Vous êtes sur la page 1sur 1

this step is not

required
Works distribution for Earth Works, Pile Driving and Concrete Works among Sub-Contractors
1. Before Site Preparation Work 2. Excavation to Top of Pilecap 3. Pile Driving 4. Primary Pile Cut
Sub-Contractor : Site Preparation Work Sub-Contractor : Pile Driving Sub-Contractor : Pile Driving
Cut Level: around 30cm above Top of Pilecap
Original Ground Pile

Top of Pilecap Top of Pilecap Top of Pilecap Top of Pilecap

Bottom of Pilecap Bottom of Pilecap Bottom of Pilecap Bottom of Pilecap

5. Excavation to Bottom of Pilecap 6. Final Pile Cut 7. Pile Head Treatment 8. Pilecap Concrete Placement
Sub-Contractor : Concrete Work Sub-Contractor : Pile Driving Sub-Contractor : Concrete Work Sub-Contractor : Concrete Work
Cut Level: Specified cutting level

Top of Pilecap Top of Pilecap Top of Pilecap Top of Pilecap


Pilecap
Re-Bar

Bottom of Pilecap Bottom of Pilecap Bottom of Pilecap Bottom of Pilecap

in this step, pile


still not cutted yet
by any party,
pile will be cutted
by S/C Concrete
works

Vous aimerez peut-être aussi