TNB Contract No.

: TNB 140/2015
TNB Tender No. : TNBT 811914

TENAGA
NASIONAL BERHAD

ESTABLISHMENT OF PMU 500/275/132kV


(2x1050MVA & 2X240MVA) BENTONG SOUTH,
PAHANG

METHOD STATEMENT FOR:


MULTICORE CABLNG WORK FOR NEW TRANSFORMER BAY
AT 132kV SWITCHYARD PMU 132kV BENTONG SOUTH

MAIN CONTRACTOR

Transgrid Ventures Sdn. Bhd. - HMS Oil & Gas Sdn. Bhd.
Joint Venture,
E-07-3, East Wing Business Park, Subang Square,
Jalan SS15/4G
47050 Subang Jaya, Selangor.
Tel No: 03-56219624 Fax No: 03-56219752

Prepare By Review By Review By Agreed By

(ABDUL HADI ( ) ( ) ( )
MOHAMAD) ENGINEER/SENIOR ENGINEER/SENIOR STATE MANAGER AM
TGV-HMS JV ENGINEER AD ENGINEER AM
METHOD STATEMENT FOR DOC REF.: TRANSGRID/MS/E/002
ERECTION PRIMARY EQUIPMENT REV. NO.: 0
TENDER NO. : TNBT 811914 FOR NEW TRANSFORMER BAY AT ISSUE DATE: 6 DECEMBER 2016
132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

TABLE OF CONTENT:

1. TNB PTW DOCUMENT CHECKLIST

2. SCOPE OF WORK

3. WORK PROGRAM

4. JOB SAFETY AND RISK ANALYSIS

5. LIST OF WORKER & CIDB / NTSP COPY

6. COMPETENT ENGINEER CERTIFICATE

7. LIST OF EQUIPMENT & CALIBRATION CERTIFICATE

8. METHOD OF STATEMENT

9. APPENDIX
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

SCOPE OF WORK:

PREFACE

This Method of Statement (MOS) is meant for multicore cabling works extension 132kV
Transformer bay PMU 132kV Bentong South.

SAFETY PRECAUTION AND MEASURE

1. Work Planning

1.1 Site Condition


The site supervisor shall properly verify and inspect that the site / work area is safe to carry out
installation work before any work commencement. Amongst things to verify are yard condition,
trenching, isolation of live parts, obstacles and others.
Should the condition is considered not suitable to proceed with work program, site supervisor shall
highlight it to the assigned competent person / project responsible person.

1.2 Accessibility and Clearance


The site supervisor shall ensure sufficient and suitable road access for machineries to move into
and work within the work area.

The supervisor shall also ensure that the working area is within safe perimeter, for example from
live parts if any.

2. Ensuring Working Area Clearance

2.1 Barricading
If the working area is near or interfacing with live parts, a proper barricade using red and white tape
shall be established. No works shall be allowed to be carried out outside the designated area. The
area shall be defined by the competent person assigned.

The barricade (if there is) shall not be removed until work completion and only with authorization
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

of the competent person.

2.2 Signage
In addition to the tape, proper signage may be required. A clear indication shall be made visible
during the work duration.

The signage (if there is) shall not be removed until work completion and only with authorization of
the competent person.

Personal Protective Equipment (PPE)

All workers are required to wear PPE while in the work area. A suitable and minimum PPE shall be
made available. Depending on the activity, working condition and working area, the PPE could be
and not limited to:
Hard hat
Safety boot
General Safety Guideline

This document shall only discuss the safety measure that required to be taken in a general manner
only. Any particular and specific measure shall be discussed depending on the situation and
environment.

1. Lifting Load
Inspect the materials that shall be used to lift load. Ant defective materials shall not
be used and shall be replaced
Ensure that rope or chain is secured to the designated lifting hook
Ensure that both end of the rope/chain are properly secured
Ensure that the are below the load while lifting is cleared
Ensure that no hands or foot are placed underneath the load while placing the load
on its location
Ensure that sufficient work area is available for the lifting
Ensure that the load swing radius is minimized while lifting using guide rope
attached to the load
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

Ensure that the lofting process is carried as smooth as possible


Ensure that all workers is wearing PPE

2. Climbing / Working Above 2.5m Height


Ensure that safety belt is used while working above 2.5m
Check the safety belt condition. The belt shall be replaced if defective
Ensure that the belt is secured to the worker and to the work area
Ensure that the area below the work area and its vicinity is cleared
If tools is used, ensure that appropriate tools pooch is used
Never throw-up or down tools or equipments
If required to bring up material to the work area, use rope to secure the material and
slowly lift it up. Ensure that the area below the lifted material cleared

3. Working With Crane


Ensure safety of access road for crane to move
Before moving the crane in, check the area clearance
Check and verify crane condition including its booms and chain.
Check for sufficient area for crane to move and swing its boom while working
If the crane is required to cross trenches, prepare enough steel / checking plates and
install them on-top the trenches
Ensure excellent communication level between the crane operator and workers
supervisor
Ensure that no one is sitting on the crane (not designated for) while the crane is
working
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

General Action Plan In Case of Accident

Should an incident happen within during the authorized working time and within the working area
perimeter, immediately contact and inform site / project responsible personnel.

Person to Contact:

TENAGA NASIONAL BERHAD

TNB Site Supervisor(Civil) Ahmad Farid Hasan (019-3347411)


TNB Site Supervisor(Electrical) - Moktar b. Daud (011-33345722)

TRANSGRID VENTURES SDN BHD HMS OIL & GAS SDN. BHD. JOINT VENTURE

Site Engineer (Civil) Yusmin b. Yahya (019-4437966)


Site Engineer (Electrical) Mohd Ariff Radzuan (017-4691253)
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
REV. NO.: 0
MULTICORE CABLNG WORK
ISSUE DATE: 6 DECEMBER 2016
TENDER NO. : TNBT 811914 FOR NEW TRANSFORMER BAY Page :
AT 132kV SWITCHYARD PMU
132kV BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

WORK PROGRAM:

Please refer Approved Work Program in the next page.


TNB CONTRACT 140/2015 (TENDER NO. TNBT 811914) TGV-HMS J.V.
REV.0
ESTABLISHMENT OF PMU 500/275/132kV BENTONG SOUTH (2X1050MVA & 2X240MVA), PAHANG

132kV ERECTION WORK PROGRAM


ID Task Name Duration Start Finish 1 March 21 March 11 April 1 May 21 May
26/2 5/3 12/3 19/3 26/3 2/4 9/4 16/4 23/4 30/4 7/5 14/5 21/5 28/5
1 Electrical Erection Works 132kV Switchyard 60 days Wed 15/3/17 Sat 13/5/17
2 Erection of Primary Equipments 30 days Wed 15/3/17 Thu 13/4/17
3 Erection of Steel Structure Support 10 days Wed 15/3/17 Fri 24/3/17
4 Erection of Primary Equipments Structure 10 days Wed 15/3/17 Fri 24/3/17
5 Erection of 132kV Busbar Disconnector 10 days Sat 25/3/17 Mon 3/4/17
6 Erection of 132kV Line Disconnector 10 days Sat 25/3/17 Mon 3/4/17
7 Outage Resrve Busbar 10 days Tue 4/4/17 Thu 13/4/17
8 Erection of 132kV Circuit Breaker 5 days Tue 4/4/17 Sat 8/4/17
9 Erection of 132kV Current Transformer 5 days Sun 9/4/17 Thu 13/4/17
10 Erection of 132kV Capacitor Voltage Transformer 5 days Sun 9/4/17 Thu 13/4/17
11 Erection of 132kV Surge Arrester 5 days Sun 9/4/17 Thu 13/4/17
12 Erection of Secondary Equipments 11 days Fri 14/4/17 Mon 24/4/17
13 Erection of 132kV Marshalling Kiosk 5 days Fri 14/4/17 Tue 18/4/17
14 Erection of 132kV Control Panel & Relay Panel 5 days Fri 14/4/17 Tue 18/4/17
15 Erection of 132kV Supervisory Interface Panel 3 days Wed 19/4/17 Fri 21/4/17
16 Expansion of Existing 132kV Remote Terminal Unit 3 days Sat 22/4/17 Mon 24/4/17
17 Erection of Ancillary Equipment 30 days Fri 14/4/17 Sat 13/5/17
18 Conductoring Works 15 days Fri 14/4/17 Fri 28/4/17
19 Conductoring Works for Isolator Reseve, CB & CT 5 days Fri 14/4/17 Tue 18/4/17
20 Outage Main Busbar 4 days Wed 19/4/17 Sat 22/4/17
21 Dismantle Existing Conductor from Main Busbar to Main Busbar Isolator 1 day Wed 19/4/17 Wed 19/4/17
OHL Bentong & Raub
22 Install Rigid Aluminium Tube from Main Busbar Isolatator OHL Bentong 1 day Thu 20/4/17 Thu 20/4/17
& Raub to Main Busbar SGT1 & SGT2
23 Install Conductor from Main Busbar to Ridgid Aluminium Tube 1 day Fri 21/4/17 Fri 21/4/17
24 Isolator Aligment Check & Clamps Contact Resistance Test 1 day Sat 22/4/17 Sat 22/4/17
25 Outage Reserve Busbar 6 days Sun 23/4/17 Fri 28/4/17
26 Install Conductor from Main Busbar to Reserve Busbar Isolator for GT1 1 day Sun 23/4/17 Sun 23/4/17
& GT2
27 Isolator Aligment Check & Contact Resistance Test 1 day Mon 24/4/17 Mon 24/4/17
28 Install Conductor from LLG to Gantry 2 days Tue 25/4/17 Wed 26/4/17
29 Install Conductor for CT, CVT & SA 1 day Thu 27/4/17 Thu 27/4/17
30 Clamps Contact Resistance Test 1 day Fri 28/4/17 Fri 28/4/17
31 Earthing Works 17 days Fri 14/4/17 Sun 30/4/17
32 Switchyard 14 days Fri 14/4/17 Thu 27/4/17
33 For Maingrid 7 days Fri 14/4/17 Thu 20/4/17
34 For Primary Equipment 7 days Fri 21/4/17 Thu 27/4/17
35 Building 3 days Fri 28/4/17 Sun 30/4/17
36 For Indoor Equipment 3 days Fri 28/4/17 Sun 30/4/17
37 Multicore Cables Laying & Termination 30 days Fri 14/4/17 Sat 13/5/17
38 Multicore Cable Laying for 132kV System 20 days Fri 14/4/17 Wed 3/5/17
39 Equipment to MK 10 days Fri 14/4/17 Sun 23/4/17
40 MK to Building 10 days Mon 24/4/17 Wed 3/5/17
41 Multicore Cable Termination for 132kV System 20 days Mon 24/4/17 Sat 13/5/17

Task Rolled Up Critical Task Project Summary Inactive Summary Start-only


Rolled Up Milestone Finish-only
Critical Task Group By Summary Manual Task
Project: PMU BNTS 500/275/132kV
Letter of Award : 19 Jun 2015 Milestone Rolled Up Progress Inactive Task Duration-only Progress
Proposed Works Schedule Rev.0
Summary Split Inactive Task Manual Summary Rollup Deadline
External Tasks Inactive Milestone
Rolled Up Task Manual Summary Manual Progress
Prepared By: Abdul Hadi Checked By: Mohd. Ali Page 1 of 1
TRANSGRID VENTURES SDN BHD HMS OIL & GAS SDN BHD (JV)

HAZARD IDENTIFICATION, RISK ASSESSMENT AND DETERMINING CONTROL (HIRADC)


PROJECT: DESCRIPTION OF JOB: CONDUCTED BY: Mohd Ali, Peter, Isrul HIRADC NO. 048
Kumaraguru, Sara, Zapri, Shahrul Ikram, Wan
PMU BENTONG SOUTH MULTICORE CABLING & TERMINATION WORK REV. NO. 0
Afiq & Ahmad Imaduddin, Shahir
PAGE 1 of 2
LOCATION: LEGAL AND OTHER REQUIREMENTS: APPROVED BY: (Name, Signature & Date)
PAHANG OSHA 1994 Act 514, ELECTRICITY SUPPLY ACT 1990 Abdul Hadi (06/08/2015)
FMA 1967 Act 139 (BOWEC)

NO. WORK ACTIVITY R/ HAZARD IDENTIFICATION TYPE OF EXISTING RISK CONTROL RISK ASSESSMENT TYPE OF FURTHER ACTION / CONTROL PIC
NR CONTROL CONTROL
LH SEV RL
Hazard Effect

1. Preparation work R Sharp edges from Bodily Injury Admin Identified and avoid sharp edges. Wear 2 2 4 SS,
material/Structure hand glove at all the times. (L) GW
PPE

Untidy work area Slip, Trip & Fall Admin The work area shall be kept clear from 2 2 4 SS,
(Housekeeping) any obstruction. (L) GW
PPE
Soft spots / holes to be identified and
barricade if necessary. Wear Safety
Boots.
2. Manually pull the cable R Struck by object Bodily Injury Admin Cordon off the work area with warning 2 2 4 PE,
from drum signage. Wear hand glove, safety (L) SS
PPE
helmet, and safety boots.

Manual handling Muscular Stress Admin Correct body posture (Ergonomic). 3 1 3 SS,
Lifting & Carrying Request manpower. Do not carry excess (L) GW
weight (Weight to be known)

LIKELIHOOD SEVERITY RISK = L X S

Most Likely (5) The most likely result of the hazard/event being realized Catastrophic (5) Numerous fatalities, irrecoverable property damage and productivity 1 - 4 : LOW RISK
Possible (4) Has a good chance of occurring and is not unusual Fatal (4) Approximately one single fatality major property damage if hazard is realized 5 - 12 : MEDIUM RISK
Conceivable (3) Might be occur at some time in future Serious (3) Non-fatal injury, permanent disability 15 - 25 : HIGH RISK
Remote (2 ) Has not been known to occur after many years Minor (2) Disabling but not permanent injury R = Routine
Inconceivable (1) Is practically impossible and has never occurred Negligible (1) Minor abrasions, bruises, cuts, first aid type injury NR = Non-Routine

Note: 1. Legend for Responsibility: PE Project Engineer, SS Site Supervisor, GW- General Workers (include Subcontractors & Workers)
2. Medium & High risk Implement further action / control (s) prior to commencement of work.

Doc Ref: TRANSGRID/PI/HIRADC Issue Date: 02/04/2015 Revision: 2


TRANSGRID VENTURES SDN BHD HMS OIL & GAS SDN BHD (JV)

HAZARD IDENTIFICATION, RISK ASSESSMENT AND DETERMINING CONTROL (HIRADC)


PROJECT: DESCRIPTION OF JOB: CONDUCTED BY: Mohd Ali, Peter, Isrul HIRADC NO. 048
Kumaraguru, Sara, Zapri, Shahrul Ikram, Wan
PMU BENTONG SOUTH MULTICORE CABLING & TERMINATION WORK REV. NO. 0
Afiq & Ahmad Imaduddin, Shahir
PAGE 2 of 2
LOCATION: LEGAL AND OTHER REQUIREMENTS: APPROVED BY: (Name, Signature & Date)
PAHANG OSHA 1994 Act 514, ELECTRICITY SUPPLY ACT 1990 Abdul Hadi (06/08/2015)
FMA 1967 Act 139 (BOWEC)

NO. WORK ACTIVITY R/ HAZARD IDENTIFICATION TYPE OF EXISTING RISK CONTROL RISK ASSESSMENT TYPE OF FURTHER ACTION / CONTROL PIC
NR CONTROL CONTROL
LH SEV RL
Hazard Effect

3. Cable termination works R Sharp edges from Bodily Injury Admin Identified and avoid sharp edges. Wear 2 2 4 SS,
material/Structure hand glove at all the times. (L) GW
PPE

Ergonomics (awkward Fatigue & Admin Correct body posture (Ergonomic). 3 1 4 SS,
postures) Muscular Stress Request manpower. Do not carry excess (L) GW
weight (Weight to be known)

Falling objects. Bodily injury Admin Loose parts / material must be 2 2 4 PE,
removed. Equipment/Materials should (L) SS
be secured properly and balanced.
Cordon off work area and display
warning signage

Untidy work area Slip, Trip & Fall Admin The work area shall be kept clear from 2 1 2 PE,
(Housekeeping) any obstruction. (L) SS
PPE
Soft spots / holes to be identified and
barricade if necessary. Wear Safety
Boots.

LIKELIHOOD SEVERITY RISK = L X S

Most Likely (5) The most likely result of the hazard/event being realized Catastrophic (5) Numerous fatalities, irrecoverable property damage and productivity 1 - 4 : LOW RISK
Possible (4) Has a good chance of occurring and is not unusual Fatal (4) Approximately one single fatality major property damage if hazard is realized 5 - 12 : MEDIUM RISK
Conceivable (3) Might be occur at some time in future Serious (3) Non-fatal injury, permanent disability 15 - 25 : HIGH RISK
Remote (2 ) Has not been known to occur after many years Minor (2) Disabling but not permanent injury R = Routine
Inconceivable (1) Is practically impossible and has never occurred Negligible (1) Minor abrasions, bruises, cuts, first aid type injury NR = Non-Routine

Note: 1. Legend for Responsibility: PE Project Engineer, SS Site Supervisor, GW- General Workers (include Subcontractors & Workers)
2. Medium & High risk Implement further action / control (s) prior to commencement of work.

Doc Ref: TRANSGRID/PI/HIRADC Issue Date: 02/04/2015 Revision: 2


METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

LIST OF WORKERS NTSP & CIDB COPY:

Please refer attached list of workers in the next page.

Change of Worker Subject to Prior Notice


ZAMCO TECHNOLOGY ENTERPRISE Appendix-I
SUBSTATION PROJECT ZTE WORKS - ELECTRICAL TEAM

Item Descriptions I/C CIDB EXP.DATE CIDB-No NIOSH EXP.DATE NIOSH-No Remarks
Erector
1 Al-Hafis 930310-08-5961 17/09/2017 New CIDB No-NIL 3/8/2019 TNB004611J
2 Zunaidie 791018-03-5003 26/10/2017 New CIDB No-NIL 18/04/2019 TNB029144J
3 Muhamad Aliff 920326-06-5457 17/09/2017 New CIDB No-NIL 3/8/2019 TNB 099414J

Final Worker shall be update prior to work start.

Page 1 of 1
ZAMCO TECHNOLOGY ENTERPRISE(SA0252061M)
NO. 23A, 1ST FLOOR, JALAN ALFA F U6/F,
PUSAT PERDAGANGAN SUBANG PERMAI, SEKSYEN U6, SELANGOR DARUL EHSAN
Tel:017-2714566/019-3552032

Workers NTSP & CIDB Copy Date: As of 13/09/2016

Page 1 of 4
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.
METHOD STATEMENT FOR DOC REF.: TRANSGRID/MS/E/002
ERECTION PRIMARY EQUIPMENT REV. NO.: 0
TENDER NO. : TNBT 811914 FOR NEW TRANSFORMER BAY AT ISSUE DATE: 6 DECEMBER 2016
132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

List of Equipment.

1. Standard tools for cabling work


2. Cable drum stand
METHOD STATEMENT FOR: DOC REF.: TRANSGRID/MS/E/002
MULTICORE CABLNG WORK FOR REV. NO.: 0
TENDER NO. : TNBT 811914 NEW TRANSFORMER BAY ISSUE DATE: 6 DECEMBER 2016
AT 132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & (2X240MVA), Zulfahmi Abdul Hadi
PAHANG.

METHOD STATEMENT FOR MULTICORE CABLE & TERMINATION WORK (MK TO INDOOR PANEL &
INDOOR PANEL):

1. Installation Steps
Identify cable to be laid and its route.
Cut the cable to required length
Put temporary marker onto the cable
Carefully pull (using suitable method) and lay the cable following its route
Secure the cables (if necessary) with cable ties or other suitable method
Install cable marker / tag as specified
Make appropriate opening for the cable at panels, kiosk and switchgear for
termination purposes (control cables)
Gland the cables using appropriate cable glands size (control cables)
Slice the cable and identify cores to be used. Installed the ferrule number and cable
lug
Terminate the cable properly & as per termination schedule
Earth the glands to the equipment earth grid

2. Safety Precaution
Use appropriate PPE while working
If working with existing system, be careful with existing cables
METHOD STATEMENT FOR DOC REF.: TRANSGRID/MS/E/002
ERECTION PRIMARY EQUIPMENT REV. NO.: 0
TENDER NO. : TNBT 811914 FOR NEW TRANSFORMER BAY AT ISSUE DATE: 6 DECEMBER 2016
132kV SWITCHYARD PMU 132kV Page :
BENTONG SOUTH
CONTRACT NO. : TNB140/2015
PROJECT TITLE: PREPARED VERIFIED
ESTABLISHMENT OF PMU 500/275/132KV
BENTONG SOUTH (2X1050MVA) & Zulfahmi Abdul Hadi
(2X240MVA), PAHANG.

APPENDIX:

1. Single Line Diagram


2. General Layout & Sectional View
3. Control Building Layout
4. Multicore Cable Route