Académique Documents
Professionnel Documents
Culture Documents
Where instruments are mounted at higher elevations, it must Branch headers should be self draining and have adequate
be ensured that they are accessible either by permanent or drainage/blow-off facilities. On small headers this may be
temporary means. achieved by the instrument air filter/regulators.
Instruments should be located as close as possible to Each instrument air user should have an individual filter
their process tapping points in order to minimize the length regulator. Piping and fittings installed after filter regulators
of impulse lines, but consideration should be paid to the pos- should be non-ferrous.
sibility of expansion of piping or vessels which could take
place under operating conditions and which could result in
damage if not properly catered for. All brackets and supports 38.5.2Pneumatic Signals
should be adequately protected against corrosion by priming
Pneumatic transmission signals are normally in the range
and painting.
of 0.21.0 bar (315psig), and for these signals copper
When installing final control elements such as control
tubing is most commonly used, preferably with a PVC
valves, again, the requirement for maintenance access must
outer sheath. Other materials are sometimes used, depend-
be considered, and clearance should be allowed above and
ing on environmental considerations (e.g., alloy tubing or
below the valve to facilitate servicing of the valve actuator
stainless steel). Although expensive, stainless steel tubing
and the valve internals.
is the most durable and will withstand the most arduous
service conditions.
Plastic tubing should preferably only be used within
38.5Piping systems control panels. There are several problems to be considered
when using plastic tubes on a plant site, as they are very
All instrument piping or tubing runs should be routed to vulnerable to damage unless adequately protected, they gen-
meet the following requirements: erally cannot be installed at subzero temperatures, and they
1. They should be kept as short as possible. can be considerably weakened by exposure to hot surfaces.
2. They should not cause any obstruction that would pro- Also, it should be remembered that they can be totally lost
hibit personnel or traffic access. in the event of a fire.
3. They should not interfere with the accessibility for main- Pneumatic tubing should be run on a cable tray or simi-
tenance of other items of equipment. lar supporting steelwork for its entire length and securely
4. They should avoid hot environments or potential fire- clipped at regular intervals. Where a number of pneumatic
risk areas. signals are to be routed to a remote control room they
5. They should be located with sufficient clearance to permit should be marshaled in a remote junction box and the sig-
lagging which may be required on adjacent pipework. nals conveyed to the control room via multitube bundles.
6. The number of joints should be kept to a minimum con- Such junction boxes should be carefully positioned in the
sistent with good practice. plant in order to minimize the lengths of the individually run
7. All piping and tubing should be adequately supported tubes. (See Figure 38.1 for typical termination of pneumatic
along its entire length from supports attached to firm multitubes.)
steelwork or structures (not handrails).
(Note: Tubing can be regarded as thin-walled seamless 38.5.3 Impulse Lines
pipe that cannot be threaded and which is joined by compres-
sion fittings, as opposed to piping, which can be threaded or These are the lines containing process fluid which run
welded.) between the instrument impulse connection and the process
tapping point, and are usually made up from piping and pipe
fittings or tubing and compression fittings. Piping materials
must be compatible with the process fluid.
38.5.1Air Supplies Generally, tubing is easier to install and is capable of
Air supplies to instruments should be clean, dry, and oil free. handling most service conditions provided that the correct
Air is normally distributed around a plant from a high-pres- fittings are used for terminating the tubing. Such fittings
sure header (e.g., 67 bar g), ideally forming a ring main. must be compatible with the tubing being run (i.e., of the
This header, usually of galvanized steel, should be sized to same material).
cope with the maximum demand of the instrument air users Impulse lines should be designed to be as short as pos-
being serviced, and an allowance should be made for pos- sible, and should be installed so that they are self-draining
sible future expansion or modifications to its duty. for liquids and self-venting for vapors or gases. If neces-
Branch headers should be provided to supply individual sary, vent plugs or valves should be located at high points
instruments or groups of instruments. Again, adequate spare in liquid-filled lines and, similarly, drain plugs or valves
tappings should be allowed to cater for future expansion. should be fitted at low points in gas or vapor-filled lines. In
Chapter | 38 Instrument Installation and Commissioning 657
any case, it should be ensured that there are provisions for individually run cables, always bearing in mind the potential
isolation and depressurizing of instruments for maintenance hazards that could be created by fire.
purposes. Furthermore, filling plugs should be provided Cable routes should be selected to meet the following
where lines are to be liquid scaled for chemical protection requirements:
and, on services which are prone to plugging, rodding-out
1. They should be kept as short as possible.
connections should be provided close to the tapping points.
2. They should not cause any obstruction that would pro-
hibit personnel or traffic access.
3. They should not interfere with the accessibility for main-
38.6Cabling tenance of other items of equipment.
4. They should avoid hot environments or potential fire-
38.6.1 General Requirements risk areas.
5. They should avoid areas where spillage is liable to
Instrument cabling is generally run in multicore cables from
occur or where escaping vapors or gases could present a
the control room to the plant area (either below or above
hazard.
ground) and then from field junction boxes in single pairs to
the field measurement or actuating devices. Cables should be supported for their whole run length
For distributed microprocessor systems the inter-con- by a cable tray or similar supporting steelwork. Cable trays
nection between the field and the control room is usually via should preferably be installed with their breadth in a vertical
duplicate data highways from remote located multiplexers plane. The layout of cable trays on a plant should be carefully
or process interface units. Such duplicate highways would selected so that the minimum number of instruments in the
take totally independent routes from each other for plant immediate vicinity would be affected in the case of a local
security reasons. fire. Cable joints should be avoided other than in approved
Junction boxes must meet the hazardous area require- junction boxes or termination points. Cables entering junc-
ments applicable to their intended location and should be tion boxes from below ground should be specially protected
carefully positioned in order to minimize the lengths of by fire-resistant ducting or something similar.
658 PART | VI Automation and Control Systems
test being made. Control valves should be tested in situ after or apparatus. The resistance should be checked core to core
the pipework fabrication has been finished and flushing oper- and core to ground.
ations completed. Control valves should be checked for cor- Cable screens must also be checked for continuity and
rect stroking at 0, 50, and 100 percent open, and at the same insulation. Cable tests should comply with the requirements
time the valves should be checked for correct closure action. of Part 6 of the IEE Regulation for Electrical Installations
(latest edition), or the rules and regulations with which the
installation has to comply. Where cables are installed below
38.8.3Piping and Cable Testing ground, testing should be carried out before the trenches are
back filled. Coaxial cables should be tested using sine-wave
This is an essential operation prior to loop testing.
reflective testing techniques. As a prerequisite to cable test-
ing it should be ensured that all cables and cable ends are
38.8.3.1 Pneumatic Lines properly identified.
All air lines should be blown through with clean, dry air
prior to final connection to instruments, and they should also 38.8.4Loop Testing
be pressure tested for a timed interval to ensure that they are
leak free. This should be in the form of a continuity test from The purpose of loop testing is to ensure that all instrumen-
the field end to its destination (e.g., the control room). tation components in a loop are in full operational order
when interconnected and are in a state ready for plant
commissioning.
38.8.3.2 Process Piping Prior to loop testing, inspection of the whole installation,
Impulse lines should also be flushed through and hydro- including piping, wiring, mounting, etc., should be carried
statically tested prior to connection of the instruments. All out to ensure that the installation is complete and that the
isolation valves or manifold valves should be checked for work has been carried out in a professional manner. The
tight shutoff. On completion of hydrostatic tests, all piping control room panels or display stations must also be in a
should be drained and thoroughly dried out prior to recon- fully functional state.
necting to any instruments. Loop testing is generally a two-person operation, one in
the field and one in the control room who should be equipped
with some form of communication, e.g., field telephones or
38.8.3.3 Instrument Cables
radio transceivers. Simulation signals should be injected
All instrument cables should be checked for continuity and at the field end equivalent to 0, 50, and 100 percent of the
insulation resistance before connection to any instrument instrument range, and the loop function should be checked
660 PART | VI Automation and Control Systems
for correct operation in both rising and falling modes. All Commissioning is usually achieved by first commission-
results should be properly documented on calibration or loop ing the measuring system with any controller mode overrid-
check sheets. All ancillary components in the loop should be den. When a satisfactory measured variable is obtained, the
checked at the same time. responsiveness of a control system can be checked by vary-
Alarm and shutdown systems must also be systematically ing the control valve position using the manual control
tested, and all systems should be checked for fail-safe function. Once the system is seen to respond correctly and
operation, including the checking of burn-out features on the required process variable reading is obtained, it is then
thermocouple installations. At the loop-checking stage all possible to switch to auto in order to bring the controller
ancillary work should be completed, such as setting zeros, function into action. The controller responses should then
filling liquid seals, and fitting of accessories such as charts, be adjusted to obtain optimum settings to suit the automatic
ink, fuses, etc. operation of plant.
Alarm and shutdown systems should also be systemati-
cally brought into operation, but it is necessary to obtain the
strict agreement of the plant operation supervisor before any
38.9Plant commissioning overriding of trip systems is attempted or shutdown features
are operated.
Commissioning is the bringing on-stream of a process
Finally, all instrumentation and control systems would
plant and the tuning of all instruments and controls to suit
need to be demonstrated to work satisfactorily before formal
the process operational requirements. A plant or section
acceptance by the plant owner.
thereof is considered to be ready for commissioning when
all instrument installations are mechanically complete and
all testing, including loop testing, has been effected.
Before commissioning can be attempted it should be References
ensured that all air supplies are available and that all power
BS 6739, British Standard Code of Practice for Instrumentation in Process
supplies are fully functional, including any emergency Control Systems: Installation Design and Practice (1986).
standby supplies. It should also be ensured that all ancillary Regulations for electrical installations 15th ed. (1981) as issued by the
devices are operational, such as protective heating systems, Institution of Electrical Engineers.
air conditioning, etc. All control valve lubricators (when The reader is also referred to the National Electrical Code of the United
fitted) should be charged with the correct lubricant. States (current edition) and relevant ANSI, IEC, and ISA standards.