Class rules principally concerned with strength and structural integrity of the
ship, the provision of adequate equipment and reliability of the machinery.
(SOLAS; Load line and tonnage)
In making Rules for vessels, classification societies generally have to:
Certification
Certificate of Class issued after survey and valid for 5 years. Existing ships
surveyed and assigned class provided it meets rules regarding scantling,
material, workmanship and conditions.
To retain vessel in class (Maintenance of class) : annual survey; docking survey;
intermediate survey (hull, cargo holds, ballast tanks); tail shaft; boiler;
machinery; (conditions of hull and machinery, equipment and appliances meet
rules) special survey; occasional surveys if any damage to hull, machinery or
equipment affecting sea worthiness; any repairs or alterations.
Class society works closely with ship owner to set up an inspection program that
integrates class requirements with owners PMS. This helps reduce scope of
periodical surveys like the Hull PMS.
Survey cycle
1st annual survey = COC+12 months (+/- 3 months); 2nd annual survey =
COC+24 months (+/- 3 months)
3rd annual survey = COC+36 months (+/- 3 months); 2nd or 3rd annual survey
= intermediate survey
4th annual survey = COC+48 months (+/- 3 months); 5th annual survey =
COC+60 months (-3 months)
* The class society can only allow the + 3 months window at the 5th annual
survey if it is due to non-commercial reasons (e.g. waiting for spare parts for
dock related repairs).
Condition of class
If anything not complying, CoC imposed, 3 months time given to resurvey and
get accredited. CoC has to be deleted to comply with maintenance of class.
The vessel is safe for intended passage until the next port for further repair and
examination.
Renewal of certificates
Every 5 years - Issued to a classed vessel. This is issued by a classification
society surveyor. Enables the vessel to proceed to voyage when as per surveyor:
Chief Engineers are approved to perform surveys on behalf of the class society.
He may only survey items of machinery and only those items agreed with the
class society. The class surveyor will verify the Chief Engineers surveys when he
is on-board for annual survey or for any other survey.
(f) Shafting:
Intermediate shafts.
(e) Shafting:
Screw-shafts.
Stern bearings
(f) Propellers:
Complete unit.
Under special circumstances, tanks may be inspected by the C/E if the class has
agreed and it is a part of the approved PMS.
Surveys
Annual Survey (Classification)
SURVEY: Examination, testing and evaluation of results and decision making.
Annual survey
Some certificates; the class society may want to survey, for example, at least
one of the main bearings on the main engine every year; most of the machinery
equipment can be surveyed by the Chief
Engineer but the class surveyor needs to verify it; equipment such as
air/pressure vessels should only be surveyed by the class surveyor; the class
records are checked by a surveyor every year.
Structure and propulsion machinery and equipment
Hull plating and its closing appliances as far as can be seen; examination of
watertight penetrations
Hatch cover and coamings covers, coamings, sealing and securing devices:
compression bars, gaskets, drainage channels, gasket lips, retaining bars, cleats,
clamps, chain or pulley ropes, guides, guide rails and track wheels, stoppers,
wires, chains, tensioning devices, hydraulic systems for closing and securing.
Intermediate Survey
The content of the intermediate survey is more or less the same as a regular
annual survey.
If the vessel is approved for five-year docking intervals, this bottom survey can
be performed as an underwater examination or In the Water Survey.
If the vessel is not approved for five-year docking intervals, the vessel has to go
into dry dock.
Cargo holds Overall survey of all holds (shell frame, brackets, transverse
bulkhead of forward cargo hold suspect areas close up)
In water survey requires following satisfying conditions: Size (beam) of the ship;
High resistance paint; In water visibility; suitable draft; Clean hull; Good
communications between the diver and the surveyor; Done by a recognized firm;
Personnel involved are competent.
Normally, the special survey is started 48 months after the Certificate of Class
date (12 months before the end of the five-year class period). But sometimes
there is good reason to complete the special survey before this date (60 months
after the Certificate of Class date).
One reason could be that the vessel has to go into dry dock before schedule due
to damage to the vessel or a major repair.
Cargo holds, SW ballast tanks, DB tanks, pipe tunnel, cofferdams, void spaces
bounding cargo hold, decks and outer hull examined and thickness measured
and tested.
Tank testing ballast tank and cargo holds water level to top of hatches; ballast
fuel tanks water level to top of air pipes
NOTE: The special survey may not start without the approval of the technical
managers.
3rd and 4th special surveys very stringent gauging of plates etc.
The requirements set forth in SOLAS has been put into twelve (12) chapters.
MARPOL
The first international convention for the prevention of pollution of the sea by oil
was adopted in 1954 and this was called the OILPOL, 1954. It was amended
many times before the IMO adopted
MARPOL 73 came into being. This covered all aspects of marine pollution then,
but did not take into consideration accidental pollution. The protocol of 1978
incorporated that (as a result of increased tanker accidents) and so included
provisions to tanker design and operation. Protocol 1 introduced the duty to
report a pollution incident (which has a direct impact on the seafarer) and
protocol 2 dealt with arbitration on dispute (which of course does not have a
direct impact on the seafarer).This was then called the International
Convention for the Prevention of Marine Pollution from Ships, 1973, as
modified by the Protocol of 1978 relating thereto (MARPOL 73/78), and it
entered into force on 2
October 1983 (Annexes I and II).
There are six annexes which cover the various regulations and they are
There are special areas designated where certain operations are restricted.
Special areas are applicable to Annex 1, Annex 2 and Annex 5 and they are
different for each.
To meet the above requirements surveys are conducted and certificates issued
when found satisfactory.
Load Line
The purpose of load line convention adopted in 1966 was to assign a freeboard
for every vessel which is indicated by load line markings on the vessels hull on
either sides. The fundamental aim of the load line convention can be mentioned
as to have the vessels hull water-tight below the freeboard deck and
weather-tight above the freeboard deck. So, the watertight integrity (closing
appliances, protection of openings in hull and super structure); protection of the
crew (deck house, guard rails etc.) are to be ensured. The provision of a
freeboard ensures reserve buoyancy to the vessel. Intact (stability in the normal
loaded condition) and damage stability conditions (ability to remain afloat
without capsizing during and after flooding due to a breach of hull) are taken into
consideration.
The areas that are of importance and those engineers need to maintain are:
Weather tight Doors
Scuttles &Windows
Access Hatches
Man Holes
Air and sounding pipes
Ventilators
Bulwarks, Guardrails and life lines
Freeing ports
Scuppers& Discharges
Cargo Hatch covers and coamings
Spurling pipe of Chain locker
ISM CODE
This is a very important part of the SOLAS convention. SOLAS requirement
Chapter IX -
Management for the safe operation of ships. It came into force from 1998 for
tankers and passenger ships, 2002 for other ships.
The purpose of this Code is to provide an international standard for the safe
management and operation of ships and for pollution prevention.
The objectives of the Code are to ensure safety at sea, prevention of human
injury or loss of life, and avoidance of damage to the environment, in particular
to the marine environment and to property.
For implementation of the ISM Code, Every Company has to develop, implement
and maintain a Safety Management System such that it should meet
the following objectives:
Dry- Docking
Dry docking of ships is done to carry out major repairs, surveys, conversions, and
modifications by taking the ship out of water.
Pre-planning
The planning for the ship's dry dock starts as soon as the ship comes out of sea
trials of the previous dry dock. Each department i.e. engine and deck will have its
own dry dock specification files, which will include all major and minor defects
that cannot be repaired while the ship is sailing at sea.
Every time a ship comes out of dry dock, a new dry dock specification file is
made. Most of the shipping companies use different software tools, which include
details on defect lists, expiry dates of certificates, and other major
maintenance/repair jobs that are due or require support which can be provided
only when the ship is in dry dock (for Eg. stern tube bearing inspection,
overboard valves and hull survey, anode renewal, major de-carb of main engine
etc.).
Planning for dry dock includes listing of jobs that need to be carried out in the
scheduled dry-docking period. The selection of the dry docking place is done by a
company representative, followed by visiting the dry dock and arranging for the
necessary manpower and repairing workshops.
All these jobs are identified before-hand and analysed for the requirement of
spares, tools and expertise. Pre-planning of the dry dock is extremely important,
as accordingly, arrangements for the planned jobs are made by the company's
superintendent and technical department.
The ships crew will start planning by making a list of all the jobs that are
supposed to be carried out in the dry dock. A general plan of the ships crew
would involve:
All major defects listed in the dry dock specification file
All scheduled maintenance tasks of the main engine and related systems,
which cannot be performed at sea are noted in the dry dock specifications
file
All scheduled maintenance and repairs for auxiliary machinery (Diesel
Generator, Boiler, Compressors, and Fresh Water Generator etc.) and
related parts which cannot be performed during voyage are noted in the
specifications file.
All rusted pipe fittings, including temporarily repaired sea water and fresh
water pipes, which cannot be repaired by the ship's staff are listed in the
specifications file
Repair and maintenance jobs on condensers and heat exchangers are
noted
Repair and renewal jobs of valves (especially overboard valves) are noted
Maintenance, overhauling and repairs jobs of all engine room pumps are
noted
Maintenance and overhauling jobs of deck machinery systems are
included in the file
Maintenance and overhauling of electrical systems, including alternators,
main switchboard, emergency switchboard, ICCP, MGPS etc. is noted
A requisition is raised for the required spares of all machinery systems.
After consulting with the superintendent, it is decided which jobs will be
performed by the ship's staff and how much additional man power will be
required in the dry dock.
All the above mentioned points are noted in the dry dock specifications file and it
is then sent to the company.
Ship-Shore collaboration
Dry docking of a ship is a complicated task, which is handled by both - the ships
crew and the companys office staff.
Both the departments work in collaboration for planning a successful dry dock. A
general plan of the company office would require the representative to:
Ensure dry dock specification file is updated regularly by the ship's staff
Check the expiry dates of all the ship certificates and plans for surveys in
the dry dock
Check ship's Continuous Machinery Survey (CMS) program and arrange for
surveyors. Try to complete as many machinery surveys under CMS as
possible in the dry dock itself
Visit the ship once before planning a dry dock to discuss and check the
repairs to be performed with the chief engineer (C/E)
Produce a repair specification list generated from the dry dock
specifications file
Prepare technical specifications for ship modifications, dry docking, and
refit work
Monitor work with respect to dry dock schedule and budget, and manage
warranty claims when required
Once the repair specification is done, check the tentative budget allotted
for the dry dock
Decide the shipyard to be used for the dry docking of the ship
Plan the number of days for dry docking and the number of days for lay-up
before and after the dry dock
As per the allotted budget, do the tendering of jobs to various service
providers for receiving quotes
Ensure that enough spares and additional manpower is provided to the
ship's crew for the dry dock
Assemble and manage a team of engineers/specialists according to the
scope of the work to be carried out
Send all the collected quotes, jobs to be done, and days of off-hire/ service
to the owner or operator.
After reviewing the specifications sent by the ship's staff and superintendent, the
owner with consultation of the company's technical department, decides the best
option to carry out the dry docking of the ship.
Preparation
Once the planning of dry dock is completed, a ship would be given a tentative
date for arrival at the dry docking yard. Preparations for the dry dock start
several days or even weeks before the ship arrives at the dry dock.
Preparing a ship for the dry dock is as important as the planning process. The
first step towards preparing for dry dock is to establish an interface between the
company/ ship to be docked and the shore facilities that will perform repair and
maintenance jobs is the ship's engine room.
Safety
Ship becomes an extremely hazardous area during the dry dock period. The
chances of accidents and personal injury are extremely high as a result of slips/
falls, fire hazards, open machinery systems etc.
It is important for the ship's crew to ensure that safety is never compromised at
any level.
However, accidents still occur mainly because of negligence and errors. Consider
the following points for utmost level of safety during dry dock:
Preparing a ship for the dry dock is as important as the planning process. The
first step towards preparing for dry dock is to establish an interface between the
company/ ship to be docked and the shore facilities that will perform repair and
maintenance jobs is the ship's engine room.
As mentioned earlier, it is important to prepare the ship staff well in advance for
the dry dock. It is the responsibility of the Master and Chief Engineer of the ship
to ensure that their staff is ready for the big task. The following points are to be
considered during dry dock preparation:
Have a meeting with the ship staff staff to notify the schedule of lay-up
and dry dock
Put forward all the jobs to be performed by the ship's staff in the meeting
Allot various jobs to the engineers, ensuring the required manpower for
the jobs by giving them assisting hands
Divide the staff into groups to oversee the work carried out by the shore
staff
Calculate the quantity of lube oil present on-board before dry dock to
ensure that the amount is enough to do the complete oil renewal of
systems such as - Bow thruster system, Stern tube system, Main engine
system, Auxiliary engine system etc.
Consume the bunker oil according to the docking plan and ensure that
minimum bunker and water is carried on the ship
Chief engineer should ensure that all the tanks which are required to be
cleaned and inspected are stripped off water/oil and no more filling in the
tanks is instructed to the crew
Before lay up or dry dock, start ventilating fuel oil tanks so that gas levels
are below the entry limit
Clean and prepare empty drums (200 litres) to collect all the dirty soot,
sludge or bilge water that will be collected during dry dock
Clean and dry the bilge wells to prevent any kind of fire or accident as
plenty of hot work jobs will be performed in the dry dock
All engine room and related tanks for fuel oil, bilges, sludge, and water to
be sounded and recorded thoroughly before docking
Electrical preparation
During dry dock, shore electrical supply is provided to the ship as most of the
electrical machinery systems are isolated and different types of portable
machinery are used for repair and cleaning tasks. The safety and operational
aspects of the electrical systems must be ensured to complete the dry dock
without any delays or errors. Consider the following points:
Check the shore connection box provided on the ship and ensure that all
connections are functioning properly
Provide information to the office about the frequency and voltage supply
of the ship taking shore supply
Check all emergency lightings and emergency generators
Check and prepare enough number of extension boards as electrical
supply connections will be used in plenty
Ensure that enough number of hand lamps are available and all are in
working condition
Ensure that there are no naked lamps and also prepare for explosion proof
hand lamps and lightings
Arrange enough number of high power rating halogen lamps to ensure a
well-lit engine room
Check all portable blowers are in working condition as plenty of them will
be used especially for gas freeing and ventilation
Raise requisition if there is shortage of bulbs, tube lights and wirings
Ensure that all testing meters on-board ships are in good working
condition, including voltmeter, multimeter, clamp-meter etc.
Additional portable heaters/ fans to be ordered as ship's AC/ heater system
will be isolated for maintenance
Paper Work
With regards to the implementation of ISM code on board ships, it is very
important for engineers, officers and surveyors on ships to log down all the
events and prepare reports of each and every work carried out in the engine
room. This would require to:
Prepare a separate file for blank landing report, which will be filled and
signed by the chief engineer (C/E) and the shore in-charge when any
machinery or part from the ship is landed ashore for repairs or checks
Make a separate file to collect all the invoices of spares received during
dry dock
Make a separate log file to note down valve operations in the engine room.
Whenever anybody in the engine room operates a valve (opens or closes),
he/she should record it in this log file along with the date, time and current
position of the valve (open / close)
Prepare a separate Isolation log file to include the date, time and the
machinery isolated, so as to ensure that it is brought back to normal when
the dry dock is completed
A work-done file to be arranged for the dry dock, which is to be filled
with type of work and date of completion of each job
Keep all manuals readily available for important machinery and systems
which will be required by the ship's staff and shore people for reference
Make a separate set of photocopies of layouts, line diagrams, and systems
of all machinery as they will be required by the shore staff. This would
avoid losing or misplacing of the original diagrams
Previous dry dock reports to be kept ready for reference
Records of all the clearances of different machinery last measured (in last
dry dock or during repairs) to be kept available in separate files for ready
reference
A separate file with all kinds of work permit forms (blank) to be arranged
and kept ready
Manpower management in Dry-Dock
The key to a productive and accident-free dry docking is efficient manpower
management.
Different types of jobs require different number of people to successfully carry
them out.
When every task is provided with the right number of people, executing them not
only becomes easy but it also prevents time wastage and errors.
Efficient manpower management during dry dock also ensures that there is
proper work distribution among crew, allowing them to have sufficient rest hours
and preventing excessive workload.
Fire safety
Whenever there is welding, gas cutting, or any other type of hot-work carried out
in the engine room, a responsible crew member from the ship staff must be
placed to do the fire watch.
A dry dock safety supervisor (sometimes 2 in nos.) should always be present in
the engine room. It's also important to communicate with him/her prior to
starting the hot work for rechecking all the safety aspects related to the job.
Before any hot work is carried out, ensure that proper permit is taken from the
dry dock authorities in case the work is performed by the shore staff.
Take and follow ship's hot work permit if the job is to be carried out by the ship's
staff.
A fire watch is a must and should include arranging fire hoses and portable
extinguishers as per the location and job performed.
Also mark the nearest fire alarm call point and the escape route from the job
location.
Watch-keeping
Normally, before and after the dry dock, the ship is berthed in lay-off to do
additional maintenance and repair jobs as the cost of dry docking is extremely
high.
While the ship is in the lay-up berth, the power is generated by the ship's
generator and hence a normal watch keeping routine must be carried out
(Depending on UMS or Manned ship) at all times.
Even when the ship is in the dock, machinery such as reefer compressors are
always in running condition, and hence a responsible person should be assigned
to regularly check the operation of such machinery.
If there is any load shifting inside the engine room, which can lead to
change in stability, inform about it to the dock master
Go through the checklist again and the satisfactory checklist is to be
finally signed by the master
Master must sign the authority for flooding certificate
Once dry dock flooding is in process, a responsible engineer should go to
the bow thruster and steering gear room to check the water tightness if
any repair is performed on these machinery
When dock flooding reaches the overboard valve level, stop the process
and check valves and stern tube for leakages
Shore power cables will be removed once the cooling water is available for
suction in the generator system
If required, use emergency generator power before starting the main
generator
Instructions must be given to all crew members to stay vigilant while
undocking. They must continuously keep checking the water tightness of
the engine room throughout the process
If crew member finds any kind of water leakage in the engine room, same
must be informed immediately to the chief officer or department in-charge
as he/she will ask the dock master to stop flooding immediately
After the completion of the dry dock, the ship is re-floated and thorough sea
trials are carried out.
Sea Trials
Sea trial of the ship is done post-dry dock to ensure that all the major repair
works that were carried out on various systems, especially main engine,
generators, sea water system etc. are successful and there is no breakdown of
any machinery.
Another important reason for which sea trial is carried out is to check the water
tightness integrity of the ship.
In a sea trial, the ship staff along with the shore representatives do a complete
inspection of those machinery systems on which repair jobs were performed
during the dry dock.
Sea trial plays a very important role in discovering problems with the vessels
machinery and instrumentation systems.
The sea trial are done in open water, wherein all the machinery systems of the
ship are operated for a longer duration to ensure that no trouble is associated
with any of the repaired parts
It is the duty of the ship superintendent and the owner representative to ensure
that the contract with the shore workshop comes with a clause of sea trials,
which includes an expert professional, who represents the shore workshop and
makes sure that the ship and the owner representative are satisfied by the job
done.