Document Number: 2016-ENG-SOW-0044

Rev 0: 18 September 2016


Engineering

Pot Line Basement Fence

1. INTRODUCTION
The pot line basement at Sohar Aluminium is a restricted area. Access to this area is controlled
by a rope barricade and a basement permit system. Due to the severity of the risks associated
with access to the Buss bar and pot structures SA has decide to install a physical barrier
system to prevent accidental uncontrolled access to the basement.
This SOW is for the supply and installation of a series of gates and fencing to eliminate
uncontrolled access to the basement.

WORK INCLUDED

The scope of work shall include the following:

1.1 General (as applicable)


1.1-1 Supply and install all the construction fencing and gate materials needed for
fencing to the site (reduction area).
1.1-2 External potline fencing approximately 2600M
1.1-2.1 All chain link fencing and gates must be supplied and installed as per
drawing CLFMI-CLO (Typical fencing section), CLFMI-CLGA-2 (Typical
double swing gate) and sketch 01 around the external sides of the potline.
Approximately 2600 meters.
1.1-2.2 All specifications as per drawing CLFMI-CLO Typical fencing section and
CLFMI-CLGA-2 (Typical double swing gate) must be complied with. All
deviations to the specifications must be clearly stated in the submitted offer.
1.1-2.3 All materials supplied must be hot dipped galvanized.
1.1-2.4 Terminal posts and bracing must be installed every 50 meters maximum
1.1-2.5 Supply and install Earthing straps to all gates and fencing posts as per
drawings 25180-000-EG-0000-01214 and 25180-000-EG-0000-01217
1.1-2.6 Supply and install 28 signs as per sketch 0003

1.1-3 Courtyard fencing and gates.


1.1-3.1 Supply and install 360 x 4 M wide gates as per drawing 0002
1.1-3.2 Supply and install 50 x 2 M wide gates as per drawing 0002
1.1-3.3 Supply and install 300M of chain link fencing as per drawing CLFMI-CLO
(Typical fencing section)
1.1-3.4 All materials supplied must be hot dipped galvanized.
1.1-3.5 Supply and install Earthing straps to all gates and fencing posts as per
drawing 25180-000-EG-0000-01214 and 25180-000-EG-0000-01217

Page 2 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

1.1-3.6 Supply and install 180 signs as per sketch 0003 on to each pair of courtyard
gates.
1.1-4 General notes
1.1-4.1 Each pair of gates should be fitted with a lockable latch mechanism and
drop rod to prevent gates from moving unassisted in open or closed
position.
1.1-4.2 Access via the west end of pot line is not possible due to current installed
facilities. Therefore, No work will be performed on the west end.
1.1-4.3 Supply of labor in sufficient numbers and skilled to perform the work.
1.1-4.4 A dedicated supervisor is required to manage the site work and resources.
This shall include management of the EHS aspects.
1.1-4.5 All gates supplied for the courtyard must be supplied with clamp on fixings
to install onto existing GTC duct structures. No welding or drill is allowed.
1.1-4.6 Gate hinge mechanisms must be adjustable to ensure each set of 2 four
meter gates can be adjusted for level alignment.
1.1-4.7 Contractor may submit gate designs for factory built gates as a substitute for
drawing 0002 for approval by project engineer.

1.2 Civil Works


1.2.1 Contractor must supply labour or mobile equipment for post hole excavations as per
drawing CLFMI-CLO (Typical fencing section)
1.2.2 Supply and installation of all concrete for fixing the fencing posts and supports.
1.2.3 Supply and fixing of all chemical anchors for posts where concrete already exists.

1.3 Electrical services


1.3.1 Supply and install Earthing straps to all gates and fencing posts as per drawing 25180-
000-EG-0000-01214 and 25180-000-EG-0000-0121

1.4 Mobilization and site establishment

1.5 Demobilization and Site clean up

2. WORK EXCLUDED

2.1 Work is limited to this scope of work.

Page 3 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

3. BATTERY LIMITS

3.1 4.1 (as applicable)

4. QA/QC

4.1 Contractor shall submit Quality plan. Inspection and test plan (containing in-process,
witness hold points). A preliminary quality plan and inspection and test plan shall be
provided along with the Bid. A firm quality plan and inspection and test plan shall be
provided for review and approval after acceptance of order and before start of execution.

4.2 All equipment calibration certificates record and shall form part of quality plan.

4.3 SA engineers shall have access to all quality documents and will be called for stage
inspections as agreed.

4.4 On completion work, final comprehensive quality document including signed inspection
witness forms, material test certificates and site test reports shall be submitted in 1soft
copy and 1 hard copies.

5. SA EHS REQUIREMENT
The contractor shall comply with the requirements of the attached SA Engineering EHS
standard 2012-ENG-PRC-000-0012. Reference is made specifically to the following items:

5.1 ENVIRONMENTAL MANAGEMENT SYSTEM

SA is committed to ensure that the construction works for SA is completed to the


highest environment standard. Contractor are required to manage the environmental
impact associated with the entire scope of work including their subcontractor scope of
work. Contractor environmental management plan (EMP) shall be submitted to SA for
approval before contractor is mobilize to site.

Please refer SA Engineering EHS standard 2012-ENG-PRC-000-0012 section B.1 to


B.20 for detail SA requirement for environment Management system.

5.2 HEALTH & SAFTEY


The contractor shall comply with the Health & safety requirements the mentioned
below

5.2.1 All lifting equipment shall be subject to periodic inspection by Sohar Aluminium EHS
departments

Page 4 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

5.2.2 The Contractor shall assign a safety representative to the Jobsite. Such safety
representative shall be physically located at the Jobsite, shall have the authority for
correcting unsafe acts or conditions by the Contractor, its employees, and employees of
the Contractors suppliers or subcontractors of any tier, and shall participate in periodic
safety meetings with Sohar Aluminium.

5.2.3 All Contractor employees on site are to complete Sohar Aluminium Induction and an area
induction prior to commence the job.

5.2.4 All electric powered tools shall be earthed. Double insulated power tools are acceptable.
5.2.5 Violation of Safety standards may lead to cancellation of the work/contract.
5.2.6 The General Work Permit will not be issued unless the Contractor meets specific EHS
requirements for the job i.e. PPE and equipment. Any delay or loss caused by EHS non-
compliance will be for the contractors account. All persons on site are to wear certain
PPE as a minimum, which minimum includes steel-toe footwear, long pants, long-
sleeved shirt, safety spectacles and hardhat.
5.2.7 Throughout performance of the Work, the Contractor shall conduct all operations in such
a way as to minimize the impact upon the natural environment and prevent the spread
or release of contaminated or hazardous substances.
5.2.8 All work carried out in the smelter shall be barricaded to safeguard the workers.
5.2.9 Facemasks with replaceable cartridges (valid for 3 months) shall be used for dusty areas
in the Carbon area. All other areas shall use the standard issue dust masks. The face
and dust masks will be issued by SA for the project.
5.2.10 In addition to the above standard the following items are banned from Sohar Aluminium
site:

Page 5 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

5.2.10.1 Glass bottles

5.2.10.2 Visible jewelry

5.2.10.3 Pressurized spray cans

5.2.10.4 Any metal cans and tins

5.2.10.5 Butane cigarette lighters

5.2.10.6 Watches with metallic wrist bands

5.2.10.7 Any drugs or alcohol

5.2.10.8 Cameras (Restricted use GM Approval is required)

5.2.10.9 Weapons or explosives of any kind

5.2.10.10 Thermos flask

5.2.10.11 Pacemakers (Restricted in certain areas)

5.3 In addition to the above standard the following tools are banned from Sohar Aluminium
site.
5.3.1 Metal ladders
5.3.2 Manual carabineer
5.3.3 Double ended crowbars
5.3.4 Adjustable spanners (an exception is made for 150mm adjustable spanners used in electrical
work)
5.3.5 Tools that use explosive cartridges
5.3.6 Screw drivers used for voltage detection
5.3.7 Knives (auto retractable box knives are permitted)
5.3.8 9 grinders
5.3.9 Hand-made (home-made) tools
5.3.10 Damaged tools
5.3.11 Metal cut-off saw
5.3.12 Hand-held Power Tools without a Dead Mans Switch

Page 6 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

6.2.11 Hard Barricading


The purpose of a solid barricade is to provide a physical barrier capable of performing
the same function as a permanent guardrail. Solid barricades shall be erected in areas
where medium to high risk exposure exists and must be risk assessed to determine the
distance from the work to the barricade and / or the distance from an external threat to
the work area. A Solid Barricade shall be constructed as follows:

6.2.11.1 Scaffold made barricade or metal barricade

Have a solid top and mid rail (e.g. Scaffold tube or equivalent) with the
applicable sign attached. The top rail must be between 900mm and
1100mm high; mid rail shall be no more than 560mm from the floor if no
toe board is fitted and 450mm between rails.
The installation of a kick rail or mesh to contain objects etc. shall be by
risk assessment and detailed in the risk assessment.
Be able to withstand an impact of 550N outwards or down on the top rail.
Additional controls may be required to secure free standing barricades.
If barriers are to be left overnight where visibility is poor warning lamps
must be installed every 5 meters.

6.2.11.2 Water filled plastic solid barricades and Concrete barricades

Shall be used where there is a potential for a vehicle impact, they shall
be linked together. (plastic barricades must be filled if used)
Must be interlocked with only the access points opened. Access points
must be controlled.
Appropriate, barricade tape may be used to highlight the existence of the
barricaded area.
Solid barricade shall be used for excavation work, scaffolding exposed to
damage from external forces, exposure to high risks activities, exposure
to other operational activities, segregation of work areas etc., the list can
be exhaustive and the installation shall be based on the level of risk.
Solid barriers shall also be used to close off areas where a potential exist
where items can fall from height.
For high risk areas where activities are to be carried out a flag man or
watchman must be used in addition to solid barricades.

Page 7 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

If barriers are to be left overnight in high traffic areas and / or visibility is


poor, warning lamps must be installed every 5 meters.

6. PROJECT COST
The contractor shall submit prices for materials and labour as separate line items and as a
cost for the complete works as per this scope, however a complete breakdown of the cost
shall also be submitted. Non-compliance to this will result in rejection of the bid.

7. PROJECT SCHEDULE
The vendor shall provide a schedule with the quotation for the full scope of work
commencing from the receipt of purchase order. The schedule may be in Microsoft Projects,
Primavera or Excel.
Note that Sohar Aluminium employees have a 5 day work week with Fridays and Saturdays
as the weekend. No work will be permitted to be done on Fridays, Saturday& public holidays
without special written permission from the Engineer. No work will be permitted without the
Project Engineer or Engineering Site Supervisor being on site.
The contractor shall take cognisance of the above in preparing the project schedule.

8. PENALTY

The vendor shall be subject to a penalty of 0.5% per week up to a maximum of 10% for late
delivery on the project.

9. WARRANTY:
The vendor warrants that -

9.1 The construction required under this order shall be performed with the high degree of
skill, current methods, sound practices and good judgement normally exercised by
recognized professional firms rendering services of a similar nature.

Page 8 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

9.2 All equipment and materials incorporated into the Work shall be new and of the most
suitable grade of their respective kinds for their intended uses unless otherwise specified;

9.3 Works will be free from defects (including quality, safety and latent defects), of
merchantable quality and fit for their intended purposes;

9.4 All such warrantees apply to all Work for a period of at least twelve months.

9.5 The warranty period begins as soon as practical Completion has been signed off.

10. GENERAL NOTES

10.1 A Work Method Statement (WMS) and Risk Assessment (RA) will be required for
approval by the Project Engineer at least two weeks before the proposed start date and
contractor should maintain Sohar aluminium template for RA along with approved risk
matrix.

10.2 All project documentation including drawings, MASs (material approval sheets),
schedules, commissioning and testing plans, operating and maintenance manuals, etc.,
shall be approved by the engineer. The contractor shall allow in his project schedule a
period of five days, from the time of receipt (excluding weekends and public holidays) for
the comments/approvals of these documents.

10.3 All drawings and design details shall be provided before the project is completed. The
drawings shall be provided in the native format (.dwg, .dgn or .dxf) marked up as-built.

10.4 Quality Plans in the form of a quality control procedure (QCP) sheet shall be required for
all steel fabrication and construction work carried out on the project. The QCPs shall be
reviewed and agreed with the SA engineer at the kick off meeting.

10.5 Dumping of waste material is prohibited and documentary evidence (consignment notes)
will be required for all materials taken off site and dumped at the approved municipal site.
The Waste Disposal form will have to be completed and approved by SA before the
waste material may be removed form site. Penalties will be imposed on the contractor for
not complying with the approved Waste disposal Plan.

10.6 Before handover of the site to SA the area around the site shall be rehabilitated, i.e.
returned to the condition it was before the project was started and the ground blended in
as much as possible to the building.

10.7 Steel and wooden waste material considered recyclable by the SA engineer shall be
removed from the construction site and offloaded, as directed, at the applicable area
within the smelter.

10.8 Toilet and washing facilities shall be provided at all times to the workmen on the site. This
facility shall be provided by the contractor in the project. Special exemption may be given
by the owner of the area to use the facilities; however, the onus is on the vendor to

Page 9 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

confirm this permission before the tender is closed.

10.9 The contractor shall provide a sheltered cool room with chairs and tables, as required, for
the work force for dining and rest purposes. Mist fans shall be provided during the hot
month of the year.

10.10 Where potable water is available and provided for the project it shall not be used for
industrial purposes.

10.11 If scaffolding work is required for the construction work the following approved contractors
may be used:
10.11.1 Cape East Contact Krishnan Mobile 96386370 / Ranjan Mobile 96020497
10.11.2 Al Nahda Khalid Fazal Mobile 99269622
10.11.3 Dohat Khaleej JT Ansari Mobile 95123851
10.11.4 NAFAL Nicolas Lazar Mobile 994413247/Alex Maxton Mobile 94270691

10.12 For service contracts the vendor shall submit, for SA approval, its organization chart for
the key personnel in the company, including the project engineers, EHS representatives
and site supervisors. No supervisor or key personnel on the approved organization chart
may be removed or exchanged without the approval of the project engineer.

10.13 CVs of all the key personnel to be used in the project shall be submitted with the tender.
These shall as a minimum include the project manager, supervisors and EHS
representative.

10.14 It is mandatory that all workers have valid labour cards and have the correct job
classification on their cards, i.e. electrician, bricklayer, etc. For contractors who use
subcontractors a written agreement should be in place between the two parties. An order
on the subcontractor is considered acceptable.

10.15 The contractor shall include a Deviation List of all deviations/exclusions from the Scope of
Work. If no Deviation list is included with the tender it shall be assumed that the
contractor complies fully with the Scope of Work.

10.16 Contractor shall note that all scope changes to the project require written approval from
the SA engineer and a new P.O before the work can start. Any work undertaken without a
P.O shall not be paid by SA.

10.17 All Material/Equipment deliveries shall be offloaded at the work site if possible and the
offloading operation shall be approved by Sohar Aluminium.

10.18 For all equipment supplied a spares list shall be issued, one month after the purchase
order date, for commissioning and start-up and two years operation. A priced preliminary
spares list is requested with the main tender.

10.19 All isolation requirement to comply to SA standard.

Page 10 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

10.20 The quotation for the above scope of work shall remain valid for 3 months.

10.21 Payment terms shall be stated in the contractors bid. A retention of 10% for the total
tender price shall be held by SA for six (6) months to ensure the project performs to
specification. The contractor may, as an alternative, issue a performance bond in lieu of
the 10% retention.

11. DRAWINGS & DOCUMENTATION


All projects shall have a handover package which will be issued to the client on Industrial
completion of the project. For projects that include equipment (mechanical, electrical and
automation) the following will be required:
The Handover Package shall include, as applicable:

11.1 Project drawings marked up

11.2 Recommended spares list

11.3 FMECA (Failure Mode Effect & Cause Analysis) the template should be attached to the
SOW as an appendix.

11.4 Operational & Maintenance instructions

11.5 Pre-commissioning report

11.6 Commissioning report with full details of settings used for each of the equipment

11.7 Equipment performance results

11.8 Training requirements

11.9 Copy of Performance Guarantee

11.10 Copy of Warranty

11.11 A Full set of working document are required at Practical completion.

12. SPECIFICATIONS THIS SHOULD BE A TABLE GIVING DOCUMENT NO, TITLE AND
REVISION NO
(Include/delete as applicable)

Document number Title Discipline Added


in SOW

2012-ENG-PRC-000-0012 SA Engineering EHS standard EHS


Page 11 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

ENG-SPE-C-A000-00001 Standard Specification for Building Architectural


Works

ENG-SPE-C-A000-00002 Standard Specification for Roofing Architectural

ENG-SPE-C-A000-00003 Standard Specification for Built-Up Architectural


Roofing on Flat Concrete Slab Non
Process Buildings

ENG-SPE-C-A000-00004 Standard Specification for Sanitary Architectural


ware, Plumbing and Engineering
Installations

ENG-SPE-C-A000-00005 Standard Specification for Architectural


Carpentry, Joinery and
Ironmongery

ENG-SPE-C-A000-00006 Standard Specification for Glazing Architectural


and Glass Blocks

ENG-SPE-C-A000-00007 Standard Specification for Architectural


Metalwork

ENG-SPE-C-A000-00008 Standard Specification for Architectural


Plasterwork and Other Floor, Wall
& Ceiling Finishes

ENG-SPE-C-A000-00009 Standard Specification for Painting Architectural


and Decorating

ENG-SPE-C-A000-00010 Standard Specification for Steel Architectural


Fire Doors for Use in Electrical
Installations

ENG-SPE-C-A000-00011 Standard Specification for Design, Architectural


Supply and Erection of Roofing and
Siding

ENG-SPE-C-A000-00012 Standard Specification for External Architectural


Work

ENG-SPE-C-C000-00001 Standard Specification for Civil


Temporary Erosion and Sediment
Control

Page 12 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

ENG-SPE-C-CE00-00001 Standard Specification for Earth Civil


Works

ENG-SPE-C-CE00-00002 Standard Specification for Roads Civil


and Paving

ENG-SPE-C-DB00-00001 Standard Specification for Civil


Concrete and Masonry work

ENG-SPE-C-DB00-00002 Standard Specification for Precast Civil


Concrete

ENG-SPE-C-DB00-00003 Standard Specification for Bored Civil


Cast-in Place Concrete Piles

ENG-SPE-E-E000-00001 Standard Specification for Electrical


Electrical Installations

ENG-SPE-E-E000-00002 Standard Specification Electrical Electrical


Equipment on Packaged
Mechanical Equipment

ENG-SPE-E-E000-00003 Standard Specification for Electrical


Preferred Instrumentation and
Electrical Equipment

ENG-SPE-E-E000-00004 Standard Specification for Labels Electrical


and Nameplates for Electrical
Equipment

ENG-SPE-E-EA00-00001 Standard Specification for Painting Electrical


of Elecrtrical Switchboards, Desks
and Equipment

ENG-SPE-E-EAA0-00001 Standard Specification for Lighting Electrical


& Power Distribution Panels

ENG-SPE-E-ECM1-00001 Standard Specification for Low Electrical


Voltage Motor Control Centres

ENG-SPE-E-ED00-00001 Standard Specification for Electrical


Substation Batteries and Chargers

ENG-SPE-E-ED00-00002 Standard Specification for Electrical


Emergency Lighting Rectifier,
Battery and Inverter Systems

Page 13 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

ENG-SPE-E-EGR2-00001 Standard Specification for Neutral Electrical


Earthing Resistors

ENG-SPE-E-EH00-00001 Standard Specification for Electrical


Electrical Heat Tracing

ENG-SPE-E-EL00-00001 Standard Specification for Plant Electrical


Lighting

ENG-SPE-E-EPI0-00001 Standard Specification for LV Electrical


Motor Local Safety Isolator Boxes
(Local Control Station)

ENG-SPE-E-EQ00-00001 Standard Specification for Cathodic Electrical


Protection

ENG-SPE-E-ESI1-00001 Standard Specification for Medium Electrical


Voltage Switchgear

ENG-SPE-E-ESL1-00001 Standard Specification for Low Electrical


Voltage Main Switchgear

ENG-SPE-E-ETP0-00001 Standard Specification for Liquid Electrical


Immersed Power Transformers

ENG-SPE-E-EU00-00001 Standard Specification for Electrical


Uninterruptible Power Supply
(UPS) Systems

ENG-SPE-E-EVV1-00001 Standard Specification for AC Electrical


Adjustable Speed Drives

ENG-SPE-E-EW00-00001 Standard Specification for Power, Electrical


Control and Instrument Cable

ENG-SPE-G-G000-00001 Standard Specification for Civil


Documentation for new Plant

25180-000-3SS-G000-00002 Standard Specification for Painting Civil


of Mechanical Equipment, Piping
and Structural Steel

ENG-SPE-G-G000-00003 Standard Specification for Spare Mechanical


Parts / Special Tools

ENG-SPE-I-J000-00005 Standard Specification for Control


Seller/Contractor Instrumentation Systems

Page 14 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

Electronic Data Exchange

ENG-SPE-I-JD02-00001 Standard Specification for the Control


Application of Programmable Logic Systems
Controllers (PLC's)

ENG-SPE-I-JD02-00013 Standard Specification for Level 1 Control


Control Systems Architectural and Systems
Network Topology Design and
Implementation

ENG-SPE-I-JD06-00001 Standard Specification for Control


Supervisory Control Systems Systems

ENG-SPE-I-JD06-00014 Standard Specification for Level 2 Control


Control Systems - Architectural, Systems
Design and Implementation

ENG-SPE-I-JQ05-00001 Standard Specification for Fire Control


Detection System Systems

ENG-SPE-I-JQ08-00001 Standard Specification for Control


Installation, Calibration and Testing Systems
of Instruments and Control
Systems

ENG-SPE-I-JV00-00001 Standard Specification for Relief Control


Valves, Control Valves and Systems
Actuators

ENG-SPE-M-M000-00001 Standard Specification for Mechanical


Mechanical Equipment

ENG-SPE-M-M000-00002 Standard Specification for Mechanical


Mechanical Installation

ENG-SPE-M-M000-00003 Standard Specification for Mechanical


Mechanical Equipment
Standardization

ENG-SPE-M-M000-00004 Standard Specification for Oil, Mechanical


Lubricants and Lubrication

ENG-SPE-M-MA00-00001 Standard Specification for Fans Mechanical

ENG-SPE-M-MHBE-00001 Standard Specification for Bucket Mechanical


Elevators

Page 15 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

ENG-SPE-M-MHCB-00010 Standard Specification for Belt Mechanical


Conveyors

ENG-SPE-M-MJE0-00001 Standard Specification for Mechanical


Elevators and Load Elevators

ENG-SPE-M-MJK0-00001 Standard Specification for Mechanical


Overhead Cranes, Hoists and
Lifting Equipment

ENG-SPE-M-MJR0-00001 Standard Specification for Roller Mechanical


Conveyors

ENG-SPE-M-MKA0-00001 Standard Specification for Mechanical


Mechanical Gas Treatment Centre
Performance

ENG-SPE-M-MKBB-00001 Standard Specification for Dust Mechanical


Collection Systems

ENG-SPE-M-MKH0-00001 Standard Specification for HVAC Mechanical


for Non-Process Buildings

ENG-SPE-M-MPF0-00001 Standard Specification for Mechanical


Hydraulic Systems Design and
Installation

ENG-SPE-E-MUMI-00001 Standard Specification for Medium Electrical


Voltage Motors

ENG-SPE-E-MUMI-00002 Standard Specification for Low Electrical


Voltage Motors

ENG-SPE-M-MUPV-00001 Standard Specification for Mechanical


Pneumatic System Design

ENG-SPE-M-NW00-00001 Standard Specification for Welding Mechanical


of Mechanical Equipment and Plate
work

ENG-SPE-M-NW00-00002 Standard Specification for Welding Mechanical


Requirements for Pressure
Retaining Equipment and Piping

ENG-SPE-M-NW00-00003 Standard Specification for General Mechanical


Welding and NDE Requirements
for Supplier Fabricated Piping

Page 16 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

ENG-SPE-M-P000-00001 Standard Specification for Piping Plant Design &


Design and Materials Piping

ENG-SPE-M-P000-00002 Standard Specification for Shop Plant Design &


Fabricated Piping Piping

ENG-SPE-M-P000-00003 Standard Specification for Field Plant Design &


Fabrication and Installation of Piping
Piping

ENG-SPE-M-P000-00004 Standard Specification for Fibre Plant Design &


Reinforced Plastic (FRP) Piping Piping

ENG-SPE-M-SS00-00001 Standard Specification for Civil


Structural Steel work - Supply and
Fabrication

25180-433-3PS-MKAF-00002 Standard Specification for Mechanical


Mechanical Fume Treatment
Centre (FTC) Performance

Document number Title Discipline Added


in SOW

13. DRAWINGS

21580-000-EG-0000-01217 Electrical installation standard for Electrical


Earthing of gates

21580-000-EG-0000-01214 Electrical installation standard for Electrical


Earthing of metal fence posts

CLFMI-CLO Typical fencing section Mechanical

CLFMI-CLGA-2 Typical double swing gate Mechanical

Drawing 0002 Courtyard gate detail Mechanical

Sketch 0001 Fencing general layout Mechanical

14. DATA SHEETS


Another table giving doc no title and revision No.

Page 17 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Engineering

Pot Line Basement Fence

15. APPENDICIES

Page 18 of 18
This document is the property of Sohar Aluminium.
It is STRICTLY CONFIDENTIAL and may on no account be reproduced, copied or divulged without prior authorization.

Headquarters: P.O. Box 80 P.C.327 Sohar Industrial Estate, Sohar Sultanate of Oman Commercial Registration 1/76671/6
Existing
IBeam Dimensions between existing Ibeam posts varies between 8100mm to 8200mm
Gate mounting brackets must be adjustable to ensure gates can be adjusted to suit each
individual opening

Loackable Existing
latch IBeam
1200 mm
300mm
100mm

Drop rod
Ground level

M12 x 8.8 Typical Bottom Hinge bracket detail


General Notes
Galvinised U Bolt, Typical Top hinge bracket
nut & washer MS galvanised Plate 12mm detail Gate frame and braces are to be
Top view fabricated from 25mm nb pipe
minimum with minimum wall
Top view thichness of 3mm

Gate mesh should be made from MS


mesh with maximum 200mm x
200mm openings minimum wire
160mm
100mm

thickness 4mm
25nb gate frame
Completed gate must be hot
dipped galvinized

All gate fittings including plates,


ubolts, nuts, washer and hinges must
M16 x 8.8 be hot dipped galvinised.
Galvinised U Bolt,
100mm nut & washer Each pair of gates should be fitted
M16 x 8.8 Galvinised with a lockable latch mechanism and
Existing Ibeam bottom gate hinge Existing IBeam drop rod to prevent gate from
100x100mm moving un assisted in open or closed
Side View
Side View position

24.5mm OD Self Gate fixings to existing I beam


lubricating Nylon must be bolt on arrangement No
bush drilling or welding required to fix
gates to posts

M16 Galvinised Eartning point shall be installed on


washer- Min OD all gates as per drawing 25180-000-
150mm

32mm EG-0000-01217

Earthing points shall be installed on


M16 x 8.8 Galvinised
all posts as per drawing 25180-000-
bottom gate hinge
EG-0000-01214

Gate design for 2 and 4 M gates

Drawing 0002
N Sketch - 01

B Room

A Room

Existing concrete path

Legend

Fencing

Gate