Overview
• What’s Needed?
• Why Invest in Infrastructure?
• Capital Improvement Plan
• Financial Update
• Recommendation
3
Team
4
What’s Needed?
NEED ANNUAL CIP INVESTMENT OF $24-$40M
• Replace Failing Infrastructure
– Goal: 40 to 60 yr life
• Master Plan for Growth
• Water Supplies and Pipeline Capacity
• Water Reuse
• Operations and Maintenance
5
Importance of Water and Sewer
Infrastructure
6
Why Invest in Infrastructure?
Aging and Becoming Less Reliable
• Almost 1500 miles total
• Unlined Cast Iron
– 35 to 60 yrs old
– 140 miles
– Breaks easily
– Water quality issues
• Cement Pipe
– 28 to 40 yrs old
– 130 miles
– Breaks easily
• Concrete Sewers
– Corrosion failures 7
Water Infrastructure Grades
8
News Video
9
Water Infrastructure Problem
• “..out-of-sight, out-of-mind predicament”
• Failure examples:
• Dallas County Records Bldg
• Stemmons Freeway
• Los Angeles – 43 breaks in a month
$30
$20
$15.0 $15.1 $15.3
$14.0
$11.0 $11.0
$10 $8.0 $7.6
$6.7
$5.3 $5.6
$4.5 $4.4 $4.0
$3.4
$1.2
$0
12
Failing Pipe Impacts
• Pipe Breaks
– Cartwright St (55 yrs old), 12 repairs in 2 yrs
– Pennington St (46 yrs old), 9 repairs in 2 yrs
• Red Water
– Fowler St (54 yrs old)
– Marie Ln (55 yrs old)
• Sewer Overflows
• Impacts:
– Loss of service (frustration)
– Cost (overtime and repair)
– Regulatory
– Flushing
13
“Band Aid” Repairs-Britain 5/2/10
Three pipe failures
14
Water Supply Investment Needed
Princeton Pump Station
- Future Improvements
16
Finances
• System Fund needs to stand on its own
– Rates have to supply adequate revenue
– Avoid General Fund bailout as in 2007 ($4M)
• Water revenues down almost 9.8%
• Cash reserve projection down $3.6M
• Will not meet debt service coverage goals
• Bond ratings are at risk – higher rates
17
Costs Trending Up
• TCEQ Fees and Requirements up $500,000
• Water Treatment (Dallas)
– Last 4 years up $1.045M (18% Increase)
• Wastewater Treatment (TRA)
– Last 4 yrs up $3.975M (39% Increase)
• Development Costs (TXDOT, DART)
• Maintenance Costs
18
Public Communications
• Audit and Finance Committee
– 10/2009, 12/2009 and 5/2010
• Public Works Committee
– 10/2009
• City Council Work Session
– 10/21/2009, 12/2/2009, 1/13/2010
• City Council Meeting
– 1/14/2010
• City Spectrum
– 11/2009, 1/2010, 2/2010, 6/2010
• Website – Video and 5-yr Plans for Pipe Replacements
19
Voice of the Customer
• Customer complaints for the last 2 years
– Leaks concerns 1,418
– Water Quality (dirty, discolored) 420
– Low pressure concerns 255
– Sewer backups, slow drainage 2,609
– TOTAL 4,702
20
Recommendation
• Adopt a 5% Rate Increase
– Helps meet legal debt service coverage commitments
– Helps cover FY 2009-10 operations
– Doesn’t fund the water supply booster pump station
– Doesn’t fund new CIP (highest priorities only)
• Impact to Residential Customer
– $2.66/month increase ($53.37 total) typical
– Rates still lowest among 20 plus member cities (Dallas)
– “Lowest rate among the cities in (North Texas in) the
study” (The Celina Record Star - McLain Decision Support
System rate study)
21
No Rate Increase Option
• Would not sell water and sewer bonds
• Limited, if any, CIP for FY 2010-11
• High risk of bond rating downgrade
• Evaluate going from 20 to 30 year debt
• Would not participate in Lake Chapman
Booster Pump Station
– 32% future capacity loss (75 MGD vs. 110 MGD)
– Loss of pipeline operational control and drought
flexibility
22
Questions