Building Management System (BMS) Validation Overview

Bogie D. Manendra
Technical Manager Synetec Asia
Dec 7, 2015

Building Management System (BMS) is a wide range of applications which


covers Heating Ventilation Air Conditioning (HVAC), Environmental monitoring,
Fire Protection system, Alarms & Surveillance System, Lift Management
System, Smart Building Technologies and Energy Conservations.

Why We Need to Validate a BMS?


The objective to conduct validation is to produce documents evident which
ensure high level of confidence, ensuring system compliance, reduce risk of
failures, and assurance that will improve operational efficiency to process.
Validation is conducted to prove system functionality and consistently measure
as per design specification.

Building Monitoring System (BMS) covers computerize system, network


architecture, software as source code programming and instrumentations/
devices as controller (Input/output) whereas it is monitoring for GMP elements
and Non-GMP elements. As parts of Code of Federal regulation, GMP
elements/ critical areas are mandatory to VALIDATE. There has to be
segregation physically and logically between GMP and Non-GMP elements to
avoid conflict of I/O.
Regulatory Frame

EU Directive 2003/94/EC (Good Manufacturing Practice) Article 8


Premises and equipment to be used for manufacturing operations, which are
critical to the quality of the products, shall be subjected to appropriate
qualification and validation.

Chapter 21 Part 11 Of the Code of Federal Regulation 11.10 Controls for


closed systems.
Validation of systems to ensure accuracy, reliability, consistent intended
performance, and the ability to discern invalid or altered records.

Chapter 21 Part 211 of the Code of Federal Regulations 211.68


Automatic, mechanical, and electronic equipment.
Input to and output from the computer or related system of formulas or other
records or data shall be checked for accuracy. The degree and frequency of
input/output verification shall be based on the complexity and reliability of the
computer or related system.

System Evaluation
System evaluation is very crucial, evaluating the system against standards
including GxP, evaluating the system against established requirements,
evaluating the needs of system and environment configuration, evaluating the
requirements for installation and training requirements.

Risk Assessment
Risk Management should apply throughout life cycle of computer system.
Identifies the Critical Control Point to be defined, justified and documented.
They key of risk assessment is in understanding of critical parameters that have
high probability of affecting product attributes if deviate from ranges standard for
a defined period of time.
Regulated Company must be able to justify their in-house standard, protocol,
operation procedures, and records, acceptance criteria based on analysis and
risk assessment into consideration.

Testing, Verification and Commissioning


Perform a commissioning procedure consisting of field I/O testing, sequential
test phase test and commissioning and integrated system program
commissioning for entire system.

Document all commissioning information on commissioning data sheets that


shall be submitted prior to acceptance testing.

Prior to system program commissioning, verify that each control panel has been
installed according to plans, specifications and approved shop drawings. Test,
calibrate and bring on line each control sensor and device.

Some of Tests have to be conduct before/ during Factory Acceptance Test and
or Site Acceptance Test, not limited to:

BMS Unit P&ID Verification


The objective of this verification is to ensure that all the system instrument and
equipment have been properly connected, tagged, and identified, in accordance
with the process and instrumentation diagram.

System Components Verification and Installation


The objective of this verification is to ensure that for each component required
for the system, all of the as-found conditions comply with the specifications, and
that the components required for this system are installed as specified.

Wiring and Cabling Verification


The objective of this verification is to ensure that all wiring and cabling to the
system has been properly connected, tagged, identified, and is in accordance
with manufacturers specifications and/or engineering drawings. During
execution of this section ensure that equipment visually checked to ensure that
all component and wiring securely mounted.

Input and Output Verification/ Test


The objective of this verification is to ensure that all input/output points are
addressed properly and connected to the field devices as per manufacturer
specifications.

System Sequence Test/ Phase Test


The objective of this system sequence test/ phase test is to ensure that all
system schematic running as process flow which has been designed.

Software Functionality, Backup, Archiving, and Version


Verification
The objective of this verification is to determine that the installed software is
perfectly functioning as determined in this URS. Scope also includes verification
of ladder logic program name, version number, archiving capability and
ensuring availability of the backups.

Software Structure Verification


The objective of this verification is to verify integration of software and hardware
as a complete system. Scope includes system setups (hardware and software),
to align with user requirements. User would require full simulation and In Circuit
Test for the BMS System.

IT Infrastructure Verification
The objective of this verification is to verify integration of software, hardware
and networking as a complete system. Scope includes system setups,
configuration of network, remote accessibilities and remote notification.

Validation Approach
Perform a complete set of Validation after completion of Site Acceptance Test
(SAT) for the critical system which Direct Impact to the process quality.
Validation consist of Installation Qualification (P&ID check, instrument check,
wiring check, safety check and instruments calibration as well), Operational
Qualification consists of System Operational test verification comparing with
Functional Specification of the system as define in the System Design
Specification.

Document all Validations and information on Validation data sheets that shall be
submitted prior to Validation testing.

Implementation of BMS
Nowadays, modern technology makes everything easily. Everything can be
reach in hand. Building Management System (BMS) using Real time monitoring
will be displaying process status, generate Reports (includes trends, graph),
sensor calibration expiry, generate alarm & warning according pre-set value in
the system and event recording.

Perform the Facility Management (Generate reports, graph and annunciate


alarms) when there is a problem and to ensure that monitored data is securely
stored and have not been altered for future reference (audit/ investigation).

User/ client responsibility to provide proper procedure on the Data Recovery


and Software Back-up Procedure and manage the stored data location as per
company policy.

Defining of BMS Alarms


Correct strategy has to carefully implement to comply with regulatory
requirements for BMS system itself. During conducting Risk Assessment and
measurement studies should be assess for critical elements on the software
features which derive as alarms, reporting, data historical tabular in total point of
view to avoid unnecessary alarms, eg. Sometime in the Operation mode, door
open by operator and it will be immediately trigger an alarms due to differential
pressure out of ranges. It is very difficult if we have to acknowledge alarms and
answer in the event of OOS/ CAPA raise by QA.
Statistical Process Control/ Conditioning Alarms should be implement and
access through Risk Management, Validated and Documented as evidence.

Review of Electronic Records and Electronic Signatures


BMS system continuously records data in real time monitoring with certain
define period of data collection. When BMS system consider and define as
critical in the GMP environment, assessment of direct impact to the system
should be made. Relevant parties should be manage, control on the reviewing
of the electronic records, applies signatures and by proper procedure.

Electronic records and signatures should be define clearly during generate the
User Requirement Specification (URS) and it is verify during design review and
testing/ validation.

References
GAMP 5: Risk Based Approach to Compliant GxP Computerized System.
Title 21 Code of Federal Regulation, 21 CFR Part 11: Electronic Records,
Electronic Signatures.
ISPE Pharmaceutical Engineering Guide, Commissioning and
Qualification.