. Baber, C. Harris, N. Caldwell, P. Keding, K. Rahrig, L. Pho and R. Wlezian,
NASA N+3 Subsonic Fixed Wing Silent Efficient Low-Emissions Commercial Transport
(SELECT) Vehicle Study, NASA/CR-2010-216789, 2010.
[6] P. Patel, Electric Power Technologies For All Electric Aircraft, GE Aviation Systems,
2010.
[7] M. A. Manzo, Battery and Fuel Cell Development Overview, Battelle Energy Storage
Roadmap Workshop, NASA, Seattle, 2011.
[8] A. Mozdzanowska and R. J. Hansman, Evaluation of Regional Jet Operating Patterns in
the Continental United States, International Center for Air Transportation, 2004.
[9] M. Zeinali and D. Rutherford, Trends in Aircraft Efficiency and Design Parameters,
International Council on Clean Transportation, 2008.
[10] D. P. Schrage, "Technology for Rotorcraft Affordability Through Integrated
Product/Process Development," 1999.
[11] W. Engler III, P. Biltgen and D. Mavris, "Concept Selection Using an Interactive
Reconfigurable Matrix of Alternatives (IRMA)," AIAA, 2007.
[12] T. Nam, A Generalized Sizing Method For Revolutionary Concepts Under Probabilistic
Design Constraints, Georgia Institute of Technology, 2007.
[13] Boeing, Current Market Outlook: 2012-2031, Boeing Commercial Airplanes, 2011.
[14] M. K. Bradley and C. K. Droney, "Subsonic Ultra Green Aircraft Research: Phase I Final
Report," NASA/CR-2011-216847, 2011.
[15] FAA, FAA Aerospace Forecast: Fiscal Years 2011-2031, U.S. Department of
Transportation, 2011.
[16] FAA, Report To Congress: National Plan of Integrated Airport Systems (NPIAS) 2013-
2017, U.S. Department of Transportation, 2012.
[17] W. Cao, B. C. Mecrow, G. J. Atkinson, J. W. Bennet and D. J. Atkinson, Overview of
Electric Motor Technologies Used for, IEEE Transactions on Industrial Electronics, vol.
59, no. 9, 2012.
[18] K. K. Jameson, D. D. Marshall, R. Ehrmann, E. Paciano, R. Golden and D. Mason, "Design
and Wind Tunnel Testing of Cal Poly's AMELIA 10 Foot Span Hybrid Wing-Body Low
Noise CESTOL Aircraft," ICAS, 2010.
[19] C. A. Luongo, J. P. Masson, T. Nam, D. Mavris, H. D. Kim, G. V. Brown, M. Waters and
D. Hall, Next Generation More-Electric Aircraft: A Potential Application for HTS
F-1
Superconductors, IEEE Transactions on Applied Superconductivity, vol. 19, no. 3, 2009.
[20] B. Collum, Soaring Tech., Soaring Society of America, pp. 16, 18 -21, 2010.
[21] I. Kowalczk, J. Read and M. Salomon, Li-Air batteries: A Classic Example of Limitations
Owing to Solubilities, Pure Applied Chemistry, vol. 79, no. 5, pp. 851 - 860, 2007.
[22] FAA, Portfolio of Goals, U.S. Department of Transportation, 2012.
[23] Aerospace Systems Design Laboratory, "History," Aerospace Systems Design Laboratory,
2013. [Online]. Available: http://www.asdl.gatech.edu/History.html.
[24] Bombardier Aerospace, Regional Aircraft, Bombardier CRJ200, Bombardiar Inc., 2006.
[25] NASA, "OpenVSP: NASA open source parametric geometry," [Online]. Available:
http://www.openvsp.org/.
[26] L. McCullers, FLOPS FLight Optimization System - FLOPS User Manual, NASA.
[27] Federal Aviation Administration, Electronic Code of Federal Regulations, U.S.
Government Printing Office, Washington, DC, 2013.
[28] J. J. Berton, "Empennage Noise Shielding Benefits for an Open Rotor Transport," NASA,
2012.
[29] D. P. Raymer, Aircraft Design: A Conceptual Approach 4th Edition, Reston, Virginia:
AIAA, Inc., 2006.
[30] D. J. Roskam, Airplane Design, Part II: Preliminary Configuration Design and Integration
of the Propulsion System, Lawrence, KS: DARcorporation, 2004.
[31] J. Hale, "Boeing 787: From the Ground Up," Boeing, 2006. [Online]. Available:
http://www.boeing.com/commercial/aeromagazine/articles/qtr_4_06/AERO_Q406_article4.
pdf.
[32] Alternative Fuels Data Center, U.S. Department of Energy, 2013. [Online]. Available:
www.afdc.energy.gov/vehicle/electric_basics_hev.html.
[33] Boeing, "FAA approves the certification plan for a battery solution," Boeing, 2013.
[Online]. Available: http://787updates.newairplane.com/Certification/FAA-approves-
plan?gclid=COSesavaw7YCFRRbnAodCksAPA.
[34] A. Abdel-Hafez, Power Generation and Distribution System for a More Electric Aircraft -
A Review, Recent Advances in Aircraft Technology, vol. InTech, no. ISBN: 978-965-51-
0150-5, 2012.
[35] M. Sinnett, 787 No-Bleed Systems: Saving Fuel and Enhancing Operational Efficiencies,
Aero Magazine, 2007.
[36] X. Xia, Dynamics Power Distribution Management for All Electric Aircraft, Cranfield
University, 2011.
[37] R. Gillian, "Aircraft Noise Predition Proram User's Manual," NASA TM 84486, 1982.
[38] International Civil Aviation Organization, "ICAO Aircraft Engine Emissions Data Bank,"
2013. [Online]. Available: http://noisedb.stac.aviation-civile.gouv.fr. [Accessed Mar 2013].
[39] Argonne National Laboratory, "GREET 1 2012 rev2".
[40] U.S. Energy Information Administration, "AEO2013 Early Release Overview," 5 Dec 2012.
[Online]. Available: http://www.eia.gov/forecasts/aeo/er/early_elecgen.cfm.
[41] Argonne National Laboratory, "GREET 2 2012 Vehicle Cycle Model".
F-2
[42] J. B. Dunn, J. Sullivan and M. Q. Wang, "Impact of Recycling on Cradle-to-Gate Energy
Consumption and Greenhouse Gas Emissions of Automotoive Lithium-Ion Batteries,"
Environmental Science and Technology, 17 Oct 2012.
[43] General Motors, 2013 Chevolet Volt Boosts EV Range to 38 Miles, GM News, 7 June
2012. [Online]. Available:
http://media.gm.com/media/us/en/gm/news.detail.html/content/Pages/news/us/en/2012/Jun/
0607_volt.html.
[44] M. a. T. M. Eberhard, "The 21st Century Electric Car," 2006.
[45] H. D. E. B. E. He, "Integrated Noise Model (INM) Version 7.0 User's Guide," 2007.
[46] Bombardier Aerospace, "Commercial Aircraft Market Forecast 2012-2031," 2012. [Online].
Available:
http://www2.bombardier.com/en/3_0/3_8/market_forecast/BCA_2012_Market_Forecast.pd
f. [Accessed Mar 2013].
[47] Bombardier Aerospace, "Commercial Aircraft Update," [Online]. Available:
http://read.uberflip.com/i/68865/7. [Accessed Mar 2013].
[48] US Dept of Transportation, Federal Aviation Administration, "Advisory Circular AC
150/5200-37," 2007.
[49] Federal Aviation Administration, "Safety Management System Manual," 2004.
[50] B. Wojdyla, "The Straight Story on the Chevy Volt Battery Fire," Popular Mechanics, 28
November 2011. [Online]. Available: http://www.popularmechanics.com/cars/alternative-
fuel/hybrids/the-straight-story-on-the-chevy-volt-battery-fire-6601217. [Accessed April
2013].
[51] Electrical Safety Foundation International, "Workplace Electrical Injury and Fatality
Statistics, 2003-2010," Electrical Safety Foundation International, 2010. [Online].
Available: http://www.esfi.org/index.cfm/page/Facts-and-Figures/pid/11743. [Accessed
April 2013].
[52] Argonne National Lab Ramping Up Lithium-Air Research and Development: Li-Ion as EV
'Bridge Technology', Green Car Congress: Energy, Technology, Issues, and Policies for
Sustainable Mobility, December 2009. [Online]. Available:
http://www.greencarcongress.com/2009/12/anl-air-20091221.html. [Accessed March 2013].
[53] Power Systems International, 400 Hz Aircraft Ground Power Frequency Converters, May
2011. [Online]. Available:
http://www.powersystemsinternational.com/documents/library/doc_20111007144411.pdf.
[54] Fellman, Megan; Sarah Ostman, "Better Batteries: New Technology Improves Both Energy
Capacity and Charge Rate in Rechargable Batteries.," Northwestern University, 14
November 2011. [Online]. Available:
http://www.northwestern.edu/newscenter/stories/2011/11/batteries-energy-kung.html.
[Accessed April 2013].
[55] D. Coldewey, "Battery Breakthrough Could Improve Capacity and Reduce Charge Time by
a Factor of Ten Each," Tech Chrunch, 14 November 2011. [Online]. Available:
http://techcrunch.com/2011/11/14/battery-breakthrough-could-improve-capacity-and-
reduce-charge-time-by-a-factor-of-ten-each/. [Accessed April 2013].
[56] D. Levitan, "For Electric Car Batteries, The Race for a Rapid Charge," Yale
F-3
Environment360, 06 September 2012. [Online]. Available:
http://e360.yale.edu/feature/for_electric_car_batteries__the_race_for_a_rapid_charge/2569/
. [Accessed April 2013].
[57] F. Malarkey, "Policy Analysis," Regional Airline Association, 2008. [Online]. Available:
http://www.raa.org/Portals/0/Presentations/demand_management_deck_final.pdf.
[Accessed April 2013].
[58] Air Traffic Atlanta, Atlanta Airport's Expansion, 2011. [Online]. Available:
http://airtrafficatlanta.com/atlexpansion.html.
[59] Predicting Effects of Electric Vehicles on the Electricity Grid, European Commission:
Science for Environment Policy, July 2010. [Online]. Available:
http://ec.europa.eu/environment/integration/research/newsalert/pdf/203na1.pdf. [Accessed
March 2013].
[60] Borin, Seth, Joy Wang, and Valerie Thomas, City of Atlanta Greenhouse Gas Emissions
Inventory, Georgia Institute of Technology: School of Industrial and Systems Enginering,
ans School of Public Policy., March 2009.
[61] J. S. John, Electric Car Boom Could Deliver a Surge in Grid Power, Gigaom, 29 April
2011. [Online]. Available: http://gigaom.com/2011/04/29/electric-car-boom-could-deliver-
a-surge-in-grid-power/. [Accessed March 2013].
[62] R. Hudson, Energy Projections 2006-2030: Price and Policy Considerations, Oak Ridge
National Laboratory, 2006.
[63] "Jet Fuel Daily Prices," Index Mundi, March 2013. [Online]. Available:
http://www.indexmundi.com/commodities/?commodity=jet-fuel. [Accessed April 2013].
[64] J. E. Joyner III Ph.D., Interviewee, Manager-Electrical & NavAid Design, Delta Airport
Consultants. [Interview]. March 2013.
[65] Aircraft Industrial Support Facilities Design Guide, Air Mobility Command, [Online].
Available: <http://www.wbdg.org/ccb/AF/AFDG/aircraftindustrial.pdf. [Accessed March
2013].
[66] The DCD Industrial Building Cos Per Square Foot Analysis, Design Cost Data Magazine,
p. 1, July-August 2011.
[67] Time Required to Build a Warehouse (Days), The World Bank, [Online]. Available:
http://data.worldbank.org/indicator/IC.WRH.DURS. [Accessed March 2013].
[68] Boeing Commercial Airplanes, "Training: Pilot & Technician Outlook," Boeing, 2012.
[69] L. L. Blackman and R. P. Freeman, "The Environmental Consequences of Muncipal
Airports: A Subject of Federal Mandate?," Journal of Air Law and Commerce, vol. 53, no.
375, 1987.
[70] G. Motors, "Chevy Volt Specifications," [Online]. Available: http://gm-volt.com/full-
specifications/. [Accessed 11 April 2013].
[71] J. Voelcker, "Lithium Batteries for Hybrid Cars," IEEE Spectrum, January 2007. [Online].
Available: http://spectrum.ieee.org/green-tech/advanced-cars/lithium-batteries-for-hybrid-
cars. [Accessed 11 April 2013].
[72] T. Murphy, "The Battery Performance Deficit Disorder," 31 August 2012. [Online].
Available: http://gigaom.com/2012/08/31/the-battery-performance-deficit-disorder/.
F-4
[Accessed 11 April 2013].
[73] CNN, "Public charging stations fuel desire for electric cars," October 2012.
[74] PWC Challenge, "La vrit sur la consommation des voitures lectriques," August 2012.
[Online]. Available: http://automobile.challenges.fr/dossiers/20120807.LQA3178/la-verite-
sur-la-consommation-des-voitures-electriques.html.
[75] Boeing, "Electrical and Avionics Initial - Courses," 2011. [Online]. Available:
http://www.myboeingtraining.com/Courses/63/electrical-and-avionics-initial.
[76] About Tech, History and Traditions, Georgia Tech, [Online]. Available:
http://www.gatech.edu/about/history.html. [Accessed March 2013].
[77] About Tech, About Georgia Tech, Georgia Tech, [Online]. Available:
http://www.gatech.edu/about/. [Accessed March 2013].
[78] Georgia Tech College of Engineering, Stats & Rankings, Georgia Tech, [Online].
Available: http://www.coe.gatech.edu/content/stats-rankings. [Accessed March 2013].
[79] The Daniel Guggenheim School of Aerospace Engineering, Welcome to the Daniel
Guggenheim School of Aerospace Engineering, Georgia Tech College of Engineering,
[Online]. Available: http://www.ae.gatech.edu/outreach. [Accessed March 2013].
[80] US News & World Report, Grad Schools Rankings, 2012. [Online]. Available:
http://grad-schools.usnews.rankingsandreviews.com/best-graduate-schools/top-engineering-
schools/aerospace-rankings.
[81] The Daniel Guggenheim School of Aerospace Engineering, Quick Facts about the School
of Aerospace Engineering, Georgia Tech College of Engineering, [Online]. Available:
http://www.ae.gatech.edu/outreach/quickfacts. [Accessed March 2013].
[82] C. Amos, "Surface Passivation of Lithium-Ion Electrodes: A Path to High-Performance
Energy Storage," NASA, 16 Feburary 2013. [Online]. Available:
http://www.nasa.gov/directorates/spacetech/strg/2012_nstrf_amos.html.
[83] J. Fitzgerald and N. O'Bryan, "Fuel Cells: A Better Energy Source for Earth and Space," 11
February 2005. [Online]. Available:
http://www.nasa.gov/centers/glenn/technology/fuel_cells.html.
[84] G. V. Brown, R. H. Jansen, T. P. Dever, A. S. Nagorny and J. J. Trudell, "Specific Power of
Cryogenic Motor Increased 50 Percent," 26 November 2007. [Online]. Available:
http://www.grc.nasa.gov/WWW/RT/2006/RX/RX51S-brown.html.
[85] Transportation Research Board of the National Academies, Handbook for Evaluating
Emissions and Costs of APUs and Alternative Systems, National Academy of Sciences,
2012.
[86] NASA, "The Supercritical Airfoil," Dryden Flight Research Center, 3 March 2008.
[Online]. Available:
http://www.nasa.gov/centers/dryden/about/Organizations/Technology/Facts/TF-2004-13-
DFRC.html.
[87] General Electric, "GE and NASA to Test Open Rotor Jet Engine Systems," GE Reports, 12
June 2009. [Online]. Available: http://www.gereports.com/ge-and-nasa-to-test-open-rotor-
jet-engine-systems/.
[88] M. R. Khorrami, "Airframe Noise Reduction Status and Plans," National Aeronautics and
F-5
Space Administration, 2011.
[89] H. Pfaender, H. Jimenez and D. Mavris, "Fleet Assessment of Fuel Burn and NOx
Emissions for NASA Environmentally Responsible Aviation (ERA) Technologies and
Concepts," AIAA, Indianapolis, 2012.
[90] Virtual Aircraft Musuem, [Online]. Available:
http://www.aviastar.org/pictures/canada/bombardier_crj-200.gif.
[91] Sun Airlines Team, Bombardier CRJ200 Specifications, Sun Airlines, 12 June 2012.
[Online]. Available: http://www.flysunairlines.com/bombardier-crj200/bombardier-crj200-
specifications. [Accessed 23 March 2013].
[92] Delta Air Lines, Embraer ERJ145, Delta, 2012. [Online]. Available:
http://www.delta.com/content/www/en_US/traveling-with-us/airports-and-
aircraft/Aircraft/embraer-erj145.html. [Accessed 23 March 2013].
[93] J. Roskam, "Airplane Design Part VII: Determination of Stability and Control and
Performance Characteristics: FAR and Military Requirements," Design Analysis &
Research, 1991.
[94] I. Delta Airlines, "United States Securities and Exchange Commission Form 10-K," 2012.
[95] Modak Illustrations, [Online]. Available:
http://www.kmodak.com/images/TechTower_orig.jpg.
[96] Aviation Week Research, [Online]. Available:
http://www.aviationweek.com/Portals/AWeek/Images/commercial/787_Slideshow/Lithium-
ionChart-AWST.jpg.
F-6
Appendix G Additional Documentation
Problem Statement and Background
TABLE XV: INDUSTRY EXPERTS
G-1
Literature Review and Problem Solving Approach
G-2
FIGURE 22: NOTIONAL IRMA WITH COMPATIBILITY (RED=INCOMPATIBLE)
G-3
FIGURE 24: BOMBARDIER CRJ200 [90]
No. of Fuselages 1 1 1 1 1
Structure and S&C
Power Transmission
Motor/Gearbox Motor/Gearbox Motor/Gearbox Motor/Gearbox Motor/Gearbox
Augmentation Batteries Batteries Batteries Batteries Batteries
Thrust Effector Fan Open Rotor Fan Fan Fan
No. Thrust Devices 2 2 2 2 2
Location Under Wing Under Wing Aft Fuselage Under Wing Aft Fuselage
G-4
FIGURE 25: DESIGN EXPLORATION AND MODELING AND SIMULATION ARCHITECTURE
G-5
FIGURE 27: DETAILED MISSION PROFILE
G-6
TABLE XVIII: FUSELAGE TRADE STUDY
G-7
Weight Breakdown
CRJ Type NexGen
ANTI-ICING
AIR CONDITIONING
FURNISHINGS AND EQUIPMENT
AVIONICS
ELECTRICAL
HYDRAULICS
INSTRUMENTS
AUXILIARY POWER
SURFACE CONTROLS
PROPULSION TOTAL
LANDING GEAR
FUSELAGE
VERTICAL TAIL
HORIZONTAL TAIL
WING
0 1000 2000 3000 4000 5000 6000 7000 8000
Weight (lbs)
55,000
50,000
Fuel
45,000
Pax+Bag.
40,000
OEW
35,000
Empty Weight
30,000
12.3% 12.5% 12.7% 12.9% 13.1% 13.3%
C.G. Location (%M.A.C.)
G-8
Component Zero-Lift Drag Overall Drag Breakdown
0.0005, 5%
0.0006, 6%
0.025
0.0005, 5%
Wing
0.02
Horizontal Tail CDP
0.0038, Vertical Fins 0.015 CDI
37%
Fuselage CDC
0.0031, 0.01 CD0
30% Nacelle
Nacelle 0.005
0.0010,
Misc
0.0007, 7%
10%
0
Cruise
0.9
0.8
0.7
0.6
0.5
CL
0.4
0.3
0.2
0.1
0
0 0.02 0.04 0.06 0.08
CD
G-9
16,000
14,000
12,000
Payload (LB)
10,000
8,000
6,000
4,000
2,000
0
0 200 400 600 800 1,000 1,200 1,400
Range (NMI)
Digital DATCOM, built from the USAF Stability and Control prediction method derived
from flight test data, was used to estimate the stability derivatives for the NXG-50. Using the
methods provided in Roskam [93] the NXG-50 was evaluated and found to meet all of the Level
I handling quality requirements based on the MIL-F-8785B Military Specification. This analysis
G-10
FIGURE 35: SUBSYSTEM LAYOUT
Environmental Benefits
Baseline Aircraft Calibration
Acoustics
Certification Noise Prediction
NASAs ANOPP was used to assess the noise for the baseline configuration [25]. The
suppression module was used to calibrate to the certification levels. The sideline, approach, and
takeoff trajectories that were used for the noise assessment are defined in the FAA Federal
The initial results from the ANOPP analysis were compared with the certification levels
of the Bombardier CRJ200. The International Civil Aviation Organization (ICAO) Certification
Database contained a Bombardier CRJ200 with a GE CF34-3B1 engine and takeoff weight of
53,000 pounds [24]. The baseline aircraft is similar in size to the CRJ200, but has slightly less
thrust and a lower gross weight. The differences are very small between the CRJ200 and the
G-11
baseline aircraft, so there was no difference in the noise certification levels. The baseline aircraft
does meet the Stage IV noise requirements with a cumulative noise margin of 27.7 dB, shown in
Table XV. Table XVI shows the noise results for each of the three trajectories. The baseline
aircraft ANOPP input files were modified to reflect the NXG-50 geometry. The results are
points defined in the ICAO Emissions Databank [38]. Figure 42 shows the results of the baseline
aircraft LTO NOx analysis. Figure 43 shows the results of the NXG-50 LTO NOx analysis.
G-12
FIGURE 42: BASELINE AIRCRAFT LANDING AND TAKEOFF NOX ANALYSIS.
Mission Analysis
The FLOPS baseline model was calibrated to Bombardier CRJ200 data [24]. The
geometry and design mission were input into the FLOPS model. The model was calibrated to the
design maximum weights and then to the fuel required to make the design range by varying the
wing area and the takeoff thrust. The calibration results are shown in Table XVIII.
G-13
TABLE XIX: INDIVIDUAL AIRCRAFT ENVIRONMENTAL PERFORMANCE SUMMARY.
Business Case
Using ALCAA and the Delta Airlines, Inc. 2012 annual report [94], a baseline cost analysis was
G-14
75 450
70
Breakeven Unit #
65
60 350
55 300
50
250
45
40 200
0 2 4 6 8 10
Return on Investment (%)
$12,000
$10,000
Cost ($/Trip)
$8,000
$6,000
$4,000
$2,000
$0
G-15
125
$/RPM =
115 0.395
85
$/RPM =
75 0.425
$/RPM =
65 0.465
-8 -6 -4 -2 0 2 4 6
Return on Investment (RoI)
CRJ200Type NXG-500
G-16
TABLE XXI: OPERATING COST BREAKDOWN PER TRIP
G-17
G-18
TABLE XXII: EVALUATION CRITERIA COMPLIANCE MATRIX
Page #
Introductory Material
Executive Summary i
Table of Contents ii
Problem Statement and Background
Design Challenge Statement 1
Current Conditions, Approaches and Design Issues 1
Literature Review and Problem Solving Approach
Understanding of Current and Future Issues 4
Evidence of thorough Design Process 8
Design Support (Drawings, Computer Codes, Charts, etc.) 6, 15,
Evidence of Understanding of Regulatory and Certification
15, 25, 25, 28,
Issues
Supported Conclusion 39
Safety Risk Assessment
Safety Risk Assessment of Proposed Design 31
Appropriate FAA documents (FAA Advisory Circular 150/5200-
25, 31
37, etc.)
Effective Interaction with Airport Operators and Industry Experts
Effective Interaction with an Airport Operator G-17
Effective Interaction with Industry Experts G-1
Practicality and Feasibility of the Proposed Design
Proposed Design meets Identified National Needs i, 27, 39
Solid Cost-Benefit Analysis 37
Potential Real-World Impact of Proposed Solution 36
Description of Process required for Implementation 36
Overall Quality of Design Package
A-1, B-1, C-1, D-1,
Required Appendices Present and Complete
E-1, F-1, G-1
Solid Evaluation of Educational Experience E-1
G-19