McNally Bharat Engineering Co Ltd

C/o Bhavnagar Energy Company Limited


2x250 MW LIGNITE BASED TPP AT PADVA, BHAVNAGAR
Structural Steel Works - Daily Progress Report

Progress Date: 30.1.17

Today's Total
Description

Previous
Sr. No.

UOM
Work

Scope (Approx.)

1 Materials Received at Site TOTAL PRE FABRICATED STRUCTURE


2 Erection 1050 MT 4.00 930.21
4 Alignment 1050 MT 2.00 759.72
5 Final welding 1050 MT 0.00 644.00
6 Final paint 1050 MT
Status of erection Status of alig
Sr.No. Mark No. Qty. unit Wt. (MT) total wt(KG) Sr.No
R

Reporting Date 31. 1.17


Total Cumm.

This Month
(.Jan 2016)
(31.12.16)

Remarks
Previous
Month
Upto

TRUCTURE
934.21 850.00 84.21
761.72 678.00 83.72
644.00 644.00 0.00

Status of alignment
Item Description Qty. Wt.(MT)