Académique Documents
Professionnel Documents
Culture Documents
1
The views expressed in this presentation are those of the presenter and do not necessarily represent those of the Asian Development Bank.
Power Sector Overview
1. Population 87 million; 96% connected to the grid
2. Power Generation – 58% fossil fuel-based, 4% import, 37% Renewable Energy
3. RE Capacity: Hydro – 6,304 MW, Biomass – 150 MW, Wind –10.5 MW, Solar –1.25 MW, MSW
– 0.75 MW
4. Electricity Tariff – US cents 5.3/kWh – among world’s lowest
Region Technical
potential (MW)
North 50
Centre 880
South 855
Total 1785
% RE in
Primary Energy 1,5 3,4 8,1
Supply
Target Target
1623 KTOE 6075 KTOE
RE heat - PV: 51 - PV: 262
- Biogas: 274 - Biogas 529
- Biomass: 1.289 - Biomass: 5.266
Target Target
Meeting 1% gasoil Meeting 5% gasoil
Biofuel
demand demand
(174 ktoe) (1253 ktoe)
SALIENT FEATURES
1. Renewable Energy
Development Office (REDO) -
Proposition
2. RE Development Fund -
Proposition
3. Different Assistance Programs
Wind Power Projects
Around 50 projects on pipeline (Pre-Development Contracts)
Around 10 projects completed F/S, waiting for approval and PPA
Some Projects Under Development
Designed Capacity: 30 MW 1. EVN – Thuan Binh Wind farm
REVN-BIT Wind Power Project 24 MW (50MW) Thuan Binh win farm, Binh Thuan
Commune Binh Thach - Tuy Phong – Binh Thuan Estimated Cost: US$
2. REVN (RE Vietnam Joint stock company )
Four phases (30+32+30+28 MW) Binh Thuan wind
farm
Estimated cost: 80US$ M (phase 1)
3. Thuan Phong RE development Joint Stock
70 MW phase I and 110 MW phase 2 An Phong wind
farm Project
Estomated cost: 144 US$ M (phase I); 223 US$ M
(phase II)
4. Phuong Mai Joint stock company
15 MW Phuong Mai I Wind farm Project (50MW)
Installed capacity: 20x1.5 MW
5. GGP (Germany)
(Operational: 5x1.5MW in 2009)
200 MW Phuong Mai II wind farm project
Height of hub : 85 m
6. Central wind Investment & Development company
Cost = US$ 80 M
50.4 MW Phuong Mai III wind farm
Project Development Issues
Technical Aspects
– Resource Assessment: No reliable assessment and data; Few measurements
– Project Development Rights: First comes first served basis Investors tend to
grasp place first, develop later.
– Grid and Transmission system (Interconnection): Connection and transmission
rights is under elaboration. Potential congestion in near future.
– Intermittent resource: No study on this issue yet
– Capacity Factor: Too high (0.35-0.45)?? Lack of reliable sources for verification
Non-technical Aspects
– Institutional/Organizational: Arrangement is in place but lack of coordination.
– Socio-cultural: Acceptance and tolerance, but risk of erosion in supporting in future
– Financing: Most difficult issue. Need innovative approaches and mechanisms
– Political: Relatively strong support, but not really committed
Principal risk
• Long term PPA
• No reliable wind measurements
References: