JABATAN PEMBANGUNAN KEMAHIRAN

KEMENTERIAN SUMBER MANUSIA


ARAS 7 & 8 BLOK D4, KOMPLEKS D
62530 PUTRAJAYA

KERTAS KERJA
PROGRAM / PROGRAM NCS CORE ABILITIES (Z-009)

TAHAP / LEVEL L4

NO. DAN TAJUK MODUL


02 PROJECT MANAGEMENT
/ MODULE NO. AND TITLE

05.05 : COORDINATE CONTRACT AND TENDER


ACTIVITIES
KEBOLEHAN / ABILITIES 05.03 : ALLOCATE AND RECORD USAGE OF FINANCIAL
AND PHYSICAL RESOURCES
04.09 : PREPARE PROJECT / WORK PLAN

AT THE END OF THIS MODULE, TRAINEES WILL BE ABLE


TO ;
OBJEKTIF MODUL / 1. COORDINATE CONTRACT AND TENDER ACTIVITIES
MODULE OBJECTIVE 2. ALLOCATE AND RECORD USAGE OF FINANCIAL AND
PHYSICAL RESOURCES
3. PREPARE PROJECT / WORK PLAN

NO. KOD / CODE NO Z-009-4/ M02/K(3/3) Page : 1 of : 4

TAJUK / TITLE : PROJECT MANAGEMENT DECISION MAKING

TUJUAN / OBJECTIVE(S) :

The trainee must be able:-

1. Calculate the shortest duration


2. Determine the ordering/reordering points using MRP.
3. Determine the EOQ.

LUKISAN/DATA/JADUAL/DRAWING/DATA/SCHEDULE :

Nil
NO. KOD / CODE NO Z-009-4/M02/K(3/3) Page: 2 of : 4

ARAHAN/INSTRUCTION:

You are appointed to manage a project and required to handover/deliver the products based on
the time required as below:

3 days

4 days
8 days
3 days

5 days

4 days

The project need to go all the stages (A to F).

1. Calculate the shortest duration to complete the project.


2. If at stage C,
a. Lean time is 4 days,
b. The daily usage of material is 5 units
c. And the buffer stocks is set at 2 units,

Determine the ordering/reordering points using MRP.

3. If at stage D
a. Order quantity is 5
b. Demand per unit is 20 units
c. Periodical is based on the duration of the stage
d. Carrying / Holding Cost is RM3
e. Order Cost is RM0.50

Calculate the EOQ.

PERALATAN/PERKAKASAN/BAHAN/TOOLS, EQUIPMENT/MATERIALS :

1. Stationeries
2. White board
3. Computer set
4. Calculator
NO. KOD / CODE NO Z-009-4/M02/K(3/3) Page: 3 of : 4

WORK STEPS WORK DETAILS

1. Calculate the
1.1 Identify The critical path.
shortest duration
1.2 Calculate the duration.

2. Determine the
2.1 Identify the MRP formula.
ordering/reordering
points using MRP. 2.2 Calculate the value.
2.3 Determine the ordering/reordering point.

3. Determine the EOQ.


3.1 Identify the MRP formula.
3.2 Calculate the value.
3.3 Determine the ideal amount of order.
3.4 Determine the order cost.
NO. KOD / CODE NO Z-009-4/M02/K(3/3) Page: 4 of : 4

CHECK LIST :

(Must be filled in by Assessor)

Not
No. Steps / Work Procedure Accepted
Accepted
1. The critical path identified.
2. The duration calculated.
3.
The MRP formula identified.
4. The value calculated.
5. The ordering/reordering point determined.
6. The MRP formula identified.
7. The value calculated.
8. The ideal amount of order determined.
9. The order cost determined.

___________________________ ________________________

(Trainees Signature) (Assessors Signature)

__________________________ ________________________

Date Date

RUJUKAN/REFERENCE(S):

1. Information Sheet Z-009-4/M02/P(2/2) Project Management Decision Making