Vous êtes sur la page 1sur 131

Insulation Coordination

in the Alberta Interconnected Electric System


Part 1
Ligong Gan, P.Eng.
Transmission Engineering & Performance
Alberta Electric System Operator (AESO)
AGENDA

Why do we need insulation?

What is insulation coordination?

Recap of May 13/15 2014 Course by Dr. Peelo


Temporary over-voltages
Switching over-voltages
Lightning over-voltages
Typical approaches to insulation coordination

IEEE and IEC standards

Q&A
2
Before Lightning Rod was Invented

Lightning has always been a prominent part of all ancient religions


and mythologies in the world
In the old days, lightning was considered an act of god(s) to
express their anger
For example
In the Middle Ages in Europe, it was common practice to ring church
bells during a lightning storm to break up thunderstorms and to avert
lightning
The uneducated people believed that this would disperse evil spirits,
while the more educated believed that it would cause vibration in air
which broke up the continuity of the lightning path
However, during a 33 year period, 386 church steeples were hit by
lightning, killing 103 bell ringers at the rope

3
Characteristics of Lightning

2000 lightning occurrences on the earth by


the time you finish reading this slide
A lightning flash typically lasts for 0.2s
Usually made of several shorter discharges,
each of which lasts for 10 to 50 s
Typical length of lightning path is 2-3 km
Individual discharges are called strokes
Most visible when return stroke occurs
Lightning bolt can carry a potential
difference of >1000 kV and >100 kA with
>20 GJ
4
Lightning Facts of Alberta

In an average year, 270,000 cloud-to-ground (CG)


lightning strikes occur in Alberta (in contrast, Manitoba
has only 70,000 per year)
Most CG lightning occurs in the mountain and west-
central areas
Virtually all CG lightning strikes occur in July (45%),
August (32%) and June (23%)
On a typical day, most lightning strikes happen between
3:00 pm and 11:00 am
Source Alberta
Average lightning strike density in Alberta is only 0.8 to Environment and
1 s/km2 Sustainable Resource
Development (ESRD)
The worst strike density is about 4 website

s/km2, mainly in two areas, one 20


km north of Edson, and the other
50 km southeast of Edson
The least density is 0.1 s/km2 in
the north and far southeast
5
Power Industry Structure in Alberta

Minister of Energy
(Appoints AESO Board Members, MSA & AUC Chair)

Electric Utilities Act

Balancing Independent Alberta Utilities Market


System Surveillance
Pool Commission (AUC)
Operator Administrator
(AESO) (MSA)

Transmission Distribution
Generators Retailers
Facility Owners Facility Owners

6
What is AESO?

The AESO
Was formed in 2003 under the Electric
Utilities Act (EUA)

Contracts with TFOs to acquire transmission


services

Develops and publishes binding ISO rules


and standards

Develops and issues Functional


Specifications for projects

Works closely with TFOs and market


participants on transmission projects

7
Why Do We Need Insulation?

1. Public and utility


personnel safety

2. Ensure current flows


only along conductors

3. Prevent damage to
equipment due to high
voltage. In particular,
prevent or reduce
permanent damage to
Transformers
Cables

8
How Insulation Breakdown Takes Place

Chemical Oxidation, hydrolysis, etc.


Mechanical Cracks, channels, tracks, deforming, etc.
Thermal Overheating (e.g., transformers are generally
limited to 2 seconds over-current)
Typical failure rate of equipment due to insulation breakdown
Failure Rate Failure Rate
HV xformers 0.1% Cables 25 kV 83% of all failures
LV xformers 0.15% CTs 0.35%
HV shunt reactors 0.4% PTs 0.2%
HV breakers 0.09% Surge arresters 0.01%
Source: Research conducted by Bueno & Mak Group.

9
Insulation Coordination Definition

IEEE 1313.1 The selection of the insulation strength of equipment in


relation to the voltages, which can appear on the system for which the
equipment is intended and taking into account the service
environment and the characteristics of the available protective devices
IEC 60071-01 Selection of the dielectric strength of equipment in
relation to the operating voltages and over-voltages which can appear
on the system for which the equipment is intended, taking into
account the service environment and the characteristics of the
available preventing and protective devices
Plain Language Arrangement of insulation levels in such a manner
that an insulation failure, if one occurs, would be confined to the place
on the system where it would result in the least damage, be the least
expensive to repair and cause the least disturbance to the continuity
of supply
10
Insulation Coordination (cont.)

Keep in Mind
Its impossible to design a
system that is 100% protected

No perfect solution practicality


is the key
Number of insulator units

Insulation coordination is both


an art and science

Insulation coordination is often


an economic decision
Over-Voltage
11
An Example of Insulation Coordination

Tower type steel


Shielding wire Yes
Line BIL = 1050 kV
Transformer BIL = 850 kV
Breaker BIL = 1050 kV
Arrester Switch & post insulators BIL
Breaker
= 900 kV
Transformer
Arrester
Tower & Line
Continuous voltage = 190 kV
240 kV system
Discharge voltage = 600 kV
Separation distance 3 m
between arrester & xformer
(as per IEEE C62.22)

12
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

The following voltages are always phase-to-phase r.m.s.


values
Nominal system voltage
Minimum continuous operating voltage
Maximum continuous operating voltage (MCOV)
The following voltage is phase-to-ground r.m.s. value
Short-duration low-frequency withstand voltage
The following voltages are phase-to-ground (sometimes
phase-to-phase) peak values
Lightning impulse insulation withstand voltage
Switching impulse insulation withstand voltage
13
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Nominal system voltage the phase-to-phase


r.m.s. voltage by which the system is designed. Its
generally 10% below the maximum system voltage
as defined below
Maximum continuous operating voltage (MCOV)
the highest phase-to-phase r.m.s. voltage under
normal operating conditions
AESOs reliability standards (TPL and VAR in particular)
AESOs Transmission Planning Criteria and Guidelines specifies
Steady State Voltage Criteria (Table 8.2-1) for transmission elements
MCOV = Extreme Maximum Voltage in AESOs Functional Spec

14
What Is MCOV?

Highest voltage under normal operating conditions

Highest voltage for which equipment is designed for


satisfactory continuous operation without intended
derates

In defining MCOV, voltage transients and short


duration temporary over-voltages are normally
excluded

However, voltage transients and temporary over-


voltages may affect equipment operating
performance and should be considered in design

15
Acceptable Range of Voltages in the AIES

Extreme Normal Normal Extreme


Nominal
Minimum Minimum Maximum Maximum
(kV)
(kV) (kV) (kV) (kV)

69/72 62 69 76 79
138 124 135 145 152
144 130 137 151 155
240 216 234 252 264
260 234 247 266 275
500 475 500 525 550
Note: Extreme Maximum kV = MCOV (as mentioned previously)

16
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Over-Voltage Any voltage that exceeds the MCOV.


Often expressed in p.u. with reference to the peak
phase-to-ground maximum voltage

1 p.u. = MCOV 2 3
Critical flashover (CFO) voltage A voltage with a
given waveform that causes flashover on 50% of all
tests
The breakdown of most insulation materials is basically probabilistic in
nature. It often follows a normal (Gaussian) distribution. The CFO is
simply the mean value of the statistical distribution.

17
Recap of May 15/17 2012 Course
Understanding Grounding by Dr. Xu

At any point of a network,


3
If-1 can be times of If-3
+2

3(1++2 )
TOV can be times of rated V (MCOV)
+2

0
Where =
1

When <3 Effectively grounded (as per IEEE and IEC)

18
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Representative over-voltage (Urp) A voltage that


produces the same dielectric effect on insulation as over-
voltages of a given class occurring in services
(There are up to four representative over-voltages in a power system)
Coordination withstand voltage (Ucw) for each class of
voltage, the value of the withstand voltage of the insulation
configuration in actual service conditions, that meets the
performance criteria
(Adjusted Urp considering inaccuracy of initial data)
Required withstand voltage (Urw) the test voltage that
the insulation must withstand in a standard withstand test to
ensure that the insulation meets the performance criteria
when subjected to a given class of over-voltages in actual
service conditions and for the whole service duration
(Adjusted Ucw considering the difference between standard test
conditions and real-life operating conditions)
19
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Coordination factor (Kc) the factor by which the value of Urp


must be multiplied to arrive at the value of Ucw
Ucw = Urp x Kc

Atmospheric correction factor (Ka) the factor to be applied to


Ucw to account for the actual atmospheric conditions (applies
only to external insulation)
Safety factor (Ks) the factor to be applied to Ucw to account for
the actual service conditions
Test conversion factor (Ktc) the factor to be applied to Urw in a
given over-voltage class, in the case where the standard
withstand shape of the selected withstand test is that of a
different over-voltage class

20
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Conventional (deterministic) BIL or BSL the insulation


strength expressed in terms of the crest value of a
standard lightning impulse (for BIL) or a standard
switching impulse (for BSL) for which the insulation shall
not exhibit ANY disruptive discharge (generally
applicable to non-self-restorable insulations)
Applicable to non-self-restoring insulation

Statistical BIL or BSL the insulation strength expressed


in terms of the crest value of a standard lightning impulse
(for BIL) or a standard switching impulse (for BSL) for
which the insulation exhibits a 10% probability of failure
(generally applicable to self-restorable insulations)
Applicable to self-restoring insulation

21
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Basic Impulse Level (BIL or


BSL)
The crest voltage of a standard wave
(either a 1.2/50 impulse or a 250/2500
impulse) that will not (or in 90% of the 1.2/50
tests, will not) cause a flashover of the
insulation is referred to as Basic Impulse
Level or BIL

The insulation strength of equipment as


tested should be equal or above the BIL
as specified in an AESOs Functional
Spec
250/2500
22
How the BIL (or BSL) is Determined

BIL or BSL
Test conversion
factor Ktc

Required withstand voltage Urw


Atmospheric factor Ka
Safety factor Ks
Coordination withstand voltage Ucw
Coordination factor Kc

Representative over-voltage Urp

MCOV
(between 5% and 10%)
Nominal voltage (138/144/240/500 kV)

Ground

23
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

Standard lightning impulse voltage waveform Standard switching impulse voltage waveform

Very fast front short duration over-voltage Temporary over-voltage


24
Margins of Protection
Magnitude of over-voltage pu

0
Fast-front over-voltage Slow-front over-voltage Temporary over-voltage Continuous operating
(Lightning, s) (Switching, s to ms) (seconds to minutes) voltage (life time)

25
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo

26
Recap of May 13/15 2014 Course
Insulation Coordination by Dr. Peelo
Temporary Over Voltage (TOV)
An oscillatory phase-to-ground or phase-to-phase over-voltage, at a
given location and of relatively long duration (1s to 10s), is undamped or
only weakly damped
TOV level establishes the rating of surge arrestors
The general rule is that surge arresters should not activate at TOV but
will activate when experiencing higher voltages

Major causes of TOV


Load rejection
Ground faults
Resonance phenomena or harmonics
Line energization/deenergization

Duration of TOV
Typically 1s to 10s (or minutes in extreme cases)
27
Surges and Transient Over-Voltages

A short-duration highly damped,


oscillatory or non-oscillatory over-
voltage, having a duration of a few
milliseconds or less. Transient
over-voltage is normally classified
as one of the following types
Slow front
Fast front
Very fast front

28
Surges and Transient Over-Voltages (contd.)

Slow front (20 s to 5 ms)


Line energization/deenergization
Faults or load rejection
Switching of capacitors/reactors
Fast front (0.1 s to 20 s)
Lightning
Switching operations
Very fast front (1 ns to 0.1 s)
Switching of disconnects or circuit
breakers (typically with GIS
applications)
29
Class and Shapes of Over-Voltage and Tests

Source: IEC 60071-2 30


Over-Voltages Amplitudes

Power-Frequency Temporary Switching Over-Voltage


Over-Voltage
Slow front 30-300 s
Generally 10s Tail @ 50%: 100-2000s
SLG faults <1.5 pu
Ferranti effect <1.3 pu Energizing lines 1.5-2 pu
Load rejection < 1.4 pu Re-energizing lines 3-3.4 pu
Resonance > 2 pu Switching no-load xformr > 2 pu
Energization/re-energ. < 1.5 pu Switching reactor > 2 pu
Stuck breaker pole < 2 pu Switching capacitors 1.5-2 pu
Fault interruption 1.5 pu
Lightning Over-Voltage
Fast front 1-6 s > 5 pu
Tail @ 50%: 50 s

31
Typical Insulation Coordination Studies
Transmission substation insulation coordination study
Primary purpose is to determine the location of lightning masts, location and rating
of surge arresters, the mitigation techniques such as pre-insertion breakers, point-
on-wave breaker control, current-limiting reactors, and to determine appropriate
protection relay settings
Look at all sources of surge over-voltages: Temporary over-voltage, switching
surge and lightning surge
Determine the probabilities and protection margins for all transients entering the
substation
Transmission line insulation coordination study
Primary intention is to determine
Location of arresters if back flashover is of a concern
Necessity and location of arresters if the terminal breakers do not have pre-insertion
resistors
Power plant (including WAGF) or user-owned substation IC study
Typically performed by the owner of the power plant or substations
Similar to transmission substation insulation coordination study for the substations
Primary intention is to determine grounding requirement and location of surge
arresters
32
Over-Voltage Protection Devices

Surge Pre-Insertion
arrester Resistor

Grounding

Shielding wire

More insulation
Controlled closing
33
Characteristics of SiC and ZnO Arresters

Characteristics
of different
surge arresters

34
Selection of Surge Arresters

Location
Maximum continuous operating voltage
Amplitude and shape of over-voltages
Nominal discharge current
Residual voltage at the nominal discharge
current
Energy absorbing capability (Arrester class)
Surge impedance and/or capacitance of the
protected equipment
35
Selection of Surge Arresters

Example Find a suitable lightning arrester for a 240 kV transformer.

For the transformer, MCOV = 264 kV (=240110%) and BIL = 850 kV (as per AESO FS)
Therefore, the arresters voltage rating (Vr) and continuous operating voltage (Vc) is 153 kV
(= 264 3)

The following arresters can be chosen:


Voltage Rating (kV rms) TOV Max Residual Voltage (kV peak)
(kV rms) SPL (1 kA) SPL (2 kA) LPL (5 kA) LPL (10 kA)
Vr Vc (10 sec) 30/60 s 30/60 s 8/20 s 8/20 s
210 156 231 417 433 469 494
240 191 264 476 495 536 564
276 221 303 547 569 617 648

Insulation strength (BIL) = 850 kV


Therefore, protective margin = (850/564 1) = 0.51 or 51% (which is >25%)

Assuming an effectively grounded system, and the power frequency over-voltage is limited
to no more than 40% at the arrester,

so MCOV 140% = 153 140% = 214 kV (which is less than 264 kV)
36
Procedure for Insulation Coordination

Transient analysis & simulation


Determination of representative

Origin and level of over-voltages
Statistical distribution of over-voltages
Protective level of arresters over-voltage Urp
Insulation characteristics
Determine contamination severity
Verification of data and assumptions
Kc
Determine coordination factor Kc
Determination of coordination
withstand voltage Ucw

Determine altitude correction factor Ka
Determine safety factor Ks Ka Ks
Determination of required
withstand voltage Urw

Determine test conversion factor Ktc
Determine level and range of Uw (for Ktc
both internal and external)
Rated or standard
insulation level Uw

37
Differences between IEEE and IEC

Both IEEE 1313 and IEC 60071 are excellent reference standards
Procedures and methodologies in both standards are same or similar
In many cases IEEE 1313 cites directly IEC 60071 recommendations
The differences are minor and subtle

IEEE 1313 IEC 60071

Nomenclature BIL, SIL LIWV, SIWL, ACWV


Detailed with more
Detail Tend to be concise
examples
Generally more Generally more
Performance criteria
aggressive conservative
MCOV 15 kV 1 kV

38
Typical Nominal, Minimum, MCOV and BIL
Values in AESOs Functional Specification

Nominal Minimum MCOV BIL


(kV) (kV) (kV) (kV)
25 23 28 150
69 62 79 350
138 124 152 650
144 130 155 650
240 216 264 1050
500 475 550 1800

39
Insulation Coordination for Transmission Lines

Transmission Line Insulation Coordination Involves


Shielding angle of the shielding wire
Clearance of conductors
Selection of the type and length of insulators
Keep in Mind

Shielding Failure Flashover Rate (SFFOR) and Back Flashover Rate (BFR)
are two typical design criteria typical SFFOR is 0.05 f/100km-yr and BFR
is 1 f/100km-yr
The higher the tower and voltage, the smaller the shielding angle
BFR impacts substation insulation requirements
Contamination influences creepage distance (mm/kV) and consequently
the number of insulator units
Generally, from an insulation perspective, transmission line reliability
performance is 10% of substation reliability criterion
40
Insulation Coordination for Substations

Substation Insulation Coordination Involves


Determination of BILs for major equipment or equipment group
Location of shielding masts and/or shielding wires
Clearance of conductors
Surge arresters Rating, number & locations
Keep in Mind
MTBF (and BFR) determine if line-entrance arresters are required
Transformers and cables should always be primary concerns
Protective margin is generally for non-self-restoring insulation
Cost of equipment failure generally determines sequence of failure
Gap configuration can change CFO level by 30%
Lightning flash can be multiple strokes longitudinal insulation
There may be back-and-forth calculations/adjustments required
41
Protection and Insulation Coordination of
Substation Components

Substation Type

Air-insulated substation
Gas-insulated substation

Major Equipment

Transformers
Circuit breakers
CTs and PTs
Capacitors/Reactors
Cables
42
Insulation Coordination between T and D

General Principles
Similar to protection coordination between transmission
and distribution

Should a surge result in insulation breakdown, it should


generally be on the distribution system first

Interruptions to consumers are more confined and


localized, i.e., fewer customers impacted per event
Distribution utilities are generally closer to the failed
equipment faster response

43
Typical BIL Levels of Distribution Class &
Power Class

Voltage Distribution Power Class


(rms kV) Class BIL (kV) BIL (kV)
5 60 75
8.7 75 95
15 95 110
25 110 150
34.5 150 200
72 250 350
44
Insulation Coordination between T and G

Keep in Mind
Rotating machines (incl. generators/motors) do not have BIL
ratings
For conventional power plants, insulation coordination is primarily
between plant substation and TFO system
Wind Aggregated Generating Facility (WAGF):
Most wind power plants in Alberta use 34.5 kV collector systems
Most wind generators (WTGs) are not typically grounded
Induction WTGs can continue to generate if sufficient capacitance
is present (self excitation) voltage can be high
As above, MCOV and TOV can become constraints for arresters
Most WTGs use distribution class equipment (for economic
reasons) with up to 150 kV BIL
45
Insulation Coordination between
Transmission Lines and Substations

General Principles
Insulation performance of overhead lines has a large impact on the
insulation performance of substations
Re-energization operations
Towers close to substations
Transmission lines should be designed to enable no injection of
over-voltage in excess of the rated impulse withstand voltage of the
connecting substations into the substations

In mountain areas, the reduction in Critical Flashover (CFO)


voltage due to higher elevations should be taken into account

Substation insulation strength should be at least equal to line


insulation strength for switching surges if no line-side arresters
46
Things to Remember in Insulation Coordination

The TFOs and Market Participants, not the equipment


manufacturers, are responsible for insulation coordination
studies
There is nothing more important than knowing your system
better
There is not always a single best solution to insulation
coordination
Back-and-forth calculations and adjustments are often
needed in insulation coordination studies
Deterministic approach should always be applied to non-
self-restoring equipment
Statistical approach can be applied to self-restoring
equipment
Surge arresters are generally not used to limit temporary
over-voltages (TOVs)
47
Things to Remember in Insulation Coordination
(contd)
Basically, the basic impulse level (BIL) is equal to the
Representative Over-Voltage Urp with many correction factors on top
Insulation coordination is both an art and science, and is often an
economic decision. Many parameters or requirements are conflicting
in reality.
Example To reduce BFR of a transmission line
Option: increase conductor spacing and insulator units larger tower higher
cost and increased surge impedance increased BFR
Power system insulation is an ever-evolving field. More research
needs to be done to more fully understand the transient behavior of
lightning, switching surges, etc.
IEEE 1243 Guide for Improving the Lightning Performance of Transmission Lines
says
The methods for estimating the lightning performance of transmission lines show
several approaches to a reallife engineering problem that is illdefined. Precise
constants are rarely known and are often not really constant, input data is difficult
to describe mathematically except in idealized ways
48
THANK YOU

Questions?
Insulation Coordination
in the Alberta Interconnected Electric System
Part 2
Ligong Gan, P.Eng.
Transmission Engineering & Performance
Alberta Electric System Operator (AESO)
APIC Insulation Coordination Agenda

AESOs role in transmission system


insulation coordination

Evolution of BIL requirements in


Alberta

Insulation Requirements in AESOs


Functional Specifications

Thoughts on Possible Future Changes


to Current BIL Levels

Q&A

2
The Power Industry of Alberta

Generation Competition

Retail
Regulated

Transmission

Distribution

AESO
3
Power Industry Structure in Alberta

Minister of Energy
(Appoints AESO Board Members, MSA & AUC Chair)

Electric Utilities Act

Balancing Independent Alberta Utilities Market


System Surveillance
Pool Commission (AUC)
Operator Administrator
(AESO) (MSA)

Transmission Distribution
Generators Retailers
Facility Owners Facility Owners

4
AESOs Core Functions

Transmission System Access System Operations


Provide access for both electricity Direct the reliable 24/7 operation of
generators, large industrial Albertas power grid
customers and distribution utilities

Transmission
Market Services
System Development
Develop and operate Albertas
real-time wholesale energy Plan the transmission grid to
market to facilitate fair, ensure continued reliability to
efficient and open competition facilitate a competitive market and
investments in new supply

5
Albertas Bulk Transmission System
240-500 kV (now and near future)

Virtually all 240 kV lines


The KEG loop (500 kV) Dover

Thickwood

Two 500 kV HVDC lines between Wesley


Creek

Livock
Brintnell

Edmonton area and Calgary area


Conklin
McMillan
Leismer
Christina
Lake

Mitsue Heart

Two 500 kV AC lines planned from


Lake
Little
Smoky
Marguerite
Louise Lake
Creek Heathfield
Heartland

Edmonton area to Fort McMurray WhitefishLake


Deerland
Josephburg

Clover Bar

area
Wabamun
Sagitawah

Sundance
Bickerdike Sunnybrook
Keep-
hills Genesee Ellerslie

One 500 kV AC interconnection to Brazeau Battle


River
Metiskow

British Columbia Benalto Red Deer


Cordel
Hansman Lake

Pemukan

One 240 kV interconnection to


Sheerness
Anderson
Lanfine
Beddington

Crossing

Montana Sarcee Janet


E. CalgaryShepard
SS-65
Langdon
Bennett
SC2
Jenner

Empress

Milo Cassils
West
Foothills Brooks

One 150 MW (HVDC) Stavely


SC1
MATL
Newell
Bowmanton

Peigan

interconnection to Saskatchewan
Chapel Rock

Windy N. Lethbridge Whitla


Filder Flats

Etzikom
Goose Lake Coulee

6
Albertas Existing Transmission System

Substations Xmission Lines (km)


Voltage (energized) (energized)
TFO Customer TFO Customer

69/72 kV 70 11 2,246 21

138/144 kV 403 57 12,824 282

240 kV 101 23 10,361 223

500 kV 8 602
Note: Circuit length (km) includes both overhead lines and underground cables
Evolution of Insulation Requirements in
Alberta Transmission System

First 138 kV line 80L from Ghost


Substation to Edmonton was built in
1929
MCOV of the first 138 kV line 80L was
set at 145 kV (105%)
Today the following MCOV and BIL
levels are used:

138 kV 144 kV

MCOV 152 155

BIL (1) 550 550

BIL (2) 650 650

8
Evolution of Insulation Requirements in
Alberta Transmission System
First 230 kV line, between Wabamun
and Sarcee 42S was built in 1961
MCOV of the first 230 kV line was set
at 242 kV
Wabamun had to operate at 253 kV
in order to maintain acceptable
voltage at Sarcee
Because of the circuit length (>450
km), special equipment with MCOV of
264 kV was installed at Wabamun
The system was then classified as
240 kV nominal voltage
BIL levels of 900 kV and 1050 kV
were chosen, assuming a grounding
factor of 1.4
9
Evolution of Insulation Requirements in
Alberta Transmission System

In 1986, first 500 kV tie-line 1201L,


between Langdon and Cranbrook (B.C.),
was built Thickwood
Dover

In 1982, first intra-Alberta 500 kV line


Livock
Brintnel
l

1202L, between Keephills and Ellerslie, Heart


Lake

was built but operated at 240 kV Heartland


Heathfield

WhitefishLake

In 2010, 1202L re-energized at 500 kV Sundance


Wabamun
Sunnybroo
k
Clover Bar

Keep-
hills Genesee Ellerslie

MCOV of 1201L/1202L was set at 550 kV


Hansman
Lake

BIL of 1425/1550/1800 kV chosen for Pemukan

substations 89S/320P/102S Thermal Plant Crossing


Lanfine

Hydro Plant SC2


Shepard
Bennett

Since around 2011, 1550/1800 kV


SS- 65
Existing 240 kV Cassils
Existing 500 kV
Foothill
Future 240 kV s
Future 500 kV Newell
Stavely

became BIL levels for 500 kV system Future 500 kV HVDC SC1 Bowmanto
MATL
n

Chapel
Rock
AIES Filder
Windy
Flats
Whitla

Transmission System
Etzikom
500 /240 kV System Overview Coulee

10
AESOs Role in Transmission Insulation
Coordination
In general, AESO only defines functionality requirements
of transmission elements in its Functional Spec
Operating conditions of equipment
Input and desired output (for RASs etc.)
Provides a direction (or guidance) for design
Reference for equipment bidding and procurement
Requirements (or guidance) for compliance with standards

A Functional Specification does not


Define inner workings
Specify the manufacturer to be used or avoided
Dictate how equipment is procured
Provide details of how equipment is installed

11
AESOs Role in Transmission Insulation
Coordination (contd)

Typically, AESOs Functional Spec contains


Purpose
Interpretation and Variances
Project Overview
Scope of work
Standards
Scope of work for TFO and Market Participant
Transmission System Operating Characteristics
Normal operating levels and constraints
Emergency operating requirement
Appendices
Single line diagrams for substation configuration and SCADA
requirements

12
Some Relevant Rules & Standards

ISO rule 502.1 Wind Aggregated Generating Facilities Technical


Requirements
Section 21 provides lightning surge protection requirements for the collector
stations, and between collector substation and transmission line
ISO rule 502.2 Bulk Transmission Line Technical Requirements
Specifies the standards to be used in setting electrical clearances, the conditions
under which an insulation study is required, and the minimum insulation levels of a
bulk transmission line
The Information Document (ID) further provides detailed explanation as to how
insulation coordination is conducted, and the recommended BIL levels
Generation & Load Interconnection Standard 2006
Section 2.3 sets out the general requirements for insulation studies and the
specific IEEE standard (P998) to be employed
ARS FAC-001-AB Facility Connection Requirements
Section R2.6 requires that the AESOs interconnection requirement or projects
Functional Spec must address insulation and insulation coordination

13
AESOs Philosophy on Insulation Coordination

AESO specifies rules & standards which set out


minimum technical requirements

AESO provides minimum BIL levels without


distinguishing

between BIL & BSL


between conventional & statistical

TFOs and market participants are required to


perform any and all insulation coordination
studies and determine appropriate insulation
levels

TFOs and market participants are required to


coordinate with each other in setting equipment
insulation levels
14
AESO Rule 502.2 Transmission Lines

Section 14(2) Shield wires must be installed on


138/240/500 kV AC or 500 kV DC bulk transmission
lines
Section 14(3) Number and positioning of the shield
wires must be so as to produce lightning flashover rates
that are consistent with all reliability requirements of the
lines
Section 17(5) Electrical clearances for use with the
wind pressure values of Table 3 must be determined
from the application of the methodology outlined in IEEE
Standard 1313.2 The Application of Insulation
Coordination, for transmission line phase to ground
switching over voltages

15
AESO Rule 502.2 Transmission Lines

Section 21(7) The minimum insulation levels for a bulk


transmission line and any 25 kV distribution line located on bulk
transmission line structures must be as set out in the following
table:

Nominal Voltage (kV) Critical Impulse Flashover CIFO (kV)


25 kV 165
138/144 kV 715
240 kV 1,155

ID 2010-005R, Section 21 Insulation levels for 500 kV AC or


500 kV DC lines are determined from insulation studies carried
out for each such line, as part of the design process.

16
AESO Rule 502.2 Transmission Lines

ID 2010-005R, Section 21 25 kV insulation requirement


applies only to those 25 kV distribution lines placed on bulk
transmission line structures. 502.2 recognizes the need for
insulation coordination between circuits of different voltages
located on common structures

ID 2010-005R, Section 21 Insulation levels for 500 kV AC


or 500 kV HVDC lines are determined from insulation
studies carried out for each such line, as part of the design
process. Hence, 502.2 does not include insulation levels for
500 kV class lines

17
AESO Functional Specification

In the Project Scope section:

(the legal owner of the transmission facility) shall


complete insulation coordination studies and coordinate
with the market participant as required to establish
appropriate insulation levels
Undertake insulation, grounding, protection and
communication studies as necessary to accommodate the
proposed system additions and modifications

18
AESO Functional Specification

6.3 Insulation Levels


(1) The following provides the minimum required basic impulse levels for the
transmission system. Station equipment with lower insulation levels may be used
provided that protection and coordination can be maintained with judicious insulation
design and use of appropriate surge arresting equipment.

(2) For 25 kV circuit breakers where there is a grounded wye transformer and surge
arrestors are installed, a basic impulse level of 125 kV is acceptable.

Nominal Voltage (kV rms) 25 69/72 138/144 240 500

Station post insulators and airbreaks 150 350 550 900 1,550

Circuit breakers 150 350 650 1,050 1,800

Current and potential transformers 150 350 650 1,050 1,800

Transformer windings (with arresters) 150 350 550 850 1,550


19
Thoughts on Possible Future Changes to
Current BIL Levels

Should we split the current basic insulation levels into BIL


and BSL levels?
In some 500 kV projects, it has been suggested that the BIL
level for the 500/240 kV autotransformers be set at 1425 kV
for lower cost and easier transportation
Should we create a new nominal voltage level of 260 kV
with MCOV of 286 kV (or 275 kV)?
Should we raise the current BIL for 240/260 kV
transformers from 850 kV to 900 kV (or higher)?
Should we differentiate GIS from AIS equipment, especially
for 500 kV equipment, on the BIL levels?
Any other from you?
20
Upcoming AESO Rule for Substations
502.11
The AESO is now in the process of developing
a Substation Rule (502.11) which sets out the
minimum technical requirements respecting
design, engineering and construction of (new)
transmission substations

Insulation coordination and grounding will be a


major part of Rule 502.11

Proposed Process (2015-2016)


Industry Workgroup (WG)
Recommendation paper to WG & stakeholders
Draft and post Rule for comments from industry
Filing of Rule 502.11 with AUC
21
THANK YOU

Questions?
Over-Voltages and the
Distribution System

Thomas C. Hartman, P.Eng.


APIC Professional Development
May 12 & 14, 2015

University of Alberta
Discussion Outline - OVERVIEW
The Origin and Shapes of Distribution System Surges
Insulation Systems And How They Go Bad
Where Surges Matter And What They Do
Overhead Systems
Underground Systems
Distribution Surge Arresters Design and Application
Reality Check
Q&A
NOTE: References are in parenthesis - (xx)

1
University of Alberta
Disclaimer

I will mention many companies during this presentation.


Please keep in mind:
1 I have NO financial interest or otherwise in any of the
companies I mention
2 I work for ATCO Electric Distribution and that is my only
source of income
3 This presentation is my opinion only and does not
necessarily reflect ATCO policy, practices, or standards
4 I expect that you will use this presentation for illustrative
purposes only. Any arrester applications you design shall
be based on your own professional judgement

2
University of Alberta
The Origin and Shapes of
Distribution System Surges
Overhead

(16)

(1) (2)

Underground Mostly same as O/H, (12)

but with some twists!


3
University of Alberta
What is a Surge?

Surge
IEEE Std 100: A transient wave of current, potential, or
power in an electric circuit. Note: The use of this term to
describe a momentary overvoltage consisting in a mere
increase of the mains voltage for several cycles is
deprecated. See also: swell.

Temporary Overvoltage (TOV)


IEEE Std 100: . An oscillatory overvoltage, associated
with switching or faults and/or nonlinearities of
relatively long duration, which is undamped or slightly
damped.

4
University of Alberta
TOV
It is NOT a Surge!
Accidental Grounding - Leg of Delta
Loss of Neutral
Fault Conditions
Comingling

When Overbuild Meets Underbuild


Surge arresters provide a simple solution to a complex overvoltage
problem
Daniel J. Ward, Dominion Virginia Power
T&D World Magazine - Mar 1, 2011
5
University of Alberta
World Ground Flash Density

www.arresterworks.com/resources/calculator_images/GFD_World.jpg

6
University of Alberta
A Natural Cause - Lightning

(13)
(14)

(3)
(15)

Lightning Current MIL-STD-464

7
University of Alberta
Vacuum Switch TRV Behavior (7)

Simulated TRV Response


Source Voltage: 3.4 kV (6 kV System)
Current at Opening: 4.7 A

8
University of Alberta
Shunt Capacitors

Effect of switching re-strikes on capacitor voltage

(6)

(5)

9
University of Alberta
Current Limiting Fuse Operation

(11)

10
University of Alberta
Current Limiting Fuse Arc Interruption Voltage

(34)

11
University of Alberta
Other Surge Waveforms

(37)

Switching Surge (36)

(38)

12
University of Alberta
Surges and Their Waveforms
Just So YOU Know
Lead Length can ADD up to 1500 Volts/Foot
Lead length is the physical wire distance between the
Apparatus and the Line Side of the Surge Arrester
PLUS (+)
The Line Length from the Ground of the Surge
Arrester to the Ground of Apparatus

AND for the Love of Goodness,


Please Dont COIL the Leads!!!

13 University of Alberta
Insulation Systems
And How They Go Bad
If we lived in a perfect world, our insulation systems
would last forever. But

We dont.

All Insulation Systems are Doomed from the Start!


Embedded Manufacturing Defects
Environmental Contamination
Shipping and Handling
Some Field Assembly Required
(32)
14
University of Alberta
Insulation Systems How Do They Fail?
External Sources
Physical Damage Rocks and Rifles, External Arc
Contamination Farming, Exhaust, Salt, etc.
Internal Sources
Water Ingress
Arcing under Oil or SF6
Built-In Defects Either from Vendor or Customer

15
University of Alberta
Insulation Systems
Contamination and Built-In Defects
Contamination Surge Arresters Really Wont Help
The Failure Mechanisms Associated with
Contamination are Active at 60 Hz System Voltage

Built-In Defects Surge Arresters May Help


If the Failure Mechanism is Triggered by a Surge,
then a Surge Arrester will Delay the Trouble
If the Built-In Defect is Active at System Voltage,
then a Surge Arrester Wont Help.

16
University of Alberta
Insulation Systems Failure Triggers
Contamination
Dry Band Arcing is the Beginning of the End

Built-In Defects
It is All About Capacitance, Dielectric
Constants, and Dielectric Strength
C = (k*e0*A)/d
where k: Air =1, Silicone = 4, EPDM = 2.6
Glass = 6, Polyethylene = 2.25, Porcelain = 6
Which Equals an Evil Voltage Divider
17
University of Alberta
Ceramic / Glass
One Tough Insulation System!
Can Last a Century or More
Surges / Flashovers are Generally Benign
Failure Mechanisms
Slow Clearing Times Crack Ceramic/Glass
Susceptible to Point Pressures Resulting in Crack
Propagation
Pin Threads (lead/nylon)
Ice Expansion Forms Cracks
External Contamination / Cleaning
18
University of Alberta
Polymers
Organic/Semi-Organic System (31)

Manufacturing Process
Sensitive
Failure Mechanisms
Embedded
Manufacturing/Material Defect
If Small Enough, the Defect
Lays Dormant Longer
Surges Reduce PD Inception
Levels
Ultimate Demise of Insulator (30)

19
University of Alberta
Dielectric Fluid Oil (29)

1. Oxidation: Oxidation is the most common cause of oil deterioration, which is the reason
that transformer manufacturers are careful to seal the transformer from the atmosphere.
2. Contamination: Moisture is the main contaminant. Its presence can react with the oil in the
presence of heat. It also lowers the dielectric properties of the insulating oil.
3. Excessively high temperature: Excessively high heat will cause decomposition of the oil
and will increase the rate of oxidation. The best way to avoid excessive heat is to avoid
overloading the transformer.

4. Corona discharges: Arcing and localized overheating can also break down the oil,
producing gases and water, which can lead to the formation of acids and sludge.

5. Static electricity: The existence of an insulating fluid flowing past an insulating solid
(paper), results in charge separation at the interface of the two materials. Physically, these
charges separate at the interface of the oil and paper in any transformer; thus reducing the
dielectric strength of the insulating oil. This could also cause internal flashover.
6. Furans: Furan derivatives are a measure of degradation of paper insulation. When the
paper ages, the long-chain cellulose molecules (polymers) break down in smaller fractions
and its physical strength is reduced. The degree of polymerization can be directly related to
the concentration of furan derivatives, which are formed in the oil.

20
University of Alberta
SF6 (28)

Sulfur hexafluoride (SF6) is a relatively nontoxic gas used in a number of applications for its
inert qualities. The dielectric and other physical and chemical properties related to its lack
of reactivity have led to the extensive use of SF6 as an insulating medium in switching
equipment (e.g., circuit breakers) by electric utilities. While SF6 is inert during normal use,
when electrical discharges occur within SF6-filled equipment, toxic byproducts can be
produced that pose a threat to health of workers who come into contact with them.

SF6 can decompose into byproducts when exposed to four types of electric discharges
(CIGRE1 1997)
partial corona discharges caused by insulation defects;
spark discharges that occur at insulation defects or during switching operations;
switching arcs that occur in load break switches and power circuit breakers; and
failure arcs that occur due to insulation breakdown or switchgear interruption failure.

Each discharge can result in different mixtures and concentrations of byproducts.

21
University of Alberta
Where Surges Matter ~ OVERHEAD SYSTEMS
And What They Do There

Pin Insulator
Transformer
Regulator
Capacitor
Riser Pole
On the Secondary

22
University of Alberta
At the Pin Insulator (16)

23
University of Alberta
At the Transformer

(9) (24)

24
University of Alberta
At the Secondary
Transformer Secondary Protection
Surge Suppression Inc.

At the secondary bushing Inside (9) EATONs Cooper Power Systems

25
University of Alberta
At the Capacitor (17)

(18)

(17)

26
University of Alberta
At the Regulator

(19)

(35)

27
University of Alberta
Where Surges Matter ~ UNDERGROUND
And What They Do There

Underground Systems
Riser Pole
Cable
At an Open Point

28
University of Alberta
At the Riser Pole

(20)

(22)
(21)
29
University of Alberta
In the Cable

(25)

(27) (26) (26)

30
University of Alberta
At an Open Point

(4)

(10)

31
University of Alberta
At ANY Place on your System
Just So YOU Know
Lead Length can ADD up to 1500 Volts/Foot
Lead length is the physical wire distance between the
Apparatus and the Line Side of the Surge Arrester
PLUS (+)
The Line Length from the Ground of the Surge
Arrester to the Ground of Apparatus

AND for the Love of Goodness,


Please Dont COIL the Leads!!!

32 University of Alberta
Distribution Surge Arresters
Design and Application

A Very Brief History of Surge Arrester Evolution


Explanation of Surge Arrester Classes
Which Class to Use
How Arresters Eventually Fail

Surge Arresters have ONE Job Protect Insulation

33
University of Alberta
A Brief History
Air Gap Beginning of Time to Now
Silicon Carbide (SiC) 1930 to Mid 1980s
Metal Oxide Varistors (MOV) 1975+

(41)
http://www.arresterworks.com/ http://www.arresterworks.com/

34
University of Alberta
Differences Between Manufacturers
None Really
Arresters are essentially COMMODITIES
Purchase on your preferences such as:
Price
Vendor Service
Availabilities
Vendor Preference
Etc.
You will likely be satisfied!
My Preference???
35
University of Alberta
Surge Arresters Parameters
Critical Parameters (Minimum Needed)
1. MCOV Maximum Continuous Operating Voltage
2. TOV Temporary Over-Voltage Withstand
3. EFOW Equivalent Front-of-Wave (0.5 uS, Lightning)
Lesser Parameters (May be hard to Coordinate)
4. Discharge Voltage At: 1.5 kA, 5 kA, 10kA, & 20 kA
5. Switching Surge 250 or 500 amps (Class Dependent)
6. Arrester Class ND, HD, RP, Intermediate, Station
Only 6?!, Really?!

But What is a Surge Arrester RATING?!


36
University of Alberta
Critical Parameter #1 MCOV

Impedance
Solid Multi-
Maximum Uni-Grounded Grounded,
Nominal System Maximum Grounded
Line to GND Systems Ungrounded,
L-L Voltage L-L Voltage Systems
Voltage (3-Wire) and Delta
(4-Wire)
Systems
kV rms kV rms kV rms MCOV MCOV MCOV
4.16 4.37 2.25 2.55 5.1 5.1
4.8 5.04 2.91 -- -- 5.1
6.9 7.25 4.19 -- -- 7.65
24.9 26.2 15.1 15.3 22 --

Do You See a RATING Here?

37
University of Alberta
Critical Parameter #2 TOV (41)

38
University of Alberta
Critical Parameter #3 EFOW (BIL)

(39)

39
University of Alberta
Lesser Parameters 4 & 5
4. Discharge Voltage At: 1.5 kA, 5 kA, 10kA, & 20 kA
5. Switching Surge 250 or 500 amps (Class Dependent)

These two parameters will one used based on the type


of equipment you are protecting.

The Discharge Voltage is use at the End of Lightning


Protective Levels.

40
University of Alberta
Capacitors Coordinate to Surge Arrester
Schneider Electric Hong Kong

General Specification for Fixed Capacitor Bank for Electrical Network up to 36kV

According to network rated voltage, the insulation level of equipment is as follows :

(40)

Rated Voltage (Vdim) Insulation Level Power Frequency Voltage


Impulse Voltage Withstand
Withstand
(kV peak)
(kV rms)
(V) (kV)

6600 7,2 20 60

11000 12 28 75

15000 17,5 38 95

22000 24 50 125

33000 36 70 170

41
University of Alberta
Insulators Coordinate to Surge Arrester
PPC Pin Type Insulators

Catalog Number Frequency 253-S 261-S 263-S 366-S 380-S 386-ST


ANSI Class 55-2 55-3 n/a 55-4 55-5 55-6
Neck Type C C C F F J

Typical Application (kV) 60 Hz 7.2 11.5 11.5 13.2 14.4 23


Dry Flashover Voltage (kV) 60 Hz 45 55 55 65 80 100
Wet Flashover Voltage (kV) 60 Hz 25 30 30 35 45 50
Puncture Voltage (kV) 60 Hz 70 90 90 95 115 135
Impulse Flashover Positive (kV) Impulse 70 90 90 105 130 150
Impulse Flashover Negative (kV) Impulse 85 110 110 130 150 170
Leakage Distance 5" 7" 7" 9" 12" 15"
Dry Arcing Distance 3 3/8" 4 1/2" 4 1/2" 5" 6 1/4" 8"
Cantilever Strength (lbs) 2500 2500 2500 3000 3000 3000
Minimum Pin Height 4" 5" 5" 5" 6" 7 1/2"
Net Weight per 100 (lbs) 183 225 260 390 500 890
Package Weight per 100 (lbs) 191 254 288 400 617 938
Standard Package Quantity 48 24 24 12 12 8

42
University of Alberta
Arrester Class - Parameter #6

Normal Duty (ND)


Heavy Duty (HD)
Riser Pole (RP) (Not a Real Class)
Intermediate Class
Station Class

Arrester Class size is Mostly Determined by the


Diameter of the MOV Disk

ND = 1, HD = 2, RP = 2, Inter. = 3, Station = 4+
43
University of Alberta
Class Comparisons

0.5 sec 8/20 Test Waveform Tempoary


500 A
Rated 10kA Maximum Discharge Voltage - kV Over-Voltage
Hubbell Voltage MCOV Switching 1 sec 10 sec
Product
EFOW 1.5 kA 3 kA 5 kA 10 kA 20 kA 40 kA
kV kV Surge kV rms kV rms
Normal Duty PDV65-Optima 18 15.3 62.8 46.4 50.1 53.8 57 63.3 72.6 91.2 22.7 21.7
Heavy Duty PDV100-Optima 18 15.3 60.6 43.5 45.4 48.4 51.3 56.4 63.5 75.5 23.5 22.2
Riser Pole PVR-Optima 18 15.3 53.4 35.5 38.9 41.9 44.3 48.9 56.1 66.2 22.2 21.0
Intermediate PVI-LP 18 15.3 51.6 38.3 40.9 43.2 45.2 48.8 54 60.9 21.4 20.5
Station EVP 18 15.3 51.6 36.1 38.5 40.4 42.4 45.5 49.1 56.1 21.7 20.8

44
University of Alberta
Protection Level
Protective Margin = ((Insulation Level / Arrester Discharge Voltage) 1) * 100%

(33)

45
University of Alberta
Generic MOV I-V Curve

46
University of Alberta
(42)

47
University of Alberta
Which Arrester Class What Purpose?
Your Choice In Alberta, a low lightning region -
Normal Duty is good enough for general purpose
protection
Riser Poles How important is the circuit?
Capacitors
Normal Duty is OK,
Big Banks consider Heavy Duty or Intermediate
Transformers
Normal Duty is OK
Big Expensive Transformers Heavy Duty or Intermediate
48
University of Alberta
Surge Arresters How Do They Fail?
TOV is the Number 1 Killer of Surge Arresters in
Alberta (As reported on Global National, just kidding)
The Process is Simple: Overvoltage Physically Heats the
MOV disk, Heat Lowers the MCOV Which Increases the
Heat Generated, Which Lowers the MCOV More, Which
Increases th Heat Generated, until BOOM!

Todays Surge Arresters Rarely Fail Due to a Surge


in Alberta. The Quality is Really That Good!

49
University of Alberta
Surge Arresters Disconnector

(41)

50
University of Alberta
~ Reality Check ~

Should You Be Worried about a Surge Armageddon?

(23)

51
University of Alberta
~ Reality Check ~

No, of course not.


Your own historical data is proof!

But, Asset Life would be Extended Significantly with


the Proper Application of Surge Arresters!

52
University of Alberta
Where to Focus Your Protection

Transformer Primaries SHORTEST Lead Length!!!


Riser Poles SHORTEST Lead Length!!!
UG Open Points
Regulators Primary & By-Pass
Reclosers Line AND Load Sides
Capacitors
O/H Dead Ends and N/O Switches

53
University of Alberta
Careful There, Electrical Current!
One Last Thing

Be Careful Where You Place an Arrester


Fuses Surge Current Will Hurt a Fuse
Capacitors, Regulators, Reclosers, etc
There is NO line or load on these devices,
at least as surge currents are concerned.

54
University of Alberta
Where to Focus your Protection
Just So YOU Know
Lead Length can ADD up to 1500 Volts/Foot
Lead length is the physical wire distance between the
Apparatus and the Line Side of the Surge Arrester
PLUS (+)
The Line Length from the Ground of the Surge
Arrester to the Ground of Apparatus

AND for the Love of Goodness,


Please Dont COIL the Leads!!!

55 University of Alberta
A Shameless Promotion
arresterworks.com

Jonathan Woodworth Deborah Limburg


Principal Engineer Web and Business Developer

Jonathan started his career at Fermi National Accelerator Laboratory in Deborah is a long term veteran in the arrester industry having worked for
Batavia, Illinois, where he was an integral member of the high energy Cooper Industries for over 25 years. During that time she held a number of
particle physics team in search of the elusive quark. Returning to his home positions in the product engineering department, including leader of the
state of NY, he joined the design engineering team at McGraw Edison Engineering Design Services group. One of her major accomplishments at
(later Cooper Power Systems) in Olean. During his tenure at Cooper he Cooper was the design and implementation of a virtual product drawing
was involved in the design, development and manufacturing of arresters. systems for all major product lines. This lead to a considerable reduction in
He served as Engineering Manager as well as Arrester Marketing Manager the number of Designers and CAD operators required to maintain the
during that time. Since 2008 he has been the Principal Engineer for product documentation system. This database system also helped to
ArresterWorks. improve the overall documentation process due to the reduction in human
errors.
Though his entire career, Jonathan has been active in the IEEE and IEC
standard associations. He is past chair of the IEEE SPD Committee, he is Additionally she developed the software to handle disk selection process for
past chair of NEMA 8LA Arrester Committee, and presently co-chair of IEC the tightly matched disk columns required for series capacitor banks and
TC37 MT4. He is inventor/co-inventor on five US patents. Jonathan the management of the varistor assembly process. Deborah received her
received his Bachelor's degree in Electronic Engineering from The Ohio BS in Computer Software from the University of New York State and is a
Institute of Technology and his MBA from St. Bonaventure University. co-inventor on several US patents.

Contact at 716-307-2431 or Jonathan.Woodworth@ArresterWorks.com Since 2010 Deborah has been the Web and Business Developer for
Arresterworks.

Contact at 716-378-1419 or Deborah.Limburg@ArresterWorks.com

56
University of Alberta
Over-Voltages and the Distribution System

QUESTIONS?

57
University of Alberta
References
1 http://www.picturesof.net/pages/090326-134616-923048.html
2 www.wordy.photos/index.php?keyword=11%20kv%20fuse%20explodes&photo=0XVPcDxoV2g&category=people&title=electric+power+line+explosion
3 http://www.satcomlimited.com/transparent_over_voltages.html
4 http://www.hubbellpowersystems.com/cable-accessories/elbow-arresters/description/
5 http://www.sandc.com/edocs_pdfs/edoc_024494.pdf
6 SURGE ARRESTER APPLICATION OF MV-CAPACITOR BANKS TO MITIGATE PROBLEMS OF SWITCHING RESTRIKES
Lutz GEBHARDT - ABB Switzerland, lutz.gebhardt@ch.abb.com & Bernhard RICHTER - ABB Switzerland, bernhard.richter@ch.abb.com
7 COMPUTATION OF FAST TRANSIENT VOLTAGE DISTRIBUTION IN TRANSFORMER WINDINGS CAUSED BY VACUUM CIRCUIT
BREAKER SWITCHING
Casimiro lvarez-Mario and Xos M. Lpez-Fernndez, Dept. of Electrical Engineering, Universidade de Vigo, EEI,
Vigo, Spain, xmlopez@uvigo.es
8 http://new.abb.com/products/transformers/distribution
9 http://commons.wikimedia.org/wiki/File:37.5kVA_three_phase_utility_stepdown.jpg
10 http://uqu.edu.sa/files2/tiny_mce/plugins/filemanager/files/4310333/traveling_wave.pdf
11 http://revistas.unal.edu.co/index.php/ingeinv/rt/printerFriendly/25218/33722
12 http://io9.com/photos-from-the-days-when-thousands-of-cables-crowded-t-1629961917
13 http://www.edn.com/Home/PrintView?contentItemId=4426566
14 http://www.ecnmag.com/articles/2011/07/advanced-tvs-construction-improves-lightning-protection
15 http://www.nautel.com/support/technical-resources/tips-n-tricks/04-09-2012/
16 http:// www.slideshare.net
17 https://library.e.abb.com/public/a8c42d637aa10aa2c12577ee0055faad/ABB_DPDQPole_Qpole_revB_EN.pdf
18 http://www.cooperindustries.com/content/dam/public/powersystems/resources/library/230_PowerCapacitors/23012.pdf
19 http://www.cooperindustries.com/content/dam/public/powersystems/resources/library/225_VoltageRegulators/MN225008EN.pdf
20 https://www.osha.gov/SLTC/etools/electric_power/illustrated_glossary/substation_equipment/potheads.html
21 http://ecmweb.com/archive/applying-pole-mounted-overvoltage-protection
22 http://www.cpuc.ca.gov/gos/Resmajor/SU6/GO95/SU6_GO95_rule_54_6-F.html

Continued on Next Page

58
University of Alberta
References - continued

23 http://creepypasta.wikia.com/wiki/File:5178_apocalyptic_destruction.jpg
24 http://en.wikipedia.org/wiki/Distribution_transformer
25 http://www.icccable.com/company_product.html?cid=208
26 http://www.powertechlabs.com/areas-of-focus/power-labs/cable-technologies/condition-assessment-the-whole-picture/
27 http://www.ee.washington.edu/research/seal/projects/seal_robot/sensors.html
28 http://www.epa.gov/electricpower-sf6/documents/sf6_byproducts.pdf
29 http://cdn2.hubspot.net/hub/272197/file-251812186-pdf/white_papers/afi-wp-transoil1.pdf
30 http://reliabilityweb.com/index.php/print/defects_in_nonceramic_insulators_can_they_be_detected_in_a_timely_manner1
31 http://www.inmr.com/thermal-inspection-program-finds-failing-dead-end-polymeric-insulators-2/5/
32 http://en.wikipedia.org/wiki/Fallout_shelter
33 http://classicconnectors.com/wp-content/uploads/2012/07/Illustration.jpg
34 Electrical Distribution System Protection, 3rd Edition, Cooper Power Systems, 1990
35 http://www.cooperindustries.com/content/public/en/power_systems/products/voltage_regulators/32-step_single-phase.html
36 https://fisitech.wordpress.com/2010/10/22/practical-issues-switching-surgeac-transcient/
37 http://nepsi.com/services/power-systems-studies/
38 http://file.scirp.org/Html/3-9800140_1113.htm
39 http://electrical-engineering-portal.com/definition-basic-insulation-level-bil
40 http://www.schneider-electric.com/download/hk/en/details/18865768-General-Specification-for-Fixed-Capacitor-Bank-for-Electrical-Network-up-to-
36kV/?reference=Fixed_capacitor_bank_36kV_specENv2
41 http://www.hubbellpowersystems.com/catalogs/arresters/31_optima.pdf
42 http://www.coe.montana.edu/ee/seniordesign/archive/SP13/150mwwindfarm/Data_Content/InsulationCoordination.pdf
43 - http://electrons.wikidot.com/semiconducting-ceramics:varistor-applications

59
University of Alberta

Vous aimerez peut-être aussi