Vous êtes sur la page 1sur 3

1

CASE STUDY: CONTINGENCY BOREHOLES AN ADDITIONAL INTERVENTION TO MAKE AVAILABLE EMERGENCY WATER SUPPLIES
DURING THE 1999-2001 DROUGHT

FOCUS AREA: WAJIR DISTRICT

KEY FEATURES and livestock were concentrated around a limited number of operational
boreholes. Pasture around these boreholes was becoming heavily depleted
Core Problem and livestock was forced to move further and further from the watering site to
find grazing. In some areas watering intervals were as long as 5-7 days for
Extended drought period leading to depleted grazing, increasing watering cattle and more for goats and camels (up to 70km between the grazing and
intervals and hence weakening animals the borehole).
Good grazing available in key locations but no water
Provision of new boreholes results in permanent settlements, degradation Oxfam GBs ongoing drought mitigation programme was keeping the existing
of grazing and hence loss of strategic grazing reserves boreholes operational through support to the Rapid Response Teams based
in Wajir and Habaswein. However it was clear that additional water supplies
Intervention and additional grazing were required to prevent further livestock losses. At the
same time the availability of donor funds for drought relief all over the country
Selection of three locations for contingency boreholes in strategic grazing was creating intense political and social pressure for new water supplies,
reserves particularly new boreholes.
Careful negotiation with communities, pastoralist associations (PAs), local
leaders and MPs to agree terms and conditions for borehole operations. Oxfam GB had been operational in Wajir for eight years and had strong
Rapid drilling and equipping of boreholes at Harakotkot, Hadado and working relationships with both communities and District stakeholders. Oxfam
Arbajahan without permanent infrastructure used these relationships to design and implement an intervention which
Operation of boreholes by local Water Users Associations (WUAs) focussed on the provision of three new boreholes. This was planned on the
supported by PAs condition that the boreholes were for contingency purposes only and would be
Closure of boreholes at end of drought period as per agreement with closed immediately after the drought ended. Contingency boreholes had
WUAs been tried in other districts during previous droughts but had never been
closed again resulting in permanent settlement and loss of strategic grazing
Achievements reserves due to year round over grazing. Hence other development and relief
actors met the intervention with some scepticism.
Reduction of watering intervals and hence prevention of loss of life for up
to 500 head of cattle and 1000 shoats. PROCESS
Relief of burden on women collecting water with related social and
financial benefits Goal: - To Make Additional Water Supplies Available During the Dry Period
Distribution of grazing pressure and improved use of natural resources
leading to increased livestock production Objectives
Demonstration of effective operation of boreholes on contingency basis
only with full stakeholder support To select strategic locations for contingency boreholes within existing
grazing reserves
CONTEXT To negotiate terms and conditions for operating, closing and reopening
the boreholes strictly on a contingency basis
The extended drought of 1999-2001 effected Northeastern province severely. To drill and equip three boreholes at Harakotkot, Hadado and Arbajahan
In Wajir District, by June 2000 all non-permanent water supplies had dried up without permanent infrastructure
Case Study: Contingency Boreholes in Wajir District Rural Focus Ltd
2

To operate and maintain the boreholes with full involvement of local 2. Drilling And Equipping Boreholes At Harakhotkhot, Hadado And
WUAs and PAs Arbajahan
To close the boreholes at the end of the drought period
The sites selected for the boreholes were all alongside existing boreholes so
The intervention involved the following steps: there the hydrogeology was known and the chance of successful drilling was
high. Oxfam chose to invite local contractors to tender for the drilling contract.
1. Negotiating Terms And Conditions For Operating Contingency This proved to be highly efficient as the drillers were available at short notice
Boreholes and could mobilise to site quickly. Having decided to go ahead with the
boreholes in June, Oxfam GB was able to have the boreholes equipped and
A team of representatives from the DSG, Oxfam GB and DFID toured the operational by the end of July.
District discussing options for contingency borehole sites with WUAs and
PAs. The sites which provided the best opportunities for successful The WUAs at Hadado and Arbajahan requested to have the boreholes drilled
contingency boreholes were selected based on a number of criteria including: along side their existing, but low yielding, boreholes in the settlement centres.
The reasons given for this were as follows:
Community preferences,
Available grazing, Nearby grazing areas are insecure (alongside borders shared with
Groundwater potential and neighbouring Boran herders) and the safety of the equipment was too
The strength of local WUAs and PAs. difficult to guarantee
Locating the borehole at the settlement rather than in the grazing area
In one case (Khorof-Harar) the PA asked not to be considered as they chose meant that nearby grazing could be accessed but the furthest grazing
not to have a new borehole, with the attendant environmental risks, in their was not depleted during the drought and could be saved for use in the
area. wet season.

Once the sites were selected detailed discussions were held with the three The location of these two boreholes meant that the grazing, which was
WUAs concerned and agreements were drawn up between the WUAs, Oxfam already accessible from Hadado and Arbajahan, could be used by more
and the DSG. These agreements detailed where each borehole would be livestock because there was sufficient water available. The third borehole was
drilled, who was responsible for operating and maintaining it and how it would located at Harakhotkhot, 70km from Habaswein, and genuinely opened up a
be closed and re-opened. It is clear that all the communities concerned fully new grazing area that was not accessible without the contingency borehole.
understood the fragile nature of their strategic grazing reserves and were not
in favour of permanent water supplies in these areas. All WUAs agreed that 3. Operation And Maintenance Of The Boreholes
the boreholes should be closed at the end of the drought and equipment
should be held by the WUA or local PA until it was needed again. The The ownership of the boreholes was made clear in the agreement and the
agreement stated that the District Water Office could be asked to assist in WUAs were responsible for operating the boreholes. This included providing
removing and reinstalling equipment on request of the WUA and with the operators and organising sufficient revenue collection to cover the cost of fuel
approval of the DSG. and oil. Oxfam GBs ongoing support to the Rapid Response team based in
the District Water Office meant that maintenance and repair services and
At the same time Oxfam GB contacted the area MPs and sought their support spare parts were available at no cost to the WUAs. This guaranteed
for the contingency boreholes. This involved extracting commitments from the continuous running of the boreholes but undermined the concept of self-
MPs to support the closure of the boreholes at the appropriate time. The aim reliance being promoted by development projects.
of this was to avoid the usual political pressure on stakeholders to keep
boreholes open and create permanent settlement. The contingency boreholes were used by herders from all over the district but
run by the local WUAs. This caused some conflict between different clan

Case Study: Contingency Boreholes in Wajir District Rural Focus Ltd


3

groups in at least one case but the problems were resolved rapidly by the temporary and some permanent infrastructure had to be constructed at all
election of an interim committee at Harkhotkhot with representatives from all three sites.
the users. Once equipped the boreholes were kept operational by the Oxfam
supported Rapid Response Team. The sustainability of the boreholes is
4. Closure Of The Boreholes At The End Of The Drought questionable without an institutionalised maintenance and repair system
in the District.
The boreholes were all operational throughout the second half of 2000 when Despite the considerable efforts of Oxfam and the expressed desire of all
the expected short rains failed completely. However the long rains did start in stakeholders to avoid permanent water supplies in the fragile grazing
March/April 2001 and all three WUAs requested the District Water Office and reserves, another development actor drilled three new boreholes in the
Oxfam GB to assist them to close the boreholes as agreed. This was done same areas immediately after the contingency boreholes became
and the equipment was removed from the site. operational. These new boreholes present a serious threat of new
settlement which would destroy the existing grazing reserves.
The WUAs then wrote to Oxfam GB again in July and requested to reopen the
boreholes as the rains had been insufficient. This was agreed, the boreholes OUTPUTS AND IMPACTS
were re-opened and operated until November 2001 when they were again
closed. This raises the question; under what circumstances should o Three boreholes which significantly increase access to vital grazing
contingency boreholes be opened? What criteria can be used to judge reserves in Wajir and hence increase livestock production
whether conditions justify the opening of the boreholes to prevent boreholes o Committed stakeholders with a common understanding of the value of a
being opening every dry season? correctly operated contingency boreholes
o Savings in womens time and related improvement in family health from
TECHNIQUES reduced distance to water
o Documentation and dissemination of the innovative approach and
The successful implementation of contingency boreholes would not have implementation methodology to other development and relief actors for
been possible without full involvement of all stakeholders. Careful negotiation replication in other Districts
with community and local leaders ensured that all stakeholders were working
together towards a common goal of providing temporary water supplies with LESSONS LEARNT
minimum long term environmental and social impact.
o Contingency boreholes can provide a vital means of sustaining livelihoods
LIMITATIONS AND DIFFICULTIES in drought prone areas, if properly planned and managed.
o Boreholes inside the grazing area are more likely to operate as genuine
Two of the boreholes had to be drilled alongside existing, operational contingency water supplies than boreholes in centres.
boreholes and are, therefore, difficult to distinguish from replacement o Policy of district (eg on no new boreholes) should be enforceable so that
boreholes in other settlements. It seems likely that there will be external actors cannot carry out interventions which contravene the
considerable pressure to open these boreholes to ease watering every agreed policy
dry season. o Contingency boreholes should be managed by a representative
Establishing acceptable committees to run contingency boreholes which committee and overseen by the PA
genuinely represent all users interests is difficult when the boreholes are o Long term solutions to the problem of unsustainable spare parts supply
used by herds from a wide area. Conflicts over the use of the water were and maintenance service provision are essential to ensure that boreholes
inevitable and did occur. can operate without significant down time.
The boreholes were deliberately constructed with no permanent
infrastructure but there were considerable constraints watering large
numbers of livestock without a storage tank or troughs. Eventually, some

Case Study: Contingency Boreholes in Wajir District Rural Focus Ltd

Vous aimerez peut-être aussi