Académique Documents
Professionnel Documents
Culture Documents
doi: 10.1680/cien.2010.163.6.33
Keywords
composite structures;
dynamics; fatigue
The structural
design of Almas
Tower, Dubai, UAE
Ranjith Chandunni
MTech
The Almas Tower is a 360 m high office tower in Dubai, UAE.
is a senior structural engineer and
associate at WS Atkins in Dubai The design comprises two intersecting elliptical towers located
on a sculpted three-storey podium. The architectural form and
clients requirement for floor efficiencies of 80% resulted in
significant challenges for the structural design team. This paper
discusses the structural framing adopted, wind-tunnel studies
undertaken including building acceleration, lateral movements
and column-shortening effects and mitigation measures
introduced. It also describes the design of the towers spire, which
Farshad Berahman
PhD
features tuned mass dampers.
is a senior structural engineer at WS
Atkins in Dubai
0 m 20
Figure 2. Typical structural floor plan up to level +232 m showing hollow core slab supported on external
beams to core walls and internal beams
which are connected to each other by with the roof to the plant floors being
central spine beams on each floor and a 400 mm thick solid reinforced con-
outrigger walls at service floor levels. crete slab (except the top plant floor) to
A parametric study of the effective- provide an acoustic barrier to the floor
ness of different arrangements of the immediately above.
external frame, belt walls and outrigger The building was designed to British
walls was carried out and the findings standards, while UBC-97 (ICBO, 1997)
are shown in Table 1. was used for seismic load assessment in
The peripheral frame consists of accordance with local authority require-
1000mm deep, 500 mm wide beams ments. The concrete grades range from 45
supporting precast units which span onto to 70 MPa cube strength with a reinforce-
peripheral columns. The columns are ment grade 460 (fy = 460 MPa) and struc-
at a maximum spacing of 5 m and form tural steelwork S355 (fy = 355 MPa).
part of the lateral load resisting system.
The columns are designed compositely Finite-element modelling
in the lower half of the building to keep
the column sizes small compared to what A three-dimensional finite-element
Figure 1. The 360 m high Almas Tower in Dubai, would be needed for a reinforced con- model of the tower and podium was
UAE was completed in 2008 crete column alone (Figure 3). generated in Etabs (CSI, 2005), which
A typical floor slab consists of included the raft slab on spring supports
1100 320mm thick hollow-core precast pan- to simulate the piles although the raft
els with 80 mm thick structural topping. weight was not considered for the pur-
It ties the external frame to the central pose of assessing the seismic base shear.
reinforced concrete core walls or central An allowance was made in the section
spine beam. The floor is also designed properties for cracking under ultimate
to act as a diaphragm, transferring later- limit state according to UBC-97 and it
al wind and seismic forces to the central was assumed that all loads would be
core and external frame. The precast transferred to the ground through the
slab option was chosen because of pro- piles.
gramme benefits: they are comparatively The spring stiffness for the piles was
lightweight and provide uninterrupted based on the pile working load capacity
356 x 406 UC 634 space for services. and the theoretical settlement of the pile
Vertical Reinf: 24T32
The plant floors at levels 42, 121, 212 under that load, which was taken from
Figure 3. Cross section through a typical and 279 m above ground are 450 mm the geotechnical assessment. The effect
composite column (dimensions in mm) thick solid reinforced concrete slabs, of the podium on the lateral movement
Delivered by ICEVirtualLibrary.com to:
34 ProCeedings of the Institution of Civil Engineers CIVIL ENGINEERING, 2010, 163, No. CE6
IP: 86.96.227.93 issn 0965 089 X
On: Mon, 22 Nov 2010 04:40:42
The structural design of
Almas Tower, Dubai, UAE
1000
Core wall
1400
2700
7850
Belt wall Core
wall
2500
2350
Belt wall Service
floor
for cracked walls and 0.35 for beams. realistic and required further investigation. 35% higher than the codified values and
Ductile detailing for the coupling beams Furthermore, the analysis model does not the compressive strength of concrete was
using diagonal reinforcement was speci- take into account the fact that about 10% higher than design strength.
fied according to UBC-97, although this Considering these factors, the long-term
is not required for zone 2A. n all floors are cast horizontally at the deflection at completion of the last floor
level shown on the design drawings, was estimated as 189 mm (H/1470) at
Foundation system thereby reducing the differential short- level +279 m and 126 mm (H/1900) at
ening calculated in the analysis model level +236 m. These values are well with-
The foundation for the tower is a 3m n vertical elements are built plumb in the acceptable range of H/1000.
thick piled raft supported on 1200 mm with reference to a fixed benchmark Although the analysis indicated that in
diameter friction piles, which are approxi- at ground level, thereby reducing the theory the sway would be within accept-
mately 40 m long. To mitigate the effect sway calculated in the analysis model able limits, the contractor monitored the
of the heat of hydration, 50% of the raft n effects of time-dependent factors such verticality of the building during construc-
cement was replaced with ground granu- as creep, shrinkage and age of concrete tion and made adjustments to account
lated blastfurnace slag (ggbs). Appropriate n modulus of elasticity achieved for for this sway by casting floors level to the
concrete cover was provided for the foun- concrete is usually 30% higher than ground benchmark. Adjustments were
dation and perimeter retaining walls to codified values relatively small for the lower symmetrical
achieve the intended building design life. n compressive strength of concrete part and relatively large for the upper
The columns and walls in the podium achieved is normally 10% higher asymmetrical part of the building.
area are supported by slabs spanning than specified values. Lateral sway recorded on site imme-
between pile caps and, to reduce the diately upon completion of the last floor
slab thickness, tension piles are designed Long-term dead load sway was 55 mm (H/5070) at level +279 m
to resist uplift in the podium basement Whereas a long-term dead load sway and 53 mm (H/4450) at level +236 m.
caused by the high water table. of H/1000 would be deemed acceptable, The procedure demonstrated that with
further assessments were carried out to simple compensation techniques on site,
Vertical asymmetry get a better estimate of the anticipated lateral dead load sway can be controlled
gravity load sway. to a large extent. Other factors such as
The tower has an inbuilt vertical The following procedure was under- stiffening effects of internal block wall
asymmetry due to one part of the tower taken to estimate dead load sway of the partitions and faade elements might have
extending 12 floors above the other building. also contributed to the reduction in sway.
while connected to one core throughout Sway analysis was carried out using a
the height of the building. It was realised full model of the building, with construc- Long term axial deformation and
early on in the design that there could tion sequence analysis performed from differential shortening
be lateral movement in the building that levels +236 m to +279 m. The instanta- As with all tall buildings, it was nec-
would be in excess of sways in a conven- neous dead load sway was 150 mm at essary to estimate the long-term axial
tional, symmetrically loaded building. +236m and 225 mm at the uppermost deformation (see Figure 7) and the dif-
Building movement monitoring was floor (+279 m). ferential shortening between the core
included in the specification to allow the The effect of time-dependent creep and the columns (see Figure 8). This
structural designers to compare actual was allowed for by a reduction in the deformation has an impact on the design
movements with those estimated. This effective elastic modulus. Calculations of connecting elements and also requires
required survey points at each floor, were carried out based on the principle adjustments while casting the floors to
which were monitored by laser surveying of area moment to work out a multiplier ensure that the floors are horizontal.
instruments (Leica TPS700) for lateral on lateral movement. This resulted in a Two approaches were considered one
drift against a fixed benchmark located net increase of 110% on the calculated using the Eurocode 2 (BSI, 2004) and
at ground level outside the building. value of lateral movement due to load another using the American Concrete
Further points were located at the core from level +236 m and above. Institute 209 (ACI Committee 209,
and periphery of each floor to monitor In applying a creep coefficient of 1.1, 1997) model.
movement due to axial shortening. long-term deflections were found to be The Eurocode method does not take
The results from the three-dimensional 472 mm (H/590) at level +279 m and into account the relaxation of creep
analysis model indicated that the horizon- 315 mm (H/750) at level +236 m. due to the presence of reinforcement,
tal gravity load sway would be of the order As a result of the calculated long-term whereas the ACI model does. This was a
of 225 mm (short term) at the uppermost sway values based on codified material significant factor in this building consid-
floor level. This value is an overestimate properties, the core walls in the taller ering that the columns were composite
as the model assumes the structure is portion of the building were thickened. and contained significant amounts of
built and then all loads are applied instan- The actual material test results from reinforcement and that the walls were
taneously a phenomenon known as site demonstrated that the values of heavily reinforced at lower levels.
switch-on gravity which is obviously not modulus of elasticity used were about It was therefore decided to use the ACI
Delivered by ICEVirtualLibrary.com to:
36 ProCeedings of the Institution of Civil Engineers CIVIL ENGINEERING, 2010, 163, No. CE6
IP: 86.96.227.93 issn 0965 089 X
On: Mon, 22 Nov 2010 04:40:42
The structural design of
Almas Tower, Dubai, UAE
60 60
40 40
Stories
Storey
30 30
20 20
10 10
0 0
0 20 40 60 80 100 120 140 0 20 40 60 80 100 120 140 160 180
Shortening: mm Settlement: mm
Figure 7. Long-term settlement curve for elastic shortening, creep and Figure 8. Settlement of a typical tower column (TC-3) and the core wall as well
shrinkage as well as the total shortening of a typical column as the differential settlement between the two typical column and core
method for the assessment. A computer 25mm either way in the 200 mm struc- diamond. The podium comprises an array
program was developed based on the tural depth allowance for cladding fixing. of eight triangular glass petals that radiate
procedure outlined in the ACI as well as from the central core (Figure 9). The dia-
that presented by the Portland Cement Podium mond exchange is accommodated within
Association (Fintel et al., 1987). the north-eastern petal that juts out over a
The program assessed the long-term The design of the podium was inspired terraced water feature stepping down to a
axial shortening of columns and walls by the inherent angular geometry of a lake. The three-storey podium accommo-
by considering elastic shortening, creep,
shrinkage and by allowing for the fact that 0 m 40
floors would be cast levelled to the position
indicated on the drawings. The calculation
was carried out for the core walls and col-
umns and the difference was allowed for in
the construction of the floors between the
cores and the columns. A typical difference
between the core walls and one column is
shown in Figure 8.
Cladding
The building faade consists of a
unitised cladding and curtain walling
system, which is manufactured incorpo-
rating aluminium, glass and insulation as
a complete module.
The vertical spacing was based on a
floor-to-floor height of 4 m while the
horizontal spacing was based on a com-
bination of the structural grid and the
widths of offices to achieve a maximum
number of vision bays.
A 10 mm gap was provided between
each panel for thermal and seismic move-
ment as well as the long-term movement
of the concrete frame due to creep and
shrinkage. The full depth of the mul-
lions, including the glazing or cladding Figure 9. Plan view of podium the largest of eight triangular-shaped petals radiating from the central core
is 150 mm, which left a tolerance of accommodates a diamond exchange centre
Mode shape