Académique Documents
Professionnel Documents
Culture Documents
Scholars' Mine
International Conference on Case Histories in (2004) - Fifth International Conference on Case
Geotechnical Engineering Histories in Geotechnical Engineering
K. Gwizdaa
Gdansk University of Technology, Gdansk, Poland
A. Sabek
Gdansk University of Technology, Gdansk, Poland
Recommended Citation
Tejchman, A.; Gwizdaa, K.; and Sabek, A., "Investigations of Settlement of Piled Raft Foundation" (2004). International Conference on
Case Histories in Geotechnical Engineering. 33.
http://scholarsmine.mst.edu/icchge/5icchge/session01/33
This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International
Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright
Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact
scholarsmine@mst.edu.
INVESTIGATIONS OF SETTLEMENT OF PILED RAFT FOUNDATION
Prof. A. Tejchman Prof. K. Gwizdaa MSc. Eng. A. Sabek
Gdansk University of Technology Gdansk University of Technology Gdansk University of Technology
Gdansk, Poland Gdansk, Poland Gdansk, Poland
ABSTRACT
On the Tychy Brewery site a set of 6 tanks of the diameter varying from 5.4 m to 17 m was designed. The tanks are elements of Sewage
Treatment Plant. Due to unfavourable soil conditions (plastic clay) the tanks were founded on 15 m long CFA piles with the diameter of 400 and
600 mm. In order to save construction costs piled raft foundation system was proposed. Based on the analysis and respective calculations it was
assumed that raft foundations, founded of gravel fill under each tank, would bear up to 20 % to 30% of total load. The assumption allowed
shortening of all piles about 3 m minimum. The loading test of 3 piles showed that approximately 80 % of total load is transferred by piles into
the subsoil. In order to confirm the assumptions assumed and to measure real settlement of tanks, loading tests of all tanks were carried out by
means of its gradual water filling. The comparison of the results of tank settlement measurements and respective calculations showed good
agreement between calculated and measured values. The latter did not exceed permissible settlements assumed for this type of constructions and
installations. In the paper soil conditions, calculations, solution of tanks foundation, field tests and results obtained are described.
Fig. 2a Averaged soil profile of the subsoil near tanks No. 2 and 6
Paper No 1.51 2
Fig. 2b CPT test resuls.
account piles spacing grid, (Fig. 5 ). In order to model the
The slab-soil interaction was taken into account by designing the response of piles for such foundation the elastic supports with Kzp
piles for lower safety factors what resulted in 3 m decrease of the rigidity in the grid nodes are assumed whereas the areas between
pile length with respect to the foundation on the pile group without piles are modelled by elastic subsoil with kzg rigidity. Such static
contribution of the slab. scheme is to simulate the interaction between slab, piles and the
Such assumption is with accordance to the design of piled raft subsoil.
foundations based on creep piling concept, (Randolph, 1994), in
which the piles are designed for working loads at which, in turn,
pile creeping initiates what mostly corresponds to 70% 80% of
ultimate bearing capacity. The rest of load is transmitted by the slab
on the soil between piles. The correctness of the assumption was
confirmed by the results of load tests carried out on 600 piles
under structures Nos. 2 and 6, see Fig. 4. The bearing capacities
obtained from load tests are equal to 60%70% of its calculated
ultimate bearing capacity. The rest of the load was planned to be
transmitted by the slab through the contact with the subsoil
between piles.
The appropriate soil-slab interaction was achieved in terms of
dolomite key aggregate layer which was put after removal of the
tops of piles to the designed foundation layer.
Paper No 1.51 3
Load Q [kN] Basic calculation problem in this case are characteristics of elastic
piling and subsoil supports, Kzp and kzp, respectively. Pile axial
0 200 400 600 800 1000 1200
0
rigidity for piles in the group can be determined based on the
calculations of piles in terms of either the influence coefficients
2
method (Poulos and Davis, 1980), Gwizdaa and Dyka (2002) or
4 one of the theoretical approaches e.g. Chow, (1986). The axial
6 rigidity of piling support can be calculated from the following
8
formula:
Q pi
10 K zp = , (1)
s pi
12
14
where:
Qpi load of i-th pile,
16
spi settlement of i-th pile in the group.
18
Struct. No 2, CFA
20 tested pile, No 21,
The correction of the calculations or calibration of the parameters
22
D=600mm, L = 10,0 m assumed by back-analysis can be made using the results of load
tests.
24 Struct. No 6, CFA Axial rigidity of the subsoil between piles can be also determined
tested pile, No 37,
26
D=600 mm, L = 12,0 m based on the calculation of subsoil settlements induced by loads
28 Structure No 2 - Np=610 kN;
from shallow flexible foundation, according to the formula:
Ng=940 kN q gj
30
Structure No 6 - Np=720kN; k zg = , (2)
32 Ng=1030 kN s gj
34 where:
36 qj load applied for j-th elementary foundation,
Settlement S [mm]
Paper No 1.51 4
Fig. 6 Calculation algorithm for the analysis of piled raft foundation
Slab rigidity, which partially compensates the settlements of piles differentiated due to non-uniform settlement of the elementary
what results in the change of the rigidity of elastic supports, is foundations (side foundation elements settle less than those located
included in the static calculations of the slab with piles on elastic near the middle of the slab).
subsoil. Having the results of static load tests the correction of the The results of calculations have been presented in terms of the
flexibility of elastic supports corresponding to real soil conditions distributions of pile forces, internal forces in the foundation slab
can be made. The load test results for two piles were included in (bending moments and shear forces) as well as displacements of
the calculations of whole foundations in the FEM numerical code. piles and slab. Calculated total settlements for slabs are shown in
Rigidity of the subsoil between piles was determined based on Figs. 7 and 8. Calculated values were next compared to the
the settlements of shallow foundation, according to Eq. (2). measured settlements of the foundations.
According to the Polish Standard, the settlements of the subsoil Besides calculated quantities described above, the distribution of
were calculated in terms of classical, one-dimensional method for forces between piles and slab was also assessed. Although, the
irregular system of layers and total thickness H = Zmax. Due to high distribution can not be directly compared with the measurements,
ratio of slab diameter to its thickness (13 m and 17 m to 0.5 m) however allows the verification of the assumptions. The percentage
flexible foundation slabs have been assumed. The foundations of contribution of piles and slab in the transmission of loads into the
structures Nos. 2 and 6 were divided into 45 and 69 elements, subsoil for structures analysed is schematically presented in Fig. 9.
respectively. In the division process such factors as slab geometry, In both cases essential part of loads (78% and 65% for structures
localisation and magnitude of loads and soil conditions were Nos. 2 and 6, respectively) are transmitted by piles. Somewhat
considered. The soil elastic constant kzg was calculated for uniform larger load comparing to the assumed value is transmitted by the
load q = 30 kPa what corresponds to 20% of total load acting on slab in structure No. 6 (35%, approximately). Larger contribution
the foundation. The rigidities of pile and soil supports were of the slab caused smaller forces acting on piles but larger internal
forces in the slab, itself. Average load on single pile decreased
Paper No 1.51 5
around 10%. Assumed division of loads enabled to properly 3, 4, 5 and 6 as well in the cap of the structure No. 1. Totally, 40
determine the distribution of moments in the foundation slabs and benchmarks were being observed. Each monitored foundation slab
in turn safe design of its reinforcement. contained 6 benchmarks evenly distributed along its perimeter.
-contribution of piles
Structure - contribution of
No 6 65 %
foundation slab
35 %
Structure 78 %
No 2
22 %
0 10 20 30 40 50 60 70 80 90 100
load [%]
Averaged
Averaged
settlement
No. Period of settlement for
after
of structure observations maximum load
unloading
in [mm]
in [mm]
2 29.1113.12.02 15.8 13.3
3 13-23.12.02 26.0
4 22-29.11.02 4.5 4.0
5 9-20.11.02 38.8 37.5
6 28.0106.02.03 13.0 10.0
Paper No 1.51 6
steps which corresponded to gradual filling of the tanks with water SUMMARY
what enabled the comparison of observed and calculated
displacements for whole range of loads applied. The comparison
The procedure of the assessment of settlements for piling
for two foundations slabs is presented in Figs. 10 and 11,
foundations, which takes into account the interaction between piles,
respectively.
piling cap and the subsoil is presented. The procedure is based on
It can be seen that measured and calculated final settlements do not
the easily accessible numerical codes for static spatial analysis of
differ too much. Somewhat greater differences are observed in the
the constructions. The comparison of observed and calculated
initial loading stage what most likely results from the fact that the
values of settlements in terms of described method is satisfactory.
benchmarks have been installed after execution of foundation slab
The method enables the determination of internal forces as well as
(structure No. 6) and from partial assembling of the tank (structure
takes into account non-uniformity of the settlements of both: piles
No. 2). Other factor influencing calculated settlements is strain
working in the group and the subsoil. Such non-uniformity may
modulus which has been assumed as constant value whereas it is
cause essential increase of bending moments and internal stresses
load dependent. Such dependence will be included in next
in the foundation slab. The disadvantage of the method is relatively
calculation series. Largest calculated settlements, which occurred
large amount of work for data preparation as well as two different
in the middle part of foundation slab varied from 18 to 20 mm and
numerical codes assumed for the determination of the pile and
from 20 to 24.6 mm for structures Nos. 2 and 6, respectively.
subsoil rigidities.
15
REFERENCES
load x 10 [%]
10
1. Chow, Y. K. (1986): Analysis of Vertically Loaded Pile
5
Groups. International Journal for Numerical and Analytical
time [h]
0
Methods in Geomechanics, Vol. 10, p. 59-72.
0 50 100 150 200 250 300 350 2. Gwizdaa, K. (1997): Polish design methods for single
-5
axially loaded piles. Design of Axially Loaded Piles
-10 European Practice, De Cook & Legroud, Balkema,
Rotterdam,, p. 291-306.
settlement [mm]
-15
3. Gwizdaa, K., Dyka, I. (2002): Estimation of settlements of
-20 piles in group. Proc. International Conf. on Deep
Foundation. Nicea, p. 257-262.
-25
10
5
6. Tejchman, A., Krasi ski, A., Sabek, A. (2002): A proposal
of calculation of piled raft foundations. Proc. International
time [h]
0 Conf. on Deep Foundation. Nicea, p. 287-291.
0 20 40 60 80 100 120 140 160 180 200 220 240
-5 7. Polish Piling Code PN-83/B-02482. Building foundations.
Bearing capacity of piles and pile foundations.
-10
settlement [mm]
-15
-20
-25
Paper No 1.51 7