Académique Documents
Professionnel Documents
Culture Documents
MARITIME
Consulting Group
Consulting Naval Architects and Marine Engineers, Project Managers
Introduction
This is a collection of articles selected from the newsletters Upright & Afloat published
by Fisher Maritime Consulting Group. Most of these articles (#'s 1-27) are intended to convey
to the reader the costly lessons learned by others in the maritime industry in association with
projects being undertaken by shipyards on behalf of ship owners. Hopefully, the availability of
these "lessons learned" will enable the readers of this compilation to avoid having to re-learn
such lessons at great expense to any of the involved organizations. Several of the articles at
the end of this compilation introduce the reader to the availability of the services of Fisher
Maritime Consulting Group. January 2008
====================================================================
Contents 11 Owner Furnished Equipment -- Oppor-
1 Contracting Strategies Central to Suc- tunities for Contract Risks
cess of Project 12 Equipment Integration and Interfaces
2 The Second Translation of Technical 13 Color Coded Features -- The Vanishing
Requirements Information
3 Unusual Contracting Brings Risks to 14 Shipbuilding Specifications: Best Prac-
Owners and Builders tice Guidelines
4 Identifying All the Contract Deliverables 15 The Flow of Contract Information
5 Remaining Responsible -- General Dis- 16 Repaired During Construction: Is it
claimers Don't Work 'New'?
6 Design Completion Responsibility -- 17 Contractually, is it a Good Deed or a
Whose Naval Architect? Misdeed?
7 Amateur Contracts a Cause of Disaster 18 The Risks of FPSO Conversions
8 Definitions vs. Controversy in Ship 19 VLCC's for FPSO Conversions
Repair and Construction 20 Damage Due To Erroneous Docking
9 Sisters, Not Twins -- A Source of Speci- Plans
fication Errors 21 False Economies Prove Costly
10 OFE in a Design-Build Contract -- Con- 22 Shipyard Safety Concerns -- Put it in
fusion All Around
147 Columbia Turnpike, Suite 203, Florham Park, New Jersey 07932 U.S.A. !
www.fishermaritime.com ! email@fishermaritime.com
Tel. +1 973 660 1116 ! Fax. +1 973 660 1144
Management of Shipyard Projects Insights and Lessons Learned
to complete the design from the contract plans owner much greater opportunity for input into
and specifications. The risks of unwarranted the design since the shipyard's price was not
design compromises, construction delays and based on its own interpretation of the antici-
extra costs cannot be tolerated by either the pated design. Fisher Maritime translated the
owner or the shipyard. Thus, a comprehensive strategy into reality by developing the engi-
contracting strategy needs to be developed for neering/design contract (professional services
both the design and construction, especially for agreement) as well as the ship construction
relatively-unique vessel designs and for nearly contract.
all conversion projects.
The key observation is this: the success
A Fisher Maritime client wanted to con- of a project is just as dependent on good con-
tract for a new specialty vessel for use in the tracting strategy as it is on good ship design.
offshore industry. Fisher Maritime realized that One without the other inevitably leads to a
very few organizations had the capability to compromised outcome. Ship owners are urged
execute the design, so that it was too risky to to contact Fisher Maritime to work out a com-
allow the shipyard to choose the designer as a prehensive strategy, for both the design con-
subcontractor. Accordingly, Fisher Maritime tract and building contract, that will meet the
arranged for competitive bids from the few needs of the owner while minimizing risks of
qualified design firms to complete the design, unwarranted design trade-offs, delays, extra
including classification approvals and details of costs, and disputes over interpretation of the
all distributive systems, before the shipbuilding intent of the design.
contract was executed. This process gave the
====================================================================
the specifications into estimated quantities of contractor has to first translate the specifications
man-hours, material costs, subcontractor costs into reasonably close quantitative estimates of
and schedule days. Only when the specifica- man-hours, material costs, subcontractor costs
tions are sufficiently clear can such quantitative and schedule days. Only later does the con-
translations be reliable, and thus included in the tractor translate them in to tangible hardware.
fixed price bid. Accordingly, specification writers should re-
examine their writings, before sending them out
Thus there is burden on the writers of
in a bid package, to ensure that the specs can
specifications to provide to contractors sufficient
be quantitatively translated.
information to enable a quantitative translation,
so a firm, fixed price can be negotiated and Often, specification writers are too famil-
relied upon. Negative examples of specifications iar with their own specifications to see that they
-- ones that cannot be reasonably translated cannot be reasonably translated into those
into quantities -- include these. None of these forms of quantities. Fisher Maritime routinely
examples are fictitious, but well keep the iden- provides quality assurance and risk-minimization
tities confidential to prevent embarrassment. reviews of major specifications, for conversions
and newbuildings, to ensure that all the ambi-
(a) Vee and weld eroded bottom plate
guities and vagueness are identified and cor-
welds as considered necessary [tug boat]. (b)
rected before the bid package is released to
Repair or replace seals and bolts as needed
potential contractors.
[work boat]. (c) Furnish and install suitable
lighting in all passenger-occupied spaces [crew In addition to ensuring that the specifi-
boat]. (d) All work necessary to accomplish cations can be quantitatively translated, other
the specified work shall be deemed specified forms of ambiguities are resolved by the quality
whether specified or not [fisheries vessel]. assurance review. A major form of ambiguity
that is often overlooked by persons drafting
How many man-hours and how much
specifications is the identification of the stan-
material costs should the contractor have in-
dards by which the workmanship and/or materi-
cluded in its budget for each of those items?
als will be judged acceptable. Contact Fisher
Obviously, a contractor cannot know whether it
Maritime while you are developing your specifi-
is 10, 100 or 1000 man-hours or any other
cations to find out how such a quality assurance,
approximate number.
risk-minimization review can be economically
The specification writer has to keep in arranged.
mind that when asking for a fixed price bid, the
====================================================================
the owners marine interests and production ("OFE"). These risks exist in conversions be-
interests are suitably coordinated. cause the starting point for conversions is often
ill-defined, although the end-point of the con-
Shipyards that accept fast-track con-
version is well-defined unless the owner starts
struction or conversion projects predicated on
introducing many changes as the conversion
significant owner-provided engineering have
progresses. The highest risks that arise in
often found that the owners delayed engineer-
conjunction with OFE are those of system inte-
ing output impacted the shipyard's engineering
gration involving products from multiple ven-
as well as the anticipated production schedule.
dors.
Subcontractors that take on an assign-
To minimize all forms of project and con-
ment several times larger than any prior job also
tract risks, organizations should maintain a high
face considerable risk of overruns unless greatly
level of contract management ("CM) training
expanded management resources are provided.
specific to the industry for all their involved
Design firms that accept assignments from a
personnel, not just the front-line staff that inter-
new category of client also incur risks of misun-
acts with the other parties. Shipyard estimators
derstandings, under-budgeting and time exten-
and purchasers benefit just as much from the
sions.
CM training as do the project managers. The
Shipyards that subcontract engineering ship owners technical staff need to understand
to design consultancies must be sure those the impacts of their role in on-going projects
designers have the shipyard interests in mind just as much as the owners representative. No
when developing the details (least cost solutions profession in the marine industry is exempt from
consistent with all contract requirements) and the need for continuing industry-specific project
that the designers do not inadvertently improve and contract management training.
the vessel's design details at the shipyard's
To arrange an in-house training program
expense.
on Contract Management for Ship Construction,
Those are only examples of many high- Conversion and Design, see the general syllabus
risk contracting situations in the maritime indus- on Fisher Maritimes website, but allow for
try. modification to suit the needs of your organiza-
Perhaps the two highest risk types of tion. After selecting several possible sets of
projects, for both owners and shipyards, are dates for the three-day program, contact Fisher
major conversions of any kind and projects Maritime to schedule the in-house training pro-
relying on a lot of owner-furnished equipment gram.
====================================================================
are expected to be on paper only, and others getting an incomplete or insufficient deliverable,
may be expected on computer diskette, too. or none at all in particular categories.
Ship owners have to appreciate that a For both ship owners and shipyards,
shipyard incurs considerable, real costs to Fisher Maritime routinely reviews draft contracts
achieve the production of all those non-hard- (agreements, specifications, plans) for com-
ware deliverables. If the owner wants to avoid pleteness and consistency as well as to eliminate
surprises and/or disputes, the necessity of the ambiguities. One of the items always focused
shipyards development of those deliverables upon is that of the identification of all the deliv-
has to be clearly addressed in the bid package. erables. If your organization is either preparing
Absent clear requirements for those deliverables a contract or bidding on one, get Fisher Mari-
in the bid package, bidding shipyards may not time involved to minimize the likelihood of mis-
create adequate budgetary allowance for the understandings or disputes.
development of them. The owner then risks
====================================================================
====================================================================
rated too severely, however, these amateur in shipbuilding contracts to develop the contract,
contracts may become the focus of post-delivery rather than saving some costs at the com-
litigation, requiring both the specialized consult- mencement of the project and paying many
ants as well as attorneys. It would have been far times over for that mistake later.
more cost-effective to use professionals skilled
====================================================================
SSDG using ships equipment for the electrical tion organization, the debate that inevitably
load. The vessels chief engineer as well as the ensues, of course, centers on whose interpreta-
port engineer would not allow that; they ex- tion of those rules will apply: the shipyard or
pected that the shipyard would use a test load the owner? This form of dispute is completely
bank instead. The shipyard pointed out that predictable when an owner attempts to get
because the specification did not mention a load something for nothing. Even if the owner does
bank, the rental of one was not included in the not intend to maintain the vessel in class after
bid. This problem involving both cost and delay delivery, there is nothing barring the construc-
would have been avoidable if the means of the tion and delivery of it in class, as determined by
test was defined. Again, this was an opportu- the classification organization. This assures a
nity for the ship owner to appreciate that the certain level of design, workmanship and mate-
contractor would select a least-cost solution rial selection consistent with classification rules,
unless the specification clearly required other- but requires that the classification organization
wise. be duly involved during construction and deliv-
ery. Simply, there is no short cut to obtaining
What is New? A shipbuilder committed
the benefits of classification.
to constructing several new vessels, each of
which was to include an item of special equip- Oxymoron: Ambiguous Specifications:
ment. The vessels were produced, including the Grammatically, the phrase ambiguous specifi-
items of special equipment; but the vessel cations is an oxymoron, because the compo-
owner complained that those items were not nents of the phrase are inconsistent; something
new. The shipbuilder pointed out that the items that is specific cannot concurrently be ambigu-
were new, as evidenced by the fact that they ous. Yet, numerous repair, conversion and
had never been used, never installed on any construction specifications have been ambigu-
other vessel, and had arrived at the shipyard in ous, causing disputes, costly fixes and substan-
their original packing crates. The problem, as tial delays to completions of the projects. Some
perceived by the owner, was that they were ship owners representatives express the atti-
manufactured over 20 years earlier, but had tude, I know what that specification means
never been sold by the supplier, only ware- because I wrote it. This, of course, does not
housed. To exclude the possibility of such event alter the fact that the specification as written is
recurring, an owner can specify that all materials ambiguous; it simply confirms that it has to be
and equipment being used shall be new and interpreted. The shipyard already knew that,
manufactured not more than [number] years and planned to achieve its interpretation of the
prior to installation. specification using a least cost solution. The
remedy at that point, if essential to the owner,
Interpretation of Rules: Some ship own-
is a costly and perhaps project-delaying change
ers want to obtain the benefit of having their
order.
new vessel constructed to the standards of a
classification organization, but do not wish to Specification Quality Assurance: For ma-
pay the fees of the organization that are in- jor shipbuilding and offshore construction and
curred in granting the vessel classification conversion projects, significant contract price
status. In those instances, the construction growth can be minimized by subjecting the
specification states something like, All work- proposed contract specifications and drawings to
manship accomplished and all materials and an independent quality assurance review proc-
equipment supplied and incorporated into the ess. Fisher Maritime, having reviewed hundreds
vessel shall conform to the classification rules of of specifications and having helped resolve
the [name of classification organization]. But many disputes arising from ambiguous specifi-
without the direct involvement of the classifica- cations, provides a unique service to the marine
industry. A thorough review of proposed con- cations and projects for ship conversion or
tract documents is undertaken to identify ambi- construction, Fisher Maritime has three papers
guities, incomplete items, and inconsistencies in that can improve your capabilities and enhance
order to assure a less-troublesome contractual your insights. Each of these papers have been
relationship than may otherwise develop. Start- approved and published by SNAME or RINA.
ing with the initially proposed contract docu- They are: (a) Shipbuilding Specifications: Best
ments, Fisher Maritime will return to its client a Practice Guidelines; (b) An Owners Manage-
marked-up set of documents, indicating sug- ment of Ship Construction Contracts; and (c)
gested alterations and identifying areas needing Responsibilities Pertaining to Drawing Approvals
more definition or selection of possible choices During Ship Construction and Modification. The
before the contract package is finalized. Contact three of them can be can be ordered at minimal
Dr. Kenneth Fisher at Fisher Maritime for more cost from Fisher Maritime. Merely send an email
details, cost estimates and examples of this with the subject line Three Papers to Fisher
service: kfisher@fishermaritime.com. Maritime (email@fishermaritime.com) and we
will send a two-page PDF file description and
Improving Shipbuilding Specifications: If
order form.
your professional responsibilities involve specifi-
====================================================================
portions of the ship being provided by the ship- sion project. The OFE vendors testing and
builder. Horizontal integration specifically refers commissioning requirements had not been
to ensuring the compatibility of multiple OFE communicated to the shipyard. Major schedule
components with one another. problems developed at the end of the conver-
sion project when the owners vendor required
Because the contractor or shipyard is
far more time for testing and certification (sev-
not automatically vested with integration re-
eral weeks) than the shipyard had been told to
sponsibilities, the contracting party that has
allow (several days).
such integration responsibilities has to be clearly
identified in the contract documents, and has to Fisher Maritime was called in by the
be given authority to seek necessary alterations shipyard to help develop a revised schedule that
if there is not a good fit in all those areas. minimized the total delay. Fisher Maritime then
developed an assessment of the impacts on
Fisher Maritime has often been called
both cost and schedule that resulted from hav-
upon to assist in troubled contractual relation-
ing overlooked the commissioning requirements
ships when, the owner alleges, the shipyard is
for the OFE. That analysis was used to negoti-
creating difficulties over the OFE. Sometimes
ate a resolution of the responsibilities for those
our analyses result in the appreciation that the
costs and delays.
ship owner did not clearly nominate the shipyard
to be the OFE integrator, thus causing the inte- Organizations planning to incorporate
gration process to have been overlooked. Fisher major OFE items into a vessel construction or
Maritime then has developed recovery plans to conversion project should consider having Fisher
minimize the impacts of the late-assignment of Maritime review the planned acquisitions and
integrator responsibilities. deliveries to ensure minimization of the risks
associated with OFE, and to make certain that
In one matter, the owner provide a com-
they are wholly compatible with the shipyards
plete propulsion system (diesel generators,
contractually-defined responsibilities.
motors, thrusters, power management system,
etc.) for a dynamically-positioned vessel conver-
====================================================================
of the parts (from the subcontractors) did not Component and system integration, in-
equal the whole requirement of the prime con- stallation and testing are often found to be
tract -- but the shipyard did not otherwise planareas that have been partially overlooked or
for that shortfall. incompletely addressed, especially when sub-
contractors and vendors are involved. To avoid
Upon analysis it was observed that the
such problems, Fisher Maritimes pre-contract
fundamental cause of the problem was that,
reviews on behalf of shipyards ensures that the
during the bidding stage, the shipyard assumed
entirety of the prime contracts workscope is
that the subcontractors were bidding on the
addressed and bid by the shipyard itself or its
entirety of the workscope related to the equip-
subcontractors. If your organization is bidding
ment they were to supply. Instead, the sub-
on a complex contract requiring multiple sub-
contractors bid proposals addressed only those
contracts, a pre-bid review by Fisher Maritime
elements that were independent of the work of
can minimize the likelihood of errors in the bid
other subcontractors.
due to such oversights.
====================================================================
them cannot be sure how the selected ship- engineering staff is clarified in this paper, thus
builder will interpret any ambiguities in them. giving the developers of the Contract Specifica-
Based on numerous lessons learned, which tions the opportunity to alter the point in design
lessons have undoubtedly been learned the development at which that transfer of authority
hard way, a paper published by the Royal takes place.
Institution of Naval Architects, authored by Dr.
Means of overcoming the often-encoun-
Kenneth Fisher, presents perspectives that
tered perils of owner-furnished equipment are
should be borne in mind when developing those
also addressed through improved specification
specifications and plans.
writing. Many other aspects of the development
The differentiation between different of Shipbuilding Contract Specifications and
forms of specifications is made, for example, to Contract Plans are also discussed in this paper.
illustrate that responsibilities and risks are as- Published in the International Journal of Mari-
signed to different parties for each different time Engineering, Royal Institution of Naval
form of specification; and the developer has to Architects, London, March 2004. A copy of the
decide in advance which party is to have which paper in an electronic PDF format can be ob-
responsibilities. Similarly, for design develop- tained by sending an email request to:
ment, the transfer of decision-making authority email@fishermaritime.com with the subject
from the Purchaser's (i.e., owners) architect- "Best Practices."
engineer to the Contractor's (i.e., shipbuilders)
====================================================================
has been the basis of disputes, large and small. yard performed the engineering, only to learn
For example, when a large change order during that the HVAC distribution system would not fit.
ship repair would impact vessel redelivery date, This led to the necessity of an extensive altera-
the parties agreed that the extent of the con- tion in the configuration of the already fabri-
tract extension was to be determined, with no cated deckhouse. If the engineering had been
further description given. Later, in arbitration required to be accomplished pre-fabrication, a
over that issue, the owner said a pre-completion much less costly fix could have been arranged.
formal schedule impact analysis was expected; Lesson learned: get the engineering done
while the shipyard said the extension was to be before the construction begins. This is an ex-
determined by the sequence of actual comple- ample of why the flow of information (HVAC
tion events, however it turned out. This is but engineering) should include the timing of when
one example of the necessity of defining the it is to be accomplished (before fabrication of
content of information that is to be communi- the deckhouse).
cated at some later time. Regarding the medium for the transmis-
Form: Once the content of a given sion of information, Fisher Maritimes recent
specification item has been nailed down, the review of a proposed ship construction specifi-
next point to consider is that of form. Especially cation noted that it required that a certain dy-
since the advent of computers and related tech- namic test result be tape recorded. At a
nologies this point has become increasingly number of other places it specified that data be
more important and complicated. Paper or stored on magnetic media. With the apprecia-
electronic? Merely using "electronic" may result tion that the owner did not want to receive
in a non-searchable pdf file. Instead, identify these documents on an outdated floppy disc or
the application and the version of it by which magnetic tape, it was recommended that these
the information can be effectively used. Exam- specifications be updated to identify a more
ple: As-fitted drawings were to be provided in modern (i.e., optical) means of data storage.
both printed and electronic form. When the This illustrates why the medium by which infor-
owner received the drawings as a pdf file, the mation will be conveyed sometimes needs to be
owners unhappy response was initially directed defined, as well.
toward the contractor, but later toward his own There are numerous opportunities for in-
specification writers. (The shipyard had asked consistencies and incompleteness in specifica-
for an additional fee to provide them in a more tions for shipyard projects. Often they may be
useable electronic format.) largely avoided by having persons other than
Timing: When is the most appropriate the specification writer independently reviewing
time for the owner to receive the information? the specifications. Fisher Maritime routinely
An example of that question not being explicitly provides specification quality assurance services,
answered in the specifications involved the ensuring uniformity throughout the specifica-
conversion of a ro-ro to a training ship, requiring tions. To assist owners during the contract
much more accommodation space. All design development and execution processes, Fisher
engineering was provided by the owner except Maritime also has a number of other resources
that the shipyard was to accomplish the HVAC available including training programs and publi-
engineering and design. The contract did not cations. Additional information pertaining to
require that the HVAC engineering be done resources available from Fisher Maritime may be
before assembly of the new accommodation found by visiting our website at
structure. So after the structure was mostly www.fishermaritime.com.
fabricated (to accelerate cash flow), the ship-
====================================================================
The cosmetic quality of the finishes on In the end, when a vessel has been sig-
the damaged, nearly-complete, high-value, nificantly damaged while under construction,
custom yacht presented a special problem. The there will have to be a common agreement
surfaces of nearly all the extensive, custom- between the owner, the shipyard and the
manufactured, stainless railings were etched by builder's risk insurance interests as to the out-
the acidic tars and ash of the products of com- come. The owner may agree to take the vessel
bustion. While they could be polished to a shiny at full price or at reduced price if the repairs
finish, they would never be as smooth as when have been substantial, reducing the value of the
new, suggesting that they have to be replaced, vessel. If the owner no longer wants the vessel
not merely polished, if the vessel is to look because it cannot be practicably renewed, the
"new" in all regards. Other cosmetic features yard may offer it on the market while returning
were also impacted. The hull, house and bul- the owner's payments.
wark sides are not merely painted. Instead, two
The standards for final acceptance of a
layers of high-quality filler are used to create
vessel damaged during construction will vary for
absolutely smooth finishes at every section and
different categories of owners. The owner of a
joint, followed by the application of several
work boat that has been repaired during con-
layers of finish to create a highly reflective
struction will not be as demanding as the own-
appearance. Repairs to those surfaces, without
ers of a custom yacht or a cruise ship that need
complete renewal, present a cosmetic finish that
extensive renewals. To the best of our knowl-
is somewhat less perfect than the new finishes;
edge, this is an area that is relatively undefined
but complete renewal of them is a very expen-
by prior legal precedents. Thus, thorough
sive matter that may not be justifiable from an
analyses of contractual and technical issues
insurance perspective.
have to be integrated in order to ascertain what
Even if the damaged vessel is, after cor- is technically accomplishable, what is practicably
rective action, accepted as "new" by the owner, and financially feasible, and what is contractu-
there may be a contractual assessment of liqui- ally appropriate. No one wants vessels dam-
dated damages due to late delivery resulting aged while under construction; but Fisher
from the damages and renewals. Thus, even if a Maritime is ready to assist shipyards or ship
shipyard recovers the extra direct costs to renew owners in the development of those analyses
the vessel from the underwriter of the builder's when the need arises to assist in facilitating a
risk policy, it may still have to pay liquidated workable agreement between the interested
damages. parties.
====================================================================
theme that becomes obvious is this: Do not order for the materials by the time the vessel
relieve the other contracting party of any of its arrived. The contractor reported to the vessel
contractual obligations without first assessing all owner that it was having trouble securing the
the risks and consequences that may arise. materials, and requested the owner to obtain
them on the basis that the owners staff was
Use of Shipboard Equipment: A gov-
more familiar with the equipment. The owners
ernment agencys vessel was undergoing re-
staff then ordered the materials, but the lengthy
pairs, including hot work in the machinery
lead time for their arrival delayed completion of
space. The agencys representative complained
the refit. The delay would have been avoided if
to the shipyard that the space was not being
materials had been ordered shortly after con-
adequately ventilated, allowing too much smoke
tract execution. But in agreeing to relieve the
and fumes to impair work and inspections. The
contractor of the obligation to obtain the mate-
shipyard agreed to increase the ventilation as
rials, the owners staff neglected to address the
required by the contract, but lacking sufficient
schedule impacts, resulting in the owner being
equipment, sought to borrow the blowers from
responsible for the delay. Adding insult to
the vessels bosuns locker. The agency allowed
injury, the shipyard sought additional fees for
the blowers to be used, including the long spiral-
maintaining the vessel at the shipyard extra
wound hoses attached to them. On the second
weeks while awaiting the owner-purchased
day of use of the blowers, the sparks from hot
materials. Next time the owner should monitor
work ignited one of those hoses, and the fire
the shipyards pre-arrival purchasing efforts
spread. The damage to the vessel and project
whenever long-lead time materials are an essen-
delays were significant. The agency tried to
tial part of the contract workscope.
hold the shipyard responsible, since the fire was
started by the contractors hot work. But the Place of Delivery: A vessel owner was
shipyard considered the agency responsible, for obligated to deliver to the shipyards warehouse
not having alerted the shipyard to the fact that an overhauled replacement for a dredges com-
the hose was flammable, even though the bination pump/motor. The 18-ton replacement
agency knew the hose was going to be used in unit was located at the owners warehouse, on
the presence of hot work. The agency replied by the other side of the river from the shipyard.
pointing out that the shipyard's fire watch per- Shortly before the replacement unit was needed
sonnel were ill-equipped to snuff out the incipi- by the shipyard, the owners staff requested the
ent fire, allowing it to spread. The outcome was shipyard to send a truck across the river to the
the shipyard's (and its insurer's) accepting the owners warehouse to pick-up the unit. The
cost of repairing the damage, and the owner shipyard complied. But during transit from the
accepted the loss of the blower and accepted owners warehouse to the shipyard, a roadway
the delay as force majeure. Next time the accident caused the truck to roll into a ditch,
agency should simply insist that the shipyard resulting in damage to the replacement unit.
comply with its contractual obligation to supply Project completion was delayed more than a
all the equipment needed for proper accom- week while repairs were made to the unit that
plishment of the work. had been on that truck. The owner alleged the
shipyard was responsible for not providing
Advance Material Purchases: As part of
appropriate transportation. The shipyard re-
a 12-week vessel modification project, a ship-
sponded that the owner was responsible for the
yard was obligated to obtain special materials
delay since the pump/motor was late in being
for integration into a shipboard cargo-handling
delivered to the shipyard's warehouse as re-
system. Although the contract was executed
quired by the contract, which had not been
about six weeks before the refit period was to
amended when the shipyard agreed to send a
commence, the contractor had not placed an
truck. Next time, the shipyard should politely public officials, the shipyard could quickly paint
insist that it looks forward to receiving the only one side of the vessel (so the TV cameras
owner's equipment at the warehouse, per the would have a good view). This meant that the
contract. vessel had to be drydocked later to complete the
hull painting, which drydocking had not been
Shipyard, not Storage Yard: A shipyard
planned as part of the ship construction process.
had contracted to convert a vessel into a float-
The extra costs were borne by the shipyard.
ing restaurant. Upon completion, the vessel
Thus, the shipyard paid for doing the good deed
would be permanently moored at a pier under-
of accepting changes without altering the
going modification to receive the new floating
launching date.
restaurant. The vessel conversion was com-
pleted prior to the pier being ready to receive Expanded Skills means Expanded Risks:
the floating restaurant. The shipyard, tempo- In the course of planning the replacement of the
rarily having extra dock space available, agreed entire propulsion system in an older ferry, a
to keep the vessel at its dock, for a daily fee, shipyard retained a specialist subcontractor to
while the pier was completed. Several weeks perform the required lead-paint abatement in
later, the restaurant vessel capsized at the the hull before bringing in the new machinery.
shipyards dock due to the accumulation of Just as the subcontractor was finishing its sev-
water in the bilges. This blocked the shipyards eral-week assignment, the vessel owners de-
dock, impacting other projects, until salvage was cided that, in addition to the contractually
completed. The restaurant owner, not being a required lead-paint abatement in the machinery
traditional ship owner, had not understood the spaces, the ferrys entire deckhouse should also
need to continuously monitor the bilges. The be subjected to a lead-paint abatement. The
shipyard considered its only obligation for the subcontractor was already committed to another
daily fee was to provide the dock to temporarily job elsewhere, and could not stay at the ship-
secure the vessel, but not to provide any form yard. Other specialist subcontractors were not
of guard service. The fundamental cause of this timely available, either. The shipyard agreed,
incident was that the shipyard offered to provide under pressure from the vessel owner, to send
a service (keeping an idle, unmanned vessel at some of its own personnel for training to man-
its dock) that it doesn't normally provide, with- age the abatement of toxic materials, and
out defining to the owner the limited scope of rented the special equipment, as well. Being the
services it would provide at that time. first lead-paint abatement job that the ship-
yards own personnel directed and accom-
Fixed Schedule, but No Fixed Workscope:
plished, it went far over budget and schedule.
A shipyard, constructing a large public vessel,
Moreover, it required the suspension and delay
made a commitment to launch the vessel on a
of much of the work originally planned. Only
specific future date so that highly-placed public
after lengthy litigation, did the shipyard get
officials could be scheduled, far in advance, to
some compensation for that extra effort, but
participate in the launching, with TV and news-
was never compensated for all of its direct
paper reporters present in large numbers.
litigation costs. Though Fisher Maritime assisted
Some time after making that commitment, but
in settling the matter, it would have been bene-
still long before launching, the public agency
ficial and less costly if the shipyard had con-
requested numerous changes that had con-
tacted Fisher Maritime for advice at the time
struction schedule impacts, but the launch date
that such substantial changes to the contract
was not allowed to be altered. As the long-
work were requested by the vessel owners.
planned launching date approached, the vessel
was far from ready for exterior hull painting. Contractual Difficulties: Fisher Maritime
But in order to keep to the schedule of the hopes that your organization does not find itself
facing contractual difficulties similar to those contracting process and project management
described above. We work with organizations to run smoothly. If you find yourself facing con-
plan and contract for major shipyard projects so tractual difficulties, utilizing our 30 years of
that the likelihood of contractual difficulties is experience in a wide variety of contract-related
minimized. If you are planning a major project, support services, we can help restore the project
please contact us to learn of the variety of to a less-troubled status. Bon voyage!
support services we provide to make your entire
====================================================================
A vessel owner sold two VLCC's for con- only on each vessel going through a classifica-
version to FPSOs (floating production, storage & tion Special Survey for the vessel to remain as a
off-loading). Although they were each over 20 VLCC. In contrast, nearly all the 1100 tons of
years old, they had been maintained in excellent new steel was required to satisfy classification
condition. The seller warranted to the purchaser as an FPSO that would be on station 15+ years,
that each vessel would not need more than 100 not as a VLCC that is drydocked every 4-5 years.
tons of steel, and guaranteed payment for any We then supported our client in subsequent
steel work in excess of that amount that was negotiations to resolve that misunderstanding
attributable to the condition of the vessels. between the seller and purchaser of the VLCCs.
However, it was later learned that each conver- The lesson learned is that a reasonable
sion to the FPSOs required over 1100 tons of expectation applicable to one vessel type under-
steel work, thus placing the seller in an unex- going conversion may not be a reasonable
pected predicament. expectation applicable to the converted vessel
Fisher Maritime was retained by the type. This observation may also apply to emer-
seller to analyze why there was such a discrep- gency electrical requirements, fire-suppression
ancy. Following review of the owners technical systems, battery back-up requirements, redun-
practices and the classification rules for both dancy of bilge systems, and other safety fea-
VLCCs and FPSOs, we were able to advise our tures.
client that the 100-ton amount was predicated
====================================================================
costs to correct the work that was erroneously drawings and the ship will continue to grow. If
accomplished because of the errors in the draw- the drawing modification costs are not included
ings, or (b) have to develop its new work by on- in the workscope, then it becomes the owner's
site reverse engineering to know what is already obligation to get the drawings modified at a
there in order to proceed with the new work, later time to ensure that the drawings continue
with such reverse engineering being a source of to match the ship. But since many owners'
delay and extra costs. Moreover, emergency organizations do not follow-through with the
repairs will certainly take longer when the draw- drawing modifications after the ship leaves the
ings cannot be relied upon. yard, the gap between drawings and the ship is
essentially guaranteed to grow. This is not a
For ship repairs and maintenance, the
good way to manage the ship for future repairs
recommended means of dealing with drawing
and maintenance because, in addition to causing
issues is to ensure that the specifications for
damage, it will cost several times as much later
work items that will physically modify the ship
to make up for a lack of accurate as-built draw-
include a requirement that the shipyard per-
ings than it would to keep them up to date in
forming the modifications also update the rele-
the first place.
vant drawings; otherwise the gap between
====================================================================
endure for as long as the shipyards work con- ately upon detection of perceived safety haz-
tinues, although that implementation has a cost ards. Second, there is no misunderstanding
impact on the shipyard. The challenge is for an regarding the particulars of a given issue. Third,
owners representative to effectively convince the issue has been preserved in the event of
the shipyard to implement for the duration of future disputes. Fourth and perhaps most
the contract all the safety features that it con- importantly, knowledge of the existence of this
tractually promised. contemporaneously-developed document puts
pressure on shipyard management to implement
Fisher Maritimes expertise was called
for the duration of the contract all the safety
upon to help resolve a dispute centering on a
features that it contractually promised.
vessel which experienced a significant fire
stemming from hot work during the repair proc- An owners representative may even find
ess for which there was inadequate fire watch it useful to create a form in advance in order to
and fire protection. During the ensuing litigation easily record such important parameters as the
over responsibility for the cost and schedule nature of the issue, reference to particular
impact of the fire and subsequent repairs, an contractual and statutory requirements, and
owners representative alleged that he had identification of the location, date, time, person
passed through the space before the fire oc- notified, and corrective actions to be taken,
curred, asking for improvement in the fire watch among other possible factors.
situation and the greater use of appropriate fire
Dovetailing into this issue is the confu-
blankets. The shipyard denied that they had
sion regarding the intent of occupational safety
been advised of those alleged deficiencies.
and health regulations pertaining to ship repair,
Orally calling safety issues to the atten- conversion, construction, and breaking. Those
tion of the shipyard is often believed sufficient. regulations have been promulgated to ensure
However, these conversations are often subject the safety and protection of shipyard employees
to differing recollections, especially as time from unsafe working conditions. That is, those
passes, memories fade and unfortunate events regulations exist to protect the shipyard em-
occur. In order to ensure that the communi- ployees, not the vessel, from unsafe working
cated concern is properly preserved, a safety conditions. With this in mind, the owner may
issue which has been verbally communicated to find that those regulations fall short of ade-
the shipyard probably should be followed up quately protecting the vessel from unsafe condi-
immediately in writing to shipyard project man- tions. Accordingly, many owners find it
agement. important to contractually define supplemental
requirements that focus on the safety of the
This process achieves four objectives.
vessel above those regulations that focus on
First, it ensures that the shipyard management,
safety for shipyard employees.
beyond the production staff, is notified immedi-
====================================================================
course that commences once the decision to relevant experience of the naval architect, the
acquire a new ship is made, noting that multiple locale of the shipbuilder, the applicable law,
follow-on decisions are necessary. Many of financial guarantees, and the relevant experi-
those subsequent decisions are reflected in the ence of the ship owners staff that is managing
technical specifications and plans which define the ship acquisition process, among other fac-
the physical ship that will satisfy the require- tors. The process of developing the contract for
ments of the ship owner. However, many non- ship construction and the letting of the contract
technical decisions are needed also, some of by the ship owner is, accordingly, an orderly
which involve: selecting a naval architectural sequence of risk evaluation at each step along
firm to develop the technical requirements; the the way, followed by action that minimizes the
extent to which the design will be developed by relevant risks or considers other factors if a
the ship owner before the contract is executed; slightly greater risk is found acceptable.
and the identification of qualified shipyards that
The four major sections of Dr. Fisher's
will be invited to submit bids or proposals; and
48-page chapter are: (1) Understanding and
many other non-technical decisions. The ship
Defining Shipbuilding Contracts (18 sub-sec-
owners organization also must select: the
tions), (2) Formation of the Shipbuilding Agree-
means of financing the construction and mort-
ment (32 sub-sections), (3) Formation of
gage of the ship; the basis of comparison of
Contract Specifications and Plans (25 sub-sec-
offers or bids from several shipbuilders; a ship-
tions), (4) Management of Contracts During
builder from among the responsive bidders; the
Performance (11 sub-sections), and an Appendix
format of the shipbuilding contract; and other
listing and describing the 38 components of the
non-technical decisions that need to be made
five phases of contract management perform-
just to initiate the acquisition process.
ance. The book was officially released by
Dr. Fisher's chapter goes on to demon- SNAME at the October 2003 World Maritime
strate that there are hazards associated with Conference in San Francisco. Copies of the book
each such non-technical decision, which hazards are available through SNAME (www.sname.org).
are in the form of risks associated with the
====================================================================
approach to contract management, but is based can be obtained by sending an email request to:
on numerous analyses of contractual problems email@fishermaritime.com, with the subject
and disputes experienced by ship owners. A "owner's management."
copy of the paper in an electronic pdf format
====================================================================
shipyards, five engineering organizations, and a tered significant problems applying coatings to a
number of vendors and subcontractors. When series of several new ships. The need to remove
the project fell behind schedule due to a break- or repair and recoat a significant percentage of
down in communication between the various the coatings on the hulls, decks and bulkheads
parties, the owner called Fisher Maritime to led the shipyard to assert a claim against the
assist in regaining control over the project. coating supplier, alleging the coating materials
were defective products.
Fisher Maritime was required to immedi-
ately assess the status of the project from an The shipyard had a fully-protected blast-
overall perspective. It was readily apparent to and-coat facility in which much of the coating
Fisher Maritime that focusing solely on the work was accomplished. Fisher Maritimes re-
primary shipyard's effort was precluding a com- view of records led to the observation that
plete assessment of the status of the overall nearly all of the alleged product failures oc-
project. To realistically assess the state of the curred, however, to the coatings which were
project, each contributor's efforts, including the applied outside of the protected facility. Fisher
owner's, had to be scrutinized. A realistic as- Maritime also observed from a review of the
sessment of the project was the first step in supervisors logs, the labor reports and other
formulating a plan to bring the project under documents that the incidence of coating failures
control. was clearly of greatest frequency during cold
weather, and second-most frequent during hot,
Through a comprehensive understanding
humid weather. Fisher Maritimes report identi-
of where the weaknesses were with respect to
fied the application of coatings onto steel that
satisfactory project performance, a plan was
was colder than the air as a major cause of
formulated to mitigate the damages being in-
repeated occurrences of amine blush. Other
flicted by those parties providing less-than-
sources of failures, in addition to temperature-
satisfactory project performance. The project
related ones, were insufficient curing time be-
ultimately was moved to a new primary shipyard
tween successive applications, and too much
in order to obtain better performance by remov-
application to overcome shadowed areas. The
ing uncompleted work from a host of non-
matter was resolved by a negotiated settlement
performing parties.
reflecting the shipyards almost-complete with-
#4 A Supplier: A shipyard encoun- drawal of its claim.
====================================================================
owner-provided equipment and services that are be more meaningful to the projects.
incorporated into modern yachts. Such greater
Copies of the Proceedings of the Modern
owner participation and expectations result in a
Yacht Conference, including Dr. Fisher's paper
greater array of risks that the contractor ship-
accompanied by his screen presentation are
yard faces. In order to limit and contain those
available from the RINA in London
newer forms of risks, a modernized form of
(www.rina.org.uk).
contract appears to be appropriate in order to
====================================================================
mented, effectively eliminating a number of experiences to know to call upon Fisher Maritime
potential disputes before they ever had any for pre-contract reviews of the contract docu-
chance to surface. ments. Lesson learned: call Fisher Maritime if
you are about to develop contract documents
Maritime organizations do not have to go
for a new or conversion project.
through such costly and burdensome learning
====================================================================
31 -- Arbitration Services
Fisher Maritime's senior personnel have to pierce through extraneous issues to identify
provided arbitration services for a variety of the fundamental causes of the contract disputes.
contract disputes. These range from large pas- This is a result of our extensive consulting and
senger ship conversions to private yacht over- expert witness services as well as arbitration
hauls. Other arbitrations have included contract experience. Because we also routinely prepare
disputes between shipyards and their subcon- contracts and modify specifications to be con-
tractors pertaining to multi-ship Navy newbuild- sistent with the agreements, our personnel can
ings as well as to single-ship commercial identify each party's full set of contractual re-
conversions. One arbitrated dispute involved a sponsibilities.
reinforced concrete vessel.
Organizations needing arbitration serv-
Fisher Maritime personnel are skilled ar- ices for shipbuilding or ship repair contract
bitrators, having undergone training by the disputes can contact Dr. Kenneth Fisher at
American Arbitration Association. We are able Fisher Maritime Consulting Group.
====================================================================
33 -- An Ounce of Prevention
Just as a hurricane begins as small dis- get-go. It is in the interest of both the owner
turbances in the atmosphere, a shipyard claim and the shipyard to avoid claims. Such claims
may start forming without the owner being typically result from a lapse in effective contract
aware of it. Although curtailing the formation of management by either or both parties. Fisher
a hurricane isn't possible yet, curtailing a full Maritime routinely provides, to both owners and
blown shipyard claim can be. Since hurricanes shipyards, management consulting efforts to
are not controllable, avoidance of its disastrous monitor the conditions which might breed a
effects can only be achieved through early claim, and to recommend actions which can lead
forecasting and positive action to brace for the to the avoidance of one. If you are concerned
storm. Sometimes shipyard claims may also about the possibility of a claim developing and
seem inevitable. In fact, however, with appro- appreciate the benefits of avoiding it, call Fisher
priate management techniques, they are avoid- Maritime to begin claim-avoidance procedures.
able. The principles of claim avoidance are This is what Fisher Maritime does best -- its
mainly the same as when dealing with a hurri- primary mission is to develop and help manage
cane -- early detection of the conditions which ship conversion, repair and newbuilding con-
breed them, and positive action right from the tracts to avoid claims.
====================================================================
Project Fisher Maritime consultants are grounded in commercial fleet construction and repair,
Management: as well as naval repair and overhaul. Fisher Maritime provides on-deck project man-
agement services for shipyard construction and conversion projects.
Recent project: Multiple disputes between owner and shipyard about costs and
schedule for conversion and re-flagging of a research vessel led to a breakdown in the
project work. Fisher Maritime was installed by owner between its project staff and the
shipyard to get the project moving ahead and completed, all within a renegotiated
budget.
Dispute It takes many forms, from project-phase analysis through litigation. In every situation,
Resolution: we provide accurate assessments and incontrovertible analyses.
Recent case: A platform support vessel lost all power while transferring drilling fluid to
a moored drilling rig, causing multi-million dollar damage and downtime for repairs.
Fisher Maritime analyzed the cause of loss of power to be the absence of certain
design features on the PSV, resulting in a settlement in favor of our client.
Litigation We support our clients with construction and repair disputes in state, federal, civil
Support: and criminal courts, in every stage of litigation. We can also help you avoid litigation.
Recent case: The alleged improper use of intellectual property rights by a vessel
owner was challenged by a shipyard that had engaged in discussions with the owner,
but was not awarded the contract. Fisher Maritime analyzed multiple design features
to 'test' whether the constructed vessel had used the intellectual property of the first
shipyard.
For 32 years, Fisher Maritime Consulting Group has project managers, we bring strength and clarity of
been resolving technical, cost, and schedule issues insight to our clients. Our overriding goal? A well
in shipbuilding and repair contract disputes. Our cli- developed suite of contract documents,
ents come from every sector of the industry: ship- structured management controls for complex
yards, ship owners, third party vendors, government projects, rapid resolution of developing con-
agencies and private concerns. Because were ex- flicts and disputes, and projects completed
perienced naval architects, marine engineers and with minimal growth.
Call Dr. Kenneth Fisher, Capt. Richard DiNapoli or Mr. Bert Bowers: +1 973 660 1116