Topic 1 : Project Management
PM1 PhIS Project kicked off in 15 Sept 2011 and now, within five years has completed
deployment and rollout to 1118 sites as per contract.

1.1 How the project has been planned, executed and implemented?

Your opinion

1.2 What do you think that this project has achieved, from planning to execution,
implementation and risk mitigation?

Your opinion

1.3 Which aspects/achievement the project at the moment that has meet your expectation?

Your opinion

PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page


PhIS & CPS Project
Post Implementation Review

1.4 What are your expectations for the project? What is your opinion on the achievement of
this project, so far?

Your opinion

1.5 How do you find the differences (success/strength) of PhIS compared to previous
projects of the same nature? How about areas for improvement?

Your opinion

1.6 Which challenges are the most difficult?

Your opinion

1.7 How do you think the team had handle it?

Your opinion

PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page


PhIS & CPS Project
Post Implementation Review

Topic 2 : Scope
PM1 There are 12 modules developed in PhIS. Besides that, scope of deliverables include
infrastructure. As of today there are more than 3298 CRs, out of those 1341 number
completed

2.1 To what extend that this project was executed according to initial plan?

Your opinion

2.2 If there are any changes in initial plan, can you explain why that is necessary or could be
avoided?

Your opinion

2.3 How do you perceive the need to change certain specification in the project?

Your opinion

Topic 3 : Cost
PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page
PhIS & CPS Project
Post Implementation Review

PM1 Cost for PhIS project was capped at RM 340 million. Till today, the project has not burst
its spending based on planned budget

3.1 From management perspective, what are the factors that contribute to this?

Your opinion

3.2 What return from the project that you expect after huge sum of fund had been invested
to finance the project?

Your opinion

3.3 What is your opinion on the potential of this project can bring to the ministry in particular
and nation as a whole?

Your opinion

Topic 4 : Implementation

PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page


PhIS & CPS Project
Post Implementation Review

PM1 Throughout the PhIS project implementation; none of the sites has to shut down its
services to enable PhIS deployment.

4.1 Do you think the implementation strategy works for PhIS or other factor may contribute
to ease the implementation?

Your opinion

Topic 5 : User Adoption


UA1 Business Process Reengineering (BPR) and Change Management were one of the key
project activities in PhIS implementation

5.1 BPR was conducted at the very beginning of the project to address standardised
workflow and policy for all sites. PhIS software was developed based on this standard.
What do you see from this benefit perspective to MOH on this aspect?

Your opinion

5.2 Change management has been conducted aggressively prior to implementation at each
site. Change management agents were appointed along with the change sponsors
(advocates). User resistance to change is kept at minimum. Are you happy with this
situation and should change management activities continue as part of the internal
service?

Your opinion

Topic 5 : User Adoption

PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page


PhIS & CPS Project
Post Implementation Review

5.3 As of today, we have 1118 numbers of sites with more than 20,000 direct users. PhIS
seem to be quite well accepted by the users.

Can you share your view on any feedback you receive from the ground?

Your opinion

Topic 6 : Aspiration
FA1 We would like to know your opinion and aspiration pertaining to PhIS (where relevant)

6.1 How do you find PhIS is supporting National Drug Policy?

Your opinion

6.2 How will this project contribute to a sustainable healthcare service in the public sector in
Malaysia?

Your opinion

6.3 What do you wish and recommendation for the future of PhIS?

Your opinion

PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page


PhIS & CPS Project
Post Implementation Review



Interviewee Name : Interviewer Name :
Date : Date :

PhIS & CPS PROJECT_PIR QUESTIONNAIRE_SET 1a-v1.0 Page

Vous aimerez peut-être aussi