Vous êtes sur la page 1sur 18

Causes and Prevention of

Problems in Large-Scale
Prestressed Concrete
Construction

Ben C. Gerwick, Jr.


Consulting Construction Engineer
San Francisco, California
(Also, Professor of Civil Engineering,
University of California at Berkeley)

A ogy is applied extensively, we


s each new construction technol- the successes and the possibilities, we
boast of; proud of our achievement, and
gain the confidence and capability to eagerto enthuse and to generate new and
exploit its potential to ever more bolder projects.
sophisticated structures. We also build The second type, the problems, we
up a storehouse of problems: difficul- hide, dismissing unpleasant events,
ties and local failures. In most or even blaming others, getting caught up in the
all cases, we eventually repair and re- maelstrom of legal involvements, and,
construct the facility; thereby success- above all, trying to avoid on-going liabil-
fully completing the project, although ity.
not without worry, delay, and cost. Difficulties which are not openly and
We normall y treat these two types of frankly faced seem destined to repeat
experiences quite differently. The first, themselves on future projects.
Thus has run the story of prestressing
NOTE- This paper is based on a presentation in general and post-tensioning in par-
given at the Segmental Concrete Bridge Confer- ticular: great successes, exciting poten-
ence in Kansas City, Missouri, March 9-10, 1982.
The Conference was sponsored by the Associated tial, yet beset with numerous cases of
Reinforcing Bar ProducersCRSI. Federal High- local failures and difficulties, which
way Administration, Portland Cement Association, were generally resolved and repaired to
Post-Tensioning Institute, and Prestressed Con-
crete Institute. enable successful completion of the

58
project. The learning experience gained
at great cost can only be transferred to
our widely spread profession if we are Synopsis
willing to record and study problems
and their solutions and to present them The application of prestressing to
frankly and objectively, so that all may large and complex concrete struc-
benefit from the dispersed experience. tures such as long-span bridges, nu-
In this paper, examples will he drawn clear containments, and offshore
from several recent bridges, including platforms has enormously enlarged
the 1-205 Columbia River Bridge, nu- our experience in practical construc-
clear reactor containment vessels, and tion. Major projects, although com-
concrete sea structures, especially the pleted successfully, have frequently
Ninian Central Platform. In all cases, encountered problems in the applica-
the problems and local failures were tion of the prestressing. Many of
overcome, and the projects were suc- these problems repeat themselves in
cessfully completed. The cooperation of projects of different types, locations,
the contractors and the engineers in and systems. It is believed that a
carrying out the repairs and reconstruc- frank and open discussion of these
tion promptly and effectively was in- projects will benefit both the designer
strumental in preventing their de- and constructor.
velopment into more serious problems. The specific problems described in
It must be emphasized here that the this paper were all corrected during
opinions presented in this paper are construction, the projects have been
solely those of the author and not of the successfully completed, and in-
designer, contractor, or owner. Further, service performance has been ex-
descriptions and assignment of causes tremely satisfactory. The repair
have purposely been simplified, since methods utilized included epoxy in-
in practice several causes and effects jection, stitch bolting, supplemental
are often overlapped. post-tensioning and reconstruction of
the damaged area.
On future projects, appropriate
PROBLEMS AND specifications, design details and
SOLUTIONS construction quality control can pre-
vent their recurrence. Behind the im-
mediate causes lie more fundamental
The main and anchor arm spans of the causes, inherent in our present con-
1-205 Columbia River Bridge (Fig. 1) are tracting procedures, which deserve
among the longest in North America, reconsideration.
480-600-480 ft (146-183-146 m). The con
-tracoeldnsuthpaby
the cast-in-place segmental method. He
used two pairs ofoverhead form travelers
to form and support segments until they curing, stressing the segments lon-
were temporarily post-tensioned back to gitudinally, and partially stressing the
the previously completed sections. transverse tendons in the deck ran
The cycle time for partially collaps- about 7 days; although at later stages,
ing the form, moving the traveler with a shallower section, fewer ducts
ahead, anchoring the traveler down to and more experience, the cycles were
inserts in the deck, expanding inner shortened to 4 days.
forms, placing ducts and reinforcing Concrete achieved a strength of 2500
steel, closing outer forms, concreting, psi (17.2 MPa) in 1 day, sufficient for 50

PCI JOURNAL/May-June 1982 59


Fig. 1. Main span of 1-205 Columbia River Bridge.

percent of the permanent stressing, and Freezing of Water in Ducts


3500 psi (24.1 MPa) in 2 days, sufficient In the contractor's value engineering
for full stressing. Results of field cured redesign, the shear near the piers was
concrete cylinder breaks were con- to he resisted by vertical prestressing,
firmed by the Swiss hammer test. installed in U ducts. The first winter,
Vertical and horizontal alignment were only a few months after the main span
maintained within relatively close tol- construction had commenced, a period
erances. The profile was adjusted for of heavy rains was followed by a sud-
camber and allowances were made for den freeze. Some of the ducts had not
creep. Closure pours at midspan were been tightly sealed at deck level; as a
made after a delay of several months, so result the ducts filled up with water
as to enable creep deformation to occur. which subsequently froze, causing
The extended arms of each cantilever multiple through-web cracks in the
were strutted and tied (including diag- webs and, more seriously, laminar
onal ties), so as to prevent relative cracking in the bottom flange at the
movement while the concrete of the bottom of the U's [Figs. 2 and 8(1)].
closure was placed. Ten percent of the Repairs to the webs were carried out
lower slab continuity tendons were by epoxy injection. Since there was
stressed after final set. ample reinforcement, both horizontal
Concreting was carried out in the and vertical, in the webs, no problems
evening, so cantilevers were tending to were encountered in achieving full
rise. Before full sun the next morning, restoration (Fig. 3).
the struts at the bottom were cut and 30 In the bottom slab, adjacent to the
percent more of the lower continuity web, the 12 in. (305 mm) thick flange
tendons were stressed. had laminated horizontally, usually

60
Fig. 2. Water freezing in ducts.

Fig. 3. Epoxy injection of web cracks.

PC! JOURNAL/May-June 1982 B1


Fig. 4. Epoxy injection of bottom flange.

about 4 in. (102 mm) above the soffit. 1. The deck slab itself was effec-
The extent of the area affected was de- tively divided into upper and lower
termined by hammer sound, corrobo- portions by the very closely spaced
rated by the drilling of cores. These longitudinal ducts in the deck areas
cracks were in-plane laminations, not adjacent to the pier. Although ducts
crossed by steel. were designed to be spaced apart, in
Some temporary stitch bolting was many areas, especially where they were
installed by drilling through the bottom horizontally curved, they touched. The
slab. Epoxy injection was then carried area of concrete on horizontal planes
out in small stages, working inward near midsection was less than half the
from the edges, and using low pressure deck area.
so as to avoid hydraulic fracturing and 2. The close spacing of ducts, coin-
crack propagation (Fig. 4). Test cores bined with transverse ducts, and lon-
and hammer testing indicated full gitudinal and transverse reinforcing
homogeneity of the restored section. steel in the top and bottom, made it
very difficult to effectively place and
Laminar Spalling in Deck consolidate concrete around and under
Minor laminar spalling was visually the ducts and reinforcement. Appar-
noticed in the underside of the top ently concrete did not always work its
flange (deck slab) during and after way up around the ducts [Figs. 5, 8(2)].
post-tensioning of the negative moment 3. Concreting practices were not
tendons. Acoustic checking (hammer) conducive to full concrete integrity.
revealed other and much larger areas of Concrete crews often stood or walked
delamination. in the fresh concrete, which in turn
The causes appeared to be several pushed the ducts and reinforcing bars
and were interactive. down, only to spring back up as the

62
M"
Fig. 5. Longitudinal ducts spaced too closely.

men moved. This may have caused a 6. Early grouting experience showed
laminar separation in the concrete. Vi- that considerable grout leakage was oc-
bration apparently did not always ex- curring. Not only was the grout plug-
tend deeply enough to knit top and ging adjoining ducts before the tendons
bottom layers of concrete together and were placed and stressed, but grout was
to force concrete up between closely- intruding into laminar cracks, making
spaced ducts. detection and repair more difficult.
4. Bleed water collected under the The practice was therefore adopted of
flat transverse ducts and also in the re- stressing two or more closely adjoining
cess or V formed by two touching lon- tendons before grouting any in that
gitudinal ducts. cluster. Unfortunately, in several cases
5. Longitudinal ducts were held in there was a slight horizontal bend
exact position at the leading edge form where the tendons curved out of the
stop. In between they were deflected deck slab towards the web. Stressing of
downward by the weight of the con- the tendon on the outer side of the
crete and men walking in the fresh con- curve caused the duct to crush into the
crete. This meant that there was a small adjoining duct, distorting it vertically
but significant upstanding peak in the and apparently causing the underside
duct profile at each construction joint. to spa]! (Figs. 6, 8(4)].
When the tendons were later stressed, a 7. The cause of many of the leaks in
downward component of the tendon the ducts, enabling grout to penetrate to
force was imparted to the concrete in fill adjoining ducts and to spread into
the lower portion of the slab. It ap- existing laminar cracks, thus causing
peared that this was the precipitating hydraulic crack propagation, appears
cause in many of the cases of laminar due to inadequate sealing of the splices
cracking in the deck slab LFig. 8(3)]. and to poor consolidation of the con-

PCI JOURNAL May-June 1982 63


Fig. 6. Crushing of ducts during stressing.

crete around the splices, especially from scaffolding inside the boxes, the
where they almost touched one crews drilled in and anchored stitch
another. bolts (headed expansion bolts), usually
In many cases the splice sleeve fit on 2-ft (0.61 m) centers both ways.
very loosely, leaving an annular gap. Epoxy injection was then carried out
Even though the joints were seated using closely-spaced injection points
with watertight tape, these seals appar- and keeping pressures low, generally at
ently ruptured whenever concrete was 20 psi (0.138 MPa).
not densely compacted around them. In Other methods were tried as a means
some cases where sealing tape was in of detecting laminations. They were
direct contact with the sealing tape of generally unsuccessful, due to the false
an adjoining duct, the grout could break and confused readings imposed by the
directly through. congestion of ducts and reinforcing
This problem of grout leakage at ad- steel. The hammer gave quite reliable
joining splices has reportedly occurred results, revealing laminations by a dull
in many bridges in Europe. It appears sound as opposed to a sharp ring from
that our present details are not ade- fresh concrete. Coring proved useful in
quate for cases where adjoining or determining the locations of the cracks,
touching ducts must be spliced at the i.e., the depth to the crack; and in
same point. determining the crack width.
In many cases, several causes in- Prevention of these problems should
teracted, so that it was difficult to assign properly start with design: the selection
the laminar cracking to one single fac- of tendon sizes and duct spacing to
tor. A crack initiated by one cause was maximize the concrete area at mid-
propagated by a second cause. depth (i.e., that area capable of trans-
When laminations were found, their mitting tensile forces through the
extent was carefully determined by thickness of the slab). A larger number
hammer testing and coring. Working of strands per tendon or larger wires

64
could well be employed. For example, be installed before the duct is installed.
the 19 x 0.5-in. (12.7 mm) tendons could Plastic caps, taped on, are recom-
presumably have been increased to 24 x mended,
0.6 in. (15.4 mm), thus decreasing the Drains should be provided in the
number of tendons by 40 percent and bottom of the duct profile, since caps
increasing the in-plane (horizontal) are seldom absolutely watertight.
mid-depth concrete area by 70 percent. An alternative system is to fill the
Through-slab stirrups or ties would duct with a mixture of glycol antifreeze
he useful in preventing the propagation and water, so as to lower the freezing
of laminar cracks. On the I-205 Cohun- point. This was successfully employed
bia River Bridge, after initial laminar on the Statfjord C platform.
cracking problems were discovered, Blowing out of ducts, using com-
No. 3 vertical ties were installed on pressed air, in order to assure they are
24-in. (610 mm) centers, between pairs water-free, is a questionable practice.
of closely-spaced ducts. While such ties In the first place, there can be no assur-
may limit crack spread, they cannot ance that all water has been displaced.
prevent their occurrence. More serious is the fact that the air,
Tightly-fitting splice sleeves appear under a pressure of 110 to 115 psi
to be essential. Commercial ducting is (about 8 MPa) can transfer a high pres-
available with closely spaced ribs sure to the water ahead of it or trapped
(threads) that enable the sleeve to be in cracks and voids, thus leading to hy-
screwed on with a relatively tight fit. draulic fracturing and crack propaga-
Such tightly fitting splice sleeves are tion.
now being used on the Statfjord C It is significant to note that several of
platform in Norway. Subsequent taping the cases of lamination were noted only
of both ends of the splice sleeve with during this process of blowing out; this
heavy duty waterproof tape should then apparently was when minor damage
suffice to prevent grout leakage even was transformed into serious damage.
where, due to extraneous reasons, minor This same phenomenon has been re-
voids or cracks exist. At least a 1-in. (25 ported from The Netherlands. The au-
mm) space between adjacent ducts thor believes that if the duct has be-
should be left in order to assure ade- come water-filled for any reason, it is
quate concreting. better to use a thixotropic grout to dis-
Ducts themselves should be of heavy place it, and to continue grouting lung
enough gauge to prevent local defor- enough after the first grout emerges
mation. When thin ducts deform under from the exit vent to ensure complete
bending, the seams open, permitting displacement of the water [e.g., 3 to 4
grout in-leakage. Friction factors are in- liters (about 1 gallon) of wasted grout].
creased by deformations. Splices are During concreting, all workmen (and
rendered more difficult. Angular inspectors) should work from bridges
changes and hence local bursting which span across the reinforcing steel
stresses are more prevalent and serious and fresh concrete. Great pains should
with thin ducts. Although 0.6 min be taken to work the concrete under the
(0.023 in.) gauge is widely used, ex- reinlorcement and to vibrate through all
perience indicates a thicker gauge, for interfaces as concrete layers are placed.
example, 1.0 mm (0.039 in.), would be Adjoining horizontal ducts should be
preferable. held apart by spacers in order to allow
To prevent rain water from entering mortar and concrete to work up through
vertical or inclined ducts, with sub- the gap.
sequent freezing, covers should be pro- It has been found extremely instruc-
vided. Preferably, these covers should tive to construct a full scale mockup of a

PCI JOURNALIMay-June 1982 65


Fig. 7. Inspecting the laminar cracks in deck.

short section, with all reinforcement and The thicker ducts and careful blocking
ducts, and to place the concrete; then also help.
after curing, to strip the forms and cut When closely-spaced ducts have
the concrete apart with paving break- bends, which can make them suscepti-
ers. The workmen then can actually ble to displacement into one another
see the results of their work and the during stressing, the use of spacers and
need for proper placement, while trou- saddle plates is advised. The tendon on
blesome details of congestion and in- the inside of the curve must be
terference can be corrected by the de- stressed, and grouted before the one on
signer and concrete mixes can be op- the outside of the bend is stressed. This
timized insofar as workability is con- applies, of course, to vertical as well as
cerned. Concrete mixes must be de- horizontal curves.
signed not only for workability and In one case on the I-205 bridge (Fig.
cohesiveness, i.e., lack of segregation, 7) the upper portion of the deck slab
but also to minimize bleed and air en- laminated and spalled, affecting an area
trapment. 16 x 32 ft (5 x 10 m). The lamination
Support of the extended forms in occurred at the underside of the lon-
cast-in-place segmental construction gitudinal ducts. Investigation revealed
requires heavy diagonal as well as ver- that the longitudinal ducts had been
tical ties so as to minimize deflections deflected downward to accommodate
during concreting. The soffits of slabs the deflected profile of the transverse
need to be adequately stiff to minimize ducts; the upward component of the
deformation as concrete is placed. two prestressing systems exceeded the
Ducts should be supported during tensile capacity of the remaining con-
concreting so as to prevent sag. Use of crete areas at that level [Fig. 8(5)].
an internal mandrel of relatively stiff Spatting occurred during blowing out of
pipe is one method that has been found water from the last fcw unstressed ducts.
successful in segmental construction. It is believed that this blowing out prop-

66

^^- 00 00

Ioid

I. LAMINAR CRACKING DUE TO WATER 2. CLOSELY SPACED LONGITUDINAL


FREEZING IN VERTICAL DUCTS. AND TRANSVERSE DUCTS
EFFECTIVELY DIVIDE DECK SLAB
ON HORIZONTAL PLANE.

Segment
1
Segment
2
Segment
3
00 i

3. LONGITUDINAL PROFILE OF TENDONS 4. STRESSING OF OUTER TENDON


SHOWING DOWNWARD FORCE AT DEFORMS INNER DUCT,
CONSTRUCTION JOINTS. EXERTING VERTICAL FORCES.

F*A
0000 00
___

5. PIER 13 PIER TABLE. DEFLECTION OF LONGITUDINAL TENDONS


CAUSES LAMINAR SPALLING.

Fig. 8. Schematic representation of cracking (see also Fig. 12).

agated and extended laminar fracturing Slip of Dead End Anchors and
initiated by the stressing of tendons on Spalling at Anchors
the deflected profile.
In this case, the repairs were carried There were several cases in which
out by removing the damaged concrete, the H-type dead end anchor failed
thus allowing the tendons to raise to a during stressing, especially where there
level profile; then installing drilled-in was an angle change near the anchor.
anchor bolts and using an epoxy bond- In some cases, the measured elongation
ing compound as the new concrete was was 35 to 50 percent greater than cal-
placed, so as to make it act monolithi- culated and severe laminar and
cally (Fig. 9). horizontal cracking occurred at the an-

PCI JOURNALMay-June 1982 67


Fjt &
'Pit

TI
; r Mme..: is Gam.: :

'i_a; _
___

rr4
- ..
mar .. .._
tiir4^.T
-

Fig. 9. Repairs to deck after laminar cracking.

chorage itself (Fig. 10). Usually after a amount and type of lubricant used in
slip of several inches, the anchor drawing the wire. If stress relieving is
would re-establish itself mechanically. performed by gas, it tends to burn off
Slippage of this type has also oc- contaminants whereas if performed in
curred with pretensioning, as in rail- electric furnaces, it tends to bake the
road tie manufacture. One cause ap- contaminants on as a glaze.
pears to lie with the manufacture of the Proper confining steel around the an-
strands, i.e., a long lay length reduces chorage can help to prevent such
bond. Another cause lies with the cracking and slippage. If the dead end

Fig. 10. Slip of dead-end anchor.

68
Fig. 11. Shear and tension failure at anchorage.

anchor has been allowed to sag or if Obviously, the stressed zone tends to
there is a sharp bend near the anchor, shorten although it is restrained par-
then there is a radial force developed, tially by the adjoining slab and webs.
which in some cases has led to crack When the force exceeds the shear or
initiation, followed by laminar (in- tensile strain capacity, cracking occurs,
plane) cracking and intense local which quickly propagates as the re-
spalling. Such spalling near anchorages straining force is relieved. Either a
has led to similar spalling and crack major local failure occurs around the
propagation on both the Frigg and Stat- anchor or, more seriously, cracks be-
fjord A platforms. Local confining steel, hind the anchor propagate transversely
augmented by full through-wall stirrups to the webs and up them, thus reducing
at the zone of curvature, is required, the shear capacity. The design of rein-
since the radii of curvature are usually forcement in this area must consider
sharp (intentionally or unintentionally) the transfer of stress. Sufficient lon-
even if the degree of curvature is small. gitudinal steel behind the anchor, and
transverse steel abreast the anchor,
Cracking Behind Anchorages must be provided to take the initial ten-
sioning forces (Fig. 11).
In several cases, most seriously a
bridge in Southern France, the anchor-
age of Iarge forces in a concentrated Grouting of Vertical Ducts
zone, e.g., the anchorage of positive Based on extensive experience with
moment (continuity) tendons in but- the grouting of vertical tendons in nu-
tresses in the bottom slab has led to clear reactor containment structures
serious transverse cracking behind the and on North Sea offshore platforms, a
anchorages, that is, in the unstressed thixotropic admixture was used in the
zone away from the tendon direction. grout for the vertical duets in the 1-205

PCI JOURNAL/May-June 1982 69


Stressed bolls

Form supports 4 Adjustment


Previously-concreted
segment

6. ADJUSTMENT OF EXTENDED FORM


PLACES HIGH FORCE IN BOLTS AND
ON CONCRETE, CAUSING CRACKING.
SOME BOLTS ACTUALLY PULLED THROUGH SLAB

Local
damage

r C. 1

Domaged duct

Extended
Construction joint
ducts

N1NIAN,DAMAGE TO DUCTS AT CONSTRUCTION JOINT


LEADS TO JAMMING OF TENDON IN DUCT.

Concrete dumped
onto duct

" s P
wolf
o
9

1 JI ConcreteU_ Rupture
dumped
Deformation Slob t IT Splice
Reinforcing
bar Preformed
U tube

B. DEFORMATION OF DUCTS 9, RUPTURE OF SPLICES OF


BY REINFORCING BARS. VERTICAL DUCTS TO U DUCTS.

Fig. 12. Schematic representations of local failures (see also Fig. 8).

Bridge. This greatly reduced the vent itself was filled with grout. It ap-
sedimentation and bleed but did not pears that the joint application of thixo-
entirely prevent a small void under the tropic admixtures, standpipe, and sec-
anchorage. ondary grouting, as described in the
Secondary grouting was employed FIP Report on Grouting of Vertical
but even then a tiny void was often Tendons, published in 1978, is neces-
found below the vent, even though the sary to ensure full grout encasement.

70
Form Support
As forms are moved forward for con-
struction of a new segment in cantile-
vered segmental construction of long-
span bridges, they are supported at the
leading end by the overhanging form
traveler and at the rear by anchorage to
the previously-constructed segment.
They are usually anchored down by
prestressing rods to the previously-
constructed segment. Any subsequent
adjustment of profile places very high
stresses in these anchor bars, which in
turn, cause high local stresses in the
concrete where they are anchored [Fig.
12(6)].
On the I-205 Bridge, in several cases,
this led to concrete spalling and crack-
ing and, in extreme cases, to pull-
through of the bars.
The details of these supports should
perhaps be modified. Perhaps a neo- Fig. 13. Ninian central platform.
prene pad at the compression edge
would permit a small amount of rota-
tion. Alternatively, the leading end bars, in order to provide proper shear
must be capable of readjustment of resistance. These bars were placed in
profile without placing additional two sections, the cast-in-place concrete
stresses in the support. If the profile proceeding vertically in two "seg-
were adjusted before the rearward bars ments." The bars were coupled with a
are stressed, then this would also standard threaded coupler, carefully
minimize the problem. screwed onto the first bar for a mea-
The leading ends must also be prop- sured distance.
erly held up to prevent serious deflec- When the second bar was placed, the
tion as concrete is placed. Obviously coupler was almost inaccessible and
concrete should be placed first at the hidden by the congestion of forms,
far end, working hack to the joint. In reinforcing steel, and ducts. The second
one German bridge, it is reported that bars were screwed into the couplers
diagonal rods stretched during con- and the upper segment cast. During
creting of the deck slab, allowing cracks stressing, many bars stripped the
to form along the web joint, thus re- threads of the couplers. Investigation
ducing shear transfer. While epoxy in- showed that they had engaged only a
jection proved to he a satisfactory re- portion of the threads.
pair, design of the form supports should Tests show that whether vertical or
consider deformation under each stage horizontal bars are involved, the act of
of concrete placement.
screwing in the second bar tends to ro-
tate the coupler on the first bar, screw-
Couplers ing it further on, instead of engaging
The plinth wall of the base raft of the coupler. This is because the friction
another North Sea platform required a of the second bar is higher, due to in-
large number of vertical prestressing evitable minor misalignment.

PCI JOURNAL/May-June 1982 71


After trying lock nuts and wire jam- Horizontal bends were made with
ming unsuccessfully, the practice was flexible ducting in order to work around
adopted of coating the first bar with interfering reinforcement. Although the
epoxy, so that it would bond to the cou- overall radius of the bend was large,
pler. This worked quite satisfactorily as local small but sharp bends were made,
a job-site remedy. It is believed that especially at their juncture with the
future coupler designs could be mod- heavier-walled straight duct runs.
ified to provide a positive stop at mid- Flexible ducting was deformed and
point. locally crushed as concrete was
This same problem occurred years dumped onto it. The ducts were occa-
earlier with an anchored retaining wall, sionally forced down onto crossing
but the cause at that time was incor- reinforcing bar supports, denting the
rectly assigned to careless workman- duct [Fig. 12(8)1.
ship. With vertical U tendons, the dumping
The Ninian Central Platform con- of concrete onto the U tore it loose from
structed in Scotland, is one of the the vertical duct legs, allowing mortar
largest offshore platforms in the North to fill the U [Fig. 12(9)].
Sea (Fig. 13). It has a circular base 460 As vertical ducts were extended up-
ft (140 m) in diameter and the concrete ward, many were temporarily covered
portion is over 500 ft (152 m) high. Its only by rags or left uncovered. As a re-
base consists of seven concentric walls sult, the 165 to 328 ft (50 to 100 m) long
(Fig. 14), joined by radial shear walls vertical ducts were often blocked by
(Fig. 15). Both horizontal and vertical such foreign objects as coca cola bot-
prestressing was employed. The hori- tles, screw drivers, milk cartons, gravel,
zontaI tendons radiated out to the ex- waste concrete, etc. Similar careless
terior walls, and then returned on an blockage has been reported from other
adjoining radial, whereas the vertical North Sea platforms.
tendons had a U bend at the base. Attempts to unplug ducts by high-
pressure jets, rotating flexible drills,
etc, were only partially successful and
Duct Blockages
never worked at U bends. In some
In the Ninian Central Platform a cases, it was necessary to chisel in from
number of troublesome duct blockages the side of the concrete wall to free a
occurred. These prevented insertion of plug. In other cases, rock anchors were
the tendons as planned. The causes used as a dead end anchor. In a few
were several, cases, the tendon in question had to be
At vertical construction joints, the abandoned. Fortunately, in most cases,
protruding horizontal ducts formed a it proved feasible to install larger ten-
very convenient ladder for workmen to dons than planned, i.e., more strands
climb, resulting in local crushing at the per tendon, in the adjoining ducts.
splice [Fig. 12 (7)]. Preventive steps initiated on this
The ends of ducts were often cut by a project included the following:
burning torch, resulting in ragged and 1. Use of heavier-walled duct wher-
burred ends. ever feasible, preforming bends as
A double-female splice sleeve was necessary.
used, which meant that as strands were 2. Cutting ends of ducts with a
pulled and pushed in, their nose often hacksaw, not a burning torch.
caught on the inner burred and de- 3. Changing splice details so that as
formed end. Continued efforts to insert tendons were entered, the nose always
the tendons just tore up the thin-walled travelled from a male into a female end,
duct and eventually jammed it tight. so that it could not catch.

72
Fig. 14. Radial shear walls of Ninian platform.

Fig. 15. Concentric walls of Ninian platform.

PCI JOURNALJMay-June 1982 73


4. Electrical conduit or thin-walled One fact stands out clearly: the cost
pipe mandrels were placed inside of unplugging ducts or correcting lami-
flexible ducts during concreting, then nar cracks and other problems far ex-
withdrawn after initial set. ceeds the cost of doing the job correctly
5. Colored plastic caps were taped at the start. It is true that heavier walled
onto all vertical duct segments before duct is more expensive to purchase and
being placed, and were Ieft affixed until sometimes more expensive to install,
the next duct length was installed. but its total cost is minimal in compari-
6. Where flexible duct had to be son with the correction of problems that
used, it was supported by heavy sheet may occur with ducts of minimal thick-
metal "saddles" wherever it bore on ness.
crossing reinforcing. Repair procedures have been de-
7. In the case of U ducts, a hose was veloped and proven in the field which
placed inside during concreting, with- ensure restoration of full structural
drawn after initial set. capacity in most cases of damage. How-
On both the Ninian and the other ever, their implementation requires
offshore platforms referred to, bill in- extra efforts and costs to both construc-
tegrity of the structure was accom- tor and designer, delays in project com-
plished by these repairs and supple- pletion, and often results in claims.
mental steps, but the costs in delays A major part of the problem appears
and extra work were substantial. to he contractual. The present relation-
ships of owners, designer, general con-
struction contractor and specialist sub-
CONCLUSIONS contractors are of questionable applica-
Problems such as those enumerated tion to highly sophisticated and com-
above are not unique to the particular plex work such as long-span bridges,
projects described, but appear to be nuclear reactor containment vessels,
endemic. Hence, a full discussion of and ocean structures. Three or more
them seems appropriate in order to entities are performing inter-related
eliminate or minimize their occurrence and overlapping items of work. The de-
on future projects. The problems can be signer has selected the prestressing
prevented in most cases by proper de- force and location and usually provides
tailing, proper specifications and care- sonic of the details, but he usually does
ful quality control in the field. How- not know which system will be used.
ever, since the various post-tensioning The general contractor lets one sub-
systems differ in details and each proj- contract to a reinforcing steel subcon-
ect has its own special requirements tractor, and another to a prestressing
and difficulties, it may not be possible subcontractor, almost always on the
to write general rules that will ade- basis of lowest quoted price, often the
quately cover all problem areas. In such result of severe competition and exten-
cases it is necessary to revert to basic sive haggling. This general contractor
principles, in which the effects of con- usually provides the supports, the
centrated force, the strains and distor- forms, places the concrete, vibrates it,
tions, bi- and tri-axial effects, crack and places inserts.
propagation and its antidote, a crack- The reinforcing steel subcontractor
arresting mechanism, are all carefully places reinforcing steel with only
considered. Both designer and con- superficial appreciation of the impor-
structor need to train themselves to vis- tance of accuracy in the detailed rein-
ualize the sequential three- forcement around anchorages and duct
dimensional, multi-material processes bends. Sometimes he places the ducts
involved. as well, with little appreciation of the

74
importance of alignment, grout tight- contractor, reinforcing steel subcon-
ness, etc. tractor, and prestressing steel subcon-
Then the prestressing subcontractor tractor are all working for their common
arrives. He furnishes the detailed rein- good and that of the owner and de-
forcement around the anchorages, signer. The failure of any one of them
places ducts, if not already placed, in- seriously impacts the performance of
serts tendons, stresses and grouts. He is the others. Is subcontracting of field
dependent on the general contractor for labor really advisable, or should the
hoisting and for access. three groups all be tinder the general
Each of the above is dependent on contractor's control? In some projects,
each other's performance to a high de- the subcontractor furnishes specialist
gree, yet each is under a severe con- personnel on a cost-plus-fee basis to the
straint as to costs. His profit or loss de- general contractor.
pends on labor productivity and Perhaps consideration needs to he
minimum material costs, and minimal given to the British system of a nomi-
delays. nated specialist subcontractor.
The owner has a different set and Finally, it is a tribute to the contrac-
scale of concerns. He is of course in- tors and engineers and subcontractors
terested in a low final cost, but the suc- on all the projects referred to above,
cess or failure or even the selection of that despite the many minor but im-
concrete instead of steel, seldom if ever portant problems, all were completed
depends on such small components as as fully satisfactory structures. This il-
the cost of ducting or grouting proce- Iustrates the inherent flexibility and the
dures, or reinforcing steel details. Quite wide range of solutions available with
to the contrary, his risks are those of se- this elasto-plastic composite material
vere delays, of claims, and in some rare called prestressed concrete.
cases, of a less than satisfactory final For other discussions of similar
structure. problems and solutions, see References
It is the author's opinion that the 1, 2, and 3. The first paper discusses
owner's representatives and design en- examples from France and the Nether-
gineers do not always recognize the lands; the second article, cases from
owner's true needs. In their endeavor Germany; and the third paper, causes
to secure the lowest possible bid and prevention of problems on the
prices, they often permit too wide a 1-205 Columbia River Bridge.
range of options and leave too many as-
pects up to the contractor and his sub-
contractors. The recent history of REFERENCES
post-tensioning, both problems and 1. Bouvy, J. J., and Fuzier, J,-Ph "Problems
successes, would seem to indicate that Encountered in Segmental Bridges,
the designer should give full attention Etc.," FIP Proceedings, V. 3, 1982, pp.
to a detailed original design, should 234-243.
2. Leonhardt, F., "Prevention of Damage in
write very complete and rigid specifi- Bridges," FIP Proceedings, V. 1, 1982,
cations, should check shop drawings pp. 58-65.
meticulously, and should ensure strict 3. Harwood, Alan C., "I-205 Columbia River
quality control of field operations. Bridge Design and Construction," PCI
Some contractual mechanism has to JOURNAL, V. 27, No. 2, March-April
be developed to ensure that the general 1982, pp. 56-77.

NOTE: Discussion of this paper is invited. Please submit


your discussion to PCI Headquarters by January 1, 1983.

PCI JOURNAt1May-June 1982 75

Vous aimerez peut-être aussi