DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Contents
ABSTRACT .................................................................................................................................................................................................... 5
Table 1 Key stages of SDP project ............................................................................................................................................................................................................................................. 6
Stage 1 the richest possible picture of the situation. ...................................................................................................................................... 7
Stage 2 the root definition of the select system and CATWOE. ...................................................................................................................... 9
Root Definition .................................................................................................................................................................................................................................................................................. 9
Table 2 CATWOE and root definition of SAR system .................................................................................................................................................................................................... 11
Stage 3 produces list of functional and non-functional requirement of defined system. .................................................................. 12
Functional Requirements .......................................................................................................................................................................................................................................................... 12
Non-Functional Requirements ................................................................................................................................................................................................................................................ 13
Stage 4 conceptual analysis model of SAR system orders to generated use case with the three narratives .................................................. 15
Table 3 View Attendance History narratives. ................................................................................................................................................................................................................... 17
Table 4 View Override Attendance narratives. ................................................................................................................................................................................................................ 19
Table 5 View Assign Student narratives. ............................................................................................................................................................................................................................ 21
Stage 5 outline possible of smart project plan objective, which include key stakeholders and assumptions in details. ............... 22
SMART objectives ....................................................................................................................................................................................................................................................................... 22
Key stakeholders ......................................................................................................................................................................................................................................................................... 24
Assumption ...................................................................................................................................................................................................................................................................................... 25
Stage 6 Gantt chart action based on stage one to five ................................................................................................................................. 29
Appendix .................................................................................................................................................................................................... 30
2
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure of content
Figure 1 Rich picture .................................................................................................................................................................................................... 7
Figure 2 Use case of SAR system .......................................................................................................................................................................... 15
Figure 3 List of task name ....................................................................................................................................................................................... 29
Figure 4 Details vies of system scope and software requirements ...................................................................................................... 30
Figure 5 Details view of system deign and testing plan ............................................................................................................................ 31
Figure 6 Details view of training methodology and system documentation .................................................................................... 32
Figure 7 Details view of Pilot, deployment and post implementation review ................................................................................. 33
Figure 8 Timescale and total cost of system scope and software requirements ............................................................................ 34
Figure 9 Timescale and total cost of development, testing and training ........................................................................................... 35
Figure 10 Timescale and total cost of system training and software documentation ................................................................. 36
Figure 11 Timescale and total cost of system pilot, deployment and post implementation ..................................................... 37
Figure 12 Task cost overview ............................................................................................................................................................................... 38
Figure 13 Cost overruns details ........................................................................................................................................................................... 39
Figure 14 Cost overruns, task cost and resource cost variance ............................................................................................................. 40
Figure 15 Cash flow chart ....................................................................................................................................................................................... 41
Figure 16 Work status and over allocation ..................................................................................................................................................... 42
Figure 17 Resource stats and work status ...................................................................................................................................................... 43
Figure 18 Baseline work stats ............................................................................................................................................................................... 44
Figure 19 Resource stats and remaining availability ................................................................................................................................. 45
Figure 20 Milestones due and late tasks completion .................................................................................................................................. 46
3
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
4
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
ABSTRACT
The overall aim is project to develop student attendance system for CIS Department by means of both manual
attendance sheet and PDA with an integral barcode reader. Area of system will be concentrated on registration,
lecture attendance by using PDA with an integral barcode reader, record of tutorial and exam attendance, finances,
library access and progression. The university students attendance information is the main facilitates. Course
coordinator, who provided lists of students associated with the course, sorts the information, assign them into one of
multiple lecture occurrences, into smaller tutorial or lab groups and associated to tutors with class rooms or labs.
The main purpose is computerizes PDA with an integral barcode reader and traditional way of taking attendance by
sign in sheet. Major modules of System has:
a. Academic Information System (AIS) team, who have right to updating in subjects (finances and progression), entry
of new faculty, creating spaces for new batch.
b. Academic staff, such as course coordinator, lecturer, tutor and administer as well as student there will be perform
the approved tasks. Following table described step-by-step process and evolution of SAR model of main stages and
emerged.
5
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Stage Objective
4 A conceptual analysis model order to generated use case with the three narratives.
5 Outline possible of smart project plan objective, which include key stakeholders and assumptions.
6
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 1 Rich picture
7
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
The arrow of rich picture signify:
Blue conflict
Green process
Red communication
Black sending data
The Assumption of rich picture:
Some lecture or tutor not happy with latest system, they are very used to with old system. Latest system let
every class to use PDA reader instead of certain class, as it is easy and quick. Two weeks staff training is far too
much; staff can be trained within a week.
Hence University of Greenwich is dealing with oversea student and connection with UKBA, student receive
auto generated warning email or manual from lecturer or tutor once they absent for more than three times in a
month.
8
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Stage two the root definition and CATWOE of the select system. The relevant systems need investigation having
established from rich picture. The CATWOE used to define fundamentals of root definition. As starting point
sufficient information will be store at root definition for conceptual model to build.
Root Definition
The department of Computing and Information System at the University of Greenwich operates an intranet to
support students and staffs a new system of student attendance register (X) through the development of new hybrid
system as develop, design and analysis by developers (Y) for adding alternation, convenient and more precision to
record student attendance (Z).
The following table describe more thoughtful in CATWOE and root definition of system
9
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
10
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Owners The department of Computing and Information System at the University of Greenwich.
Environmental 1. Tight deadline
Constraints 2. Job satisfaction
3. Securing trends
4. Conflicts between Vice Chancellor and CIS department
5. Developer can actually construct the system
11
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Functional Requirements
Dynamically record student attendance and display them, print blank attendance sheet.
Assign students into one of multiple lecture occurrences and into smaller tutorial or lab groups associated to
tutors name and with particular rooms or labs.
Register each of new students in system and keep finances, progression and registration record and maintain
them.
Integral barcode reader should able to uniquely recognize each student in lecture class.
12
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Non-Functional Requirements
Security and access requirements should guarantee, the stakeholder details would not share with third party
organization. All users securely logged on to have benefit from system.
Constraints: organizational constraints are teachable to new and existing member staff within two weeks and easy
operate for academic staff and student. Project constraints are system goes alive within four months, analysis,
design and development budget of 40,000 pounds and no new support posts require. A technical constraint is being
run on existing hardware.
Performance be displaying searching results in less than 60 seconds, multiple transactions using parallel control and
various keywords could use adaptive search engine.
13
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
All relevant program information and study paths should available 24/7 for enrolled students. The new student
registration formally allow on office hours to prevent any hazardous.
The catalogue of system has access from everyone (lecturer, tutor and student). Secure and private data provide for
enroll student according program access level.
The AIS and lead staff access to every part of system, when accessing system username and password (identification
check) required for all type of users accesses.
Once functional and non-functional requirements had been successfully established stage 4 require to manufacturing
the use case with the three narratives.
14
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Stage 4 conceptual analysis model of SAR system orders to generated use case with the three narratives
15
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Precondition User must have valid username and password to pass authentication check for logged
on to web interface.
16
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
2.System display currently enrolled study path information with hyperlink to view
grades, course schedule and attendant history.
Post condition Client terminal displays the attendance history with continue or logout option.
17
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Brief Description It provide user to enter the student attendance onto the system by entering tick next
to each attending students name of particular session.
Precondition User must have valid username and password to pass authentication check for logged
on to web interface.
Main flow 1. User selects a subject and date to override attendance Information
2.The system presents the user with the student's current attendance information
3. The user updates the attendance information for the particular subject
4.The system makes the change and records it in audit log and update database.
2.System display current course information with hyperlink to view student profile,
18
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
8.The system makes the change and records it in audit log and update database.
Post condition The system acknowledges whether the requested changes have been made or not.
19
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Use case Assign Student
Brief Description User maintains lists of students registered on a course; assign them into one of
multiple lecture occurrences and into the smaller tutorial or lab group.
Precondition User must have valid username and password to pass authentication check for logged
on to web interface.
Entry Condition The system needs to retrieve lists of students registered on a course data for the user.
2.System presents to user with current course information with hyperlink to updated
particular course information, add new student to exacting course, update classroom,
date and time, assign teacher to exacting course.
20
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
4.The system presents base on the user selection available room and time for lecture
or smaller for tutorial or lab.
6.Systems makes change and records it in audit log and update database.
Post condition The system acknowledges whether the requested changes have been made or not.
21
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Stage 5 outline possible of smart project plan objective, which include key stakeholders and assumptions in
details.
SMART objectives
WEEKLY MEETINGS
The regular weekly meetings with enrol student, Vice Chancellor and lead staff on SAR Project. The meetings
typically are held weekly for at lease 30 minutes at Greenwich campuses or location determined by Vice
Chancellor. The main purpose of meetings is review the planning and development of overall system
implementation and achievement progress, the new SAR system should achieve 90% client satisfaction rating by
end of complied project.
Status reporting
The Vice Chancellor receiving monthly status report by first working day after 15th of each month, reports status
presented according to requirements established in details. The latest system should reduce time taken each
operation process by 40 seconds.
22
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
System testing
Detailed of test documents is provided and develop in support of system tests and equipment that is performed
on SAR project by 8 March 2016 to Vice Chancellor. The test procedures and test plans contain testing criteria,
activities and management approach for all system testing presented in SAR project plan, aim are major bugs of
system be 0 and there should less than 8 trivial bugs and less than 5 minor bugs at the time of delivery to system
by 3 March 2016.
Program management
The implementation requirements and technology risk areas considered to meet contract specifications within 4
months time periods. The system specification requirements operate by detail benefits and features program
management approach to ensure system delivered 4 months, within 40,000 pounds budget below by 3 March
2016.
23
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
The about project plan subsections are fit within smart objectives as it described
Specific: It will be base on SAR system for CIS department.
Measurable: It should be complete within the budget of 40 k.
Achievable: It feasible in manageable steps, such as design developing, testing plan, train staff, system
documentation and post implementation review.
Relevant: It is applicable in current economic atmosphere.
Time-bound: It should be complete within 4 months.
Key stakeholders
Primary stakeholders
Academic staff includes course coordinators, lecturers, tutors, they will be using system directly to add attendance of
enrol student, print attendance sheet and view individual attendance records. Student is undergraduate or
postgraduate, they will use system directly to view their program subject and attendance. Administration staff such
as AIS team use system directly to deals centrally with student registration, finances and progression.
24
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Secondary Stakeholders
Secondary Stakeholders is Vice Chancellor, who is using system occasionally like verifying system, such as
confirming it up to date for university student used and current industry level.
Tertiary Stakeholders
Tertiary Stakeholders is board of directors, as board of directors will have affected of using it.
Assumption
Student
Student received email send by University of Greenwich team regarding special offers according their preferences by
recording their transactions and search history. Student could unofficially or temporarily register but it not
approved if they have not paid their fees.
25
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Chosen system shows whether any PC available in particular campus of specific building with room number as well
as site maps for enroll student. They could view university information, which includes university news, contact
book and directory.
Email send out to new student about registration successfully add or dropped. An important change happens in
course or poor attendance, they are alerted by email send through university lead staff via auto generate report or
manually entering.
Staff
Each staff belongs particular campus, unit and department. Salary dispatch system for current staff to view salary
details in organization. Key stakeholders change their old password to new and edit option for profile. Staff can view
staff profile, search other staff profile or student profile. Accessibility predefined to secure access of private users
details, so all type users within system not to accessible all part of data.
26
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
System
It provide student auditable records of six years after completed applicable audits and redundancy procedures,
backup. Each individual PCs current data should be automatic backups.
Support shared platform information, sharing between staff based in different university campus. Encourage
primary stakeholders provide feedback about quality of system and service of web.
Due to over approach or access at same time, system could freeze or disconnect. It locks that abnormal process made
up to point and user data save in secure catalog. All data and work provided when user sign in back with same user
Id.
Integral barcode reader have skill to display meaning full message with students Id, name with photo. It present
access denied or approved message to express student and play alert sounds for their attendance failures or
successes. This is conclusion of assumption following session include fundamentals of advantages and disadvantages
of chosen system.
27
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Advantages:
User friendly, non-intrusive, acceptable in high sociality
Auto reports system is easily generated, less time in verification.
Very less technology cost and paper work.
Accurate results in PDA barcode reader
Disadvantages
There are possibilities of frauds.
This is termination of advantages and disadvantages following session include feature of Gantt chart and essentials.
28
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 3 list of task name
29
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Appendix
Following section is various screenshot of Gantt chart details
30
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
31
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
32
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
33
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 8 Timescale and total cost of system scope and software requirements
34
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 9 Timescale and total cost of development, testing and training
35
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 10 Timescale and total cost of system training and software documentation
36
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 11 Timescale and total cost of system pilot, deployment and post implementation
The following session of appendix will demonstrate project plan details of chosen system in table and chart.
37
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 12 Task cost overview
38
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 13 Cost overruns details
39
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 14 Cost overruns, task cost and resource cost variance
40
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 15 Cash flow chart
41
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 16 Work status and over allocation
42
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 17 Resource stats and work status
43
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 18 Baseline work stats
44
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 19 Resource stats and remaining availability
45
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 20 Milestones due and late tasks completion
46
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 21 Cost of status and progress versus cost
47
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 22 Total hours of labour to build project
48
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Name Actual Cost Remaining Baseline Cost Cost
Cost Cost Variance
49
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
development
complete
Figure 23 Overall project cost structure table
50
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 24 Overall project of work and task burn down
51
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 25 Project completed milestones
52
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 26 Project slipping tasks
53
SYSTEM DEVELOPMENT PROJECT
STUDENT ATTENDANCE REGISTER SYSTEM FOR THE CIS DEPARTMENT
Figure 27 Overall project tasks planning hours
End of Appendix