Académique Documents
Professionnel Documents
Culture Documents
TUNNELLING
PART 1: GENERAL
1.01 DESCRIPTION
1.01.1 Work Included: This section covers the requirements for constructing,
furnishing, delivery, placing, jointing, installing and finishing and all other work
as required for completion of a railway tunnel work.
04100 - 1
D 2125 Elastic Joint Filler
D 345-90 Test Method for Sampling Calcium Chloride for Roads and
Structural Application
D 4595-94 Tensile Strength and Elongation of Geotextile (Strip method)
D 4632-91 Tensile Strength and Elongation of Geotextile (Grab method)
D 4533 Tear Strength of Geotextile (Trapezoid method)
D 4751 Puncture Resistance
04100 - 2
Comply with the applicable reference standards listed in Section 01201
QUALITY ASSURANCE/ CONTROL PROGRAMME and as specified
herein.
1. General:
Prior to the excavation of a new tunnel, the Contractor shall clean the
surface of the adjacent existing tunnel lining to detect deformation, cracks,
leakage of the tunnel. The Contractor shall prepare and submit a
deformation, cracks, leakage development diagram (drawing) to the
Engineer after detected observation and measurement of the location and
extent of the defective lining.
Until sixty (60) days before cleaning work commence, the Contractor shall
prepare and submit to the Engineer his detailed work plan comprising a
work schedule, work method, equipment to be used for approval.
For the cleaning, the Contractor shall take due precautions to prevent dust
accumulation inside the tunnel so as not to cause any hindrance to train
operations. Where any irregularities found on the surface of tunnel lining
during the cleaning, the Contractor shall immediately report to the
Engineer, and a remedial step shall be submitted to the Engineer for
approval.
Site lighting system for work sites and areas where observations and
measurements to be conducted shall comply with the requirements under
Clause Lighting for Underground Excavation, however, illumination shall
be tuned off during the passage of trains. Also, any facilities for the
cleaning of tunnel lining shall not interfere with the construction gauge.
3. Establishment of Control Standard
04100 - 3
Increase lining tensile stress: 0.5 MPa
Increase lining compressive stress: 2.0 MPa
After completion of construction a new tunnel and removal all track inside an
existing tunnel, the steel fences shall be installed at two (2) entrances of the
existing tunnel. The steel fence shall have a height more than three (3) meters
for preventing people entering the tunnel without permission. The steel fence
shall have a door with a door lock from outside.
After completion of construction a new tunnel and both tunnel portal walls, the
painting and decoration of two (2) portal walls, and the installation of marks,
signs and signboards shall be carried out. The design of tunnel portals, marks
and signs shall be submitted to the Engineer for approval before carrying out.
1.03.4 Instrumentation
1. General
04100 - 4
measuring equipment for reading the instruments.
The Contractor shall observe conditions in the new tunnel and the existing
tunnel subject to the following provisions and/or others as instructed and
approved by the Engineer so as to assure safety in tunnels, and judge the
appropriateness of the construction method of support, and shall notify
these to the Engineer.
The Contractor shall supply and install reflex targets on the new tunnel in
the pattern as shown or as directed by the Engineer. The reflex targets
shall be installed as soon as practicable after the tunnel has been
excavated and supported. Measurement shall be taken at intervals of 10 to
20 meters along the length of the tunnel, with five (5) measurement points
per section.
04100 - 5
installed in accordance with the manufacturers instructions. Measuring
device shall be an electronic theodolite with an integrated coaxial
electro-optical distance-measuring system (Total Station) or other
equivalent device. The device to be used shall be proposed by the
Contractor and approved by the Engineer.
Measuring shall be made at once or twice daily until the heading has
advanced five times the tunnel width or otherwise directed by the Engineer
and weekly thereafter until the final underground excavation lining is
constructed.
The Contractor shall supply and install reflex targets on the existing tunnel
in the pattern as shown or as directed by the Engineer. Measurement shall
be taken at intervals of 10 to 20 meters along the length of the tunnel, with
seven (7) measurement points per section.
Reflex targets shall be securely attached the existing lining surface prior
construction, and located as shown on drawings or directed by the
Engineer. The total station shall be used to measure the change in size of
the tunnel, if any, occurring during the period between excavation and
construction.
04100 - 6
Measuring shall be made at once or twice daily before the heading has
reached and until the heading has advanced three (3) times the tunnel
width or otherwise directed by the Engineer and weekly thereafter until the
final underground excavation lining is constructed.
Measurement of the strain on the lining surface shall be carried out using
strain gauges or strain meters to monitor deformations of the existing lining
in order to evaluate the existing structural stability. The readings must be
checked regularly to ensure they are not over the allowable strain of the
lining material. Strain gauges shall be located at six (6) sections along the
line of the tunnel, with each section having three (3) gauges one at the
crown and the other two at each spring line.
The Contractor shall supply, install, measure and test surface strain meter
at specified locations in the existing tunnel as shown on the drawings or as
directed by the Engineer. Surface strain meter assemblies shall be
installed and tested in accordance with the manufacturers
recommendations.
1.04 SUBMITTALS
(1) Detailed driving excavation and support plan. The excavation and
support plan may be revised by the Contractor during the progress of
work depending on physical and/or geological conditions encountered,
and the revised plan shall be submitted to the Engineer for approval. An
alternative plan may be submitted to the Engineer for his approval to
deal with a case in the failure of machinery to perform the required work.
(2) Structural design report based on the NATM, quantity calculation report,
design drawings and other necessary documents requested by the
Engineer.
04100 - 7
(5) Manufacturers specifications and installation/operation manuals and
instructions for the following products including laboratory test reports
and other data as required to show the compliance with specified
requirements:
- Structural steel (rock bolts), including certified copies of mill reports
covering chemical and physical properties;
- High strength bolts, including nuts and washers;
- Unfinished bolts and nuts;
- Structural steel primer paint; and
- Manufacturers data on other waterproofing membrane, geotextile
sheets, groundwater discharging hoses, and any other products and
materials deemed necessary for the work.
(7) Plans and detailed drawings of his temporary electric power supply
system, and temporary power distribution system.
Re: Locations of face at the start and the end, survey results, details of rock
support installed, men and plant engaged, elapsed time for tunnel works and
unusual occurrences.
1. Daily reports covering the previous days work. This report shall include:
- Advance face;
- At start and end of rounds;
- Cross section and results of any observation and measurement made;
- Details of rock support installed, including rock bolts, shotcrete, steel
wire mesh reinforcement, steel support, concrete, and any other
material used;
- Number and classification of men and equipment engaged in each
operation;
- Elapsed time for each of the operations moving and set-up machine,
mucking, installation of supports, extending services (vent-line, water
lines, etc.), downtime delays;
- Total cycle time per round;
- Unusual occurrence, rock-falls, zones of instability, inflow of water,
occurrence of gas, and any accident sustained by workmen;
- Safety programs for the following;
- Rock-falls and displacement or settlement of any material surrounding
excavated hollow space;
- Flammable and toxic gases;
- Measurement Results implemented during construction.
04100 - 8
Deliver all materials to the job site properly marked to identify the structure
for which it is intended.
2. Replacements:
The Contractor shall provide for his own use all necessary temporary
electrical equipment and materials such as diesel generator units,
transformers, switch-gear, protective equipment, meters and distribution
lines to surface and tunnel work sites and temporary buildings, including
staff quarters and labour camps. A concrete batching plant shall be
provided by the Contractor at locations adjacent to the work-site from
which concrete can be supplied without delay.
The Contractor will be permitted to take water from a well or from a local
river for his own use free of charge, however, shall at all times keep his use
of water to the minimum.
3. Stockyard:
Ample areas shall be secured for stockpiling all products, equipment, tools
and materials required for tunnel works at location(s) readily accessible to
the work site. Watchmen shall be deployed throughout the project life to
prevent materials from pilferage.
The air breathed by persons in sites shall contain not less than 17 percent
of oxygen, and shall not contain a concentration of contaminants such as
gases, vapours and dust greater than safe for their health, having regard to
04100 - 9
the combined effects of several contaminants.
Where diesel powered equipment is used in the site, the minimum quantity
of fresh air to be supplied shall be 3 m 3 /min., for each kW of power
employed within the site in addition to the requirements for personnel.
During excavation work, the ventilation system and the ventilation duct
shall be terminated not more than 30 meters from the face.
The Contractor shall submit, for approval, proof from prospective supplier
of diesel powered equipment for use inside a tunnel that the proposed
equipment conforms to the requirements of approved mining standards.
5. Lighting System:
All power and lighting wires shall be adequate insulated, securely installed
and regularly checked for any damage.
The power and lighting wires shall be installed on one side of the tunnel.
The Contractor shall supply, install, maintain and operate all necessary
diversion, pumping and other equipment to remove water from the site,
and discharge water to the outside.
04100 - 10
7. Temporary Waste Water Treatment System:
The Contractor shall supply, install, maintain and operate all necessary
facilities and equipment to treat waste water from construction site. The
quality of waste water shall be monitored and treated to keep its quality
under Indonesian environmental standards before discharging to the
outside.
04100 - 11
PART 2: PRODUCT
2.01 MATERIALS
2. Reinforcing Bars:
The rock bolts and forepoling bolts shall be threaded at one end and
pointed at the other to facilitate the placing operation. The sleeve
diameter shall be selected in accordance with the drill hole in order to
ensure the optimum filling of the hole.
4. Cement:
5. Aggregates:
6. Water:
7. Admixtures:
Comply with the requirements in ASTM C260-86 or JIS A 6204 for air
04100 - 12
entraining agents. The use of special cement or admixture shall be
approved by the Engineer even when used by the Contractor at his own
expense. The use of the admixture shall be proved harmless to the work
crew.
8. Shortcrete:
Comply with JIS 3551-80 Welded Wire Mesh of 5.0 mm in diameter with
150 mm opening, or equivalent quality as approved by the Engineer.
Comply with ASTM A307, non-headed type with heavy hexagonal nuts
unless otherwise indicated.
Comply with ASTM A325, heavy duty hexagonal structural bolts, heavy
duty hexagonal nuts, and hardened washers, shall be quenched and
tempered medium-carbon steel bolts, nuts and washers.
- EVA polymer shall comply with the requirements in JIS K6773 for
04100 - 13
specific gravity, hardness, tensile strength, elongation, softening
temperature and chemical resistance, and with JIS K 6301 for tear
strength or equivalent quality as approved by the Engineer.
Comply with JIS G3452-84, Carbon Steel Pipes for Ordinary Piping,
or equivalent as approved.
04100 - 14
PART 3: EXECUTION
3.01 CONSTRUCTION
1. General:
The pay-line as shown on the Drawings are the outside limits to which
measurement for payment of excavation will be made, and measurement
for payment will in all cases be made to be the pay-line regardless of
whether the limits of the actual excavation fall inside or outside of pay-line.
The support patterns for supporting excavated ground along the tunnel
shall be classified into the following four types, as shown in the Drawings:
- Type A;
Type A pattern is for supporting the excavation through IIN class rock
which is generally stable. The support members are eight (8) rock bolts
and min. 100-mm thickness of shotcrete with steel wire mesh. Rock
bolts shall be installed at the interval of 1.5 m in the longitudinal
direction.
- Type B;
Type B pattern is for supporting the excavation through I N-2 class rock.
The support members are nine (9) rock bolts, H125-type steel supports
at upper section, and min. 125-mm thickness of shotcrete with steel
wire mesh. Rock bolts, and steel supports shall be installed at the
interval of 1.2 m in the longitudinal direction.
- Type C;
04100 - 15
Type C pattern is for supporting the excavation through I N-1 class rock,
or the section which has an overburden depth less than 2 times of
tunnel width. The support members are thirteen (13) rock bolts,
H125-type steel supports at upper and lower sections, and min.
150-mm thickness of shotcrete with steel wire mesh. Rock bolts, and
steel supports shall be installed at the interval of 1.0 m in the
longitudinal direction.
- Type D;
5. Excavation Procedures:
Bench cut method shall be the typical excavation method for tunnel
excavation, and other proper excavation procedures shall be adopted to
suit the designed cross section to be accommodated the material to be
excavated and the conditions to be encountered.
During the excavation work, the Contractor shall, at his full responsibility,
maintain the lines shown on the Drawings by accurate surveying as
approved by the Engineer.
04100 - 16
of rock.
At least 14 days before the work, the Contractor shall submit his detailed
mechanical excavation plan to the Engineer for approval.
All plans shall be subject to review by the Engineer. This review shall not
relieve the Contractor of his complete responsibility for methods, means,
procedures, accuracy, adequacy and safety of the mechanical excavation,
exercising proper supervision and field judgement, and producing the
design lines specified herein.
Any and all over-excavation performed by the Contractor for any purpose
or reason, except as may be directed, and due to the fault of the Contractor,
shall be at the expense of the Contractor. The Engineer may direct that all
such over-excavation shall be backfilled with shotcrete or concrete and the
cost of furnishing and placing the backfill shall be at the expense of the
Contractor.
6. Mucking:
All excavated soil and rock shall be disposed of with reasonable measures
or stockpiled in spoil banks as directed by the Engineer. During mucking,
muck-pile shall be wetted down with fine water sprays.
1. General:
The Contractor shall furnish and install primary support for the
underground excavations as shown on the drawings or as directed by the
Engineer.
Measures will be related to chosen heading procedure, the rock type and
the results of crown and wall displacement measurements. The routine
installation of support elements in conjunction with excavation work is an
integral part of the NATM, with the ability to vary the support elements to
suit the exposed ground conditions.
The support elements described elsewhere and shown on the drawings for
any particular rock type are to be taken as typical and may be varied in
quantity and/or thickness as approved or directed by the Engineer to suit
the actual exposed ground conditions.
04100 - 17
Contractor to install support up to the face from muck-pile immediately
after excavation, and the Contractor shall not be entitled to any additional
payment for comply with such directions.
- General;
The Contractor shall furnish and install grouted rock bolts and
forepoling bolts in underground excavation as shown on the Drawings
or as directed by the Engineer. Rock bolts and forepolling bolts,
complete with all required accessories, including bearing plates, nuts,
washers, filling and grouting materials, shall be supplied by the
Contractor. The use of chemical resin anchors or cement grout
anchors shall be subject to approval by the Engineer.
The installation of grouted rock bolts and forepoling bolts shall be under
the direct supervision of personnel having at least two (2) years
experience in rock bolting works. The Contractor shall keep on site,
ready for immediate use, a sufficient stock of rock bolts and
accessories to avoid delay to the work.
- Installation pattern;
When rock bolt or forepoling bolt support is directed, the hole shall be
drilled and cleaned out, and the rock bolts and forepoling bolts shall
then be installed without delay. The forepoling bolts shall be installed
before the next excavation.
04100 - 18
bolt and forepoling bolt holes. The holes shall be drilled to the size and
depth recommended by the manufacturers instructions, manual and
approved by the Engineer.
The Engineer will select rock bolts for pullout tests, and the Contractor
shall test such bolts using a calibrated hydraulic jack. All tests shall be
witnessed by the Engineer. The Contractor shall provide and maintain
the tools, equipment and labour to perform these tests. As an average,
one bolt in 200 of the rock bolts installed shall be tested. The tests
should be performed after installing a rock bolt more than 3 days, at
tunnel crown or tunnel spring line or other positions which are
instructed by the Engineer.
Prior to installing the bolts, the rock surface shall be prepared for
accepting the washer plates. Such prepared bearing surfaces shall be
normal to the axis of the hole and if necessary tapered plates or
washers shall be used.
Each permanent rock bolts shall be provided with two independent forms
of protection against corrosion at all points of the entire surface of the
completed installation. The Contractor shall submit his proposal for
corrosion protection to the Engineer for approval.
To carry out the excavation work without delay, the Contractor shall always
have on stock sufficient quantities of rock bolts, of various types and length,
wire mesh and other accessories.
3. Shotcrete:
04100 - 19
- General;
- Design Strength;
- Mix Proportions;
The Contractor shall propose the mix proportion of shotcrete for the
approval of the Engineer together with the data enough for the
Engineer to make judgement. And if directed, the adjustment of mix
proportion shall be proposed by the Contractor.
The table below gives the reference values for mix proportions of
shotcrete.
- Equipment;
04100 - 20
pressure above operating air pressure recommended by the
manufacturer of the shotcrete delivery machine. A suitable water
pressure and flow meter shall be fitted to the water supply system.
Shotcrete machine:
The entire system shall be so arranged that the nozzle man may
use air and water in any combination to prepare surfaces on which
shotcrete will be applied.
- Field Trials;
The field application of each mix selected for field trial shall be made on
overhead horizontal and/or vertical test panels to simulate construction
conditions.
Fifty (50) to Sixty (60) mm diameter cores shall be taken from each
overhead horizontal and each vertical test panel. With the exception of
cores for one-day strength, all cores shall be taken one day before
testing.
Cores shall have a length as 2.0 times of a diameter and shall be tested
for their one and 28-day strength. The average strength of all cores as
a minimum shall be as follows:
04100 - 21
Compressive strength 28 days 18 MPa minimum
The minimum strength obtained by testing shall be not less than 80% of
the above-mentioned values. Mixes failing to meet the above
requirements will be rejected. All phases of field trail work shall be
performed in the presence of the Engineer.
- Workmanship;
- Preparation;
Any seepage water emerging locally shall be dealt with by local sealing
with drainage measures.
- Application;
After the specified preparation has been carried out and immediately
04100 - 22
before shotcreting, the surface shall, where required, be thoroughly
cleaned and wetted with a strong blast of air and water. Application
shall commence at the bottom of vertical and near vertical surface and
each layer of shotcrete shall be built up by marking several passes of
the nozzle over the working area.
The distance of the nozzle from the work shall be between 600 mm and
1,500 mm and the nozzle shall generally be held perpendicular to the
application surface. The shotcrete shall emerge from the nozzle in a
steady uninterrupted flow. When the flow becomes intermittent from
any cause, the nozzle operator shall direct it away from the work until it
again become uniform.
All rebound and other loose material shall be removed by air jets or
approved means from the surface of each layer as work proceeds.
04100 - 23
A proportion of shotcrete will be rebound. Such rebound shotcrete
shall not be reused but shall be removed to disposal at the expense of
the Contractor. All rebound shotcrete shall be removed from the Works
and disposed of by the Contractor as part of the work under this
Clause.
- Repair;
The Contractor shall submit his procedure for the fixing of steel wire mesh
for approval prior to beginning of installation. Short bolt (surface anchors),
rock pins driven into joints or shotcrete onto a previous layer, shoot-in
studs, or any combination of these means are acceptable provided the
steel wire mesh closely follows the geometry of the excavation. Under no
circumstances shall space between the underlying surface and the steel
wire mesh is more than 15 cm.
The Contractor shall furnish and place steel wire mesh on the surface of
underground excavation in conjunction with the installation of rock bolts or
steel supports. Steel wire mesh shall be properly placed and anchored to
prevent possible rock falls. A minimum overlap of 15 cm shall be used at
joints.
5. Steel Support:
- General;
Permanent steel supports completed with all bolts, tie rods, footplates
and other accessories required for assembly of the supports and
supporting them in place until the lining concrete is placed.
04100 - 24
permanent work shall be removed unless such removal is determined
impracticable by the Engineer.
Type and size of the steel supports, its miscellaneous details, location
and spacing shall be submitted to the Engineer for his approval. The
clear distance between the flanges of the installed supports shall not be
less than 30 cm unless otherwise approved by the Engineer.
- Installation;
The steel support shall be installed to the proper lines and grades and
shall be maintained by the Contractor in the proper condition and
alignment until the lining concrete is placed about them. The Contractor
shall securely brace the supports with tie rods, and shall use the
minimum practicable amount of timber blocking and wedges between
the steel arch supports and the rock. Any steel supports installed
improperly or damaged by the Contractors operation shall be adjusted
or repaired or replaced to the satisfaction of the Engineer within 24
hours after notification by the Engineer.
- Steel Lagging;
The lagging shall be placed between the flanges of steel supports and
fixed in position by wedging off of the front flange of the steel support
using hardwood timber wedges. The space between the lagging and
the excavated profile may be filled with concrete or discrete timber
packing.
- Temporary Support;
04100 - 25
Temporary timber or steel supports including bracing shall be provided
where necessary until permanent steel arch support is installed, and
also for support of temporary excavations such as tunnel drifts, and as
may be otherwise required for construction purposes. Supports that
are not required to remain in place can safely be removed, may be
removed subject to the direction or agreement of the Engineer.
Support in good condition may be reused. Suitable temporary timber,
may be used to support the crown and side walls of the concrete lining,
is placed and every precaution shall be exercised as to timing and
extent of removal to prevent accidents.
- Tunnel Markers;
Placing of concrete for lining of the tunnel and refuge niches shall be carried
out using sets of travelling steel form. The number and length of the steel form
elements will be determined by the required daily progress and the minimum
formwork stripping time.
Stripping shall not be permitted until the concrete has reached at least 2.0
Mpa cylinder compressive strength and not less than eighteen (18) hours or
as approved by the Engineer after the completion of concreting of that
element.
Equipment for concrete transport and placing shall be of such a design and
capacity as to guarantee the continuous poring of the lining. The placing
system shall provide the optimum filling of the arch vertex.
Placing of lining concrete shall be carried out after waterproofing has been
installed.
04100 - 26
The method of concreting shall be approved by the Engineer. Concrete shall
be consolidated by immersion vibrators.
Concreting wok for roadbed concrete, centre passage, cable box and portal
walls shall be carried out complying with the requirements as specified in
Section 03001 Concrete. The dimensions of concrete shall be as shown on
the drawings.
There are two types of refugee niches: medium and small types. The refuge
niches shall be constructed at both sides of a tunnel as the staggered
arrangement. The small-type refuge niches shall be constructed at the
interval of 20 meters from the other tunnel side. While the medium-type
refuge niches shall be constructed at the interval of 100 meters from the other
tunnel side. The size, shape and location of refuge niches shall be
constructed as shown in the Drawings.
Repair: Concrete with wide cracks shall be repaired by the Contractor without
additional cost to the Employer. The Contractor shall prepare and submit the
drawings of cracks with their length and width, and their repair method to the
Engineer for approval. Any remedial measures directed by the Engineer to
correct concrete cracks shall be at the expense of the Contractor.
3.01.4 Waterproofing:
1. Surface Treatment:
Except for nuts, all heads of rock bolt shall be trimmed and covered with
mortar or thick felt material.
2. Installation:
04100 - 27
1. Centre Drainage and Cross Drainage;
3. Drainage Pit
- Construction Joints
- Contraction/Expansion joints
5. Formwork
04100 - 28
left for the periods not less than the following times or as approved by the
Engineer.
Lining Concrete 15 hours
Invert Concrete 12 hours
- END OF SECTION
04100 - 29