Académique Documents
Professionnel Documents
Culture Documents
Eurocodes
AIM
ABSTRACT 2
INTRODUCTION 2
1. MATERIALS 2
2. STRUCTURAL ANALYSIS 4
6. CONCLUSIONS 15
HUT/BE/S Pekka Pulkkinen 2 (15)
ABSTRACT
In this paper the design principles and rules of pre- and post tensioning 2 are studied.
Materials, analysis and crack control of prestressed structures are presented shortly as they are
written in the present prestandards of Eurocode 2. In some issues comparison to the existing
Finnish codes are done.
PrEN 1992-1-1 Eurocode 2 (Draft for Stage 49): Design of concrete structures
General rules and rules for building
INTRODUCTION
Almost all parts of Eurocode include bridge section. Mostly they are numbered as section 2 in
code, for example in concrete structures PrEN 1992-2. The part of bridges is not an
independent code, it complements the basic code. This means that in bridge design procedure
one must take into account all code sections involved. This makes the design work quite
complicated. However the rules of pre and post tensioning are shown mostly in basic code
PrEN 1992-2.
In Finland it is not allowed to design bridges according to Eurocode 2 so far. Neither National
Annexes (NA) have been prepared. The preparing work of NA has just started and national
support group has been established. The main principle in preparing National Annexes is that
the safety level of brides will not been lowered.
The opinion of the national support group is that after completing and accepting the codes
special bridge design books similar to German practice will be prepared.
1. MATERIALS
1.1 Properties
The prestressing tendons (wires, strands and bars) shall be classified according to:
- strength, denoting the value of the 0,1% proof stress (fp0,1k) and the value of the
ratio of tensile strength to proof strength (fpk /fp0,1k) and elongation at maximum
load ( uk)
- class, indicating the relaxation behaviour
- size
- surface characteristics.
HUT/BE/S Pekka Pulkkinen 3 (15)
The design calculations of the losses due to relaxation of the prestressing steel should be
based on the value of 1000, the relaxation loss (in %) at 1000 hours after tensioning and at
a mean temperature of 20 C
The values for 1000 can be either assumed equal to 8% for Class 1, 2,5% for Class 2, and
4% for Class 3, or taken from the certificate.
The long term (final) values of the relaxation losses may be estimated for a time t equal to
500000 hours (i.e. around 57 years).
1.2 Strength
The 0,1% proof stress (fp0,1k ) and the specified value of the tensile strength (fpk ) are defined
as the characteristic value of the 0,1% proof load and the characteristic maximum load in axial
tension respectively, divided by the nominal cross sectional area as shown in Figure 1.
Adequate ductility in elongation may be assumed if the prestressing tendons obtain the
specified value of the elongation at maximum load given in EN 10138.
Adequate ductility in tension may be assumed for the prestressing tendons if fp0.1/fpk k :
The value of k for use in a Country may be found in its National Annex. The recommended
value is 1,1.
1.4 Fatigue
Prestressing tendons shall have adequate fatigue strength. The fatigue stress range for
prestressing tendons shall be in accordance with EN 10138 or given in an appropriate
European Technical Approval
HUT/BE/S Pekka Pulkkinen 4 (15)
Structural analysis is performed on the basis of the nominal cross-section area of the
prestressing steel and the characteristic values fp0,1k, fpk and uk.
The design value for the modulus of elasticity, Ep may be assumed equal to 205 GPa for
wires and bars.
The design value for the modulus of elasticity, Ep may be assumed equal to 195 GPa for
strand.
The design value for the steel stress, fpd, is taken as fp0,1k/ S (see Figure 2).
For cross-section design, either of the following assumptions may be made (see Figure 2):
- an inclined branch, with a strain limit ud. The design may also be based on the actual
stress/strain relationship, if this is known, with stress above the elastic limit reduced
analogously with Figure 2, or
- a horizontal top branch without strain limit.
Note: If more accurate values are not known the recommended values are ud = 0,02 and
fp0,1k /fpk = 0,9.
In Finland partial factors in bridge design are: concrete c=1,35, reinforced steel s= 1,10,
prestressing steel is s= 1,15
2. STRUCTURAL ANALYSIS
2.1 General
Following the assumptions of above, the contribution of the prestressing tendons to the
resistance of the section should be limited to their additional strength beyond prestressing.
This may be calculated assuming that the origin of the stress/strain relationship of the
tendons is displaced by the effects of prestressing.
Brittle failure of the member caused by failure of prestressing tendons shall be avoided.
where fck(t) is the characteristic compressive strength of the concrete at time t when it is
subjected to the prestressing force.
Measurements
In post-tensioning the prestressing force and the related elongation of the tendon shall be
checked by measurements and the actual losses due to friction shall be controlled.
At a given time t and distance x (or arc length) from the active end of the tendon the mean
prestress force Pm,t(x) is equal to the maximum force Pmax imposed at the active end,
HUT/BE/S Pekka Pulkkinen 6 (15)
minus the immediate losses and the time dependent losses (see below). Absolute values are
considered for all the losses.
The value of the initial prestress force Pm0(x) (at time t = t0) applied to the concrete
immediately after tensioning and anchoring (post-tensioning) or after transfer of
prestressing (pre-tensioning) is obtained by subtracting from the force at tensioning Pmax
the immediate losses Pi(x) which should not exceed the following value:
When determining the immediate losses Pi(x) the following immediate influences should
be considered for pre-tensioning and post-tensioning where relevant
- losses due to elastic deformation of concrete Pel
- losses due to short term relaxation Pr
- losses due to friction P(x)
- losses due to anchorage slip Psl
The mean value of the prestress force Pm,t(x) at the time t > t0 should be determined with
respect to the prestressing method. In addition to the immediate losses the time dependent
losses of prestress Pc+s+r(x) as a result of creep and shrinkage of the concrete and the
long term relaxation of the prestressing steel should be considered
Account should be taken of the loss in tendon force corresponding to the deformation of
concrete, taking account the order in which the tendons are stressed.
This loss, Pel, may be assumed as a mean loss in each tendon as follows:
where:
c (t) is the variation of stress at the centre of gravity of the tendons applied at time t
j is a coefficient equal to (n -1)/2n where n is the number of identical tendons successively
prestressed.
The losses due to friction P(x) in post-tensioned tendons may be estimated from:
where:
is the sum of the angular displacements over a distance x
is the coefficient of friction between the tendon and its duct
HUT/BE/S Pekka Pulkkinen 7 (15)
k is an unintentional angular displacement for internal tendons (per unit length) values for
unintended regular displacements for internal tendons will generally be in the range 0,005 < k
< 0,01 per metre.
x is the distance along the tendon from the point where the prestressing force is equal
to Pmax (the force at the active end during tensioning)
For external tendons, the losses of prestress due to unintentional angles may be ignored.
Account should be taken of the losses due to wedge draw-in of the anchorage devices,
during the operation of anchoring after tensioning, and due to the deformation of the
anchorage itself.
The time dependent losses may be calculated by considering the following two reductions
of stress:
(a) due to the reduction of strain, caused by the deformation of concrete due to creep and
shrinkage, under the permanent loads:
(b) the reduction of stress in the steel due to the relaxation under tension.
Note: The relaxation of steel depends on the reduction of strain due to creep and shrinkage
of concrete. This interaction can generally and approximately be taken into account by a
reduction factor 0,8.
A simplified method to evaluate time dependent losses at location x under the permanent
loads is given by Expression
where:
HUT/BE/S Pekka Pulkkinen 8 (15)
Expression shown above applies for bonded tendons when local values of stresses are used
and for unbonded tendons when mean values of stresses are used. The mean values should
be calculated between straight sections limited by the idealised deviation points for external
tendons or along the entire length in case of internal tendons.
2.9 Effects of prestressing at serviceability limit state and limit state of fatigue
3.1 General
1. Stress limitation
2. Crack control
3. Deflection control
In this contribution only Crack control is studied, which in many cases has significant
importance in designing post tensioned structures.
The bridge or specific parts of it shall be classified into environmental classes according to
Table 3 and into categories according to Table 4.
class XD3, XF2 or XF4, This will include all parapets, walls and piers within 6m from the
carriageway and surfaces such of top of piers under expansion joints wich are likely to be
exposed to water draining from the carriageway.
For bare concrete decks, without waterproofing or surfacing, the cover should be increased
by a minimum of 10 mm to allow for ware.
In order to ensure the performance required, the design criteria for the bridge or for
specific parts of it, should be classified into design categories according to Table 5. This
rule applies to both, the construction phases and persistent situations.
Table 5 contains the criteria for the verification of decompression and crack width.
When using this Table, both criteria need to be verified.
For category A the decompression limit requires that the tendons lie at least 25 mm
within concrete in compression; for others categories the tendons should lie within the
concrete in compression.
A limiting calculated crack width, wmax, taking into account of the proposed function and
nature of the structure and the costs of limiting cracking, should be established.
When designing to categories A, B and C of the table 4 for the limit state of decompression
no tensile stresses in the concrete are allowed under the relevant combination of actions.
For crack width control, the deemed to satisfy criteria given in Tables 5 and 6 are based on
the following design crack widths:
- 0,2 mm for prestressed concrete
HUT/BE/S Pekka Pulkkinen 11 (15)
For members with only unbonded tendons, the requirements for reinforced concrete
elements apply. For members with a combination of bonded and unbonded tendons
requirements for prestressed concrete members with bonded tendons apply.
The spacing of ducts or of pre-tensioned tendons shall be such as to ensure that placing and
compacting of the concrete can be carried out satisfactorily and that sufficient bond can be
attained between the concrete and the tendons.
The ducts for post-tensioned tendons shall be located and constructed so that:
- the concrete can be safely placed without damaging the ducts;
- the concrete can resist the forces from the ducts in the curved parts during and after
stressing;
- no grout will leak into other ducts during grouting process.
Bundled ducts for post-tensioned members, should not normally be bundled except in the
case of a pair of ducts placed vertically one above the other.
The minimum clear spacing between ducts should be in accordance with that shown in
Figure 3 .
The guidelines of minimum spacing given in Finnish Codes are quite limited, in principle the
minimum spacing values shown above are in the line with Finnish design practice, however
we use as absolute minimum 1,2 dg . Additionally we have some recommendations for spacing
of vibrator and casting pipes.
where
P0 is the maximum force applied to a tendon
c,c' are the dimensions of the associate rectangle
fck(t) is the concrete strength at time of tensioning
To prevent bursting and spalling of the concrete, each regularization prism should be
crossed by a minimum area of transverse
reinforcement
where Po is the maximum force applied to the tendon and s is the design strength of
the reinforcing steel.
The minimum reinforcement may be also derived from the European Technical
Approval of the prestressing system.
HUT/BE/S Pekka Pulkkinen 14 (15)
The anchorage devices used for post-tensioned tendons shall be in accordance with
those specified for the prestressing system, and the anchorage lengths in the case of
pretensioned tendons shall be such as to enable the full design strength of the tendons to
be developed, taking account of any repeated, rapidly changing action effects.
In general, couplers should be located away from intermediate supports.
The placing of couplers on 50% or more of the tendons at one cross-section should be
avoided unless:
In any case at each cross section a minimum of 30% of the tendons should be not
coupled.
5.1 General
The Finnish Road Administration ordered comparison calculations from some Finnish bridge
consultants. Calculations were prepared from prestressed concrete girder bridge and
reinforced concrete slab bridge.
In the study, which was prepared some years ago prestandards prEN 1991-2, SFS ENV
1991-1-1: Eurocode 1 and SFS ENV 1992-1-1: Eurocode 2 were used. The calculations
were prepared for superstructure by calculating design forces and moments using loads and
factors of Eurocode. The resistance of cross sections in critical points were calculated using
material properties and factors respectively. Crack control was also done in critical points.
In the following are listed the main conclusions from the study:
Loads:
Load of temperature variation between upper and lower surface is not included in
design moment in ULS, which also balances design moments between codes.
In checking of ultimate moment resistance for prestressed concrete girder results were
very close each other
In concrete deck slab the reinforcement calculated for bending was 2025 % bigger in
Eurocode
HUT/BE/S Pekka Pulkkinen 15 (15)
Design moment of torsion in girder bridge was 24 % bigger at end support and 8%
bigger at intermediate support in ULS.
When checking combined resistance of shear and torsion at intermediate supports the
utilization rate was only 42 % according to Eurocode while it was 60 % according to
Finnish code.
In checking combined resistance of bending and torsion only main compressive stress is
checked in Eurocode often combined resistance of bending and torsion is critical
when determining width of girder
Crack control:
6. CONCLUSIONS
This study showed that Eurocode 2 contains much more information and details for pre- and
post tensioning structures than existing Finnish codes and design instructions. Particularly
losses of pretensioning forces and detailing of structures are clearly presented. However using
of code requires understanding and know-how of full code, because bridge parts are divided in
different codes. In order to simplify to use of codes special bridge summary parts should
prepared as was done in Germany some time ago.
The crack control differs quite much from our present practice. This was also noticed in
comparison studies where amount of conventional reinforcement became smaller than the
amount of reinforcement designed according to our code. The environmental classes and
exposure classes differ from our practise, which can be seen in maximum crack widths.
REFERENCES:
[1] European Committee for Standardization (CEN): PrEN 1992-1-1 Eurocode 2 (Draft for
Stage 49): Design of concrete structures General rules and rules for building
[2] European Committee for Standardization (CEN): PrEN 1992-2 (Draft 32): Design of
concrete structures- Concrete bridges
31.12.2002.