System Evaluation
System evaluation is very crucial, evaluating the system against standards
including GxP, evaluating the system against established requirements,
evaluating the needs of system and environment configuration, evaluating the
requirements for installation and training requirements.
Risk Assessment
Risk Management should apply throughout life cycle of computer system.
Identifies the Critical Control Point to be defined, justified and documented.
They key of risk assessment is in understanding of critical parameters that have
high probability of affecting product attributes if deviate from ranges standard for
a defined period of time.
Regulated Company must be able to justify their in-house standard, protocol,
operation procedures, and records, acceptance criteria based on analysis and
risk assessment into consideration.
Prior to system program commissioning, verify that each control panel has been
installed according to plans, specifications and approved shop drawings. Test,
calibrate and bring on line each control sensor and device.
Some of Tests have to be conduct before/ during Factory Acceptance Test and
or Site Acceptance Test, not limited to:
IT Infrastructure Verification
The objective of this verification is to verify integration of software, hardware
and networking as a complete system. Scope includes system setups,
configuration of network, remote accessibilities and remote notification.
Validation Approach
Perform a complete set of Validation after completion of Site Acceptance Test
(SAT) for the critical system which Direct Impact to the process quality.
Validation consist of Installation Qualification (P&ID check, instrument check,
wiring check, safety check and instruments calibration as well), Operational
Qualification consists of System Operational test verification comparing with
Functional Specification of the system as define in the System Design
Specification.
Document all Validations and information on Validation data sheets that shall be
submitted prior to Validation testing.
Implementation of BMS
Nowadays, modern technology makes everything easily. Everything can be
reach in hand. Building Management System (BMS) using Real time monitoring
will be displaying process status, generate Reports (includes trends, graph),
sensor calibration expiry, generate alarm & warning according pre-set value in
the system and event recording.
Electronic records and signatures should be define clearly during generate the
User Requirement Specification (URS) and it is verify during design review and
testing/ validation.
References
GAMP 5: Risk Based Approach to Compliant GxP Computerized System.
Title 21 Code of Federal Regulation, 21 CFR Part 11: Electronic Records,
Electronic Signatures.
ISPE Pharmaceutical Engineering Guide, Commissioning and
Qualification.