Vous êtes sur la page 1sur 6

LIFTING PLAN

Document Ref MIV-CLP Client Page 1 of 6

CRANE LIFTING PLAN

CONTROLLED COPY No.:

REVISION No.:

ISSUE DATE:

DRAFTED BY: DATE:

APPROVED BY: DATE:

REGISTER OF RECIPIENT

This register is a list of Project Personnel holding this plan.

Date of issue: Aug 2010 Rev 00


LIFTING PLAN
Document Ref MIV-CLP Client Page 2 of 6

Copy Number Holders Name Organisation / Position


1 Mivan Project Manager
2 Mivan Site Manager
3 Mivan HSE Officer
4
5

RECORD OF AMANEDMENTS

Issue Date Description of Changes


1st Draft
2nd Draft
3rd Draft
4th Draft
Revisions Approved Construction Issue
1
2
3
4
5

Date of issue: Aug 2010 Rev 00


LIFTING PLAN
Document Ref MIV-CLP Client Page 3 of 6

CONTENTS

Legal application
Health and safety at Work act 1974
CDM (Construction design and management) Regulations 2007
LOLER (Lifting Operations and Lifting Equipment) Regulations 1998
The Notification of Conventional Tower Cranes Regulations 2010
PUWER (Provision and Use of Work equipment) Regulations 1998
The management of health and Safety at Work Regulations 1999
British Standards 7121

1. Planning
1.1 Notification of Cranes
1.2 Appointments
1.3 Nature and Scope of works
1.4 Stability and security of Cranes
1.5 Selection of Lifting Plant
1.6 Selection of Lifting Accessories
1.7 Restrictions
1.8 Tests and thorough examinations

2. Lifting Operations
2.1 Safe system of work
2.2 Description of loads
2.3 Competence
2.4 Factors affecting safe lifting operations
2.5 Slinging/ signalling
2.6 Communication
2.7 Safe working loads
2.8 Control of loads
2.9 Inspections

3. Emergency preparedness
3.1Emergency rescue plan

Date of issue: Aug 2010 Rev 00


LIFTING PLAN
Document Ref MIV-CLP Client Page 4 of 6

NATURE OF PROJECT

Project Details & Address:

Description of Works

Including site plans, sketches and drawings.

1. Planning

1.1 Notification of Conventional Tower Cranes.

Employer must ensure that, for any conventional tower crane installed by the employer on a construction site, the
Executive is notified in writing of
(a) any thorough examination of that conventional tower crane as required by regulation 9(2) (examination before
being put into service) within 14 days of its installation.

1.2 Appointments.
Details of competent contractor appointed for lifting operation.

1.3 Nature and Scope of works.


Uploading one shriller and steel fram from the ground to the roof
1.4 Stability and Security of Cranes.
Ground conditions, crane bases, tower cranes anchor points etc, protection hoarding around tower cranes and
segregation barriers for mobile cranes, warning signage.

1.5 Selection of Lifting Plant.


Type of cranes- Telescopic Boom on wheel crane 200T

1.6 Selection of Lifting Accessories.

Type of lifting accessories to be used for lifting loads.:-


*- 4-legged wire rope sling 19mm dia,9.5 long,IWRC,hard eyes at both ends,connected to M.L.A
and fitted to Qty: 4x 3/4'' Crosby bolt type anchor shackles G2130

*-4-legged wire rope sling 13 mm dia,two legs 7.5 long and other two legs 7.85,IWRC,hard eyes
at both ends,connected to M.L.A and fitted to Qty: 4x 5/8'' Crosby bolt type anchor shackles
G2130

Date of issue: Aug 2010 Rev 00


LIFTING PLAN
Document Ref MIV-CLP Client Page 5 of 6

1.7 Restrictions.

Details of any other cranes on site, adjacent overhead power lines, air fields, railways, near by occupied buildings etc,
underground sewages, man holes (where mobile or crawler cranes would be operated).

1.8 Test and thorough examination.

Tests and thorough examination records of cranes and lifting accessories.


The lifting accessories certificate is attached.

2. Lifting operations

2.1 Safe System of Work.

Established safe system of work including any exclusion zones etc to carry out lifting operations safely .

2.2 Description of loads.


Type of loads, weight and sizes.
Shriller unit Weight 10 ton

2.3 Competence.

Training details and certification of lifting appointed person, lifting supervisor, crane co-ordinator, crane operator and
slinger/ signaller.

2.4 Factors affecting safe lifting operations.

Weather conditions, ground conditions, nearby water sources etc.


Clear weather is required and permissible wind speed.
2.5 Slinging/ signalling.

Details of slinging/ signalling system, communication signals to be used etc.


Slinging 4-legs wire and Crosby bolt type anchor.
2.6 Communication.

Details of communication system between crane operator, slinger/ signaller, crane co-ordinator etc.
Radio communication

2.7 Safe working loads.

Details of safe working loads of the cranes and lifting accessories.


- For 160 Ton mobile crane: safe working load 10 ton at radius 30 m.
- 4-legged wire rope sling 19mm dia safe working load: 9.6 ton.
- 4x3/4" inch Crosby bolt type anchor shackles G2130,G6 safe working Load:4.75 tonnes.
- 4-legged wire rope sling 13 mm dia: safe working load 4.4 ton.
- 4x5/8" inch Crosby bolt type anchor shackles G2130,G6 safe working Load:3.25 tonnes.
-

Date of issue: Aug 2010 Rev 00


LIFTING PLAN
Document Ref MIV-CLP Client Page 6 of 6

2.8 Control of loads.

Details of how loads will be controlled.


By using two robs tied in two opposite side

2.9 Inspections.

Details of inspections of lifting plant and accessories, frequency and records.

3. Emergency preparedness.

3.1 Emergency rescue plan.

Details of emergency rescue of how crane operator would be rescued in case of emergency, cranes stopped, specialist
rescue, emergency services etc.

Date of issue: Aug 2010 Rev 00