Vous êtes sur la page 1sur 127

Chapter 6

Earthfill Dams
A. INTRODUCTION

6.1. Origin and Development.-Earthfill dams Earthfill dams have now (1987) been constructed
have been used since the early days of civilization to heights approaching 1,000 feet above their foun-
to store water for irrigation. This is attested both dations, and hundreds of large rolled earthfill dams
by history and by the remnants of ancient struc- have been constructed in the past 40 years with a
tures. Some of the structures built in antiquity were very good success record. Failures of small earthfill
very large. An earthfill dam completed in Ceylon dams, however, occur more often. Though some of
in 504 B.C. [l] was 11 miles long, 70 feet high, and these failures are probably the result of improper
contained about 17,000,OOOyd3 of embankment. To- design, many are caused by careless construction.
day, as in the past, the earthfill dam continues to Proper construction methods include adequate
be the most common type of dam, principally be- foundation preparation and the proper placement
cause its construction involves using materials in of materials in the dam embankment-with the
their natural state with little processing. necessary degree of compaction and under estab-
Until modern times, all earthfill dams were de- lished testing and control procedures.
signed by empirical methods, and engineering lit- The design of an earthfill dam must be realistic.
erature is filled with accounts of failures [2]. These It should reflect the actual foundation conditions
failures brought on the realization that empirical at the site and the materials available for embank-
methods must be replaced by rational engineering ment construction. It should not be patterned after
procedures for both the design and construction of a successful design used at a site with different con-
earthfill dams. One of the first to suggest that the ditions or materials, or even at a site with similar
slopes for earthfill dams be selected on that basis conditions. It should be designed for its specific site
was Bassell in 1907 [3]. However, little progress was geology.
made on the development of rational design pro- 6.2. Scope of Discussion.-This discussion is
cedures until the 1930s. The rapid advancement of limited to design procedures for earthfill dams of
the science of soil mechanics since that time has the rolled-fill type of construction, as defined in
resulted in the development of greatly improved section 6.3. This type of construction is now being
procedures for the design of earthfill dams. These used almost exclusively for the construction of
procedures include (1) thorough preconstruction in- earthfill dams. Semihydraulic or hydraulic fills are
vestigations of foundation conditions and of con- seldom, if ever, used.
struction materials, (2) application of engineering The information presented in this chapter is gen-
skill and technique to design, (3) carefully planned erally applicable to the design of any earthfill dam.
and controlled methods of construction, and (4) However, there are some empirical procedures pre-
carefully planned and designed instrumentation sented that are strictly for the design of small dams,
and monitoring systems. Threaded throughout the in straightforward geologic settings using trouble-
plan, design, construct, operate, and maintain free embankment materials. A small dam is one
process is the philosophy that the design is not whose maximum height above the lowest point in
complete until the dam is accomplishing its purpose the original streambed does not exceed about 50 feet
and has proved itself safe through several cycles of and whose volume is not so great that significant
operation. economical advantage would be obtained by using
the more precise design methods usually reserved
Numbers in brackets refer to entries in the bibliography (sec. 6.28). for large dams. A low dam cannot be considered

187
188 DESIGN OF SMALL DAMS

Figure6-1.-Upstreamfaceof damandfishscreened
inletstructure.CranePrairieDam
on the Deschutes
Riverin Oregon.
small if its volume exceedssay, 1 million yd3.Figures imum section is shown in figure 6-79.
6-1 and 4-1 show typical small dams constructed by The design procedures presented in this text are
the Bureau (Bureau of Reclamation). Crane Prairie not sufficiently detailed to permit their sole use for
Dam, which was completed in 1940, has a height of the design of dams where complicated conditions
31 feet and contains 29,700yd3of fill. Crescent Lake such as exceedingly soft, exceedingly pervious,
Dam, which was completed in 1956, has a height of highly fractured, or collapsible soil foundations are
22 feet and contains 16,800yd3of fill. The maximum involved. The design procedures are also inappro-
sections of these dams are shown on figures 6-64 priate where the nature of the only soil available
and 6-65, respectively. for construction of the embankment is unusual. In
Figures 6-2 and 6-3 show dams constructed by this category are dispersive soils, soils with high
the Bureau that are at the upper limit of height for plasticity, with low maximum unit weight, and with
the use of the empirical procedures presented in this very high natural water content that cannot be re-
chapter. In fact, Fruitgrowers Dam (fig. 6-2) is duced by drainage. These conditions require that
slightly above the height limit. It has a maximum an engineer specializing in earthfill dam design di-
height of 55 feet and a volume of 135,500yd3, but rect the investigations, determine the laboratory
is included herein as a matter of interest. Irrigation testing program, interpret the laboratory test re-
at this site dates back to 1898. The dam shown on suits, and supervise the preparation of the design
figure 6-2 was constructed in 1939, downstream and specifications.
from the original structure, which was breached in 6.3. Selection of Type of Earthfill Dam.-
June 1937 to forestall failure. Fruitgrowers Dam (a) General.-The selection of the type of dam
was modified in 1986,to replace a damaged spillway (earthfill, rockfill, concrete gravity, or a combina-
and to increase flood bypass capacity and earth- tion of these) is discussed in chapter 4. When the
quake resistance. A maximum section of Fruitgrow- procedure leads to the selection of an earthfill dam,
ers Dam is shown on figure 6-68. Many dams, small another decision must be made; that is, the type of
and large, are being modified to bring their capa- earthfill dam.
bilities up to modern-day requirements, especially The scope of this text includes only the rolled-
in the area of flood capacity and earthquake re- fill type of earthfill dam. For this type, the major
sistance. Shadow Mountain Dam (fig. 6-3) is a 50- portion of the embankment is constructed in suc-
foot-high structure containing 168,000 ydi of em- cessive, mechanically compacted layers. The ma-
bankment, which was completed in 1946. Its max- terial from borrow pits and that suitable from
EARTHFILL DAMS 189

Figure 6-2.-Fruitgrowers Dam, an earthfill storage dam at an offstream location in


Colorado.

required excavations for the dam and other struc- rigid materials such as concrete, have a potential
tures is delivered to the embankment, usually by for cracking caused by differential movements in-
trucks or scrapers. It is then spread by motor grad- duced by embankment consolidation, fluctuating
ers or bulldozers and sprinkled, if necessary,to form reservoir levels, and non-uniform foundation set-
lifts of limited thickness having the proper moisture tlement. The construction of an internal earth dia-
content. These lifts are then thoroughly compacted phragm with the necessaryfilters requires a higher
and bonded with the preceding layer by means of degreeof precision and closer control than that nor-
power rollers of the proper design and weight. mally used for small dams. Internal diaphragms
Rolled-fill dams consist of three types: diaphragm, made of rigid material such as concrete also have
homogeneous,and zoned. the disadvantage of not being readily available for
(b) Diaphragm 1Ype.-For this type of section, inspection or emergency repair if they are ruptured
most of the embankment is constructed of pervious by settlement of the dam or its foundation.
(permeable) material (sand, gravel, or rock), and a An earth blanket on the upstream slope of an
thin diaphragm of impermeable material is pro- otherwise pervious dam is not recommended be-
vided to form the water barrier. The position of this cause of the expense and the difficulty of con-
impervious diaphragm may vary from a blanket on structing suitable filters. Furthermore, becausethe
the upstream face to a central vertical core. The earth blanket must be protected from erosion by
diaphragm may consist of earth, portland cement wave action, it must be buried and therefore, is not
concrete, bituminous concrete, or other material. readily available for inspection or repair. If the sup-
An earth blanket or core is considered a diaphragm ply of impermeable soil is so limited that a zoned
if its horizontal thickness at any elevation is less embankment dam cannot be constructed, a dia-
than 10 feet or its thickness at any elevation is less phragm of manufactured material placed on the up-
than the height of the embankment above that el- stream slope of an otherwise pervious embankment
evation. If the impervious earth zone equals or ex- is recommended for small dams. The design of suit-
ceedsthese thicknesses, the design is considered a able impervious pavings is discussed in chapter 7.
zoned embankment type. Design and construction If most of the material in a diaphragm-type dam
of diaphragm-type dams must be approached with is rock, the dam is classified as a rockfill dam. The
care. design of rockfill dams is discussed in chapter 7.
Although successful dams have been constructed (c) Homogeneous1Ype.-A purely homogeneous
with internal (or buried) diaphragms, this type of dam is composed of only one kind of material (ex-
construction is not recommended for structures clusive of the slope protection). The material used
within the scope of this text. All internal dia- in such a dam must be sufficiently impervious to
phragms, including those constructed of earth or provide an adequate water barrier, and the slopes
190 DESIGN OF SMALL DAMS

Figure 6-3.-Shadaw Mountain Dam, an earthfill structure on the Colorado River in Colorado. Constructed as part of
a large transmountain diversion scheme. SM-175-CBT.

must be relatively flat for stability. To avoid slough- 6-5(A, or, if suitably graded materials are avail-
ing, the upstream slope must be relatively flat if able, a horizontal drainage blanket (fig. 6-5(B) ) may
rapid drawdown of the reservoir after long-term be used. The drainage and filter layers must be de-
storage is anticipated. The downstream slope must signed to meet filter requirements with surrounding
also be relatively flat to provide a slope stable fill or foundation materials (see sec. 6.10(i. Re-
enough to resist sloughing when saturated to a high cently, to avoid construction defects such as loose
level. For a completely homogeneous section, it is lifts, poor bond between lifts, inadvertent pervious
inevitable that seepagewill emerge on the down- layers, desiccation, and dispersive soils, inclined fil-
stream slope regardless of its flatness and the im- ter drains in combination with a horizontal drain-
permeability of the soil if the reservoir level is age blanket have become almost standard. Figure
maintained for long enough. The downstream slope 6-5(C) illustrates the control of seepagewith an
eventually will be affected by seepageto a height inclined chimney drain and horizontal drainage
of roughly one-third the depth of the reservoir pool blanket. Another method of providing drainage has
[4], as shown on figure 6-4. been the installation of pipe drains. These are rec-
Although formerly very common in the design of ommended for small dams only when used in COh-
small dams, the completely homogeneous section junction with a horizontal drainage blanket or
has been replaced by a modified homogeneoussec- pervious zones.Reliance should not be placed solely
tion in which small amounts of carefully placed per- upon pipe drains becausethe pipes can clog as the
vious materials control the action of seepageso as result of improper filters, root growth, or
to permit much steeper slopes. The effect of drain- deterioration.
age at the downstream toe of the embankment is Because drainage modifications to a homogene-
shown on figures 6-5(A) and 6-5(B). ous section provide a greatly improved design, the
Large rock toes may be provided for drainage (fig. fully homogeneoussection should seldom be used.
EARTHFILL DAMS 191

Reservoir water surface


/
Upper limit of seepage

Impervious foundation

Figure 6-4.-Seepage through a completely homogeneous dam. 288-D-2479.

Reservoir water surface


epage

I toe

1. _..__-- Impervious foundation-

(A) WITH ROCKFILL TOE

Upper limit of seepage

Horizontal
drainage blanket

L lmpervious foundation-

(B) WITH HORIZONTAL DRAINAGE BLANKET

Upper limit of seepage

-,-/ Inclined blanket


or chimney drain

Blanket drain

n Impervious foundation/ /

(C) WITH CHIMNEY DRAIN

Figure 6-5.-Seepage through modified homogeneous dams. 103-D- 1827.


192 DESIGN OF SMALL DAMS

Filtering and drainage should normally be provided. In any case, filter criteria given in section 6.10(i)
A homogeneous (or modified homogeneous) dam is must be met between the impervious zone and the
recommended in localities where readily available downstream shell and between the shell and the
soils show little variation in permeability, and soils foundation. For most effective control of through
of contrasting permeabilities are available only in seepage and drawdown seepage, the permeability
minor amounts or at considerably greater cost. should progressively increase from the center of the
A homogeneous section should never be used if dam out toward each slope.
the available materials are dispersive, erodible such The pervious zones may consist of sand, gravel,
as silts and line sands, or subject to moderate to cobbles, rock, or mixtures of these materials. For
severe desiccation. Soils should always be tested for purposes of this text, the dam is considered to be
these characteristics. Where these characteristics a zoned embankment if the horizontal width of the
exist, the advice of an experienced earthfill dam impervious zone at any elevation equals or exceeds
designer is recommended. the height of embankment above that elevation in
(d) Zoned Embankment Qpe.-The most com- the dam and is at least 10 feet. The maximum width
mon type of a rolled earthfill dam section is that of the impervious zone will be controlled by stability
in which a central impervious core is flanked by and seepage criteria and by the availability of ma-
zones of materials considerably more pervious, terial. A dam with an impervious core of moderate
called shells. These pervious zones or shells enclose, width composed of strong material and with per-
support, and protect the impervious core; the up- vious outer shells may have relatively steep outer
stream pervious zone affords stability against rapid slopes, limited only by the strength of the foun-
drawdown; and the downstream pervious zone acts dation, the stability of the embankment itself, and
as a drain to control seepage and lower the phreatic maintenance considerations. Conditions that tend
surface. In many cases, a filter between the im- to increase stability may be decisive in the choice
pervious zone and downstream shell and a drainage of a section even if a longer haul is necessary to
layer beneath the downstream shell are neces- obtain required embankment materials.
sary. These filter-drainage layers must meet filter If a variety of soils are readily available, the type
criteria with adjacent fill and foundation materials. of earthfill dam chosen should always be the zoned
They are sometimes multilayered for capacity embankment because its inherent advantages will
requirements. lead to more economical construction.

B. DESIGN PRINCIPLES

6.4. Design Data. -The data required for the not result in excessive maintenance costs. Main-
design of an earthfill dam are discussed in the var- tenance costs vary with the provisions of upstream
ious chapters of this manual, and the investigation and downstream slope protection, drainage fea-
of foundations and sources of construction mate- tures, and the type of appurtenant structures and
rials are described in chapter 5. The required detail mechanical equipment. To achieve minimum cost,
and the accuracy of the data are governed by the the dam must be designed for maximum use of the
nature of the project and the immediate purpose of most economical materials available, including ma-
the design; that is, whether the design is for a cost terials excavated for its foundations and for appur-
estimate to determine project feasibility, whether tenant structures.
the design is for construction, or whether some An earthfill dam must be safe and stable during
other purpose is to be served. The extent of inves- all phases of the construction and the operation of
tigations of foundations and sources of construction the reservoir. To accomplish this, the following cri-
material are also governed by the complexity of the teria must be met:
situation. (a) The embankment, foundation, abutments,
6.5. Design Criteria.-The basic principle of and reservoir rim must be stable and must
design is to produce a satisfactory, functional struc- not develop unacceptable deformations un-
ture at a minimum total cost. Consideration must der all loading conditions brought about by
be given to maintenance requirements so that sav- construction of the embankment, reservoir
ings achieved in the initial cost of construction do operation, and earthquake.
EARTHFILL DAMS 193

(b) Seepage flow through the embankment, (f) Camber should be sufficient to allow for set-
foundation, abutments, and reservoir rim tlement of the foundation and embankment,
must be controlled to prevent excessive but not included as part of the freeboard.
uplift pressures; piping; instability; slough- (g) The upstream slope must be protected
ing; removal of material by solutioning; or against wave erosion, and the crest and
erosion of material into cracks, joints, or downstream slope must be protected against
cavities. The amount of water lost through wind and rain erosion.
seepage must be controlled so that it does An earthfill dam designed to meet the above cri-
not interfere with planned project functions. teria will prove permanently safe, provided proper
(c) The reservoir rim must be stable under all construction methods and control are achieved. The
operating conditions to prevent the trigger- design procedure to meet the requirements of cri..
ing of a landslide into the reservoir that could terion (d) above is discussed in chapters 9 and 10.
cause a large wave to overtop the dam. Methods for satisfying other criteria for earthfill
(d) The embankment must be safe against ov- dams, subject to the limitations in scope described
ertopping or encroachment of freeboard dur- in section 6.2, will be discussed in this chapter. The
ing occurrence of the IDF (inflow design applicability of the procedures to a specific case
flood) by the provision of sufficient spillway depends upon the purpose of the design, the size
and outlet works capacity. and importance of the structure, and the complexity
(e) Freeboard must be sufficient to prevent of the problems.
overtopping by waves.

C. FOUNDATION DESIGN

6.6. General.-The term foundation as used various directions or the strength of the foundation
herein includes both the valley floor and the abut- can be determined by expensive, detailed field and
ments. The essential requirements of a foundation laboratory testing. Ordinarily, extensive explora-
for an earthfill dam are that it provide stable sup- tion of this nature and complex theoretical designs
port for the embankment under all conditions of are not required for small dams. For these struc-
saturation and loading, and that it provide suffi- tures, it is usually more economical to design foun-
cient resistance to seepage to prevent excessive loss dations empirically, deliberately striving for
of water. substantial safety factors. The savings in construc-
Although the foundation is not actually designed, tion costs that can be achieved by more precise de-
certain provisions for treatment are made in designs sign ordinarily do not warrant the cost of the
to ensure that the essential requirements are met. additional exploration, testing, and engineering in-
No two foundations are exactly alike; each foun- volved. There are foundations, however, where con-
dation presents its own separate and distinct prob- ditions are so unusual that empirical methods
lems requiring corresponding special treatment and cannot be relied upon to produce a design with an
preparation. Various methods of stabilization of adequate safety factor. Such conditions require the
weak foundations, reduction of seepage in pervious services of an engineer specializing in the field of
foundations, and types and locations of devices for earthfill dam design and aie beyond the scope of
the interception of underseepage must depend upon this text.
and be adapted to local conditions. The importance Because different treatments are appropriate for
of adequate foundation treatment is emphasized by different conditions, foundations are grouped into
the fact that approximately 40 percent of all earth- three main classes according to their predominant
fill dam accidents and 12 percent of all failures are characteristics:
attributed to foundation failures. 1. Foundations of rock
Theoretical solutions based on principles of soil 2. Foundations of coarse-grained material (sand
mechanics can be made for problems involving per- and gravel)
vious or weak foundations. Most of these solutions 3. Foundations of fine-grained material (silt and
are relatively complex and they may be relied upon clay)
only to the degree that the actual permeabilities in Foundations, which originate from various
194 DESIGN OF SMALL DAMS

sources, such as river alluvium, glacial outwash, 4.7. Rock Foundations .-Rock foundations are
talus, and other processesof erosion, disintegration, generally considered to be the more competent type
and deposition, are characterized by infinite vari- of foundation and usually do not present any prob-
ations in the combinations, structural arrangement, lem for small dams. Even foundations of weaker
and physical characteristics of their constituent rock are generally preferred over soil foundations.
materials. The deposits may be roughly stratified, The selection of a rock foundation is undoubtedly
containing layers of clay, silt, fine sand and gravel, justified where the rock mass is generally homo-
or they may consist of lenticular massesof the same geneous and competent throughout zones of the
material without any regularity of occurrence and foundation that will be affected by the dam and
of varying extent and thickness. Nevertheless, the reservoir. However, damsites with good rock foun-
character of a foundation, as revealed by explora- dations are becoming increasingly rare. Designers
tion, can usually be safely generalized for the design are being forced to use foundations that are far from
of small dams to fit into one of the classes given ideal because of the growth and shifting of popu-
above, and once the class is determined the nature lation centers that cause increased emphasis on
of the problem requiring treatment will be evident. water conservation for domestic, agricultural, and
Ordinarily, coarse-grained, pervious foundations industrial use in new locations. Rock foundations
present no difficulties in the matter of settlement should be carefully investigated to ensure that they
or stability for a small dam; conversely, fine- are adequately competent. If there is any doubt, an
grained, weak foundations subject to settlement or experienced earth dam designer should be
displacement usually present no seepageproblems. consulted.
The special treatments required for the different Foundation rock surfaces against which fill is to
types of foundations listed above are discussed in be placed must be properly treated to ensure that
this chapter. If the foundation material is imper- fractures, fault zones, steep faces, rough areas,
vious and comparable with the compacted em weathered zones, etc., do not lead to seepage and
bankment material in structural charactertistics, piping in the interface zone between foundation and
little foundation treatment is required. The mini- fill. Treatment of deficient foundation zones is es-
mum treatment for any foundation is stripping the pecially critical for the areas beneath the imper-
foundation area to remove sod, topsoil with high vious core and the filter and drainage zones
content of organic matter, and other unsuitable ma- immediately downstream of the impervious zone.
terial that can be disposed of by open excavation. More explicit foundation surface treatment require-
In many cases where the overburden is compara- ments are presented in chapter 3 of USBR Design
tively shallow, the entire foundation is stripped to Standard No. 13.
bedrock. In all soil foundations in which a cutoff 6.8. Methods of Treating Rock Foundations.-
trench or partial cutoff trench (see sec. 6.10) is not Rock foundations should be carefully investigated
used, a key trench should be provided. The top sev- to determine their permeability. If erosive leakage,
eral feet of the soil foundation invariably lack the excessive uplift pressure, or high water losses can
density of the underlying soil because of frost ac- occur through joints, fissures, crevices, permeable
tion, surface runoff, wind, or other cause. This layer strata, or along fault planes, consideration should
should be penetrated by the key trench to allow be given to grouting the foundation. Whether or
inspection and to ensure cutoff by the impervious not a foundation should be grouted should be de-
zone of the embankment through this questionable termined by examining the site geology and by ana-
zone. A bottom width of 20 feet for the key trench lyzing the water losses through foundation
is usually sufficient. exploration holes. A great deal of experience is re-
The foundation at any particular site usually quired to make this decision because every foun-
consists of a combination of the three main types dation is unique. Moreover, there may be more
of foundations listed above. For example, the effective or economical methods of controlling see-
stream portion often is a sand-gravel foundation, page or leakage than grouting. The advice of an
while the abutments are rock that is exposed on the experienced designer should be sought when ques-
steep slopes and mantled by deep deposits of clay tionable conditions exist.
or silt on the gentle slopes. Therefore, the design Ordinarily, the design and estimate for a storage
of any dam may involve a variety of foundation dam should provide for foundation grouting. On the
design problems. other hand, grouting of rock foundations is not gen-
EARTHFILL DAMS 195

erally required for small detention dams or for ex- then results are speculative because it is impossible
tremely low diversion and storage dams. to thoroughly grout all fractures or pores in the
Foundation grouting is a process of injecting un- foundation. A grout curtain should not be relied on
der pressure a fluid sealing material into the un- as the single provision to reduce seepage and related
derlying formations through specially drilled holes uplift pressures so that downstream seepage control
to seal off or fill joints, fractures, fissures, bedding features are reduced or eliminated. The grout cur-
planes, cavities, or other openings. Unless the geo- tain used on the abutment of Granby Dam in Col-
logic conditions dictate otherwise, the foundation orado is shown on figure 6-6.
should be grouted to a depth below the surface of In cases where large zones of fractured rock lie
the rock equal to the reservoir head above the sur- at the foundation contact or where the zone of bro-
face of the rock. ken rock within a fault has great width, it may be
The grouting of a dam foundation is usually per- possible to grout the zone by grouting to a shallow
formed along a single line of grout holes spaced 10 depth, usually 10 to 30 feet, by using a grid pattern.
to 20 feet on center. This creates some tightening This type of grouting is referred to as blanket
deep in the foundation and some reduction in grouting. It reduces leakage in the fractured zone
permeability. However, multiple lines of grout holes and provides a more firm foundation for the dam.
are necessary when severely fractured or highly In most cases, the foundation directly beneath the
permeable rock is encountered. Only multiple-line impervious zone requires some blanket grouting.
curtains improve the degree of reliability, but even Foundation grouting is generally performed with

LEGEND

E3 Pegmatlte

Figure 6-6.-Grout curtain used on the abutment of Granby Dam, Colorado. 101-D-245.
196 DESIGN OF SMALL DAMS

a mixture of cement and water, starting with a ratio Then grouting is performed at the required pres-
of 51. If considerable take in a hole is experi- sure. The grout pipe and packer are withdrawn to
enced, the grout mixture is progressively thickened. the next stage and the grouting is repeated. This
Grout mixes usually vary between 1O:l and O.&l. If upward staging continues until the entire hole is
the grout take is excessive, sand is added to give grouted.
the gout additional bulk. In some cases, bentonite Grout holes are usually drilled with the com-
is combined with the sand in small quantities, about mercial standard EX (approximately 1%inch di-
2 percent by weight of the cement, to obtain a more ameter) drill size, and a grout nipple is used to
pumpable grout mix and some expansion of the introduce the grout into the foundation. The grout
grout. A suggested gradation of sand that is used nipple is usually a 2-inch-diameter pipe from 18
for grouting on Bureau projects is given in the tab- inches to 5 feet long (depending on rock conditions)
ulation below. that is anchored into the rock by cement grout,
oakum, or other suitable calking material to facil-
itate drilling and grouting. The different drilling
Sieve size, Cumulative percent,
methods include air and water percussion and air
No. by weight retained on screen
and water rotary (plug or core bit). The primary
8 0 concern when choosing a grout-hole drilling method
16 0 to 5 is plugging fractures with cuttings. The drilling
30 15 to 40 method should be chosen on the basis of the geo-
50 50 to 80 logic conditions determined from data obtained
100 70 to 90 during the design explorations.
200 95 to 100 Packers are devices that seal off drill holes at
any elevation to permit grouting of a selected stage
Where the grout hole continues to take a large below the packer. The four types of packers most
quantity of grout, it may be advantageous to require commonly used are shown on figure 6-7 and 6-8.
intermittent pumping, waiting up to 24 hours be- The leather-cup packer (fig. 6-7(A)) seals when the
tween pumping periods to allow grout in the foun- grout forces the cups outward against the drill-hole
dation to set. wall; it is most commonly used in hard rock. The
Grouting is usually performed by one of the fol- mechanical packer (fig. 6-7(B)) requires a double-
lowing methods: (1) staging-down, or (2) staging- pipe arrangement; it is seated against the drill-hole
up. wall by compressing the annular rubber sleeve at
Grouting by the staging-down method consists the bottom of the packer pipe by tightening the nut
of drilling the grout hole to a predetermined depth, at the top of the pipe; this type of packer is more
washing the hole, pressure testing it with water, and suitable than the leather-cup packer in slightly
then grouting. After grouting but before the grout oversized holes. The pneumatic packer (fig. 6-8(C) )
in the hole has set, the grout is washed out of the is expanded by compressed air or inert gas; it is
hole and drilling for the second stage is begun. In used in poor rock where the drill holes may be con-
the second and succeeding stages, the same se- siderably oversized. The cone-type packer (fig. 6-
quence of operations is used, except that a packer B(D)) is seated when grout forces the annular rub-
is sealed near the bottom of the previously grouted ber sleeve upward on the cone; it is used in relatively
stage. In this manner, subsequent stages are grouted hard rock. Photographs of the four types of packers
until the entire length of the hole has been grouted. are shown on figure 6-9.
This method is useful when drill-hole caving occurs, A great variety of grouting equipment is avail-
when the upper layers of the foundation are exten- able. In general, the equipment consists of a grout
sively cracked, or when the hole suddenly loses drill mixer, grout agitator, grout pump, and a pipe and/
water. or hose system for circulating the grout. lhe cir-
When grouting by the staging-up method, the culating line and manifold system allows grouting
entire length of the hole is drilled, the hole washed, pressures to be controlled at the collar of the hole.
and a packer attached to the end of the grout supply Figure 6-10 illustrates the circulating-type grout
pipe, which is then lowered and seated at a pre- system and the equipment generally used for
determined distance above the bottom of the hole. grouting.
EARTHFILL DAMS 197

Adapter to connect supply hne


y Held when turnmg adjusting nul
Weld

/ Sfraghl threads Ior 8 Inches

I Std pope-For holes deeper


A than 20. use flush jotnt car,ng

lx Washer-lower
concave to hold hare
I piace

4 IO 6 plece soft I
rubber hose

IX Washer-Upper rode
CO~CBV~to hold hose
I place

Weld

(A) (B)
Figure 6-7.-Packers used for grouting by the Bureau of Reclamation: (A) Leather.
cup, (B) Mechanical. 288-D-2873.

Grout is usually pumped with a duplex piston- lQpe of rock


type pump or a helical-screw rotor-type pump; a lDegree to which rock is fractured
standby grout pump should always be required for lJointing system within the rock
the grout plant. Piston-type pumps require devices lStratification of rock
to smooth the pressure pulsations that occur at var- lDepth of zone being grouted
ious phases of the stroke. Figure 6-11 shows the lLocation of hole being grouted
grout plant used at Ruedi Dam, Colorado. lWeight of overlying material at time of
Grouting pressures are influ&ced by the follow- grouting
ing factors: The maximum grouting pressure should be such
DESIGN OF SMALL DAMS

left hand threads

1/4x 3/E Screw countersunk

(D)

Figure 6-8.-Packers used for grouting by the Bureau of Reclamation: (C) Pneu-
matic, (D) Cone-type. 288-D-2874.

that rock fracture or uplift will not occur. Excessive Unless other criteria are established, l-lb/in2 per
pressures may weaken the rock strata by fracture, foot of depth measured from the surface of the foun-
or may rupture a portion of the grout curtain al- dation to the center of the zone being grouted may
ready constructed, and result in increased perme- be used as the initial grouting pressure. Variations
ability. Maximum pressures are difficult to may be determined by observing the grout take.
determine because each foundation has a unique Current Bureau of Reclamation requirements for
rock joint pattern and stratification, which is usu- termination of grouting are presented in section
ally found by trial at the actual time of foundation G.60.
grouting or by performing grouting tests before Grout should usually be introduced into the
foundation treatment. foundation through grout nipples set directly in the
EARTHFILL DAMS 199

(A) P805-236-1594

(8) P557-420-3459

Figure 6-9.- Types of grout hole packers used by the Bureou of Reclamation.(A)
From left to right: leather-cup and cone-type, (B) From top to bottom: me-
chanical and pneumatic.

rock. Bedrock found to be badly jointed or broken of cracking in the grout cap creating high seepage
below its surface may require a concrete group cap gradients. If a grout cap is used, it generally is a
to facilitate grouting. However, use of a permanent concrete-filled trench excavatedfrom 3 to 8 feet into
grout cap can usually be avoided by leaving the the bedrock, depending on the extent of broken
foundation high and grouting through temporary rock; the trench is usually at least 3 feet wide to
grouted or concreted nipples or concrete caps. The facilitate construction. The advantages and disad-
use of grout caps under earth dams should be vantages of grout caps are shown in the following
avoided becauseof the difficulty in sealing between tabulations:
them and the foundation rock and the possibility

~
200 DESIGN OF SMALL DAMS

Grout cap specific data with which the final grouting program
Advantages Disadvantages may be carefully planned. Test grouting programs
Good anchorage for Increased costs associated can eliminate expensive delays caused by large
nipples with excavation and grout overruns and should expedite the completion
Forms near-surface seep- concrete of the job.
age barrier of zone 1 con- Creates potential for high Specifications for the performance of foundation
tact (critical where filters, gradient at contact with
slush grouting, dental con- grouting and for the excavation of the grout cap are
zone 1
crete, and blanket grout- included in sections G.56 through G.60. If an ex-
Creates the need for spe-
ing are absent) cial compaction, particu- tensive grouting program is contemplated, an en-
May allow use of shorter larly where rock gineer experienced in this type of work should be
nipples for near-surface deteriorates near the cap consulted. For additional information see [5, 6, 7,
grouting Excavation for the cap 8, 91.
Provides good work plat- may disturb (damage) At one time, concrete cutoff walls were con-
form for drilling and foundation structed to intercept seepage along the contact of
grouting Interferes with final foun- the embankment with the rock foundation. But
Erovides control for heave dation cleanup these walls are expensive and prone to cracking, and
monitoring and inspection
their usefulness is questionable. They are not rec-
No grout cap ommended for the earthfill dams discussed herein.
Advantages - - Disadvantages
However, in unusual cases where the bedrock is very
Less excavation and con- Longer nipples may be re-
crete, therefore, less cost quired for anchorage smooth, a cutoff wall may be warranted.
Encourages the use of In some cases,nipples may In some very pervious rock foundations or those
multiple-row grout require concrete anchor- containing soluble zones or layers, such as lime-
curtains age (removed during foun- stone or gypsum, it may be appropriate to provide
Potential for high seepage dation cleanup) cutoffs through pervious zones to control seepage.
gradient is not created No concrete seepage cut- Cutoffs are also sometimes advisable through upper
Less special compaction off is provided along the zones of weathered or broken foundation rock.
zone 1 contact Shallow cutoffs are usually provided by earthfilled
Easier foundation cleanup
Working platform for cutoffs with sloping sides. Where deep cutoffs are
Does not result in foun- drilling and grouting is not
dation damage provided required, thin foundation cutoffs such as a concrete
In soft or friable rock, diaphragm wall may be more economical. USBR
foundation is left high, Embankment Dams Design Standards No. 13,
and only one final foun- chapter 16, discusses foundation cutoff walls.
dation cleanup is required All loose and overhanging rock must be removed
Grout pipes (nipples) are normally embedded at from the abutments; rock slopes should not be
lo-foot centers in the foundation rock or grout cap, steeper than 0.5:1 (horizontal to vertical) and pref-
if used, during the concrete placement. Excavation erably flatter. Where flattening the rock slopes or
for any grout cap must be carefully performed so overhangs is not practicable, the slopes may be
that rock adjacent to the trench is not shattered. shaped by the useof dental concrete.
Figure 6-12 shows the construction of a typical If the bedrock is a shale that slakes in air, it may
grout cap at Navajo Dam, New Mexico. be necessary to excavate several feet into bedrock
When grouting foundations in which the surface to remove the surface disintegration just before
rock is broken or jointed, grout often rises to the placement of the embankment; in more durable
surface through these cracks and prevents complete rock types, little excavation into the bedrock (other
grouting. The cracks or seams through which grout than for a grout cap) is usually necessary. Fractured
rises to the surface should be caulked to prevent rock should be treated by slush grouting (see sec.
excessive leakage. Caulking can be done with G.61). USBR Design Standards No. 13, chapter 3,
wooden wedges, cement grout, or burlap. The grout discusses foundation surface treatment in detail. A
pumped into the foundation may also be allowed to sample specification for construction on a shale
set within the cracks. foundation subject to slaking is included in appen-
If it is highly probable that the foundation will dix G.
require extensive grouting, a preliminary test pro- In most instances, bedrock is mantled by over-
gram may be desirable. Such test programs furnish burden of various types and thicknesses. The foun-
EARTHFILL DAMS 201

Figure 6-10.-Circulating grouting system. 288-D-2866.

Figure 6-11.-Grouting plant used at Ruedi Dam, Colorado. P382-706-1134NA.


202 DESIGN OF SMALL DAMS

vious geologic formations. The pervious materials


may range from fine sand to openwork gravels, but
more often they consist of stratified heterogeneous
mixtures. Generally, sand and gravel foundations
have sufficient strength to adequately support loads
induced by the embankment and reservoir, but this
must be verified by adequate exploration, testing,
and analyses. Knowledge of the geologic deposition
processcan help determine the potential occurrence
of low strength zones.
'I\vo basic problems are found in pervious foun-
dations; one pertains to the amount of undersee-
page, and the other is concerned with the forces
exerted by the seepage. The type and extent of
treatment justified to decreasethe amount of see-
page should be determined by the purpose of the
dam, the streamflow yield in relation to the res-
ervoir conservation capacity, and the necessity for
making constant reservoir releases to serve senior
water rights or to maintain a live stream for fish
or for other conservation purposes. Loss of water
through underseepagemay be of economic concern
for a storage dam but of little consequence for a
detention dam. Economic studies of the value of
the water and the cost of limiting the amount of
Figure6-12.-Placing concretegrout cap at Navajo Dam, underseepageare required in some instances to de-
New Mexico. The 2-inch-diametergrout nipples are
fixed at 10-foot intervals. 711-422-250. termine the extent of treatment. However, adequate
measuresmust be taken to ensure the safety of the
dation design then dependson the nature and depth dam against failure caused by piping, regardless of
of the overburden as described in succeeding sec- the economic value of the seepage.
tion. The above discussion is applicable not only to A special problem may exist in foundations con-
exposed rock foundations, but also to bedrock sisting of low density sands and gravels. The loose
reached by trenching through the overburden. structure of saturated sands and gravels is subject
Filters and drains are the most important fea- to collapse under the action of a dynamic load. Al-
tures for collecting and controlling seepagethrough though the loose sand may support sizable static
rock foundations. Even though a rock foundation loads through point-to-point contact of the sand
may be grouted and cutoffs provided, appropriate grains, a vibration or shock may cause the grains
filters and drainage are still necessary to collect to try to readjust into a more dense structure. Ee-
seepageand reduce uplift pressures in the area cause drainage cannot take place instantaneously,
downstream of the impervious zone. This is a nec- part of the static load formerly carried by the sand
essary design measure that precludes unforeseen grains is then transferred temporarily to the water,
events such as foundation fracturing caused by and the effective strength of the foundation may be
earthquakes or construction deficiencies that may greatly reduced, possibly leading to failure. USER
occur in grout curtains and cutoffs. Drainage blan- Design Standards No.13, chapter 13, covers seismic
kets, toe drains, toe trenches, and relief wells should design and analyses.
be used individually or in combination as necessary Foundations consisting of cohesionless sand of
to control seepage.USER Design Standards No.13, low density are suspect, and special investigations
chapters 5 and 8, cover the design of these features. should be made to determine required remedial
6.9. Sand and Gravel Faundations.- treatment. If the relative density of the foundation
(a) General.-Often the foundations for dams is less than 50 percent, the approximate magnitude
consist of recent alluvial deposits composed of rel- of the relative density of a cohesionless sand foun-
atively p~rvious sands and gravels overlying imper- dation can be determined from the results of stan -
EARTHFILL DAMS 203

dard penetration tests described in section 5.32(b). The pump-out tests are relatively expensive, but
The number of blows per foot is related to the rel- in results are more dependable than other methods.
ative density, but is affected by the depth of the The rate-of-travel methods is costly and difficult to
test and, to some extent, by the location of the water interpret. The pump-in tests are economical for
table. The following tabulation gives average stan- small dams because they can be accomplished in
dard penetration resistance values for 50 percent conjunction with the usual exploratory drilling;
relative density irrespective of the water table, however, the results can be considered as only ap-
based on research by the Bureau [lo]. proximations. Another advantage to the pump-in
tests in drill holes (see ch. 5) is that the permeability
Effective overburden pressure
of various layers is more easily tested.
Overburden Number of Upon determination of the coefficient of perme-
pressure, blows per
lb/in2 ability of the foundation, a rough approximation of
foot
the amount of underseepage may be made by use
0 4
12 of Darcys formula:
2 17
Q = kiA (1)
Based on submerged unit weight.
where:
Special studies in triaxial shear on undisturbed
samples may be required for foundations of cohe- Q = discharge volume per unit of time,
sionless sand indicated to be below 50 percent rel- tz = coefficient of permeability for the foun-
ative density. Such studies are beyond the scope of dation; i.e., discharge through a unit
this text, and the advice of specialists in dam design area at unit hydraulic gradient,
should be obtained. i = hydraulic gradient = h/L = difference in
(b) Amount of Underseepage.-To estimate the head divided by length of path, and
volume of underseepage that may be expected, it is A = gross area of foundation through which
necessary to determine the coefficient of permea- flow takes place.
bility of the pervious foundation. This coefficient The underseepage for the example shown on fig-
is a function of the size and gradation of the coarse ure 6-13 is as follows:
particles, of the amount of tines, and of the density k = 25,000 ft/yr = 0.00079 ft/s
of the mixture. Three general field test methods are h = El. 210 - El. 175 = 35 feet
used to determine the coefficient of permeability of L = 165 feet
foundations: (1) pump-out tests, in which water is i = h/L = 351165 = 0.212
pumped from a well at a constant rate and the draw-
down of the water table observed in wells placed on Depth of foundation, d = El. 170 - El.100 = 70 feet.
radial lines at various distances from the pumped For a width of 1 foot, A = (70)(l) = 70 ft2. Q per
well; (2) tests conducted by observation of the ve- foot of width = (0.00079)(0.212)70 = 0.012 ft3/s.
locity of flow as measured by the rate of travel of For foundation width of 100 feet, Q = 1.2 ft3/s;
a dye or electrolyte from the point of injection to for foundation width of 1,000 feet, Q = 12 ft/s.
an observation well; and (3) pump-in tests, in which
water is pumped into a drill hole or test pit and the The accuracy of the amount of underseepage as
rate of seepage observed under a given head. Var- determined by Darcys formula, equation (l), de-
ious laboratory test methods are also used to de- pends on the homogeneity of the foundation and
termine the coefficient of permeability, such as the accuracy with which the coefficient of perme-
permeability and settlement tests, one-dimensional ability is determined. The results should be con-
consolidation test, and falling head and constant sidered as an indication only of the order of
head permeability tests. Most of these tests meth- magnitude of seepage in the evaluation of water loss
ods are covered in the Bureaus Earth Munual[ll] from a project-use viewpoint.
and Ground Water Manual[lB]. Seepage analyses If the foundation is stratified (as is usually the
and control are covered in chapters 5 and 8 of case), the vertical permeability will be much less
USBR Embankment Dam Design Standards than the horizontal permeability, and permeable
No. 13. layers at depth will not be fully effective in trans-
204 DESIGN OF SMALL DAMS

Pervious zone

L-Sand-gravel foundation
Average k = 25,000 ft / yr pY

El. 100
v f--
f,- ,- R1-%f,?-\ y+q

Impervious foundationf
K---

Figure 6-13.-Example computation of seepage by Darcys formula. 288-D-2481.

mitting underseepage. The quantity of seepage as flow line until a pipe is formed to the reservoir,
determined by equation (1) will be liberal if an av- allowing rapid escape of reservoir storage and sub-
erage coefficient of permeability of the various lay- sequent failure of the dam. Experience has shown
ers, obtained by weighting each coefficient by the that this action can occur rapidly or can be slow
thickness of the layer, is used in the computations. and cumulative with final failure occuring months
(c) Seepage Forces.-The flow of water through or even years later. If a more impervious layer at
a pervious foundation produces seepage forces as a the surface overlies a pervious foundation, sudden
result of the friction between the percolating water upheaval of the foundation at the downstream toe
and the walls of the pores of the soil through which of the dam can occur. Some engineers [13] refer to
it flows. This friction is similar to that developed the former type as piping failure, and the latter type
by water flowing through a pipe. Figure 6-14 shows [ 141 as a blowout. This does not mean that initial
the flow path of an infinitesimal element of water piping will always result in failure. If the foundation
through the pervious foundation of a dam. The soil is nonuniform, fine material may be carried
water percolating downward at the upstream toe of away, leaving the coarse material structural matrix
the dam adds the initial seepage force, F,,to the intact and resulting in a stable but more pervious
submerged weight, of the soil, W,, to produce the foundation. It is always difficult to determine
resultant body force, R,. As the water continues on whether piping will result in failure or will produce
the seepage path, it continues to exert seepage an eventual stabilization; therefore, it is advisable
forces in the direction of flow, which are propor- to design the structure so that piping will not occur.
tional to the friction loss per unit of distance. When The magnitude of the seepage forces throughout
the cross-sectional area through which flow takes the foundation and at the downstream toe of the
place is restricted, as under a dam, the velocity of dam, where piping usually begins, depends on the
the seepage for a given flow is increased. This in- pressure gradient driving the seepage water. Rela-
crease in velocity is accompanied by an increase in tively impervious foundations are not usually sus-
friction loss, and the seepage force is correspond- ceptible to piping because impervious soil offers a
ingly increased. This increase in seepage force is greater resistance to seepage forces and, conse-
represented on figure 6-14 by larger vectors for F, quently, to displacement. This is due to particle
and F3 than for Fl and F4. As the water percolates cohesion and the low velocity of flow as water exits
upward at the downstream toe of the dam, the see- at the toe. Pervious foundations, on the other hand,
page force tends to lift the soil, reducing the effec- permit higher flow velocity and are usually cohes-
tive weight to R,. If F4 exceeds W,, the resultant inless, offering less resistance to seepage forces. In
would be acting upward and the soil could be carried such instances, the design must include measures
our or piped out. to prevent seepage forces from heaving [13] or re-
If the foundation materials are similar through- moving soil from the downstream toe of the dam.
out, the erosion could progress backwards along the Another type of piping failure is due to internal
EARTHFILL DAMS 205

erosion from springs that start near the down- method has some serious limitations. It takes con-
stream toe and proceed upstream along the base of siderable experience to construct an accurate flow
the dam, the walls of a conduit, a bedding plane in net, especially where foundations are stratified and
the foundation, an especially pervious stratum, or where drains or partial cutoffs are installed. The
other weakness that permits a concentration of coefficients of permeability for each stratum and
seepage to reach the area downstream from the dam lens (and in different directions) are required. Ex-
without high friction losses. This type of failure is perience has shown that the grain size and grada-
termed by some engineers [13] as failure by sub- tion of the foundation material have an important
surface erosion. bearing on piping failures and that piping failures
The phenomenon known as blowout [l4] is a often occur after the dam has been in service for
type of failure usually associated with a confining some time. Therefore, it appears that many failures
layer at the downstream surface that results in caused by piping are of the subsurface erosion type
uplift seepage forces that rupture the confining as a result of seepage following minor geological
layer. This initial eruption may lead to complete weakness. This type of failure cannot be analyzed
failure if the resulting increase in velocity is large by flow nets or other theoretical methods.
enough to erode the remaining foundation by The foundation designs given in the remainder
piping. of this chapter are based upon the same theoretical
The magnitude and distribution of the seepage principles used in the design of major structures;
forces in a foundation can be obtained from a flow however, the procedures have been simplified so
net, which is a graphical representation of the paths they may be applied to small dams by those who
of percolation and lines of equal potential (lines are not specialists in the field of earthfill dam de-
drawn through points of equal total head) in sub- sign. Nevertheless, some experience in this field is
surface flow. It consists of flow lines and equipo- recommended. These procedures are for relatively
tential lines superimposed on a cross section of the straightforward geologic conditions. If the geology
foundation. Although the two families of curves is not straightforward, an experienced earthfill dam
may in simple cases be derived mathematically, the designer should be consulted.
graphical solution is more commonly used. The 6.10. Methods of Treating Sand and Gravel
method of applying the flow net to the solution of Foundations.-(a) General.-Various methods of
problems involving subsurface flow is presented in seepage and percolation control can be used, de-
many publications [15, 16, 17, 181. pending on the requirements for preventing unec-
Analysis of seepage pressures and of the safety onomical loss of water and the nature of the
of the foundation against piping by the flow net foundation in regard to stability from seepage

&.--Reservoir woter surfc

T. /
_--Pervious foundotlon- ._
/

Figure 6-14.-Seepage force components. 288-D-2482.


206 DESIGN OF SMALL DAMS

forces. Cutoff trenches, sheet piling, mixed-in-place extending to bedrock or other impervious stratum.
concrete pile curtains, slurry trenches, grouting of This is the most positive means of controlling the
alluvium, or combinations of these methods have amount of seepage and ensuring that no difficulty
been used to reduce the flow and to control seepage will be encountered by piping through the foun-
forces. Blankets of impervious material, extending dation or by uplift pressures at the downstream toe.
upstream from the toe of the dam and possibly cov- Figure 6-15 shows the cutoff trench excavation
ering all or part of the abutments, are frequently and backfill at Great Cut Dike, part of McPhee
used for the same purpose. Horizontal drainage Reservoir in southeast Colorado. Dental concrete
blankets may be incorporated in the downstream and a filter zone were used to prevent piping of zone
toe of a dam or used to blanket the area immediately 1 into fractured rock. These features can be seen
downstream from the toe of the dam through which in the photograph. Figure 6-16 shows placement of
percolating water may escape under an appreciable compacted fill in the cutoff trench at Sugar Loaf
head. The purpose of these blankets is to permit Dam in Colorado; construction of the outlet works
free flow and dissipation of pressure without dis- gate chamber is shown in the middle background.
ruption of the foundation structure and loss of fine To provide a sufficient thickness of impermeable
soil particles. Pressure-relief wells are used to re- material and an adequate contact with the rock or
lieve pressure in pervious layers or zones deeper in other impervious foundation stratum, the bottom
the foundation before the pressures are transmitted width of the cutoff trench should increase with an
to the downstream toe area. increase in reservoir head. However, the cutoff
The details of these various devices together with trench bottom width may be decreased as the depth
an appraisal of effectiveness are contained in this of the trench increases because the seepage force at
section. The application of the various devices to the foundation contact will decrease (caused by loss
the design of pervious foundations is included in of head as the water travels vertically through the
section 6.11. foundation) as the depth increases. An adequate
(b) Cutoff Den&es.-These may be classified width for the cutoff trench of a small dam may be
into two general types: sloping-side cutoff trenches determined by the formula:
and vertical-side cutoff trenches. Sloping-side w=h-d (2)
cutoff trenches are excavated by shovels, draglines,
where:
or scrapers and are backfilled with impervious ma- w = bottom of width of cutoff trench,
terials that are compacted in the same manner as h = reservoir head above ground surface, and
the impervious zone of the embankment. Vertical- d = depth of cutoff trench excavation below
side cutoff trenches may be excavated in open cut
ground surface.
by hand, by trenching machine, or by stopping
where it is necessary to remove and replace breccia A minimum bottom width of 20 feet should be
or debris in fault zones. Ordinarily, vertical-side provided so that excavating and compacting equip-
trenches are not economical because of the cost of ment can operate efficiently in trenches, which
the hand labor involved in placing and compacting must be unwatered by well points or sump pumps
the backfill material. if they are below the water table.
The cutoff trench should be located at or up- (c) Partial Cutoff 7renches.-Darcys formula
stream from the centerline of the crest of the dam, for seepage, equation (l), indicates that the amount
but not beyond a point where the cover of imper- of seepage is directly proportional to the cross-
vious embankment above the trench cannot provide sectional area of the foundation. It might be con-
resistance to percolation at least equal to that of- cluded from this that the amount of seepage could
fered by the trench itself. The centerline of the be reduced 50 percent by extending the impervious
cutoff trench should be parallel to the centerline of zone on figure 6-13 into the ground so that the depth
the dam across the canyon bottom or valley floor, of the pervious foundation is reduced from 70 to 35
but it should converge toward the centerline of the feet; however, this is not the case. The action of a
dam as it is carried up the abutments to maintain partial cutoff is similar to that of an obstruction in
the required embankment cover. a pipe-the flow is reduced because of the loss of
Whenever economically possible, seepage through head caused by the obstruction, but the reduction
a pervious foundation should be cut off by a trench in flow is not directly proportional to the reduction
EARTHFILL DAMS 207

Figure 6-15.-Cutoff trench excavotion and backfill. Great Cut Dike, Dolores Project, Colorado. CN71-438-10903NA.

in the area of the pipe. Experiments by Thrnbull layers are continuous. Pervious foundations also
and by Creager on homogeneousisotropic pervious may consist of an impervious foundation stratum
foundations have demonstrated that a cutoff ex- of considerable thickness sandwiched between up-
tending 50 percent of the distance to the impervious per and lower pervious layers. A partial cutoff ex-
stratum will reduce the seepageby only 25 percent; tending to such an impervious layer would cut off
an 80-percent cutoff penetration is required to re- only the upper pervious layer. This would be effec-
duce the seepage50 percent [19]. tive if the thicknesses of the impervious and upper
A partia~ cutoff trench may be effective in a strat- pervious layers are sufficient to resist the seepage
ified foundation by inter~epting the more pervious pressures in the lower pervious layers near the
layers in the foundation and by substantially in- downstream toe so that blowouts do not occur.
creasing the vertical path the seepagemust take. (d) Sheet Piling Cutoffs.-Steel sheet piling is
Reliance cannot be placed upon a partial cutoff relatively expensive, and experience [6, 20, 21, 27]
trench in this situation unless extensive subsurface has shown that leakage through the interlocks be-
exploration has verified that the more impervious tween the individual sheets is considerable. Never-
lO8 DESIGN OF SMALL DAMS

Figure 6-16.-Placement of compacted fill in the cutoff trench. Sugar Loaf Dam, Colorado. Construction of the outlet works
gate chamber can be seen in the middle background. P382-706-2578.

thele.ss, sheet piling is still used occasionally in piling will be only 80 to 90 percent effective in pre-
combination with a partial cutoff trench to increase venting seepage.With poor workmanship, or if the
the depth of the cutoff. Under certain conditions it piles cannot be seated in an impervious stratum,
is also used in lieu of a cutoff trench. The sheet they will not be more than 50 percent effective and
piling should be steel becauseof its high strength. may be much less.
Sheet piling cutoffs are practically limited to use in (e) Cement-Bound and Jet-Grouted Curtain
foundations of silt, sand, and fine gravel. Where Cutoffs.- The niixed-inplace cement-bound curtain
cobbles or boulders are present, or where the ma- is another means of establishing a cutoff in pervious
terial is highly resistant to penetration, driving or foundations. It has been used in the construction
jetting becomesdifficult and costly, and it is highly of Slaterville Diversion Dam near Ogden, Utah; Pu-
doubtful that an effective cutoff can be obtained tah Diversion Dam near Sacramento, California;
becauseof the tendency of the piling to wander and and Lower Thro Medicine Dam in Montana.
becomedamagedby breaks in the interlocks or tear- The curtain is constructed by successivelyover-
ing of the steel. A heavy structural section with lapping individual piles. Each mixed-in-place pile
strong interlocks should be used if the foundation consists of a column of soil intimately mixed with
contains gravel. mortar to form a pile like structure within the soil.
It is not practicable to drive sheet piling so that Such a pile is constructed by injecting mortar
it is watertight. Under the best conditions, includ- through a vertical rotating hollow shaft, the lower
ing the use of compound to seal the interlocks and end of which is equipped with a mixing head for
good contact of the bottom of the piling with an combining the soil with the mortar as the latter is
impervious foundation, it can be expected that the injected. The mortar is introduced into soil that has
EARTHFILL DAMS 209

been loosened by the mixing head as the bit is si- use of a 15-inch mixing head at 14-inch centers pro-
multaneously rotated and advanced into, or with- duced piles averaging 18 inches in diameter with a
drawn from, the soil. The piles may be reinforced minimum cross-sectional thickness of 15 inches.
as required. Photographs showing the mixing op- The maximum depth was listed as 58 feet.
eration for a single pile and a finished cutoff wall The mixed-in-place process is designed for use
are shown on figure 6-17(A) and (B). in granular soils, including silt, sand, and gravel.
Patents on the methods and some of the mate- But it is not recommendedfor predomin~ntly clayey
rials used in construction of the mixed-in-place pile materials and is not capable of handling cobbles and
are held by Intrusion-Prepakt, Inc., Cleveland, boulders. Sample specifications are given in appen-
Ohio. dix G.
The manufacturer's literature [22] states that Recently, a very similar process called jet grout-
ing has been developed. Jet grouting depends on
very high pressure jets (3,000 to 10,000 lb/in2)
rather than a mixing head to mix the soil and grout.
There are also other versions of these processes,
and along with development of better machinery,
more effective cutoffs can be constructed to greater
depths.
(f) Slurry 1rench Cutoffs.-An effective method
of constructing positive cutoffs when wet conditions
or deep cutoffs in alluvial valleys make conven-
tional construction methods uneconomical is the
slurry trench method.
The technique was adapted from well drilling
methods used by the oil industry. Bentonite clay
suspensions are used to support holes cut in soft
soils. The slurry trench method uses a water-
bentonite slurry to seal and support the trench wall
(A) Mixing operation. (Intrusion-Prepakt Co.l. during the excavation process.The sequenceof con-
288-D-2875. struction operations for a slurry trench is shown on
figure 6-18. Vertical-sided trenches, usually from 3
to 10 feet wide, are excavatedwith either draglines,
clamshells, backhoes,or trenching machines. Figure
6-19 shows excavation of a slurry trench using a
dragline at the Corps of Engineers' West Point
Dam. As material is excavated,the bentonite slurry
is pumped into the trench; care is taken to keep the
slurry elevation constant and above the water table
to avoid caving. Upon introduction to the trench,
the slurry weighs more than water. Because the
slurry tends to flow out of the trench, a relatively
thin, impermeable filter cake develops. Hydrostatic
pressure on this impermeable filter cake reduces
caving and sloughing and provides overall stability.
In the caseof a soil-bentonite backfilled cutoff wall,
the excavatedmaterial is stockpiled near the trench,
and excessslurry is allowed to drain back into the
trench. Backfill material that satisfies the gradation
requirements of the design is placed back into the
(8) Finished wall. (Intrustian-Prepakt Co.). 288-D-2876.
trench, with the filter cake to form an essentially
Figure 6-17.-Cement-bound curtain cutoff. . impermeable barrier.
210 DESIGN OF SMALL DAMs

opof Frm Rock

BEGINNING OF EXCAVATION
(A)

5, --&/#ooof Firm Rock

CLEANING TRENCH BOTTOM WITH AIRLIFT


(81

BEGINNING OF BACKFILLING
(Cl
Figure 6-19.-Excavation of a slurry trench. (U.S. Army
Corps of Engineers). 288-D-2894.

when agitated [23, 241. The density and the hydro-


static pressure the slurry exerts increase as a result
of the suspension of clay, silt, and sand particles
during the excavation process.
PROGRESSIVE EXCAVATION AND BACKFILLING Bentonite used for slurry trench construction is
(D) required to meet the standards described in section
3, API Standard 13A, Specifications for Oil-Well
Figure 6-le.-Sequence of operations for the construc- Drilling Fluid Materials, Eighth Edition, March
tion of a slurry trench. (U.S. Army Corps of Engineers).
288-D-2783.
1981 (supplemented May 1982).
Bentonite-water slurries for trench excavations
The slurry is usually made by mixing bentonite, are designed to perform several functions: (1) pre-
a clay having a high content of the mineral mont- vent seepage into the foundation by the formation
morillonite, and water. Generally, naturally pure of a filter cake, (2) suspend clay, silt, and fine-to-
premium-grade Wyoming-type sodium cation base medium-sized sand particles during excavation, and
montmorillonite is specified because of its small (3) provide hydrostatic pressure to the face of the
particle size and high swelling characteristics. After excavation. These functions are accomplished by
the slurry is mixed with water and allowed to hy- the design and either the direct or indirect control
drate, it forms a dispersed suspension that is denser of one or more of the slurry properties. Those prop-
and more viscous than water. The slurry is thixo- erties, which include bentonite concentration, den-
tropic, which means that left undisturbed, the sus- sity, viscosity, shear strength, filtration loss, sand
pension develops shear or gel strength, but fluidizes content, and pH, are measured according to pro-
EARTHFILL DAMS 211

cedures outlined by the American Pipe Institutes and connecting it to the core by an impervious blan-
API Code 13B, Standard Procedures for Testing ket, even though reservoir dewatering is required to
Drilling Fluids, Ninth Edition (May 1982). gain access to the slurry trench.
Slurry densities generally range from 65 to (2) l?unsitions.-Transitions are necessary be-
90 lb/ft3. Freshly mixed and fully hydrated slurry tween the slurry backfill and the impervious core
entering the trench usually has a density between material to compensate for the effect of differential
63 to 68 lbs/ft3. As clay, silt, and sand are suspended settlement between the backfill material and the
in the slurry during excavation, the density in- foundation. The transition is accomplished by sim-
creases. Densities ranging from 70 to 80 lb/ft3 are ply making the trench wider at the top than at the
generally sufficient to maintain stability for most bottom, usually by sloping the walls of the trench.
construction applications. Densities greater than 90 This allows settlement of the core with the slurry
lb/ft can prevent the backfill from fully displacing backfill, reducing the tendency of the core and
the slurry when it is placed in the trench and should slurry wall to separate. It also provides a greater
be desanded. width for the core to adjust to settlement, reducing
The viscosity of the slurry can vary considerably the tendency of cracking within the core.
as a result of changes in bentonite concentrations, (3) BaclzfiU.-Slurry trench backfill is selected
in the sand content, and in the concentration and to reduce or stop foundation seepage. ?LcTotypes of
type of additive. The slurry viscosity limits the pen- backfill commonly used are soil-bentonite and ce-
etration of slurry into the in situ soil structure be- ment-bentonite.
fore formation of the filter cake, but is not so great Soil-bentonite backfill is designed to provide the
as to reduce the pumpability of the slurry. The vis- desired reduction in permeability and resist the
cosity also helps control the rate at which sus- movement of backfill fines caused by the hydraulic
pended particles exceeding the gel strength settle gradients that develop across the trench. The back-
during the excavation. The gel or shear strength of fill is often made by mixing the material excavated
the slurry controls the size of the silt and sand par- from the trench with clay, silt, sand, and/or gravel,
ticles that can be maintained in suspension without as necessary to meet design requirements. A well-
settling. graded material with approximately 15 to 20 per-
The filtration loss is an indicator of the quality cent clay and silt sized particles is an excellent
of filter cake a slurry can develop. A filter cake that backfill because of its low permeability. The backfill
is continually destroyed by excavating equipment is is thoroughly mixed with slurry taken from the
required to form quickly and compactly, preventing trench until a mixture with a consistency similar
excessive seepage and filtration losses. to that of concrete with a 3- to 6-inch slump is
The slurry pH is monitored for changes that may obtained.
destabilize its gel strength and its ability to form The backfill is placed at the bottom of the trench
an adequate filter cake. Changes in the pH, outside by clamshell bucket to prevent it from segregating.
a range of 7 to 12, can cause reduction in viscosity Backfill is placed until it develops a slope of about
and gel strength. 1O:l that extends from the trench bottom to the
(1) Location and Dimensions.-The location and surface of the trench, as shown on figure 6-18(C).
dimensions of a slurry trench should satisfy the spe- Additional backfill is bulldozed in and the trench
cific requirements of the site. The cutoff may be is filled as shown on figure 6-18(D).
placed at any location beneath the dam upstream Cement-bentonite backfill is made by mixing ce-
of the centerline of the impervious core, but the ment with bentonite slurry. After mixing, the ce-
optimum location depends upon the type and lo- ment-bentonite backfill is pumped to the trench
cation of the core, the depth of impervious stratum where it provides stability during the excavation
along the foundation, variations in foundation ma- and hardens into an impermeable cutoff wall. While
terial, construction sequence, diversion require- curing, the backfill gains strength yet remains elas-
ments, and reservoir operation. Therefore, different tic enough to deform without cracking.
consideration are required at each site. Before placing soil-bentonite or cement-benton-
Central trench locations have the disadvantage ite backfill in the trench, the depth of the trench
of inaccessibility if future modification or rehabil- should be measured and samples taken to ensure
itation is required. For this reason, some designers that the bottom of the trench is keyed into the
favor placing the slurry trench upstream of the dam proper foundation material. The trench bottom is
212 DESIGN OF SMALL DAMS

cleaned by an airlift system to remove any wall Among these materials have been cement, asphalt,
slough or sand settling from the slurry, which is clay, and various chemicals.
shown on figures 6-18(B) and 6-20. Cement grouting cannot be successful in very
The use of a slurry trench should be reviewed fine granular materials because of the compara-
carefully when cobbles, boulders, or large blocks of tively large particle size of the cement, which limits
rock exist in the lower portions of the trench. In the penetration. However, coarse alluvial material
stratified foundations, extreme care must be taken has been successfully grouted in a number of cases
to ensure that the bottom of the trench contacts using cement or cement-clay grouts. Asphalt grout-
the impervious layer on which the backfill material ing is also limited by the particle size. The value of
will rest. Cases have been reported of one of the clay grouting is doubtful because the clay is easily
harder stratifications being mistaken for the trench carried away by seepage forces. Chemical grouts
bottom, which was only detected later by coring. have about the same viscosity as water and can be
This care necessitates a great delay of additional injected into pervious soils. However, chemical
construction time and expense,but can be avoided grouts are too expensive for general use in grouting
by frequent sounding operations on the trench bot- pervious overburden foundations.
tom and prior foundation investigation. For addi- Despite the disadvantages enumerated above,
tional information concerning slurry trenches, the grouting procedures that improve the impermea-
reader is referred to the references at the end of the bility of pervious overburden materials have been
chapter. USBR Design Standards No.13, chapter developed. Using these procedures, several dams
16, should also be referred to for construction of have been built at sites that would have been con-
slurry walls. sidered impossible or uneconomical using other
Table 6-1, adapted from Jones (23], presents a methods. Commonly, a cutoff curtain in overburden
general description of the materials through which consists of several rows of grout holes, in which the
slurry trenches have been constructed, the trench outer rows of holes are grouted with cement, clay,
widths used, and the hydraulic head for existing or and cement-clay grouts, and one or more of the in-
proposed structures. ner rows are grouted with a chemical grout.
(g) Grouting.-Various materials have been used Overburden grouting is a costly process, the in-
in attempts to develop grouting procedures that im- jection techniques are complex, and the selection of
prove the stability and impermeability of pervious the grout and appropriate techniques requires con-
overburden foundation. These materials have been siderable field exploration and laboratory and field
injected to act as a binder and to fill the voids. testing. Furthermore, the results of the injection
process are difficult to evaluate. For these reasons,
overburden grouting is not considered an appro-
priate treatment for the foundations of small dams
within the scope of this text. For information on
this subject, the reader is referred to [25].
(h) Upstream Blankets.- The path of percola-
tion in pervious foundations can be increased by
the construction of a blanket of impervious material
connecting with the impervious zone of the dam and
extending upstream from the toe. Blankets are com-
monly used when cutoffs to bedrock or to an im-
pervious layer are not practicable because of
excessive depth; they are also used in conjunction
with partial cutoff trenches. The topography just
upstream from the dam and the availability of im-
pervious materials are important factors in deciding
on the use of blankets. The blanket is generally used
for a stream channel or valley floor of sand and
Figure 6-20.-Airlifting sond from bottom of slurry trench gravel, but may also be required for portions of the
(U.S. Army Corps of Engineers). 288-D-2895. abutments.
EARTHFILL DAMS 213

Table 6-L-Comparison of slurry trench cutoffs*.

Maximum
Project Foundation material Trench width head Remarks

Kennewick Levee, Sandy or silty gravels with 6 ft 15ft Constructed in 1952;


McNary Dam Project, zonesof open gravel; k = 0.4 Central core maximum depth = 22 ft
ColumbiaRiver, Wash- cm/s (0.41X106ft/yr)
ington State
Owner: Corps of
Engineers
Wanapum Dam, Sandy gravels and gravelly 10 ft 88.5 ft Preconstruction test
Columbia River, sands underlain by open- Central core trench, pump-out and lab-
Washington State, work gravels; Irz(open grav- oratory piping tests;
Owner: Public Utility els)=2.5cm/s (2.6X106ft/yr), grouting beneath trench;
District No. 2 of Grant averagek = 1 cm/s (1.03~10~ construction in 1959-62;
County WYd maximum depth of cutoff
= 19oft
Mangla Closure Dam, Sandy gravel with cobbles 10 ft 230 ft Constructed in 1964;
Mangla Dam Project, and boulders; gap graded in Central core Construe- maximum depth = 22 ft
Jhelum River, West range of fine gravel and tion
Pakistan coarse sand; k = 0.4 cm/s condition
Owner: West Pakistan (0.41X106ft/yr) only
Water and Power De-
velopment Authority
Duncan Lake Dam, Surface zone of sands and 10 ft 102ft Constructed in 1965-66;
Duncan River, British gravels over zone of silt to Upstream Short maximum depth = 60 ft
Columbia, Canada fine silty sand with some berm term
Owner: British Colum- silty clay; k (surface zone) =
bia Hydro and Power 1 cm/s (1.03X106ft/yr)
Authority
West Point Dam, Chat- Upper stratum of alluvial 5 ft 61 ft Constructed in 1966;maxi-
tahoochee River, soil, alternating layers of Upstream mum depth = 60 ft, grout-
States of Georgia and clay, silt, sand, and gravel blanket ing in sound rock below
Alabama varies from lz=1.8X10-2 to the trench; maximum
Owner: Corps of 3.5~10.~ cm/s (18,600 to 36 depth of cutoff= 100ft
Engineers ft/yr); lower stratum of re-
sidual soil brown silty sand;
k = O.6X1O-5 cm/s (6 ft/yr)
Saylorville Dam, Des Surface zone of impervious 8 ft 93 ft Dam under construc-
Moines River, Iowa alluvial sandy clay; pervious Upstream Short tion; construction of cut-
Owner: Corps of zone, medium to fine sand berm term off scheduled for 196g2;
Engineers and gravelly coarse to fine maximum depth=approx.
sand; average k (gravelly 60 ft
sand) = 0.15 cm/s
(0.16X106ft/yr)
214 DESIGN OF SMALL DAMS

Table 6-L-Comparison of slurry trench cutoffs.-Continued

Maximum
Project Foundation material Trench width head Remarks

Prokopondo Project Uniform tine to coarse sand 5ft 40 ft Constructed in 1959;


(Quarry A Cofferdam), with some gravel; maximum depth = 15ft
Suriname River, Suri- D,,= 0.1 mm
name, S.A.
Owner: Suriname Alu-
minum Co.
Wells Dam, Columbia Pervious gravels 8ft 7oft Constructed in 1964;
River, Washington Central core maximum depth >80 ft
State
Owner: Public Utility
District No. 1 of Doug-
las County
Yards Creek Lower Res- Sands, gravels, cobbles, and 8ft 55 ft Constructed in 1964;
ervoir, New Jersey boulders Central core maximum depth = 40 ft
Owner: Public Service
Electric and Gas Co.,
Jersey Central Power
and Light, New Jersey
Power and Light Co.
CamancheDam-Dike 2, Alluvial deposit with upper 8 ft 135 ft Constructed in 1966;
Mokelumne River, stratum of clayeysilts, silts maximum depth = 95 ft;
California and clayeysands,and a lower maximum head on dam
Owner: East Bay Mu- stratum of poorly graded = 45 ft; head on trench
nicipal Utility District medium to fine sand over a depends on ground-
thin zone of well-graded water level downstream
gravel; average112= 7.5X10e3
cm/s (7,760 ft/yr)
Calamus Dam-Pick- Dune sands and underlying 5 ft 73 ft Constructed in 1982-84;
Sloan Missouri Basin interbedded alluvial Where fully maximum depth = 115ft,
Program, Nebraska sands and gravels; maxi- penetrating; fully penetrating for
Owner: Bureau of mum lz = 0.14 cm/s 3 ft 4,000-ft length,
Reclamation (0.14X106 ft/yr) Where partially partially; penetrating (50
penetrating; ft) for 3,000-ft length
Upstream
blanket
Adapted from table 1 of (231.
2Construction postponed until 1972.
EARTHFILL DAMS 215

Figures 6-21 and 6-22 show an abutment blanket inversely proportional to the length of the path (for
that was constructed during the rehabilitation of homogeneous isotropic foundations). Therefore, the
Ochoco Dam by the Bureau of Reclamation in 1949. blanket should be extended so that the seepage loss
The purpose of this blanket was to reduce the see- is reduced to the amount that can be tolerated from
page through the landslide debris, which forms the a project-use standpoint.
right abutment. It was successful because it reduced An upstream blanket should not be relied upon
the seepage at full reservoir level from 28 to to reduce the seepage forces in the foundation
12 ft3/s. enough to preclude piping failures. Although, the-
The blanket is continuous from the impervious oretically, an upstream blanket would accomplish
zone of the dam, and it extends about 400 feet up- this purpose in a homogeneous foundation, the nat-
stream. The abutment was dressed smooth to re- ural stratification that occurs in almost every al-
ceive the blanket, which extends from the reservoir luvial foundation allows high pressures to exist in
floor to an elevation 53 feet above. The blanket was one or more foundation strata at the downstream
constructed 5 feet thick, normal to the approximate toe of the dam. Horizontal drainage blankets or
3:l abutment slope. It is protected from erosion by pressure-relief devices (drains or wells) should al-
2 feet of riprap on 12 inches of bedding. Figure 6- ways be provided for a dam on a pervious foundation
21 shows the earthfill blanket complete and the be- when a complete cutoff trench cannot be secured.
ginning of riprap placement. Figure 6-22 shows a (i) Downstream Embankment Zones for Pervious
general view of the upstream face of the dam and Foundations.-The downstream sections of dams
the right abutment blanket completed. on pervious foundations must be constructed to per-
Natural impervious blankets sometimes help re- form the following functions:
duce seepage and related pressures. Areas of the l Relieve the uplift pressure from seepage
foundation that are covered by a natural impervious l Readily permit discharge of seepage water from
blanket should be stripped of vegetation, defective the foundation
places should be repaired, and the entire surface of l Prevent piping of the fines from the embank-
the natural blanket should be rolled to seal root ment and from the foundation
holes and other openings. Stripping a natural blan- l Provide sufficient weight to prevent uplift
ket upstream from the dam to secure impervious l Adequately convey the total amount of seepage
soil for the construction of the dam should be to the downstream channel
avoided when possible. The normal procedure is to These functions are accomplished by providing:
avoid excavating a natural impervious blanket l Extended downstream zones to lengthen seep-
within 200 to 400 feet upstream of the toe of the age paths
dam. The natural blanket is an added benefit, but l Zones so thick that their weight will prevent
should not be relied on for seepage control. uplift
Although blankets may be designed by theoret- l Pervious downstream shells or horizontal
ical means [26], a simplified approach may be used drainage blankets that meet filter require-
for small dams. A suitable blanket thickness for ments to allow water to percolate from the
small dams is 10 percent of the depth of the res- foundation, but that prevent piping
ervoir above the blanket but not less than 3 feet. l Toe drains with sufficient capacity to convey
This calculation is for blankets made from mate- the accumulated seepage water back to the
rials suitable for the construction of the impervious stream channel
zone of an earthfill dam and compacted accordingly. Downstream zones incorporating either pervious
A blanket must meet filter criteria with the foun- shells, horizontal and inclined drainage blankets,
dation material on which it is placed. If it does not, toe drains, or combinations thereof should be used
then a proper filter must be provided between the in the design of earthfill dams on relatively ho-
blanket and its foundation. See section 6.10(i) for mogeneous pervious foundations without posit.ive
filter criteria. cutoff trenches. They may also be used on relatively
The length of the blanket should be governed by homogeneous pervious foundations that are over-
the desired reduction in the amount of underseep- lain by thin impervious layers: The pervious shell
age. From an examination of equation (1) and figure will supply weight to stabilize the foundation and
6-13, it is apparent that the amount of seepage is will also effectively relieve pressures that may break
216 DESIGN OF SMALL DAMS

Figure 6-21.-Right abutment blanket construction at Ochoco Dam. On a tributary of the Crooked
River in Oregon.

Figure 6-22.-Upstream slape af Ochaca Dam.

through the impervious layer. A horizontal drainage seepage(see secs. 6.10(j) and (k) ).
blanket meeting filter requirements may be re- The required length of the downstream pervious
quired to prevent piping. Pervious foundations cov- zone can be determined theoretically by means of
ered by impervious layers may also involve trenches the flow net (sec. 6.9(c) ), provided the ratio of the
backfilled with filter drain material or pressure- horizontal to the vertical permeability of the foun-
relief wells to reduce the uplift pressure and control dation is determined by the procedure known as
EARTHFILL DAMS 217

transformed sections. This method of dealing with ket similar to that shown on figure 6-23(C) and an
anisotropy in permeable foundations is discussed inclined drainage blanket, both designed to meet
by Terzaghi and Peck [27] and Cedergren [18]. The filter requirements, should be used. For homoge-
method demonstrates that the larger the ratio of neous embankments or where the material perme-
horizontal to vertical permeabilities, the farther ability of the downstream zone is questionable,
downstream the seepage emerges from the toe of horizontal drainage blankets designed to prevent
the impervious zone of the dam, and the longer the piping should be used. Furthermore, experience has
embankment required downstream. shown that seepage through an impervious zone
Because of the difficulty or limitation in using sometimes remains higher than would be predicted
flow nets to design small dams with relatively mea- by procedures such as a flow net because of poor
ger foundation exploration, design criteria are pre- bond between lifts, inadvertent loose lifts, cracking
sented in this text to determine the lengths of caused by differential settlement, desiccation
downstream pervious zones. For small dams, it is cracks, etc. Therefore, an inclined drainage blanket,
recommended that the length of the downstream as shown on figure 6-5(C), is often used and recently
pervious zone equal three times the height of the has become almost standard. These drainage blan-
dam, as shown on figure 6-23. kets must have sufficient capacity to conduct all of
Figure 6-23 shows the typical downstream zoning the seepage from the embankment and the foun-
used with exposed pervious foundations; that is, dation to the toe drains. Horizontal drainage blan-
those not overlain by impervious material. Covered kets used (and inclined drainage blankets, if used)
pervious foundations are discussed in section with homogeneous embankments convert them to
6.11(e). Each method shown consists of an extended the modified homogeneous type of dam with the
downstream section that lengthens the seepage resultant advantages described in section 6.3.
path. In (A) and (B) of figure 6-23, the requirement Figure 6-23(A) illustrates the recommended min-
for drainage is provided by the overlying pervious imum length and vertical thickness of the down-
shell. This pervious shell should be designed to pre- stream section of a zoned embankment using the
vent piping from the foundation and impervious recommended minimum impervious core (mini-
zone. However, if the shell material is such that it mum core B, fig. 6-43) for a dam constructed on a
cannot prevent piping, a horizontal drainage blan- pervious foundation without a positive cutoff

C of Dom
zt5

IO Min.+- t+
P
Pervious shell

/3( jJ
\Originol
32 Min.+4
ground surface I=

Impervious core
greater than minimum

Note: Horizontal and inclined drainage blankets I I L3Z Min.~]


meetina filter reauirements
may be-requlred
of section 6.10(i)
beneath pervious shells in.(A)
and (6) to prevent piplng from the Impervious
I (B)
zone and foundation. An Inclined drainage
blanket should also be consldered for (C) for
these same reasons

i Horlzantol drainage blanket


meeting filter requirements
(Cl
of section 6 I0 (i!

Figure 6-23.--Downstream embankment sections for pervious foundations. 288-D-2483.


218 DESIGN OF SMALL DAMS

trench. Figure 6-23(B) illustrates the recommended experimentation has been performed by the Corps
design for a zoned dam with an impervious core of Engineers [30] and the Bureau of Reclamation
larger than minimum core B. The reverse slope of [31]. Several somewhat different sets of criteria are
the impervious core (fig. 6-23(B)) is used to: given by these authorities. The following limits are
(1) Reduce the length of the downstream per- recommended to satisfy filter stability criteria and
vious shell. to provide ample increase in permeability between
(2) Facilitate construction of the downstream base and filter. These criteria are satisfactory for
pervious shell if material excavated from the use with filters of either natural sand and gravel or
cutoff trench is used. crushed rock and for filter gradations that are either
(3) Reduce the volume of embankment, as uniform or graded:
shown on figure 6-23(B).
The dashed outline on figure 6-23(B) indicates D,, of the filter
(1) 2 5, provided that the
the drainage blanket that would be required if the D,, of base material
reverse slope were not used. filter does not contain more than 5 percent
The horizontal drainage blanket shown on figure of material finer than 0.074 mm (No. 200
6-23 and an inclined drainage blanket, if used, must sieve) after compaction.
satisfy three requirements:
(1) Gradation must be such that particles of soil D,, of the filter
(2) 5 5.
from the foundation and the upstream and OS5of base material
overlying embankment are prevented from
entering the filter and clogging it. D,, of the filter
(3) 2 2.
(2) Capacity of the filter must be such that it Maximum opening of pipe drain
adequately handles the total seepage flow
(4) Generally, the filter should be uniformly
from both the foundation and the
graded to provide adequate permeability and
embankment.
prevent segregation during processing, han-
(3) Permeability must be great enough to pro-
dling, and placing.
vide easy access of seepage water to reduce
seepage uplift forces. In the foregoing, D,, is the size at which 15 per-
Requirements for gradation and permeability are cent of the total soil particles are smaller; the per-
closely related and are discussed below. centage is by weight as determined by mechanical
A minimum drainage blanket thickness of 3 feet analysis. The D,, size is that at which 85 percent
is suggested to provide unquestionable capacity for of the total soil particles are smaller. If more than
seepage flows. one filter layer is required, the same criteria are
Multilayer filters for small earthfill dams should, followed; the finer filter is considered as the base
in general, be avoided; they are more efficient but material for selection of the gradation of the coarser
add to the cost of filter construction. In cases where filter.
large seepage quantities must be handled, it has In addition to the limiting ratios established for
been demonstrated [28] that multilayer filters can adequate filter design, the 3-inch particle size
provide an economical solution. should be the largest in a filter to minimize seg-
If the overlying pervious zones in (A) and (B) of regation and the bridging of large particles during
figure 6-23 are sand-gravel similar in gradation to placement of filter materials. In designing filters for
the sand-gravel of the foundation and they meet base materials containing gravel particles (broadly
filter requirements with zone 1 and the foundation, graded materials), the base material should be ana-
there is no danger of flushing particles from the lyzed on the basis of the gradation of the fraction
impervious zone or foundation into the pervious smaller than No. 4.
shells of the embankment, and no special filters are It is important to compact filter material to the
required. Otherwise, a filter must be provided so same density required for sand-gravel zones in em-
that the finer foundation or impervious material is bankments (see appendix G). Filter materials must
not carried into the voids of larger materials. be placed carefully to avoid segregation. A uni-
The rational approach to the design of filters is formly graded filter is advantageous in preventing
generally credited to Terzaghi [29]. Considerable segregation. The construction of thin filter layers
EARTHFILL DAMS 219

requires proper planning and adequate inspection convey it to an outfall pipe that discharges either
during placement. In many cases, the concrete sand into the spillway or outlet works stilling basin or
used in the spillway, outlet works, or appurtenant into the river channel below the dam. Pipes, rather
structures may also be used as filter material. This than French drains, are used to ensure adequate
reduces costs by eliminating any special blending capacity to carry seepage flows. Toe drains are also
requirements. A more complete discussion of filter used on impervious foundations to ensure that any
criteria is given in USBR Design Standards No. 13, seepage that may come through the foundation or
chapter 5. the embankment is collected and to ensure that
The following is an example (see fig. 6-24) of a enough of the ground water is kept below the sur-
typical design that would be applicable for filters face to avoid unsightly boggy areas below the dam.
such as those shown around the toe drain on figure The toe drains pipes may be made of any material
6-25. that has adequate durability and strength. Perfo-
rated or slotted pipe should be used instead of pipe
Example laid with open joints. The drainpipes should be
Required: placed in trenches at a sufficient depth to ensure
Gradation limits of filter materials effective interception of the seepage flow. The min-
imum depth of the trench is normally about 4 feet;
Given:
the maximum depth is that required to maintain a
Gradation range of base soil shown on figure
reasonably uniform gradient although the ground
6-24 with D,,,,, = 0.03 mm and Dssrnin = 0.10
surface may undulate. The bottom width of the
mm
trench is 3 to 4 feet, depending on the size of the
Openings in drainpipe = l/4 inch
drainpipe. The minimum pipe diameter recom-
Solution: mended for small dams is 6 inches; however, di-
(1) Lower limit of D,, of filter = 5 X 0.03 = ameters up to 18 inches may be required for long
0.15 mm reaches at flat gradients. Manholes should be pro-
(2) Upper limit of D,, of filter = 5 X 0.10 = vided at a spacing that allows adequate access for
0.50 mm inspection and maintenance. The pipe should be
To meet criteria (l), (2), and (4), sand shown as located such that access for repairs does not ad-
F, on figure 6-24 was selected. For F,, D,, ranges versely affect the embankment. The drainpipe
between 0.15 and 0.50 millimeter. This material should be surrounded by a properly designed filter
is too fine to place adjacent to a pipe with to prevent clogging of the drains by inwash of fine
%-inch openings because the requirement is for material or piping of foundation material into the
DB5 of the filter to be at least a(%) = 0.5 inch; drainage system. Two-layer filters are often re-
hence, a second filter layer of gravel is required. quired; the layer in contact with the pipe must have
(3) Lower limit of D,, of gravel = 5(0.50) = 2.5 mm particles large enough that material will not enter
(4) Upper limit of D,, of gravel = 5(1.0) = 5 mm or clog the perforations in the pipe.
(5) Lower limit of D, of gravel = 2(w) = 0.5 inch The filter in contact with the toe drain must
=13mm satisfy criterion (3) of section 6.10(i). This criterion
To meet criteria (l), (2), (3), and (4), the gravel requires that the D,, size of the filter be equal to
shown as F, on figure 6-24 was selected. or greater than twice the size of the maximum open-
ing in the pipe. The other design criteria ((l), (2),
(j) Toe Drains and Drainage Trenches.-Toe and (4)) that the filters must satisfy are given in
drains are commonly installed along the down- section 6.10(i). Figure 6-25 shows typical toe drain
stream toes of dams in conjunction with horizontal installation details used in most Bureau of Recla-
drainage blankets in the position shown on figure mation dams. Figure 6-26 shows construction of the
6-23. Beginning with smaller diameter drains laid toe drain at Calamus Dam in Nebraska.
along the abutment sections, the drains are pro- Drainage trenches are normally used when per-
gressively increased in size, and maximum diameter vious foundations are overlaid by a thin impervious
drains are placed across the canyon floor. The pur- layer. A drainage trench is simply an excavated
pose of these drains is to collect the seepage dis- trench backfilled with permeable material that pen-
charging from the embankment and foundation and etrates the impervious layer and relieves the uplift
220 DESIGN OF SMALL DAMS
HYDROMETER ANALIJI> SIEVE ANALYSIS
TlYERE*DINtl I U.S. STAYDARD SERIES I CLEAR SPVARE OPE,,l,,GS

d
. F

001 002 005 009 019 ,037 .074 149 297 590 LIP 2.38 4.76 9 51 19.1 38.1 76 2 127 151
DWR OF PARTl%EMMUMETERS
SAND I GRAVEL
FINES COBBLES
FINE [ MEDIUM I COARSE [ FINE _ 1 COARSE
DESIGN OF DRAINAGE BLANKET, GRAVEL ENVELOPE, AND DRAIN PIPE

FOR DRAINAGE BLANKET. F, FOR GRAVEL ENVELOPE. Fp FOR DRAIN PIPE WITH l/4-inch SLOTS

SD,5 base 2 D,5F, 2 5DS5bese 5015 F, 5 45 F2 :5b5 F1 DS5 F2 > 2x slot width or

5x0.03mm -C b5 FI -C Sw0.10mm 5x0.5mmIDt5 Fp C 5xl.Omm $ Of perforation


0.15mm 5 15 Ft 5 0.5Omm 2.5mm 5Dt5 Fp s6mm
DS5 F2 5 2x)in.x25.4mmlin.
1.5 5 cu (co*ficient of UnitoritY) 2 8 1.5 < cu 5 8 DS5 F2 z 13mm
De0 DBO 6.5
CG -0.45mm-
-riTzi- . 4 cu= m= 2.3 =3 SEGREGATION:

1.5 -c 4 2 8, ok 1.5 5 3 -c S.ok Maximum size filter < 3in.

Figure 6-24.-Typical filter design. 103-D- 1828.

pressures in the underlying pervious stratum. exerted by the combined weight of soil and water
Drainpipes are generally installed in the bottom of above it. For the usual condition of tailwater at the
the trench, and material satisfying the filter criteria ground surface, the uplift pressure (in feet of water)
((l), (2), (3), and (4)) of section 6.10(i) is used as at the point in question equals the depth, d, of the
backfill. point below ground plus the reservoir pressure head
A drainage trench usually is not effective if the minus the head lost in seepage through the foun-
underlying pervious foundation is stratified because dation to that point. The pressure exerted by the
it will relieve uplift pressures only in the uppermost weight of soil and water above this point is the sat-
pervious stratum. More effective drainage of strat- urated unit weight of the soil times the depth to the
ified foundations can be accomplished by pressure- point. If the thickness of the impervious layer is
relief wells. equal to the reservoir head, h, the uplift pressure
(k) Pressure-Relief Wells.-For many low dams beneath the layer cannot exceed the weight of the
on pervious foundations overlain by an impervious layer. This is so because the saturated weight of soil
stratum, the thickness of the top impervious layer equals approximately twice the weight of water, and
precludes piping, either of the blowout or internal- for h = d:
erosion type. Theoretically, piping occurs when the W,) (d)(l) = (h + d)r, (3)
fluid (uplift) pressure at some level in the founda- or pressure exerted by saturated weight equals
tion near the downstream toe reaches the pressure uplift pressure.
EARTHFILL DAMS 221

Slope protection

Embankment fi

21
Graded gravel envelope Soil foundation

3
There are many suitable drain pipes on the market.
The requirements are adequate durability and strength.
Pipe laid with open joints should not be used. Slots
or perforations should meet criteria given in section 6. 1 O(i).

1 Should meet filter criteria, given in section 6.10(i),


with adjacent material.

Figure 6-25.-Typical toe drain installation. 103-D-1829.

Figure 6-26.-Toe drain construction at Calamus Dam, Nebraska.


P801-D-81041.
222 DESIGN OF SMALL DAMS

Actually, there is always appreciable loss of res- there will be more water at the downstream toe of
ervoir head because of resistance of the soil to seep- the dam than when the permeability rates are lower.
age; hence, the value of h in the right side of Suggested well spacing is approximately 25 feet for
equation (3) is too large, and the uplift pressure will the most pervious foundations and 100 feet for less
be smaller than the pressure exerted by the over- pervious foundations.
lying weight. Therefore, if the thickness of the top Experiments have shown that, in general, the
impervious stratum is equal to the reservoir head, well diameter should not be less than 6 inches, so
it may be considered that an appreciable safety fac- that there will be little head loss for infiltrating
tor against piping is assured. In this situation, no seepage. It is recommended that a minimum thick-
further treatment of the foundation is required. ness of 6 inches of filter, which meets the criteria
However, if the thickness of the top impervious previously established (sec. 6.10(i)), be provided be-
stratum is less than the reservoir head, some pre- tween the well screens and the foundation, and that
ventive treatment is recommended. If the top im- the ratio of the D,, size of the filter to the screen
pervious stratum is less than h, but is too thick for opening be greater than 2.0.
treatment by drainage trenches, or if the pervious Examples of pressure-relief wells are shown on
foundation is stratified, pressure-relief wells are figure 6-27. Figure 6-27(A) shows the type of
required. pressure-relief well used by the Bureau of Recla-
The primary requirements for a pressure-relief mation to reduce seepage pressures at Red Willow
well system are: Dam in Nebraska. The 4-inch stainless steel well
screen is surrounded by a minimum of 6 inches of
(1) The wells should extend deep enough into filter material and sealed at the top with an im-
the pervious foundation underlying the im- pervious clay-silt mixture to prevent water from ris-
pervious top layer so that the combined ing along the outside of the pipe. The 42-inch
thickness of the impervious layer and precast concrete pipe inspection well allows easy
drained material is sufficient to provide sta- examination of the well and adequate working space
bility against underlying unrelieved pres- for any maintenance required. The relief water is
sures. Depths of wells equal to the height of dissipated through the a-inch outflow pipe to a col-
the dam are usually satisfactory. lector drain along the downstream toe of the dam.
(2) The wells must be spaced to intercept the Figure 6-27(B) shows a pressure-relief well de-
seepage and reduce the uplift pressures veloped by the Corps of Engineers [34, 351 for use
between wells to acceptable limits. in alluvium adjacent to Mississippi River levees.
(3) The wells must offer little resistance to the The well consists of a wood screen, wood riser pipe,
infiltration of seepage and the discharge gravel filter, sand backfill, and a concrete backfill
thereof. seal near the ground surface. Today, a stainless
(4) The wells must be designed so that they will steel, plastic, or fiberglass riser and screen would
not become ineffective as a result of clogging be used instead of wood, but the figure adequately
or corrosion. illustrates the components of a relief well. The in-
side diameter of the riser and screen is 8 inches and
The Corps of Engineers has conducted extensive the screen slots are ~/IS inch wide and 3% inches
research programs on the design and installation of long; the bottom of the pipe is closed with a wood
relief wells. The results of these studies have been plug. Heavily galvanized, 6-gauge winding wire at
published in a number of excellent papers [32, 33, 3-inch spacings was used to band the pipe. A reverse
34, 351. The reader is advised to consult these ref- rotary method of drilling the holes was used. This
erences for theoretical design methods. method is excellent for installing these wells be-
Well spacing usually must be based on judgment cause the material is removed through a suction
because of the lack of detailed information regard- pipe, which helps prevent sealing of the pervious
ing the foundations of small dams. This is an ac- strata. The walls of the hole are supported by hy-
ceptable procedure provided plans are made to drostatic forces acting against a thin film of fine-
install additional wells after the dam is constructed grained soil on the walls, created by maintaining a
at the first sign of excessive pressures. When the head of water in the hole several feet above the
pervious strata have high rates of permeability, ground-water table. Additional information con-
EARTHFILL DAMS 223

TOP of wei/ screen

h"Mi" pocx moterio,

4'Dw s+oin,es5 s+ee, we,,

--Plop

(A)

Natural ground---

---Concrete bockflll

,--Sand backfIll

throu.gh very fine


sand strata

s-Grovel filter

Note: Not to scale

Figure 6-27.-Pressure-relief wells and appurtenances. 288-D-2485.


224 DESIGN OF SMALL DAMS

cerning well construction procedure is contained in based largely on judgment and experience are not
[351- appropriate.
Another method of installing a pressure-relief The purpose of this section is to show the ap-
well requires lowering a casing of appropriate size plication of methods of foundation treatment to
to the required depth and washing out the soil inside specific instances. For purposes of discussion, per-
the casing. The assembled well pipe, consisting of vious foundations are divided into the following
the screen and riser, is lowered in the casing and cases:
properly aligned. The filter is then placed in 6- to Case 1: Exposed pervious foundations
&inch layers and the casing withdrawn a like Case 2: Covered pervious foundations-the per-
amount. This process is repeated until the filter is vious foundation is overlain by an im-
several feet above the top of the screen section. pervious layer that may vary in thickness
Above this point, impervious backfill or concrete is from a few feet to hundreds of feet.
placed to prevent leakage along the outside of the In both of these cases, the pervious foundation
pipe. After installation, the wells should be cleaned may be relatively homogeneous, or it may be
out and pumped or surged to remove any fine soil strongly stratified with less pervious layers so that
immediately adjacent. Pressure-relief wells should the horizontal permeability will be many times
be inspected periodically and cleaned by surging, if greater than the vertical permeability. Stratifica-
necessary. tion will influence selection of the appropriate foun-
Relief wells, like other drainage systems, have dation treatment method.
some limitations. Too great a volume of seepage The treatment of Case 2: covered pervious foun-
may require an excessive number of wells. In such dations, is influenced by the thickness of the im-
cases, upstream impervious blanketing of the areas, pervious top layer. The following three conditions,
which allows reservoir water to enter the pervious based upon the thickness of the top impervious
layers, may be used to reduce the amount of seepage. layer, are considered:
The design and installation of pressure-relief (1) Impervious layer has a thickness of 3 feet or
wells demands specialized knowledge, skill, and the less: It should be assumed that the layer will
highest quality of construction inspection to ensure be largely ineffective as a blanket in pre-
satisfactory performance. These wells also require venting seepage because thin surface strata
postconstruction supervision and maintenance. usually lack the density required for im-
Therefore, the need to use pressure relief wells permeability and because they commonly
should be carefully considered. The use of a pres- have a large number of openings through
sure relief well system should be compared with the them. There also exists the possibility that
adequacy of simpler, more maintenance-free sys- construction operations near the dam may
tems before deciding to use them. penetrate the layer or that, while filling the
6.11. Designs for Sand and Gravel Founda- reservoir, unequalized hydrostatic pressure
tions.-(a) Gene&.-Criteria (b) for the design of on the surface of the blanket may puncture
earthfill dams, presented in section 6.5, requires it. Therefore, a very thin impervious top
that the flow of seepage through the foundation and layer such as this is considered to have little
abutments be controlled so that no internal erosion effect on the imperviousness of the founda-
occurs and there is no sloughing in the area where tion. Drainage trenches or pressure-relief
the seepage emerges. This criterion also requires wells near the downstream toe may be nec-
that the amount of water lost through seepage be essary to penetrate continuous layers and re-
controlled so that it does not interfere with planned lieve uplift pressure.
project functions. Section 6.6 discusses the basis (2) Impervious layer has a thickness greater
used for designing foundations for small dams, than 3 feet but less than the reservoir head:
which requires a generalization of the nature of the This type of foundation condition is usually
foundation in lieu of detailed explorations and the treated by using drainage trenches or pres-
establishment of less theoretical design procedures sure-relief wells near the downstream toe to
than those used for major structures. Section 6.6 penetrate the impervious layer and relieve
also cautions against the use of these design pro- the uplift pressures. In the upstream reser-
cedures for unusual conditions where procedures voir areas near the dam, the natural blan-
EARTHFILL DAMS 225

keting of the impervious layer may reduce izontal drainage blanket should be provided because
seepage. If this is relied upon, the adequacy it ensures that the seepage line (phreatic line)
of the natural blanket should be carefully through the embankment will be drawn down and
evaluated. the stability of the section increased; however, the
(3) Impervious layer thickness is greater than blanket need not extend upstream closer to the cen-
the reservoir head: It can be assumed here terline of the dam than a distance of Z + 5 feet.
that there will be no major problems involved Section 6.18(d) discusses the extent of the filter re-
so far as seepage or seepage forces are con- quired for a homogeneous embankment. Toe drains
cerned. This is demonstrated by equation (3) should be installed to carry away the excess seepage
in section 6.10(k). and to keep the downstream toe of the dam dry.
The treatment of impervious foundations of silt If a shallow foundation is stratified, similar to
and clay is discussed in section 6.12. that shown on figure 6-29, a positive cutoff trench
(b) Case 1: Exposed Pervious Foundations (Shal- should be constructed. Horizontal drainage blan-
low Depth).-The foundation treatment for an ex- kets are beneficial for stratified foundations, es-
posed pervious foundation of shallow2 depth is pecially if the top layer is impervious or of doubtful
shown on figure 6-28(A). A cutoff trench excavated permeability. As stated above, grouting may be re-
to the impervious stratum, called a positive cutoff, quired if the base stratum is rock of high permea-
should always be used because it is the most pos- bility. Deeply stratified foundations are discussed
itive means of avoiding excessive seepage losses in section 6.11(d).
and piping. If the stratum is rock, grouting may be When conditions such as lack of impervious ma-
required to control the seepage. A horizontal drain- terial, short construction seasons, wet climates, and
age blanket is not necessary if the shallow pervious high dewatering costs prevent the use of a trench-
foundation can act as a filter and provide adequate type cutoff, other methods of constructing an im-
drainage capacity. For example, if the downstream permeable barrier may be used. These methods in-
portion of the embankment is sand and gravel sim- clude sheet piling, alluvial grouting, cement-bound
ilar in gradation to the foundation, the horizontal or jet-grouted curtain cutoffs, a concrete cutoff wall,
drainage blanket shown on figure 6-28(A) may not and a slurry trench. If one of these methods is used,
be necessary. Horizontal drainage blankets meeting an experienced dam designer should be consulted.
filter requirements are generally used when the fol- (c) Case 1: Exposed Pervious Foundations (In-
lowing conditions exist: termediate Depth).-A foundation is considered to
(1) The embankment is homogeneous or the be of intermediate depth when the distance to the
downstream shell is rockfill. impervious layer is too great for a cutoff trench, but
(2) The perviousness of the foundation is ques- can be economically reached by another type of pos-
tionable. itive cutoff. Whether or not a positive cutoff is eco-
(3) The possibility of piping exists, either from nomical depends heavily on three items:
the embankment into the foundation or from (1) The effect of underseepage on the stability
the foundation into the downstream zone of of the embankment
the embankment. (2) The economic value of the water lost by
(4) The foundation is stratified. underseepage
A filter may also be necessary against the down- (3) Whether or not treatment of the foundation
stream slope of the cutoff trench and impervious as if it were a Case 1 (exposed pervious foun-
zone to prevent piping. dation of great depth) (sec. 6.11(d)) is more
If the downstream portion of the embankment economical
is rockfill, a horizontal drainage blanket should be If it is decided that treatment as an intermediate
used to prevent piping from the foundation. It depth foundation is required, the following methods
should extend from the downstream slope of the of constructing a positive cutoff are available:
dam to the impervious zone, as shown on figure 6- l Sheet piling
28(A). If the embankment is homogeneous, a hor- l Cement-bound or jet-grouted curtain cutoff
l Slurry trench
The term shallow usually implies a depth approximately equal to or less
than the height of the dam. This informal definition breaks down when
l Alluvial grouting
dam heights exceed about 50 feet. l Concrete cutoff wall
226 DESIGN OF SMALL DAMS

Pervious or imFlervious zone>


ecree+,4n- -8 0-A horizontol drainage blanket
meeting filter criteria of section 6.10 l(i) is required when:
------- -_--__----- -I (I 1 The embankment is hanogeoeous
f----- 0T the downstream shell is rockfill.
2 T$yiy~& (2) %rneability of the pervious
Original i lover is cFJestlonable.
cv-d I (3) The possibility of piping exists.
I
surface- , ; The foundation is stratified.
Strip organic
material ----

-Grout curtain; May be required if


* impervious stmtum is rock

IA) SHALLOW PERVIOUS FOUNDATION

iour or impervious zone


,+torizontal drainage blanket meeting
filter criteria of section 6,lO(i,I

Rrvious foundation- , cement bound or jet 2 These treatments require


ain cutoff, concrete t the supervision of an
slurry trench, or alluvial : experienced engineer
-L--,-- ---Impervious stratum

( 8) INTERMEDIATE DEPTH OF PERVIOUS FOUNDATION

t Crest of Dm-14
--------- ______ .-Downstream slope of
7;---- minimum-size corn ( I: I )
I -Pervious or im

filter
Strip organic material-
necessary to mduce
d---
seepage josses ---Pervious foundation----.,+

(C) DEEP PERVIOUS FOUNDATION

NOTE: Filter criteria given in section 6.10(i) applies


between the impervious zone and any downsteam
zone or a properly designed filter must be
provided on (A),(B)and (C).

Figure 6-28.-Treatment of Case 1: exposed pervious foundations. 288-D-2486.


EARTHFILL DAMS 227

.-Reservoir water surface ,--Downstream slope of


# ,. minimum-size core I I: I)
rvious or impervious zone
,,Horizantal dminage blanket

*a Strongly stratified pervious foundation with very pervious


layers (~1 and relatively impervious(i) layers
Notes: (I) If stmtified foundation is bf shallow depth. a positive cutoff trench should be used.
(2) Pressure relief wells may be required for deeply stratified foundations.
(3) Filter criteria given in section 6.10(i) applies between the impervious
zone and any downstream zone or foundation layer,
otherwise a filter should be provided.

Figure 6-29.-Treatment of stratified foundations. 288-D-2487.

If one of these methods is used, an experienced the blanket should extend beneath this zone so that
engineer should supervise the design and construc- it forms a continuation of the impervious core.
tion of the entire dam. Minimum core B, for zoned The smallest impervious zone recommended for
dams on deep pervious foundations (see fig. 6-43), use with zoned embankments on deep pervious
is the smallest impervious core recommended with foundations is minimum core B, shown on figure 6-
this type of foundation treatment. Treatment of the 43. The key trench is used to intercept any critical
intermediate depth foundation is shown on figure areas of the foundation and should be located up-
6-28(B). As noted in section 6.11(b), these treat- stream from the centerline of the crest of the dam.
ments may also be required when excessively wet To avoid foundation stability problems caused by
climates, short construction seasons, shortages of seepage, an adequate thickness of pervious or im-
impervious material for upstream blanket construc- pervious material must be maintained over the per-
tion, etc., prevent the use of a positive cutoff trench. vious foundation across the valley floor. Suggested
(d) Case 1: Exposed Pervious Foundations (Great dimensions for the length and cover requirements
Depth).-The problem in dealing with deep per- for the downstream section are shown on figure 6-
vious foundations is to determine the ratio of hor- 23. Several sections should be taken along the cen-
izontal to vertical permeability. If this can be done, terline of the embankment to ensure that adequate
an accurate flow net can be constructed, correct material is provided for the most critical section.
seepage quantities determined, and appropriate If a homogeneous section is used, a horizontal
drainage measures taken. Because this ratio is dif- drainage blanket is needed to handle seepage from
ficult to determine, general assumptions must be the foundation and to reduce the height of the
made regarding the homogeneity of the pervious phreatic line in the embankment. A horizontal
layer. Contingency plans must be made in case the drainage blanket should also be used with a down-
horizontal permeability is much greater than ex- stream pervious zone when the possibility of piping
pected or the foundation contains thin layers whose from the foundation exists. The drainage blanket
permeability is much greater than the average. should meet the filter criteria presented in section
The general treatment for a pervious foundation 6.10(i).
that is too deep to permit a positive cutoff is shown Toe drains are used to collect seepage, convey it
on figure 6-28(C). The upstream blanket is provided to the downstream channel, and prevent wet areas
to lengthen the seepage path and reduce the total at the downstream toe.
quantity of seepage to acceptable limits. If an up- If the permeability is great enough to cause ex-
stream pervious zone is used in the embankment, tensive seepage, ponding, or sand boils at the down-
228 DESIGN OF SMALL DAMS

stream toe, then drainage trenches, pressure-relief essary to compact the impervious layer with a heavy
wells, extension of the downstream toe of the dam, roller. If it is not possible to adequately evaluate
or blanketing the downstream area with pervious the suitability of the upstream covering, it should
fill meeting filter criteria given in section 6.10(i) be assumed that the natural blanket is not extensive
may be required to control the situation. enough or impermeable enough to prevent seepage
In deep stratified foundations, a different treat- or cause substantial head loss to the water entering
ment is required. This type of foundation consists the pervious layer. Provisions should be made to
of alternating layers of relatively pervious and im- relieve uplift pressures at the downstream toe and
pervious material and is generally treated by con- to remove the seepage.
structing a partial cutoff trench. The depth of the If the underlying pervious layer is relatively ho-
partial cutoff must be such that the total combined mogeneous and the top impervious layer is rela-
depth of the cutoff trench and the impervious layer tively thin, the top layer should be completely
upon which it rests is not less than the reservoir penetrated by a drainage trench, as shown on figure
head. Typical embankment and foundation treat- 6-30. This will relieve the uplift pressures that de-
ment for stratified foundations is shown on figure velop beneath the impervious layer. Additional
6-29. On this figure, d must be equal to or greater drainage trenches may be required after construc-
than h. (Note that d is the depth to the uppermost tion if excessive uplift pressures still exist or if seep-
pervious layer that is not cut off. It is not the depth age quantities are large. When the overlying
of the partial cutoff trench.) If this requirement is impervious layer is too deep to penetrate econom-
met, the foundation should be stable against seep- ically with a drainage trench, pressure-relief wells
age pressures that may exist in the uppermost per- (sec. 6.10(k)) should be used along the downstream
vious layer that is not cut off (see eq. (3)). toe, as shown on figure 6-30(B). The correct spacing
A horizontal drainage blanket meeting filter re- of relief wells is difficult to determine, primarily
quirements should be used with stratified founda- because of the inaccuracy in estimating the perme-
tions in case the downstream embankment zone is ability of the strata. Wells are usually spaced from
impervious or if piping requirements are not met 50 to 100 feet apart for the initial design, and then
by an overlying pervious layer. Toe drains should additional wells are installed if postconstruction
also be used. Additional drainage measures, such as seepage analysis requires them.
the use of pressure-relief wells, may be required if When the dam embankment is homogeneous or
high uplift pressures exist below the downstream when the downstream zone has questionable
toe and are not detected until reservoir filling. permeability, a horizontal drainage blanket is con-
(e) Case 2: Covered Pervious Foundations.-In structed as shown on figure 6-30. This is done to
the case of pervious foundation covered by an im- (1) lower the height of the seepage line through the
pervious layer, the type of treatment depends on embankment, (2) provide adequate embankment,
the thickness and imperviousness of the layer cov- drainage, and (3) eliminate piping from the em-
ering the pervious zone and on the permeability of bankment. The blankets should extend from the
the underlying pervious layer. downstream toe to within a distance of Z + 5 feet
If the overlying layer is equal to or less than a from the centerline.
few feet thick (say 3 ft), its effect is generally ig- Stratified foundations should be treated as dis-
nored because of thickness variations near the dam- cussed in sections 6.11(b) and (c) and as shown on
site and the possibility of a puncture during figure 6-29.
construction of the dam or a blowout after filling. (f) Summary of Pervious Foundation Treat-
In this case, the foundation should be designed as merits.-Table 6-2 is a summary of recommended
a Case 1: exposed pervious foundation, either shal- treatments for various pervious foundation condi-
low (sec. 6.11(b)) or deep (sec. 6.11(d)). tions. Foundations are normally considered as
An overlying impervious layer having a thickness either shallow or deep because these are by far the
greater than 3 feet and less than the hydraulic head most common conditions encountered. However, if
may be assumed to act as an upstream impervious the foundation is determined to be of intermediate
blanket if the thickness, continuity, impervious depth, special construction methods are required
qualities, and upstream distance of the natural de- that should be supervised by an experienced engi-
posit have been carefully checked. It is usually nec- neer. Intermediate depth foundations are discussed
EARTHFILL DAMS 229

Q crest of Dam--- 4 ,

--2+5-z-!
+Perviour or impervious zone

(i)

Y ----Homogeneous pervious foundation---

iA1 OVERLYING IMPERVIOUS LAYER PENETRATED BY DRAINAGE DITCH

,rRewrvoir water surface

,--Impervious layer, thickness


-3ondc h----r
-- --
Pervious foundation, homogeneous Slotted pipe in pervious /j---p
or stratified ------rr-7 foundation strata- - --
b-4
(8) PRESSURE RELIEF WELL

NOTE: Filter criteria given in section 6.10(i) applies between the


impervious zone and any downstream zone or a properly
designed filter must be provided on both (A)and (8).

Figure 6-30.-Treatment of Case 2: covered previous foundations. With overlying impervious layer of thickness more
than 3 feet but less than the reservoir head. 288-D-2488.

in section 6.11(c). The treatments of shallow and bility. In addition to the obvious danger of bearing
deep foundations, both exposed and covered, are failure of foundations of saturated silts and clays,
discussed in detail in sections 6.11(d) and (e). the designs must take into account the effect of
6.12. Methods of Treating Silt and Clay Foun- foundation saturation of the dam and of appurten-
dutions.-(a) General.-Foundations of fine- ant works by the reservoir.
grained soils are usually impermeable enough to Methods of foundation treatment are based on
preclude the necessity of providing design features the soil type, the location of the water table, and
for underseepage and piping. However, as discussed the density of the soil. For saturated foundations
previously, inclined and horizontal filter-drainage of fine-grained soils (including sands containing
blankets provide good protection against unknown sufficient fines to make the material impervious),
geologic conditions, cracking, dispersive soils, and the standard penetration test described in section
design and construction defects. Purely homoge- 5.32(b) provides an approximate measure of the
neous dams are no longer recommended except for density or relative consistency. This test cannot be
the most unimportant structures. Filter-drainage relied on, however, in fine-grained soils above the
blankets should meet the criteria in section 6.10(i). water table, especially very dry soils whose resist-
The main problem with these foundations is sta- ance to penetration is high although their unit
230 DESIGN OF SMALL DAMS

Table 6-2.-Treatment of pervious foundations.

Case 1: Exposed pervious fomdutions

Thickness of
overlying Total Condition of
impervious depth of pervious Primary device for Additional requirements
Figure layer foundation material control of seepage (other than stripping)

6-28(A) None Shallow Homogeneous Positive cutoff trench Toe drain


Horizontal drainage blanket
meeting filter requirements
may be required
Grouting may be required
6-28(C) None Deep Homogeneous Upstream impervious Large core
blanket Horizontal drainage blanket
meeting filter requirements
may be required
Key trench
Toe drain

Case 2: Covered pervious foundations

6-28(A) 53ft Shallow Homogeneous Treat as Case 1: exposed


pervious foundation
(shallow)
6-28(C) 53ft Deep Homogeneous Treat as Case 1: exposed
pervious foundation
(deep)
6-28(A) >3 ft, Shallow Homogeneous Treat as Case 1: exposed
<reservoir pervious foundation
head (shallow)
6-30(A) >3 ft, Deep Homogeneous Drainage trench or pres- Key trench
or (B) <reservoir sure-relief wells Compaction of the upstream
head Impervious upstream layer
layer
>reservoir No treatment required as a pervious foundation

Stratified foundations

6-28(A) Not Shallow Stratified Positive cutoff trench Horizontal drainage blanket
important meeting filter requirements
Toe drain
Grouting may be required

6-29 Not Deep Stratified Partial cutoff trench Horizontal drainage blanket
important meeting filter requirements
Toe drain
Pressure-relief wells may be
required
EARTHFILL DAMS 231

weight is low. In these soils, the unit weight can be At water contents equal to their plastic limits
determined by inplace unit weight tests described (C,= l.O), the cohesive strengths of saturated soils
in section 5.47. vary considerably depending on their types, and the
(b) Saturated Foundations.-When the foun- shear strength can be represented by the equation:
dation of an earthfill dam consists of saturated fine-
grained soils or saturated impervious sands, their spL = C, + 0 tan # (5)
ability to resist the shear stresses imposed by the
weight of the embankment may be determined by The value of tan p on an effective stress basis
their soil group classification and their relative con- can be obtained from triaxial shear tests on samples
sistency. Soils that have never been subjected to compacted at Proctor maximum dry density and
geologic loads greater than the existing overburden optimum water content. This value is usually some-
are normally consolidated. These soils are much what smaller than tan #,. The value of cohesion at
weaker than strata that have been consolidated by the plastic limit, CpL, can be obtained from similar
hundreds or thousands of feet of ice or soil, which tests made on soil compacted at optimum water
have since been removed. Old lake deposits that content and then saturated. As explained in section
have experienced cycles of drying and submergence 5.18(b), for these samples, the intercept of the or-
often exhibit the characteristics of preconsolidated dinate with the tangent to the failure circle making
soil as a result of the capillary forces associated with an angle p with the abscissa on the Mohr diagram
the shrinkage phenomenon. Soils that have been (fig. 5-13) is designated CYsat.The water content cor-
preconsolidated are recognized by their large re- responding to Csatis usually close to the plastic limit
sistance to penetration, which is usually more than for clayey soils; that is, C, is near unity. By assuming
20 blows per foot; they provide satisfactory foun- a linear variation of cohesion with water content,
dations for small dams. On the other hand, the pres- between the liquid and plastic limits,
ence of soft, unconsolidated silts and clays
represented by a penetration resistance of less than C sat - 0.2
CPL = + 0.2 (6)
four blows per foot indicates the need for special C,
sampling and testing techniques and requires the
advice of specialists. By identifying the soil and de- where C, corresponds to Csat.
termining its resistance to penetration, the stan- Using this assumption, Coulombs equation for
dard penetration test can be used to delimit the shear strength, equation (lo), for a saturated soil
saturated foundations that can be designed by the at any C, may be written as follows:
approximate methods used in this text and to pro-
vide approximate design values. s=CLL(l-Cr)+CrCPL+cr tan$ (7)
For cohesionless soils, the relative density D,,
which equals (emax -e)/(e,,, - emin) (see sec. The last term (0 tan 9) in equation (7) repre-
5.49(f)), is known to be related to the strength of sents the frictional portion of the shear resistance
the material. For saturated cohesive soils, a similar at any point of the potential surface of sliding in
property, the relative consistency, C,, is also related the foundation. For the condition of no drainage of
to strength. C, is equal to (LL - w)/(LL - PL) = the impervious foundation during construction of
(eLL - e,)/(eLL - epL). At water contents equal to the embankment, o remains constant. The cohe-
their liquid limits (C, = 0), the cohesion at the liquid sion portion of the equation is a function of C,.
limit, CLL, of all remolded saturated soils is about Because C, cannot increase without drainage, the
0.2 lb/in2, and the shear strength can be represented shear strength of the foundation remains constant
by Coulombs equation: while the shear stresses imposed by the embank-
= 0.2 lb/in2 + 0 tan I, ment increase, thus decreasing the factor of safety
SLL (4)
against sliding. The methods of treatment appli-
Tan $, can be obtained by consolidated-drained cable to these conditions are (1) to remove the soils
(slow) shear tests on saturated soil starting from with low shear strength, (2) to provide drainage of
the liquid-limit condition. Drainage is permitted in the foundation to permit the increase of strength
these tests and the pore water pressure is zero. Tan during construction, and (3) to reduce the magni-
$, is about 0.5 even for fat clays. tude of the average shear stress along the potential
232 DESIGN OF SMALL DAMS

sliding surface by flattening the slopes of the high dry strength in the natural state. If proper
embankment. measures are not taken to control excessive settle-
Removing soft foundation soils is sometimes ment, failure of the dam may occur (1) by differ-
practicable. Relatively thin layers of soft soils over- ential settlement that causes rupture of the
lying firm material may be removed when the cost impervious portion of the embankment and thus
of excavation and refill is less than the combined allows breaching of the dam by the reservoir, or (2)
cost of special investigations and the flatter em- by foundation settlement resulting in a reduction
bankment slopes required. In the preparation of rel- of freeboard and overtopping of the dam, although
atively firm foundations, pockets of material the impervious portion of the embankment deforms
substantially more compressible or lower in without rupturing.
strength than the average are usually removed. See These low-density soils are typified by but
appendix E for a discussion of foundation stripping. not restricted to loess, a very loose, wind-
In several instances vertical drains have been deposited soil that covers vast areas of several con-
used to facilitate consolidation so that the strength tinents, including North America. True loess has
of the foundation would increase as it was loaded never been saturated and is generally composed of
by an embankment. This treatment is applicable uniform, silt-sized particles bonded together with a
primarily to nonhydraulic structures such as high- small amount of clay. When its water content is
way embankments. Special studies and precautions low, loess exhibits sufficient cohesive strength to
are required when these drains are used under an support 100-foot-high earthfills without large set-
earthfill dam, and this device is not recommended tlement. A substantial increase in water content,
for small dams within the scope of this text. however, greatly reduces the cohesion and may re-
The most practicable solution for foundations of sult in collapse of the loose structure of the soil
saturated fine-grained soils is flattening the em- under the loading imposed by dams only 20 feet
bankment slopes. This requires the critical sliding high.
surface to lengthen, thereby decreasing the average The experiences of the Bureau of Reclamation
shear stress along its path and increasing the factor with the construction of dams on loess in the Mis-
of safety against sliding. The selection of design souri River Basin are, in part, described in a pub-
slopes is discussed in section 6.13. lication of the American Society of Civil Engineers
(c) Relatively Dry Foundations.-Unsaturated [36] and in a Bureau monograph [37]. Although the
impermeable soils are generally satisfactory for properties of other loessial soils may differ from
foundations of small dams because the presence of those found in the Missouri River Basin, a discus-
air in the soil voids permits appreciable volume sion of the Bureaus experience may serve as a guide
change, increase of normal effective stress, and mo- in other areas.
bilization of frictional shear resistance without The typical undisturbed Missouri River Basin
drainage of the pore fluid. That is, for a given void loess is a tan to light brown, unstratified, light-
ratio, an impervious soil has greater bearing ca- weight soil containing many root holes and voids.
pacity in the unsaturated condition than in the sat- It consists mostly ~of silt-sized particles bonded to-
urated condition. gether by a relatively small proportion of clay. The
In addition, unsaturated soils exhibit the phe- apperance of the loess and the range of gradation
nomenon of apparent cohesion, which is the re- are shown on figure 6-31; 75 percent of the samples
sult of less than atmospheric capillary pressures in investigated were silty loess, 20 percent were clayey
the water films surrounding the soil particles. The loess, and the remainder were sandy loess. The den-
addition of water to these soils first reduces and sity of the loess ranged from a low of 65 lb/ft3 in
then destroys the apparent cohesion as saturation unusual cases to a high of 100 lb/ft in areas that
is reached. Most soils are sufficiently dense so that had been wetted and consolidated or where the loess
reduction of apparent cohesions by saturation had been eroded and redeposited.
causes no serious difficulties in foundations of small With natural water contents of about 10 percen ;,
dams. the supporting capacity of the loess is high regar l-
However, an important group of soils have low less of its unit weight. There is little reduction in
density and are subject to large settlements when bearing capacity for water contents up to about 15
saturated by the reservoir, although these soils have percent. However, further increase in moisture is
EARTHFILL DAMS 233

(a) Undisturbed loess.

Figure 6-32.- Typical compression curves for Missouri


River Basin loess. 288-D-2490.

of low-density loess at the natural moisture and at


the prewet conditions indicates that dangerous set-
tlement would result even for a 20-foot-high dam.
Figure 6-32 also demonstrates (curve C) that very
little postconstruction foundation settlement will
occur for a dam constructed on a high unit weight
loess with low natural moisture. Hence, the deter-
mination of the inplace unit weight and water con-
tent of the loess is of paramount importance in
planning its use as a foundation for a dam.
The required treatment of dry, low-unit weight
foundations is dictated by the compression char-
(bl Range of gradation and Atterberg limits. From [36]. acteristics of the soil. These characteristics are best
determined by laboratory tests on undisturbed sam-
Figure 6-31 .-Appearance and identification of Missouri ples at their natural water content to determine
River Basin laess. 288-D-2489. whether the postconstruction settlement causedby
saturation will be significant (curve A of fig. 6-32)
accompanied by an appreciable reduction in sup- or minor (curve C of fig. 6-32). For small dams, the
porting capacity for low-unjt weight loess, but has empirical criteria given in section 6.13(b) can be
little,effect on high-unit weight loess. used in lieu of laboratory tests.
Several typical laboratory compression curves If the foundation of a small dam is not subject
for loess test specimens have been plotted on figure to appreciable postconstruction settlement when
6-32 as load versus dry unit weight. These curves saturated, little foundation preparation is required.
demonstrate the effect of inplace unit weight and The foundation should be stripped to remove or-
of wetting on compression characteristics. The low- ganic material, a key trench (sec. 6.6) should be
unit weight loess that was not prewet (curve A) provided, and a toe drain (sec. 6.10(j should be
compressed5 percent under a load roughly equiv- installed to prevent saturation of the foundation at
alent to a 100-foot-high earthfill dam (100 lb/in2 on the downstream toe of the dam. Consideration
fig. 6-32); it compressedan additional 10.5 percent should be given to providing horizontal and inclined
without an increase in load when saturated. The filter-drainage blankets, as shown on figure 6-5(C).
difference between the compression characteristics If the foundation is subject to appreciable
DESIGN OF SMALL DAMS

postconstruction settlement when saturated, meas- ious combinations of cohesion and tan $ of the foun-
ures should be taken to minimize the amount. dation soil needed to provide a 1.5 safety factor for
If the low-unit weight soil exists in a top stratum, the critical condition using the Swedish slip circle
it may be economical to excavate this material and method,
replace it with compacted embankment. If the layer Figure 6-33 shows a typical section design for a
is too thick for economical replacement or if its small dam on a saturated fine-grained foundation.
removal would destroy a natural blanket over a per- Table 6-3 lists the recommended slopes for sta-
vious foundation, measures should be taken to en- bilizing fills for saturated foundations typical of the
sure that foundation consolidation is achieved groups of the Unified Soil Classification System for
during construction. different degrees of consistency. Blows per foot of
Curve B of figure 6-32 demonstrates that low- the standard penetration test are used to approxi-
unit weight loess, if prewet, compresses during load- mate relative consistency: Less than 4 blows cor-
ing. Hence, postconstruction settlement of low-unit responds to G, = 0.50,4 to 10 blows corresponds to
weight loess caused by saturation by the reservoir G, = 0.5 to 0.75, 11 to 20 blows corresponds to G,
can be avoided by prewetting the foundation to ob- = 0.75 to 1.0, and more than 20 blows corresponds
tain compression during construction of the em- to G, = 1.0. Recommendations are not made for
bankment. This method cannot be used unless slopes of soils averaging less than four blows per
drainage is ensured by an underlying pervious layer foot within a foundation depth equal to the height
or the deposit is so thick that vertical drainage may of the dam. These very soft foundations require spe-
occur during compression of the upper portion of cial sampling and testing methods that are beyond
the deposit. the scope of this text.
Because of its structure and root holes, the ver-
tical permeability of a loess deposit is much higher Example
than its horizontal permeability. The Bureau of Re- Required:
clamation has successfully consolidated founda- Slope of stabilizing fill for a safety factor of ap-
tions of low-unit weight loess during construction proximately 1.5.
by prewetting the foundation, with the result that Given:
no difficulty has been experienced with postcon- Type of dam = either homogeneous or zoned.
struction settlement upon filling of the reservoir. Foundation blow count from field tests = 15.
Sample specifications for the performance of this Saturated foundation material = CL.
work are included in appendix G. Height of dam = 40 feet.
6.13. Designs for Silt and Clay foundations.- Solution:
(a) Saturated Foundations.-The designs of From table 6-3 opposite stiff consistency and CL,
small dams on saturated fine-grained soils given in read 4.5:1 under dam height of 40 feet.
this section are based on the results of numerous
stability analyses using various heights of dam and (b) Relatively Dry Foundations.-The design of
different sets of slopes for the stabilizing fills for even very small dams on deposits of dry foundat.ions
each height. Average values of embankment prop- of low density must take into account the possibility
erties were used and the required shearing strength of settlement upon saturation by the reservoir. Be-
for a safety factor of 1.5 was determined assuming cause the penetration test results on these foun-
that no drainage occurred in the foundation during dations may be grossly misleading, natural water
construction. content and inplace unit weight tests should be
This construction condition was found to be made in portions of the deposit above the water
more severe for stability than either the steady- table for comparison with laboratory compaction
state seepage condition or the sudden drawdown values on the same soils. Section 5.47 describes the
condition. Furthermore, the type of material used procedure for determining inplace unit weight and
for embankment and stabilizing fills was found to water content, and section 5.49 describes the lah-
have no appreciable effect on the stability, which oratory compaction test. The rapid method of com-
was a function of the soil type and the relative con- paction control described in test designation IJSBR
sistency of the saturated foundation. The slopes of 7240 of the Bureaus Earth Manual [ll] can also
stabilizing fills were determined by finding the var- be used to determine the percentage of laborat,ory
EARTHFILL DAMS 235

--Slope OS determined from toble s-5 or table 6-6


OS oppropriote,but not steeper than 3:I.

;Stobilizirq fill -X-


Embankment OS designed
for stable foundation (sec.6.16)
, I- I
4 +
*- Original ground
surface Key trench
M Soturotrd fine qroined
,. 1 Depth 2 z
foundotlon moterial- - /*
Note: Outside sbpes ot the upstreomH t
ond downstreom stobilizino fills to I
bemodethesome. -

- Bedrock or other stoblr foundotion

NOTE: Consideration should be give to theneed for a horizontal and inclined


filter-drainage blanket meeting criteria in section 6.10(i)

Figure 6-33.-Design of dam on saturated fine-grained foundation. 288-D-2491.

Table 6-3.--Recommended slopes of stabilizing fills for dams on saturated silt and clay foundations.

Average number of blows per foot2 Slopes of stabilizing fills for various
Consistency within foundation depth equal to Foundation heights of dams
height of dam soil group 3 50 ft 40 ft 30 ft 20 ft 10 ft
Soft <4 Special soils tests and analyses required

SM 4.5:1 4:l 3:l 3:l 3:l


SC 6:l 51 4:l 3:l 3:l
ML 6:l 5:l 4:l 3:l 3:l
Medium 4 to 10
CL 6.51 5:l 4:l 3:l 3:l
MH 7:l 5.5:1 4.5:1 3.5:1 3:l
CH 13:l 1O:l 7:l 4:l 3:l

SM 4:l 3.5:1 3:l 3:l 3:l


SC 5.5:1 4.5:l 3.5:1 3:l 3:l
ML 5.5:1 4.5:1 3.5:1 3:I 3:l
Stiff 11 to 20 CL 6:l 4.5:1 3.5:1 3:l 3:l
MH 6.5:1 5:l 4:l 3:l 3:l
CH 11:l 9:l 6:l 3:l 3:l

SM 3.5:1 3:l 3:l 3:l 3:l


SC 5:l 4:l 3:l 3:l 3:l
ML 5:l 4:l 3.5:1 3:l 3:l
Hard CL 5:l 4:l 3:l 3:l 3:l
MH 5.5:1 4:l 3:l 3:l 3:l
CH 1O:l 8:l 5.5:1 3:l 3:l

Stabilizing fills are not needed when embankment slopes required by tables 6-5 and 6-6 are equal to or flatter than the slope
listed above.
2Standard penetration test (sec. 5.32 (b)).
Unified Soil Classification System (sec. 5.17).
236 DESIGN OF SMALL DAMS

maximum dry density in the natural soil and the only the natural density and liquid limit are avail-
approximate difference between optimum water able, another criterion, shown on figure 6-35, pro-
content and inplace water content. vides an indication of the susceptibility of the soil
Analysis of the results of 112 tests made by the to collapse on saturation [38]. Figure 6-35 is pri-
Bureau of Reclamation on samples of undisturbed marily applicable to loose, fine-grained soils. The
foundation soils indicates that density, water con- theory is based on soil unit weight. If the unit weight
tent, and applied load influence the susceptibility is low enough that void spaces are larger than re-
of a soil to large settlement upon saturation. The quired to hold the liquid-limit moisture content, as
following soil groups were represented in the tests: shown for case I on figure 6-35, the soil can become
ML, 51 percent; CL, 23 percent; ML-CL 13 percent; wetted to above the liquid-limit consistency and set-
SM, 8 percent; and MH, 5 percent. tle from collapse of the soil skeleton. Conversely, if
For loads within the range applicable for small the unit weight is high enough so that the void space
dams, an empirical relationship between D (inplace is less than required for the liquid-limit moisture,
dry unit weight divided by Proctor maximum dry as shown for case III on figure 6-35, the soil will
unit weight) and w, - w (optimum water content not collapse upon saturation, but will reach a plastic
minus inplace water content) is shown on figure 6- state. Therefore, liquid limits and inplace dry unit
34. This relationship differentiates foundation soils weights that plot above the line are indicative of
requiring treatment from those that do not. There soils susceptible to collapse. Points below the line
were 70 tests in the former category and 42 in the are indicative of soils that would settle only in a
latter. For foundations of unsaturated soils that fall normal manner caused by loading.
into the no treatment required category on the The foundation treatment at Medicine Creek
figure, only the usual foundation stripping and key Dam is typical of results achieved by preirrigation
trench are required. Soils with inplace water con- of a loess foundation. This structure is an earthfill
tent considerably greater than w, should be checked
to determine the degree of saturation. If they are
over 95 percent saturated, they should be consid-
ered as saturated and designed accordingly.
In the absence of Proctor test facilities and when

Figure 6-35.-Alternative foundation design criteria for


Figure 6-34.-Foundation design criteria for relatively dry relatively dry fine-grained soils. Adapted from Gibbs
fine-grained soils. 288-D-2492. [37]. 288-D-2785.
EARTHFILL DAMS 237

dam located in south-central Nebraska in the cen- fore, the foundation in this area was thoroughly
ter of the Missouri River Basin loess area. As shown wetted by ponding and sprinkling before fill con-
on figure 6-36, dry low-unit weight loess occurred struction. Figure 6-37 shows the dikes and ponds
on the right abutment of this dam to maximum full of water; 33,000,OOO gallons of water were used
depths of 60 to 70 feet and an average depth of about over a 2-month period to raise the average water
40 feet. Undisturbed samples were secured by sink- content in the critical area to 28 percent.
ing a test pit at a representative location to a depth Settlement measuring points throughout the
of 50 feet. Table 6-4 summarizes partial results of ponded areas revealed that no settlement occurred
laboratory tests on these samples. These tests in- from saturation alone. Baseplate apparatus was in-
dicated a possibility of dangerous postconstruction stalled in the dam to permit measurement of foun-
settlement upon saturation by the reservoir if the dation settlement in four locations as the fill was
dam were constructed on the natural loess. There- constructed (BP1 to BP4 inclusive, fig. 6-36). The

NOTE
iI: 8 and BP= settlement
measuring plates

,/LIMITS OF PONDED AREA

U<C- ,c;2y\
\\ -CT25
RCHC
Right abut:: oT3* CT29 N -
200 200 400 600
---%J DH .!26
cutoff trench L-L--LA
ci30 SCALE OF FEET
EJ
____-- ____-pONDED AREA-__--- -_---___-__--_---_-__--4
2 -- ___-_ +-----p-------- ---
m-r &
2400

m
ii ,,LOESS~~
kL---m -P ,
, J- - -4r-
,? --- -I------
+(-J
u, / OGALLALA
/

-
2300 --C--!-s . i \ 1- .
I c--
<y A ,NIDBRARA CHALK AND SHALE
<a--d-ALLUVIUM ./I ,.*
2260 t I I I
I /

--- I I I
2260 - : 1
/.Limits -----Limits
of mom of right abutment j
cutoff trench------------- 3
2246~- cutoff trench
SEGTION ALONG DAM AXIS

Figure 6-36.-Geology of right abutment of Medicine Creek Dam. An earthfill structure on Medicine Creek in Nebraska.
288-D-2493.
238 DESIGN OF SMALL DAMS

Table 6-4.-Properties of loess in Medicine Creek Dam foundation.

Total Compression at
Approx- Natural Inplace load, total load,
imate water dry (fill plus %
sample content, unit over- With After
Average
depth, w,
Average
weight, D,
burden), natural being
ft % lb/in2
w o -wl Ib/ft3 %2 moisture wetted
5 8.8 7.4 79 75 25 8.4 10.9
17 9.7 6.5 77 74 33 1.3 9.1
19 9.6 6.6 81 77 34.5 1.0 3.9
50 6.6 8.7 92 83 55 1.5 6.5
lWo -w = optimum water content for Proctor maximum dry unit weight minus natural water content.

Figure 6-37.-Ponding on foundotion of Medicine Creek Dom. 404-12278.

foundation settlements recorded by the baseplate mid-1954, when measurements were discontinued.
installations are shown on figure 6-38. Upon com- The reservoir filled to elevation 2366.0 (normal
pletion of the embankment in the fall of 1949, the water surface) in the spring of 1951,and remained
apparatus indicated a foundation settlement of close to that elevation during the period of
from 0.41 to 0.66 foot. By mid-1952, the measured measurement.
foundation settlement ranged from a maximum of The amount of foundation settlement at Medi-
2 feet at BPI to 0.8 foot at BP4. There was virtually cine Creek Dam was appreciable, although less than
no further increase in the amount of settlement by had been anticipated. The foundation consolidation
EARTHFILL DAMS 239

treatment was successful, because, as shown on fig- over a 2-year period, which allowed the dam em-
ure 6-38, a large portion of the settlement took place bankment to undergo the deformation without
while the embankment was being constructed, and distress.
the subsequent settlement was a slow consolidation

D. EMBANKMENTS
6.14. Fundamental Considerations.-Essen- ment of methods that will afford a comprehensive
tially, designing an earthfill dam embankment pri- analysis of embankment stability. These methods
marily involves determining the cross section that, provide useful design tools, especially for major
when constructed with the available materials, will structures where the cost of detailed explorations
fulfill its required function with adequate safety at and laboratory testing of available construction ma-
a minimum cost. The designer of an earthfill dam terials can be justified on the basis of savings
cannot rely on the application of mathematical achieved through precise design. Even so, present
analyses or formulas to determine the required practice in determining the required cross section
cross section to the same degree that one can for a of an earthfill dam consists largely of designing to
concrete dam. Soils occur in infinite combinations the slopes and characteristics of existing successful
of size gradation, composition, and corresponding dams, making analytical and experimental studies
variations in behavior under different conditions of for unusual conditions, and controlling closely the
saturation and loading. In addition, the stress- selection and placement of embankment materials.
strain relationships in a soil embankment are very While some modifications are necessarily made in
complex. specific designs to adapt them to particular con-
Considerable progress has been made in inves- ditions, radical innovations are avoided and fun-
tigations and studies directed toward the develop- damental changes in design concepts are developed
and adopted gradually through practical experience
and trial.
Although the above practice may be criticized as
being overly cautious and extravagant, no better
method has been conclusively demonstrated. Where
consideration is given to the possible loss of life, to
the possibility of costly property damage, and to
the waste of money incidental to the failure of a
constructed dam, ample justification is provided for
conservative procedures. For small dams, where the
cost of explorations and laboratory testing of em-
bankment materials for analytical studies together
with the cost of the engineering constitutes an in-
ordinate proportion of the total cost of the struc-
ture, the practice of designing on the basis of
successful structures and past experience becomes
even more appropriate.
The design criteria for earthfill dams are pre-
sented in section 6.5. In regard to the embankment,
they require that the slopes of the embankment be
stable under all conditions of construction and res-
ervoir operation; that excessive stresses not be in-
OPERATION PERIOD+
duced in the foundation; that seepage through the
CONSTRUCTION PERIOD
embankment be controlled; that the embankment
Figure 6-38.-Record of loess foundation settlement at
be safe against overtopping; that the slopes be pro-
Medicine Creek Dam. 288-D-2494. tected against erosion; and that the embankment
240 DESIGN OF SMALL DAMS

be stable under appropriate seismic conditions. With these qualifications, the total normal com-
This part of the chapter is concerned with the slope pressive stress, o, along a plane in an earth struc-
stability of the embankment under both static and ture can be computed:
seismic conditions and with the control of seepage
through the embankment. Embankment details 0=0+CL (8)
concerning the crest, freeboard, slope protection,
where u is pore water pressure, and 5 is the effec-
and surface drainage are discussed in part E of this
tive normal compressive stress. From considera-
chapter.
tions of equilibrium [40], the formula for shear
The stability of an embankment is determined
stress, z, along the plane is:
by its ability to resist shear stresses, which can
cause failure by inducing sliding along a shear 01 - 03
surface. 7 = ___ sin 28
2
Shear stresses result from externally applied
where:
loads, such as reservoir and earthquake loads, and
cri = total major principal stress,
from internal forces caused by the weight of the soil
0, = total minor principal stress, and
and the embankment slopes. The external and in-
8 = angle between the plane considered and
ternal forces also produce compressive stresses nor-
the plane on which CJ,acts.
mal to potential sliding surfaces. These compressive
stresses contribute both to the shear strength of It is apparent from equation (9) that the shear
the soil and to the development of destabilizing pore stress is the same whether o, and o, or their ef-
water pressures. fective components, q and 6, are used.
Granular, or noncohesive, soils are more stable The shear strength along a plane can be obtained
than cohesive soils because granular materials have from Coulombs equation:
a higher frictional resistance and because their
s = c + (cr - u) tan # (10)
greater permeability permits rapid dissipation of
pore water pressures resulting from compressive Equation (10) shows that the frictional portion
forces. Accordingly, when other conditions permit, of the resistance along a plane is reduced by the
somewhat steeper slopes may be adopted for non- pore water pressure. This equation is discussed and
cohesive soils. Embankments of homogeneous ma- the terms are defined in section 5.18(b).
terials of relatively low permeability have slopes Pore water pressures in compacted cohesive soils
generally flatter than those used for zoned em- caused by compressive stresses occur in the sealed
bankments, which have free-draining outer zones triaxial shear test in the laboratory and in the im-
supporting inner zones of relatively impervious pervious zone of an embankment during construc-
materials. tion. For the laboratory conditions, the relation
In brief, the design of an earthfill dam cross sec- between volume change and fluid pressure in a
tion is controlled by the physical properties of the loaded soil mass consisting of solid particles, water,
materials available for construction, by the char- and air, can be ,derived by using Boyles law for
acter of the foundation, by the construction compressibility of air and Henrys law for solubility
methods specified, and by the degree of con- of air and water both-at constant temperature. For
struction control anticipated. a soil mass buried in an impervious fill where drain-
6.15. Pore Wafer Pressure.-In 1936, Terzaghi age is extremely slow because of the long path of
[39] demonstrated that in impervious soils sub- percolation and the very small coefficient of perme-
jected to load, a total stress normal to any plane is ability of the material, it is both conservative and
composed of an effective stress and a fluid pressure. reasonable, on the basis of field observations, to
The concepts of plane surfaces and stresses at a assume no drainage to estimate the magnitude of
point in soils are not identical with those of an ideal pore water pressure for design and control purposes
homogeneous isotropic material. The plane in [41]. The concept is that when the moist soil mass
soils is a rather wavy surface, touching the soil par- is loaded without permitting air or water to escape,
ticles only at their contacts with one another, and part of the load causes the soil grains to deform
the point of stress is a small region containing elastically or to undergo nonelastic rearrangement,
enough of the particles to obtain an average stress. but without significant change in their solid vol-
EARTHFILL DAMS 241

ume. This part of the load is carried on the soil lGreater permeability in the embankment core
skeleton as effective stress. The remainder of the lExcessive softening and settlement after sat-
load is carried by stress in the air and water con- uration by the reservoir, resulting in possible
tained in the voids and is known as pore water cracking of the fill
pressure. On the other hand, the moisture content should
Analysis shows that the magnitude of pore water not be appreciably greater than the optimum ob-
pressures from compressive forces depends on the tained at Proctor maximum dry unit weight because
compressibility of the compacted soil and on the difficulties have been experienced with unstable
amount of air it contains. For given conditions of fills when very wet soils are used, even in small
compressibility and loading, the closer the com- dams.
pacted soil is to saturation, the higher the pore The foregoing considerations result in the rec-
water pressure will be. This leads to the practice of ommended practice of compacting cohesive soils in
controlling the moisture content of materials to in- the cores of small dams close to their optimum
crease the amount of air in the compacted soil. Bu- moisture content at Proctor maximum dry unit
reau practice has been to reduce the moisture weight.
content below optimum for compaction at Proctor 6.16. Seepage Through Embankments.--ahe
maximum unit weight in the construction of high core, or water barrier portion, of an earthfill dam
earthfill dams. However, this procedure is neither provides the resistance to seepage that contains the
necessary nor desirable for the construction of em- reservoir. Although soils vary greatly in permea-
bankments less than 50 feet high. For such heights, bility, as pointed out in section 5.18(c), even the
compaction of cohesive soils at optimum moisture tightest clays are porous and cannot prevent water
content and approximately Proctor maximum dry from seeping through them.
unit weight ensures enough air, even in the most The progress of percolation of reservoir water
compressible soils, to preclude the development of through the core depends on the constancy of the
significant pore water pressures. reservoir level, the magnitudes of permeability of
Placing the material at optimum moisture con- the core material in the horizontal and vertical di-
tent instead of drier than optimum also increases rections (anisotropy), the amount of remaining pore
the plasticity of the material and allows it to con- water pressures caused by compressive forces dur-
form more readily to the shape of the foundation ing construction, and time. Figure 6-39 shows the
and abutments during postconstruction settlement. penetration of water into a core shortly after the
It also helps reduce the probability of tension cracks first filling of the reservoir and the penetration
in the embankment. when the steady-state seepage condition has finally
For small confining loads, placing material drier been reached. The upper surface of seepage is called
than optimum is undesirable because it increases the phreatic (zero pressure) surface; in a cross sec-
the possibility of: tion it is referred to as the phreatic line. Although
l Low unit weight for the same compactive ef- the soil may be saturated by capillarity above this
fort, as shown by the shape of the compaction line, giving rise to a line of saturation, seepage is
curve (fig. 5-74) limited to the portion below the phreatic line.

,.-blormal water surface


,,--Steady-state phreatic line

Phreotlc line prior ,,I' --Intermediate-state


phreotic line
to reservoir filling--'

&.---*-- -Impervious foundation---*'

Figure 6-39.-Position of phreotic line in a zoned embankment. 288-D-2495.


242 DESIGN OF SMALL DAMS

The position of the phreatic line depends only drawdown on the pore water pressures measured in
on the geometry of the section and anisotropy of Alcova Dam, Wyoming. The reservoir water surface
the soils. For soils with vastly different permeabil- was lowered 120 feet in 40 days, an extremely rapid
ities but with the same ratio of horizontal to vertical drawdown for a dam of this height. Figure 6-40(A)
permeability, the phreatic lines eventually will shows the phreatic line and equal-pressure lines un-
reach identical position. It will take much longer der full reservoir conditions; the position of the
for the steady-state condition to be reached in clay phreatic line indicates that virtually steady-state
than in sand for the same cross section, and the conditions were present before drawdown. Figure 6-
amount of water emerging at the downstream slope 40(B) shows the pressures under drawdown
will, of course, be much greater for the more per- conditions.
vious material. The pore water pressures below the Figure 6-40 demonstrates that appreciable pore
phreatic line reduce the shear strength of the soil water pressures remain in an embankment after
mass in accordance with Coulombs law, equation drawdown. If a dam is subject to rapid drawdown
(10). The steady-state condition that involves the after long-term storage at high reservoir levels, spe-
maximum saturation of the embankment is the cial provisions for drainage should be made in the
most critical postconstruction condition for the sta- design. The upstream slope of an embankment with
bility of the downstream slope. an appreciable upstream pervious zone usually is
The most critical operating condition so far as not critical for the rapid drawdown condition. Rapid
the stability of the upstream slope is concerned is drawdown may require a flatter slope of a homo-
a rapid drawdown after a long period of high res- geneous embankment than would otherwise be
ervoir level. Figure 6-40 shows the effect of rapid needed for stability.

Eouol pressre

Rock riprap- -...

Note Pressures measured


(A) STEADY STATE CONDITION in feet of water

Equal pressure I~nes--- _


Phreotlc Ihne--.

(I31 RAPID DRAWDOWN CONDITION

Figure 6-40.-Effect of rapid drawdown on pore pressures. Alcova Dam, an earthfill structure
on the North Platte River in Wyoming. 288-D-2496.
EARTHFILL DAMS 243

The use of the flow net in determining the mag- U = summation of uplift forces caused by
nitude and distribution of seepage pressures in per- pore water pressure along the arc,
vious foundations has been described previously T = algebraic summation of tangential
(sec. 6.9(c)). The flow net can also be used to vis- forces along the arc,
ualize the flow pattern of percolating water through L = length of arc of slip circle,
embankments to estimate the magnitude and dis- c = effective cohesion intercept, and
tribution of pressures from percolating water, both $ = effective angle of internal friction.
in the steady state and in the drawdown condition.
Analytical methods of stability analyses used in the Various centers and radii are used, and compu-
design of major structures require that such pore tations are repeated until the arc that gives the min-
water pressures be determined quantitatively. Such imum safety factor is established.
a determination is not required for the design pro- To compute the safety factor by means of equa-
cedure given in this text. tion (ll), it is necessary to establish the cohesion,
6.17. Stability Analyses.-Various methods c, and the angle of internal friction, $, of the soil
have been proposed for computing the stability of and the magnitude of pore water pressures for con-
earthfill dams [6]. In general, these methods are struction, steady-state, and drawdown conditions.
based on the shear strength of the soil and certain Furthermore, the strength properties of the foun-
assumptions with respect to the character of an em- dation must be determined where the overburden
bankment failure. The Swedish, or slip-circle, above bedrock is silt or clay, because experience has
method, which supposes the surface of rupture to shown that the critical circle extends into the foun-
be a cylindrical surface, is a comparatively simple dation in such cases. It is therefore apparent that
method of analyzing embankment stability. Al- this method of analysis is more suited to the design
though other more strictly mathematical solutions of major structures, where the cost of foundation
have been developed, the slip-circle method of sta- exploration and laboratory tests of foundation and
bility analysis is generally adequate for small dams. embankment materials to determine their average
In this method, the factor of safety against sliding strength properties is justified because of the sav-
is defined as the ratio of the average shear strength, ings that may be achieved by the use of more precise
as determined from equation (lo), to the average slopes. The recommended designs for small earthfill
shear stress determined by statics on a potential dams given in this text are based on the Swedish
sliding surface. If there are weak lines or segments, slip-circle method, using average values of soil prop-
such as weak foundation layers, failure surfaces in- erties and experience for static conditions usually
volving these segments should be checked. encountered in seismically inactive regions. These
The force exerted by any segment within the slip designs will result in adequate safety factors pro-
circle is equal to the weight of the segment and acts vided proper construction control is obtained. Con-
vertically downward through its center of gravity. struction control is discussed in appendix E of this
The components of this weight acting on a portion manual. For an in-depth discussion on static sta-
of the circle are the force normal to the arc and the bility analyses refer to USBR Design Standards No.
force tangent to the arc, as determined by com- 13, chapter 4.
pleting the force triangle with lines in the radial With the availability of high-speed digital com-
and tangential directions. Pore water pressures act- puters, it is now possible to use more mathemati-
ing on the arc result in an uplift force, which reduces cally complex solution procedures for slope stability
the normal component of the weight of the segment. analyses [43]. These procedures are not restricted
Graphical means have been developed by May [42] to cylindrical slip surfaces, but can be applied to
to facilitate the solution. practically any kinematically admissible slip-
The safety factor against sliding for an assumed surface geometry. One such method commonly used
circle is computed by the equation: is the method of slices proposed by Spencer [44].
In this method, the slide mass is divided into a
Safety factor = cL + tan $ (N - U) (11)
number of slices. The magnitude and orientation of
T forces acting on the interslice boundaries are con-
where: sidered, and the safety factor and interslice force
N = summation of normal forces along the inclination are obtained by satisfying the three
arc, equations of planar static equilibrium of each slice.
244 DESIGN OF SMALL DAMS

This procedure has been written into a computer struction operations. The construction sequence is,
program [45] for static and dynamic slope-stability in turn, influenced by the follwing items:
analyses. This computer program is commonly used l Topography of the damsite
for slope-stability calculations. l Diversion requirements
6.18. Embankment Design.-(a) Use of Mate- l Hydrology of the watershed
rials from Structural Excavation.--In the discussion l Seasonal climate changes
of design criteria (sec. 6.5), it was pointed out that l Magnitude of required excavations
for minimum cost, the dam must be designed to To use material from the spillway or cutoff
make maximum use of the most economical ma- trench in the embankments without havinrg to
terials available, including the materials excavated stockpile and later rehandle large quantities of
for the dam foundation, spillway, outlet works, ca- earth and rock, an adequate placing area musit be
nals, powerhouse, roadways, and other appurtenant available. The placing area is usually restricted
structures. When the yardage from these sources early in the job; hence, the designer must decide
constitutes an appreciable portion of the total em- whether to specify that spillway excavation be de-
bankment volume, it may strongly influence the de- layed until space is available for it, or to require
sign of the dam. Although these materials are often extensive stockpiling, or to permit large quantities
less desirable than soil from available borrow areas, of material to be wasted. The amount of embank-
economy requires that they be used to the maximum ment space that can be provided during the early
practicable extent. Available borrow areas and stages of construction depends in part on the di-
structural excavations must both be considered to version requirements and in part on the divemion
arrive at a suitable design. plan that the contractor selects. Usually, the con-
The portion of the cutoff trench excavation tractor is allowed considerable flexibility in the
above the ground-water table may provide limited method of diversion; this adds to the designers un-
amounts of material for the impervious core of the certainty in planning the use of materials from
dam. Appreciable quantities of sand and gravel are structutural excavations.
usually obtained in the dewatered portion of the Zoned dams provide an opportunity to use struc-
trench from the strata intercepted. When sand and tural excavation materials. This type of dam should
gravel occur in thick, clean beds, this material can be used whenever possible. The zoning of the em-
be used in the outer zones of the dam. However, bankment should be based on the most economlical
pockets or lenses of silt and clay and highly organic use of materials that can be devised; however, the
material may also be excavated with the cutoff zoning must be consistent with the requirements
trench. These materials contaminate the clean soils for stability discussed in section 6.17. For example,
and result in wet mixtures of variable permeability the use of rockfill sections can allow continual con-
and poor workability. Such mixtures should usually struction throughout the winter, thus effecting an
be wasted. early completion date. An important use of m#ate-
Excavation for the spillway provides both over- rials from structural excavation has been in por-
burden soils and formation bedrock. In planning the tions of the embankment where the permeability
use of these materials, the designer must recognize and shear strength are not critical and where weight
that moisture control, processing, and meeting spe- and bulk are the major requirements. The stabiliz-
cial size requirements will add to the project cost. ing fills required for dams on saturated fine-grained
For this reason, material from spillway excavations foundations, discussed in section 6.13 (fig. 6-33), are
is ordinarily used primarily in the main structural an illustration of this usage.
zones of dam embankments where special control Areas within the dam into which such excavated
of moisture and processing are not as critical. material is placed are called random zones: Qpical
Tunnel excavations can provide rockfill material locations for these random zones are shown on fig-
for use in the pervious zones of the dam or can ure 6-41.
provide rock fines that may serve as a transition Because estimates of the percentage of structural
between the impervious core material and pervious excavations usable within the embankment are sub-
zones. ject to significant error, provision should be made
The feasibility of using materials from structural to use variable zone boundaries to accommodate
excavations is influenced by the sequence of con- any excess or deficiency. In some cases, special lab-
EARTHFILL DAMS 245

oratory tests or a test embankment may be required and for visualizing the construction sequence. The
before determining the disposition of questionable chart shown is for the Bureau of Reclamations San
material or selecting the dimensions of a random J&o Dike, the maximum section of which is shown
zone. on figure 6-87. In addition to showing the sources
In formulating a design, the designer must es- of all fill materials, the chart contains the assump-
timate the percentage of structural excavation that tions used for shrinkage, swell, and yield on which
will be suitable in the various zones of the em- specifications quantities are based.
bankment and the shrinkage and swell of the ma- (b) Embankment Slopes, General.-The design
terial involved. The designer must then integrate slopes of an embankment may vary significantly
these estimated quantities with the required borrow depending on the character of the materials avail-
area quantities to determine a final design that is able for construction, foundation conditions, and
both economical and has a reasonable constuction the height of the structure. The embankment
sequence. Often, several design schemes are re- slopes, as determined in this section, are the slopes
quired. The use of a materials distribution chart, required for stability of the embankment on a stable
such as that shown on figure 6-42, has been found foundation. For stability against seepage forces,
helpful for integrating excavation quantities into pervious foundations may require the addition of
the embankment section for determining the upstream blankets to reduce the amount of seepage
amounts of borrow material required for each zone or the addition of downstream inclined and hori-
zontal filter-drainage blankets. Weak foundations
may require the addition of stabilizing fills at either
or both toes of the dam. The additional embank-
ments needed because of pervious or weak foun-
Random moterial placed on a flat dations should be provided beyond the slopes
slope to ellminote slope protection
determined herein as required for embankment sta-
(A)
bility. The following procedures should be used with
simple, straightforward gedlogic conditions and
trouble-free embankment materials. If more com-
plicated conditions exist, the dam should be ana-
lyzed by an experienced embankment dam designer
using appropriate analytical techniques.
Random material used os toe
The upstream slope may vary from 2:l to as flat
support to improve stobility
(B)
as 4:l for stability; usually it is 2.5:1 or 3:l. Flat
upstream slopes are sometimes used to eliminate
expensive slope protection. A berm is often pro-
vided at an elevation slightly below the maximum
drawdown of the reservoir water surface to form a
base for the upstream slope protection, which need
not be carried below this point. The upstream slope
Random moteriol buried in the supporting shell is often steepened above the elevation where water
(Cl is stored; that is, in the surcharge range.
A storage dam subject to rapid drawdown of the
reservoir should have an upstream zone with perme-
ability sufficient to dissipate pore water pressures
exerted outwardly in the upstream part of the dam.
The rate of reservoir drawdown is important to the
stability of the upstream part of the dam. For a
Rondom moteriol used OS a transition zone
(D)
method of designing free-draining upstream shells,
refer to Cedergren [46]. Where only fine material
Figure 6-41 .-locations of random zones of fill materials
of low permeability is available, such as that pre-
within embankment sections. 288-D-2787. dominating in clays, it is necessary to provide a flat
246 DESIGN OF SMALL DAMS

slope if rapid drawdown is a design requirement. construction equipment. Because it must hold back
Conversely, if free-draining sand and gravel are the full reservoir pressure, it must be constructed
available to provide a superimposed weight for hold- carefully. To prevent piping or erosion, the dia-
ing down the fine material of low permeability, a phragm must be protected by graded filters meeting
steeper slope may be used. The same result may be criteria listed in section 6:10(i). When an earth dia-
secured by using sound and durable rock from re- phragm is centrally located, it is also referred to as
quired excavations. In the latter case, a layer of sand a thin core. An earth diaphragm constructed for
and gravel or quarry fines must be placed between Amarillo Regulating Reservoir is shown on figure
the superimposed rock and the surface of the im- 6-58.
pervious embankment to prevent damage and dis- Diaphragm-type dams are generally used under
placement from saturation and wave action. the following conditions:
Flood damage caused by the failure of the up- l A limited quantity of impervious material is
stream face is unlikely. Such a failure can occur available
only during construction or after a rapid drawdown; l Wet climatic conditions
in both cases, the reservoir should be virtually l Short construction seasons
empty. The weight of water and seepage forces act A diaphragm should be used only when the de-
as a stabilizing influence on the upstream face when sign and construction of the dam are performed
the reservoir is full. under the supervision of an experienced earth dam
The usual downstream slopes for small earthfill designer. If this type of dam is selected, it is rec-
dams are 2:l where a downstream pervious zone is ommended that a diaphragm of manufactured ma-
provided in the embankment, and 2.5:1 where the terial be placed on the upstream slope of an
embankment is impervious. These slopes are stable otherwise pervious embankment in lieu of a soil
for soil types commonly used when drainage is pro- blanket. If the pervious material is rock, the dam
vided in the design, so that the downstream slope is classified as a rockfill dam, the design of which
of the embankment does not become saturated by is discussed in chapter 7.
seepage. The pervious material used in the construction
The slopes of an earthfill dam depend on the type of a diaphragm dam must be such that it can be
of dam (i.e., diaphragm, modified homogeneous, or compacted to form a stable embankment that will
zoned embankment) and on the nature of the ma- be subject to only small amounts of postconstruc-
terials for construction. Of special importance is the tion settlement. Poorly graded sands (SP) cannot
nature of the soil that will be used for construction be satisfactorily compacted; well-graded sand-
of a modified homogeneous dam or of the core of a gravel mixtures (SW-GW) or well-graded gravels
zoned dam. In the latter case, the relation of the (GW) make satisfactory embankments. Well-
size of the core to the size of the shell is also graded sand-gravel mixtures that contain more than
significant. 5 percent of material finer than the No. 200 sieve
In this text, the slopes of the embankment are should be tested to determine whether they will
related to the classification of the soil to be used form free-draining embankments after compaction.
for construction, especially the impervious soils. Zones downstream of the diaphragm should be de-
The engineering properties of soils in the various signed in accordance with the filter criteria listed
classifications are shown in table 5-l. The slopes in section 6.10(i).
chosen are necessarily conservative and are rec- In all respects, except for the use of pervious
ommended only for small earthfill dams within the materials other than rock in construction of the
scope of this text, as discussed in section 6.2. embankment, the diaphragm earthfill dam design
(c) Diaphragm Type.-A diaphragm dam con- as recommended herein for small dams is identical
sists of a thin impervious water barrier used in con- with the design of rockfill dams, which is discussed
juction with a large pervious zone. The diaphragm in chapter 7. That discussion should be referred to
can be constructed of earth, asphalt, concrete, or for the design of foundations and upstream facings
metal. If the diaphragm is constructed of imper- for a diaphragm earthfill dam.
vious earth material, it must have a horizontal (d) Homogeneous ripe.-The homogeneous-
thickness at least great enough to accommodate type dam is recommended only where the lack of
EARTHFILL DAMS 249

free-draining materials make the construction of a placed at the outer slopes to approach, as much as
zoned embankment uneconomical, with the further possible, the advantages of zoned embankment. It
qualification that for storage dams the homogene- is also important to avoid segregation of the larger
ous dam must be modified to include internal drain- particles when the fill is dumped. Segregation leads
age facilities. The recommended drainage facilities to the formation of layers of much greater perme-
for modified homogeneous dams are described in ability than the other embankment; these layers
section 6.3 and are shown on figure 6-5. If a rockfill tend to form drainage channels for the percolating
toe is provided, a filter must be constructed between water and to increase the possibility of piping.
the embankment proper and the rockfill toe, as Because of the possibility of oversights during
shown on figure 6-5(A). This filter and the hori- construction and of cracking, dispersive soil, etc.,
zontal and inclined drainage blanket shown on fig- as discussed previously, consideration should be
ure 6-5(B) and 6-5(C) should be designed to meet given to providing an inclined filter-drain to inter-
the filter requirements described in section 6.10(i). cept any seepage along defects in the embankment.
To perform its function of lowering the phreatic The recommended slopes for small homogeneous
line and stabilizing the downstream portion of the earthfill dams are shown in table 6-5 for detention
dam, the horizontal drainage blanket shown on fig- and storage dams on stable foundations with and
ure 6-5(B) should extend from the downstream without rapid drawdown as a design condition.
slope of the dam to well within the body of the Where more than one soil classification is shown
embankment. However, it should not e+end up- for a set of slopes, the table indicates that, the dam
stream so far as to reduce the length of the path of can be constructed to the slopes shown by using
percolation through the embankment or through any of the soils or combinations thereof.
the foundation to a dangerous extent. A minimum- (e) Zoned Embankments.-(l) Gene&.-The
length filter blanket is also desirable because filters zoned embankment dam consists of a central im-
are expensive to construct. For small dams, it is pervious core flanked by zones of material that are
recommended that the horizontal drainage blanket considerably more pervious. An excellent example
start at the downstream toe of the embankment and of a zoned dam from the 1950 era is Carter Lake
extend upstream to within a distance equal to the Dam No. 3 (fig. 6-63). An excellent example from
height of the dam plus 5 feet from the centerline a more recent era is Ute Dam Dike (fig. 6-86). This
of the dam. This will afford an ample blanket, yet type of embankment should always be constructed
keep the length of the path of percolation within where there is a variety of soils readily available
desirable limits. The distance of height of dam plus because its inherent advantages lead to savings in
5 feet is selected on the basis that this will place the costs of construction. Three major advantages
the upstream limit of the horizontal drainage blan- in using zoned embankments are listed below.
ket at the downstream edge of minimum core B, l Steeper slopes may be used with consequent
that required for dams on deep pervious founda- reduction in total volume of embankment
tions without positive cutoff trenches, as shown on materials
figure 6-43. l A wide variety of materials may be used
The horizontal drainage blanket should be car- l Maximum use can be made of material exca-
ried across the valley floor and up the abutments vated from the foundation, spillway, outlet
to an elevation corresponding to the highest level works, and other appurtenant structures.
at which water will be stored in the reservoir for an (2) Zoning.-All zoning schemes are based on
appreciable time. It should be a uniformly thick the estimated quantities of required excavation and
blanket whose upstream position at a given point of borrow area materials available. The zoning
is downstream from the centerline of the dam a scheme may divide the dam into two or more zones,
distance equal to the height of the dam at that point depending on the range of variation in the character
plus 5 feet. and gradation of the materials available for con-
Even in the construction of a homogeneous em- struction. In general, the permeability of each zone
bankment, there is likely to be some variation in should increase toward the outer slopes.
the nature of the borrow material. It is important Relatively free-draining materials and, therefore,
that the coarse and more pervious material be those with a high degree of inherent stability are
250 DESIGN OF SMALL DAMS

EXPLANATION

Maximum core.

MInImum care 0, far dams on deep pervlaus


foundations without posltlve cutoff trench

Minimum core A, for dams on lmperwous


foundations or shallow pervious foundations
with pasltlve cutoff trench.

E of dam

\
Jo StrippIng----*
OrIginal ground surface

Figure 6-43.-Size range of impervious cores used in zoned embankments. 288-D-2497.

Table 6-5.-Recommended slopes for small homogeneous earthtill dams on stable foundations.

Subject to Soil Upstream Downstream


Case Purpose rapid drawdown classification* slope slope

GW,GP,SW,SP Pervious, unsuitable


Detention
A Homogeneous or
or No GC,GM,SC,SM 2.5:1 2:l
modified-homogeneous
storage CL,ML 3:l 2.5:1
CH,MH 3.5:1 2.5:1

GW,GP,SW,SP Pervious, unsuitable

B Modified-homogeneous Storage Yes GC,GM,SC,SM 3:l 2:l


CL,ML 3.5:1 2.5:1
CH,MH 4:l 2.5:1
Drawdown rates of 6 inches or more per day after prolonged storage at high reservoir levels.
*OL and OH soils are not recommended for major portions of homogeneous earthfill dams. Pt soils are unsuitable.

used to enclose and support the less stable imper- stream sections to permit dissipation of pressure on
vious core. Pervious materials are placed in the rapid drawdown.
downstream sections to avoid building up pressure Miscellaneous, or random, zones (fig. 6-41) are
from percolating water and to permit lowering the often included in the downstream sections of the
phreatic line so as to keep it well within the em- embankment to use excavated materials having un-
bankment. Pervious materials are placed in up- certain permeability. Excavated materials unsuit-
EARTHFILL DAMS

able for use in any zone and excess excavation may imum that will permit economical placement and
be wasted on the upstream or downstream toes. compaction of impervious embankment material by
Section 6.18(a) discusses the use of excavated ma- construction equipment such as trucks, dozers, and
terial more fully. tamping rollers. The criterion that the thickness of
(3) Duns&ions.-It is important that the gra- the core at any elevation be at least as great as the
dation of adjacent zones be considered so that ma- height of embankment above that elevation was
terials from one zone are not piped into the voids adopted so that the average hydraulic gradient
of adjoining zones, either by steady-state or by though the core would be less than unity. Appre-
drawdown seepage forces. Transitions prevent pip- ciably steeper gradients may result in high seepage
ing and also provide the additional advantage that forces and the necessity for construction of high-
should the embankment crack, partial sealing of the quality filter zones, which for small dams may not
cracks takes place with subsequent reduction in be economical nor practicable from a construction
seepage losses. control standpoint. It should be noted, however,
A transition of sand-gravel or rock fines must be that even for wide cores, the downstream zones
provided between an impervious zone and an ad- should meet the filter criteria in section 6.10(i). Fur-
jacent rockfill. Although these transitions need only thermore, if the core were thinner, there would be
be a few feet wide, they are usually constructed from more danger that it could be ruptured by differential
8 to 12 feet wide to accommodate construction settlement of the foundation.
equipment. Minimum core B for dams on pervious founda-
The transition zone should be designed in ac- tions (fig. 6-43) is based on consideration of seepage
cordance with the filter criteria listed in section pressures in the foundation. The minimum core ap-
6.10(i) or an inclined blanket meeting the criteria plies to dams constructed on exposed deep pervious
provided. Transition zones are not always required foundations (Case 1) or on covered deep pervious
between impervious and sand-gravel zones or be- foundations (Case 2) when the cover is 3 feet or less
tween sand-gravel zones and rockfill, but the filter (see sec. 6.11(a)). It does not apply if the pervious
criteria (sec. 6.10(i)) should be met between these foundations are covered by an impervious layer
zones. more than 3 feet thick.
(4) Impervious Cores for Zoned Embankmentc- If a positive cutoff trench is not provided in the
Figure 6-43 shows the suggested size of the min- design, it must be anticipated that regardless of
imum core for the following two conditions: what other type of device is used to control seepage,
l Impervious or pervious foundations of shallow the loss of head through the foundation will be rel-
depth penetrated by a positive cutoff trench. atively gradual and proportional to the length of
This core is hereinafter referred to as minimum the seepage path. The minimum length of path sug-
core A. gested for use with deep pervious foundations to
l Exposed pervious foundations and covered per- reduce the seepage pressure sufficiently is that pro-
vious foundations (~3 ft of cover) not pene- vided by an impervious zone whose thickness at the
trated by a positive cutoff trench regardless of contact of the dam with the foundation is at least
the depth of pervious material. This core is 2% times the height of the dam. Such an impervious
hereinafter referred to as minimum core B. zone avoids the possibility of seepage passing under
The maximum size impervious core that allows the core of the dam without an appreciable loss of
the dam to function as a zoned embankment is also head because of the ineffectiveness of sheet piling,
shown on figure 6-43. partial cutoff trench, etc., or because no such device
If the core is smaller than minimum core A, the is provided. Minimum core B, shown on figure 6-
dam is considered to be of the diaphragm type; if 43 for a dam on a pervious foundation, meets these
the core is larger than the maximum size shown, requirements and should be used for all Case 1 (ex-
the pervious zones are largely ineffective in stabi- posed pervious foundations) and for Case 2 (covered
lizing the core, and the embankment may be con- pervious foundations) having 3 feet or less of cover
sidered as the homogeneous type so far as stability for which positive cutoff trenches are not provided.
is concerned. If the covered pervious foundation has an im-
The size of minimum core A shown on figure pervious layer thickness greater than 3 feet yet less
6-43 was selected for both practical and theoretical than the reser.voir head, the size of the core selected
reasons. The width of 10 feet was taken as the min- should depend on the designers judgment of the
252 DESIGN OF SMALL DAMS

effectiveness of the natural upstream blanket. In and with maximum core. The assumption is made
general, minimum core A (fig. 6-43) should provide that the foundation is stable; if the foundation is
a sufficient thickness of core material for use with of the saturated fine-grained type, stabilizing fills,
a natural impervious blanket of this depth. as described in section 6.13, should be added. Slopes
If the thickness of the impervious cover is greater of small zoned earthfill dams with cores of inter-
than the reservoir head, the foundation may be con- mediate size (including minimum core B for dams
sidered deep and the embankment should be de- on pervious foundations) fall between those given
signed to use stabilizing fills as described in section in the table for minimum core A and for the max-
6.13(a) and as shown on figure 6-33 for saturated imum size core.
fine-grained foundations. Minimum core A should Where only one slope is shown for more than
provide sufficient core thickness for this type foun- one soil classification, it indicates that the em-
dation condition. bankment can be constructed using any of the soils
With minimum core A centrally located, as or any combination thereof.
shown on figure 6-43, the stability of the zoned em- The following example illustrates the procedure:
bankment is not greatly affected by the nature of
Example
the soil in the core. The outside slopes are governed
Required:
largely by the stability of the shell material. Rock,
Upstream and downstream slopes for a zoned
well-graded gravels (GW), and poorly graded grav-
earthfill storage dam, 50 feet high, on a stable
els (GP) provide suitable material for the shell.
foundation subject to rapid drawdown.
Well-graded sand (SW) and poorly graded sand
(SP) are suitable if they are gravelly. For any of Given:
these shell materials, assuming adequate founda- Foundation = shallow, exposed, and pervious.
tion strengths, upstream and downstream slopes of Shell material = SW and SP, both gravelly.
2:l are stable for dams not more than 50 feet higher Core material = CL.
than the lowest point in the streambed, even if sub- Solution:
ject to rapid drawdown. Because the foundation is shallow and a positive
(5) Embankment Slopes.-Table 6-6 shows the cutoff trench can be constructed, minimum core
recommended upstream and downstream slopes for A should be used. From table 6-6, select upstream
small zoned earthfill dams with minimum core A and downstream slopes of 2:l.

Table 6-6.-Recommended slopes for small zoned earthfill dams on stable foundations.

Subject to rapid Shell material Core material Upstream Downstream


Me Purpose drawdown classification classification3 slope slope

Zoned with Rockfill, GW, GP, GC, GM, SC,


minimum Any Not critical4 SW (gravelly), SM, CL, ML, 2:l 2:l
core A or SP (gravelly) CH, or MH

Zoned with Rockfill, GW, GP, GC, GM 2:l 2:l


maximum Detention or SW (gravelly), SC, SM 2.25:1 2.25:1
No
core1 storage or SP (gravelly) CL, ML 2.5:1 2.5:1
CH, MH 3:l 3:l

Zoned with Rockfill, GW, GP, GC, GM 2.5:1 2:l


maximum SW (gravelly), SC, SM 2.5:1 2.25:1
Storage Yes
core1 or SP (gravelly) CL, ML 3:l 2.5:1
CH, MH 3.5:1 3:l
Minimum and maximum size cores are as shown on figure 6-43.
2Rapid drawdown is 6 inches or more per day after prolonged storage at high reservoir levels.
30L and OH soils are not recommended for major portions of the cores of earthfill dams. Pt soils are unsuitable.
4Rapid drawdown will not affect the upstream slope of a zoned embankment that has a large upstream pervious shell.
EARTHFILL DAMS 253

6.19. Seismic Design.-The design and construc- earthquakes, the damsite should be inspected by an ex-
tion practices for small earth dams presented herein perienced engineering geologist to determine whether
are considered adequate in areas of low seismicity, and faults or detrimental geologic formations could affect
the safety factors used should preclude major damage the location of the dam, reservoir, or appurtenant
for all but the most catastrophic earthquakes. structures. If active faults, unstable alluvial founda-
Although all damsites are subject to earthquake ac- tions, or the possibility of massive landslides into the
tivity, the probability of an earthquake is greater in reservoir exist, the damsite should be relocated. In gen-
some regions than in others. This probability is gener- eral, the designer should assume that a dam within a
ally determined by the number of previous earthquakes seismic zone will be shaken by an earthquake.
in that region and their intensity. In some cases, maps If foundations consisting of low relative density
have been prepared that delineate certain areas having sands and silts (sec. 6.9) or uniform, fine-grained, cohe-
greater earthquake potential. One such seismic risk sionless materials are encountered, serious damage
map is shown on figure 6-44. This map, adapted from may result to the structure during an earthquake, and
Algermissen [47], uses the information collected and the assistance of an experienced dam designer is re-
abstracted for approximately 28,000 earthquakes in the quired. If an active fault exists at the proposed damsite,
conterminous United States. If the designer is uncer- the designs proposed herein are inadequate.
tain about the prospects of an earthquake in any area, Additional considerations concerning seismic de-
a competent geologist or seismologist should be sign for earth dams are contained in [6, 48, 49, 50, 51,
consulted. 531. USBR Design Standards No. 13, chapter 13,
After determining that the region is subject to gives the Bureau criteria for seismic design.

E. EMBANKMENT DETAILS

6.20. Crest Design.-(a) General.-In design- rule, determined empirically and largely by prece-
ing the crest of an earthfill dam, the following items dent. The following formula is suggested for the
should be considered: determination of crest width for small earthfill
l Width dams:
l Drainage
Camber
w=r+10 (12)
l
5
l Surfacing where:
l Safety requirements w = width of crest, in feet, and
l Zoning z = height of dam, in feet, above the
In addition, suitable parking areas should be pro- streambed.
vided at the abutments of the dam for the conven- For ease of construction with power equipment,
ience of visitors and others, especially for a storage the minimum width should be at least 12 feet. For
dam whose lake will be used for recreational pur- many dams, the minimum crest width is determined
poses. A turnaround should be provided where ve- by the requirements for the roadway over the dam.
hicular traffic is permitted on a dam crest that dead (c) Drainage.-Surface drainage of the crest
ends at the opposite abutment. should be provided by a crown of at least 3 inches,
(b) Width.-The crest width of an earthfill dam or by sloping the crest to drain toward the upstream
depends on considerations such as (1) nature of em- slope. The latter method is preferred unless the
bankment materials and minimum allowable per- downstream slope is protected against erosion.
colation distance through the embankment at (d) Camber.-Camber is ordinarily provided
normal reservoir water level, (2) height and impor- along the crest of earthfill dams to ensure that the
tance of structure, (3) possible roadway require- freeboard will not be diminished by foundation set-
ments, and (4) practicability of construction. The tlement or embankment consolidation. Selection of
minimum crest width should provide a safe seepage the amount of camber is necessarily somewhat ar-
gradient through the embankment at the level of bitrary. It is based on the amount of foundation
the full reservoir. Because of practical difficulties settlement and embankment consolidation ex-
in determining this factor, the crest width is, as a pected for the dam, with the objective of providing
-- r'-r.'

i
----c t-----
I i -
c---.,,
II r

I I
2/mf i
8

SEISMIC RISK MAP OF THE UNITED STATES

ZONE O-No dammga

ZONE 1-Ylnor damage: dla1ant earthquake maY c~u#.

damage to l tructuroa rlth fundmmontal period*


g,..t.r than 1.0 l .cond: corr.eponda to Intan,ltl.g
V and VI of the Y.Y. l Sc.l..

ZONE 2-Moderet* damage: corrwponde to IntenaltY


VII of tha Y.Y. Scala.

ZONE J-Major damago: corraapond* to Intonnlty


VII o, the Y.Y. Seal.

ZONE 4-Theme .r... rlthln Zen. No. 3 d.1.rmln.d bY


the proxlmlty to cortaln major twit l Yetom*.

l Yodltl.d Y.rclll IntoMltY 8)cal. tg31

Taken from the Uniform BulldIng Code 1902

Figure 6-44.-Seismic risk map of the conterminous United States. 103-D-1830.


EARTHFILL DAMS 255

enough extra height so that some residual camber (g) Zoning. -Incorrect zoning of materials at the
will remain after settlement and consolidation. This crest leads to poor construction control, lost time,
residual camber also improves the appearance of and possibly local failure of the crest.
the crest. For both homogeneous and zoned dams, the
Impervious embankment materials placed at manner in which the slope protection and bedding
densities roughly corresponding to the Proctor lab- will intersect the crest must be considered. The
oratory maximum consolidate appreciably when thickness of the slope protection may have to be
subject to overlying fill loads. It is expected that reduced by steepening the slopes near the crest to
the major portion of this consolidation will take allow construction of the impervious or pervious
place during construction before the embankment zones or to facilitate the installation of guard posts.
is completed; therefore, the expected foundation Care must be taken that the remaining slope pro-
settlement is the more important factor. For dams tection will adequately resist the wave action. In
on relatively noncompressible foundations, cambers zoned dams, it is common practice to limit the
of about 1 percent of the height are commonly pro- height of the core material to a few feet below the
vided. Several feet of camber may be required for crest because impervious zones extending to the top
dams constructed on foundations expected to settle. of the dam are subject to damage by frost action,
A method of determining foundation settlement is which causes loosening of the soil, and to the for-
given in [54] and in USBR Design Standards No. mation of shrinkage cracks when the soil drys.
13, chapter 9. Straight-line equations should be Either of these occurrences can cause flow paths
used to vary the amount of camber and to make it where erosion and possible failure can occur. In ho-
roughly proportional to the height of the embank- mogeneous dams where frost action or shrinkage
ment. These equations are easy to use and usually cracks may be problems, crest surfacing should al-
correspond well with the camber lines as con- ways be provided. The top of the impervious core
structed in the field. should also be maintained above the maximum
Little additional embankment material is usually water surface to prevent percolation through the
required to provide camber in the crest of an em- embankment or possible capillary siphoning over
bankment because the embankment height is in- the top of the core material when the reservoir is
creased by pitching the slopes near the crest of the full. The need for filters or zoning that will prevent
dam as shown on figure 6-45. The modifications to erosion of material out of cracks in impervious
the section of the embankment caused by the ad- zones should also be considered.
dition of camber are not taken into account in cal- The crest pitching provided for camber should
culating embankment stability. not be overly steep to facilitate construction.
(e) Surfacing.-Some type of surfacing should (h) Typical Crest Details.-Figure 6-84 and 6-85
be placed on top of the crest for protection against show the crest detail for Wasco Dam: 6 inches of
damage by wave splash and spray, rainfall, wind, camber were provided and a minimum top width of
frost, and traffic when the crest is used as a road- 14 feet was maintained for the impervious zone to
way. The usual treatment consists of placing a layer ensure adequate room for compaction by tamping
of selected fine rock or gravelly material at least 4 rollers. The core material was placed 3.5 feet higher
inches thick. If the crest constitutes a section of than the maximum water surface. Note also that
highway, the width of roadway and type of surfacing the top of the core material is sloped toward the
should conform to those of the highway. reservoir to facilitate drainage.
(f) Safety Requirements.-When the crest of a Additional crest details for various Bureau dams
dam is used as a highway, cable- or beam-type are shown on figure 6-45.
guardrails are usually constructed along both shoul- 6.2 1. Freeboard.-Freeboard is the vertical
ders of the crest. If a highway crossing is not an- distance between the crest of the embankment
ticipated, the crest can be lined with guard posts at (without camber) and the reservoir water surface.
25-foot intervals or, on very minor structures, by The more specific term normal freeboard is de-
boulders placed at intervals along the crest. If little fined as the difference in elevation between the
or no traffic will use the crest, treatment may not crest of the dam and the normal reservoir water
be necessary. level as fixed by design requirements. The term
256 DESIGN OF SMALL DAMS

\ \
(A)

Cr**t WlhO c.mb.r, El. 5935

..,.S. El.5

SlOlm prot.c,,on
sloD* I,..
8 I. Int.r.2.p t El. 5010
.I

(8)

Figure 6-45.-Examples of crest details at maximum camber. 103-D-1831.


EARTHFILL DAMS 257

minimum freeboard is defined as the difference of the wind, the fetch3, the depth of water, and the
in elevation between the crest of the dam and the width of the reservoir. The height of the waves as
maximum reservoir water surface that would result they approach the upstream face of the dam may
should the inflow design flood occur and the outlet be altered by the increasing depth of the water, or
works and spillway function as planned. The dif- by the decreasing width of the reservoir. Upon con-
ference between normal and minimum freeboard tact with the face of the dam, the effect of waves
represents the surcharge head (sec. (9.3).If the spill- is influenced by the angle of the wave train with
way is uncontrolled, there is always a surcharge the dam, the slope of the upstream face, and the
head; if the spillway is gated, it is possible for the texture of the slope surface. The sloping face of an
normal and minimum freeboards to be identical, in earthfill dam reduces the impact with which waves
which case the surcharge head is zero. hit the dam. The rough surface of dumped riprap
A distinction is made between normal and min- reduces wave runup to approximately 1.5 times the
imum freeboards because of the different require- height of the wave; whereas, the runup for smooth
ments for freeboard if surcharge head is involved. surfaces such as concrete is considerably greater.
The normal freeboard must meet the requirements Because there are no specific data on wave height
for longtime storage. It must be sufficient to prevent and wave runup, the determination of freeboard re-
seepage through a core that has been loosened by quires judgment and consideration of local factors.
frost action or that has cracked from drying out; A summary of empirical formulas proposed for
otherwise, zoning must be provided to control this determining wave heights is given in an American
condition. This is of particular importance for a Society of Civil Engineers report [55], from which
dam whose core is a CL or CH material and is lo- table 6-7 was extracted.
cated in areas with either a very cold or a very hot All conditions affecting exposure of the dam to
dry climate. The normal freeboard must also be suf- the wind must be considered in selecting the max-
ficient to prevent overtopping of the embankment imum wind velocity. It is believed that no locality
by abnormal and severe wave action of rare occur- is safe from an occurrence of winds of up to 100
rence that may result from unusual sustained winds mi/h at least once during a period of many years,
of high velocity from a critical direction. although a particular site may be topographically
Minimum freeboard is provided to prevent over- sheltered so that the reservoir is protected from
topping of the embankment by wave action that sustained winds of high velocity. Under these con-
may coincide with the occurrence of the inflow de- ditions, wind velocities of 75 or even 50 mi/h may
sign flood. Minimum freeboard also provides a be used.
safety factor against many contingencies, such as For the design of small dams with riprapped
settlement of the dam more than the amount an- slopes, it is recommended that the freeboard be suf-
ticipated in selecting the camber, occurrence of an ficient to prevent overtopping of the dam from wave
inflow flood somewhat larger than the inflow design runup equal to 1.5 times the height of the wave as
flood, or malfunction of spillway controls or outlet interpolated from table 6-7, measured vertically
works with an increase in maximum water surface from the still water level. Normal freeboard should
above that expected. In some instances, especially be based on a wind velocity of 100 mi/h, and min-
where the maximum probable inflow is used as a imum freeboard on a velocity of 50 mi/h. Based on
basis for design, the minimum freeboard may be these assumptions and on other considerations of
established on the assumption that the dam should the purpose of freeboard, as previously discussed,
not be overtopped as a result of a malfunction of table 6-8 lists the least amount recommended for
the controlled spillway or outlet works that would both normal and minimum freeboard on riprapped
result from human or mechanical failure to open earthfill dams; the design of the dam should satisfy
gates or valves. In such instances, allowances for the most critical requirement.
wave action or other contingencies usually are not An increase in the freeboard shown in table 6-8
made.
The rational determination of freeboard would 3The fetch is the distance over which the wind can act on a body of water.
It is generally defined as the normal distance from the windward shore
require determining the height and action of waves.
to the structure being designed. However, the effective fetch may have
The height of waves generated by winds in a a slightly curved path, as when the wind sweeps down a winding river
reservoir depends on the wind velocity, the duration valley between land ridges.
258 DESIGN OF SMALL DAMS

Table 6-7.-Wave height versus fetch and wind velocity. Table 6-K-Fetch versus recommended normal and minimum
From [55]. freeboard.

Fetch, Wind velocity, Wave height, Normal Minimum


mi mi/h ft Fetch, freeboard, freeboard,
mi ft ft
1 50 2.7
1 75 3.0 tl 4 3
2.5 50 3.2 1 5 4
2.5 75 3.6 2.5 6 5
2.5 100 3.9 5 8 6
5 50 3.7 10 10 7
5 75 4.3
5 100 4.8
10 50 4.5
10 75 5.4 furnishes the best upstream slope protection at the
10 100 6.1 lowest ultimate cost. Approximately 100 dams, lo-
cated in various sections of the Untied States with
a wide variety of climatic conditions and wave se-
verity, were examined by the Corps of Engineers.
for dams where the fetch is 2.5 miles and less may The results of this survey were used as a basis for
be required if the dam is located in a very cold or establishing the most practical and economical
a very hot dry climate, particularly if CL and CH means for slope protection [56]. The dams were
soils are used for construction of the cores. It is also from 5 to 50 years old and were constructed by
recommended that the amount of freeboard shown various agencies. This survey found that:
in table 6-8 be increased by 50 percent if a smooth 1. Dumped riprap failed in 5 percent of the cases
pavement is to be provided on the upstream slope. it was used; failures were due to improper size
The above methods for determining freeboard re- of stones.
quirements are adequate for small dams. USBR De- 2. Hand-placed riprap failed in 30 percent of the
sign Standards No. 13, chapter 6, and Bureau of cases it was used; failures were due to the
Reclamation ACER Technical Memorandum No. 2 usual method of single-course construction.
have a more in-depth discussion of freeboard and 3. Concrete pavement failed in 36 percent of the
determinations of freeboard requirements. cases it was used; failures were generally due
6.22. Upstream Slope Protection. to inherent deficiencies with this type of
(a) General.-The upstream slopes of earthfill construction.
dams must be protected against destructive wave This survey substantiated the premise that
action. In some instances, provision must be made dumped riprap is by far the most preferable type of
against burrowing animals. The usual types of sur- upstream slope protection. The excellent service
face protection for usptream slopes are rock riprap, rendered by dumped riprap is exemplified by Cold
either dry-dumped or hand-placed, and concrete Springs Dam, constructed by the Bureau of Recla-
pavement. Other types of protection that have been mation. Figure 6-46 shows the condition of the
used are steel facing, bituminous pavement, precast riprap on the upstream slope of this dam after 50
concrete blocks, soil-cement pavement, and (on years of service. The only maintenance required
small and relatively unimportant structures) wood during that period has been the replacement of
and sacked concrete. The upstream slope protection some riprap that was dislodged near the center of
should extend from the crest of the dam to a safe the dam by a severe storm in 1931. Although some
distance below minimum water level (usually sev- beaching action has occurred subsequently, it has
eral feet). In some cases, it is advantageous to not been severe enough to require further
terminate the slope protection on a supporting maintenance.
berm, but this is generally not required. The superiority of dumped rock riprap for up-
(b) Selecting the Type of Protection-Experi- stream slope protection and its low cost of main-
ence has shown that in most cases, dumped riprap tenance compared with other types of slope
EARTHFILL DAMS 259

Figure 6-46.-Riprap on upstream slope of an earthfill dam. Dam is in excellent condition after 50
years of service. The structure is Cold Springs Dam, which forms an offstream reservoir on the
Umatilla Project in Oregon. 10-2194.

protection have been demonstrated so convincingly on the behavior of the embankment, and on the
that it has been considered economical to .transport ability of the paving to resist cracking and deteri-
rock considerable distances for major dams. For ex- oration. Concrete pavement has proved satisfactory
ample, the Bureau of Reclamation has imported in some casesunder moderate wave action. An ex-
rock from sources that required a rail haul of over ample is at McKay Dam, constructed by the Bureau
200 miles and a truck haul of 24 miles from the of Reclamation near Pendleton, Oregon This pave-
railhead to the dam, and the Corps of Engineers ment, although exposed to severe weather condi-
has transported rock a distance of 170 miles. tions, was in excellent condition after more than 40
When the nearest source of suitable rock is far years of service (see fig. 6-47).
from the site, especially when only small quantities Where severe wave action is anticipated, con-
are involved, it may be economical to use hand- crete pavement appears practicable only when the
placed riprap despite its higher unit cost for labor settlement within the embankment after construc-
and material because a thinner layer of rock may tion will be insignificant. In comparing the cost of
be used. Hand-placed riprap is satisfactory where concrete pavement with riprap, the cost of all ad-
not exposed to heavy ice conditions. However, the ditional foundation measuresnecessaryto minimize
rock must be of better quality than the minimum settlement and the additional freeboard required
suitable for dumped riprap, and placement must be becauseof greater wave runup on the smooth sur-
such that the hand-placed riprap approaches good face should be considered.
dry rubble in quality and appearance. It should be Other types of upstream slope protection, such
recognizedthat hand-placed riprap is not as flexible as precast concrete blocks, asphaltic concrete, steel
as dumped riprap becauseit does not adjust as well plates, and soil-cement, should also be considered.
to foundation or local settlements. Consequently, Asphaltic concrete and soil-cement often provide
hand-placed riprap should not be used where con- economical alternatives for slope protection. Wood
siderable settlement is expected. and sacked concrete should be used only on very
Concrete paving deserves serious consideration minor structures and then only when the cost of a
for upstream slope protection where riprap is too more permanent type of slope protection is
expensive (usually because of high transportation prohibitive.
costs). The successof concrete pavement as a slope In this chapter, the following types of slope pro-
protection medium dependson the field conditions, tection will be discussed:
260 DESIGN OF SMALL DAMS

.Dumped rock riprap many of the limestones, and someof the sandstones
.Hand-placed rock riprap make excellent riprap. Limestones and sandstones
.Concrete pavement that have shale seams are undesirable. The suita-
.Soil-cement bility of rock for rip rap from a quality standpoint
Section 7.11 discusses asphaltic-concrete slope is determined by visual inspection, by laboratory
protection. tests to determine the resistance to weathering and
(c) Dumped Rock Riprap.-Dumped rock rip rap to abrasion, and by petrographic examination to
consists of stones or rock fragments dumped in determine the structure of the rock as it affects
place on the upstream slope of an embankment to durability. The laboratory tests are described in
protect it from wave action. The rip rap is placed chapter 5.
on a properly graded filter, which may be a specially The individual rocks must be heavy enough to
placed blanket or the upstream zone of a zoned em- resist displacement by wave action, which is not
bankment. Figure 6-48 shows dumped rock riprap necessarily a function of the height of the dam. It
being placed on Meeks Cabin Dam, constructed by is a misconception to think that large rocks are
the Bureau of Reclamation. The riprap is felds- needed only on higher structures and that small
pathic sandstone having a specific gravity of 2.58. rocks afford ample slope protection for low fills,
The efficacy of dumped rock riprap depends on without considering factors such as wind velocity,
the following characteristics: wind direction, and fetch. This can be demonstrated
.Quality of the rock by comparing figure 6-49 with figure 6-46. Cold
.Weight or size of the individual pieces Springs Dam (fig. 6-46) is a 90-foot-high dam whose
.Thickness of the riprap upstream slope is protected by a 24-inch layer of
.Shape of the stones or rock fragments basalt rock whose larger fragments probably do not
.Slopes of the embankment on which the riprap weigh more than about 100pounds. The waveaction
is placed on this reservoir is not severe, and the rip rap has
.Stability and effectiveness of the filter on given satisfactory service for 60 years with rela-
which the riprap is placed tively little maintenance required. Figure 6-49
Rock for riprap should be hard, dense, and du- shows riprap containing relatively large fragments
rable, and able to resist long exposure to weather- that have been dislodged from the upstream slope
ing. Most of the igneous and metamorphic rocks, of a low dike section of another dam subject to heav-
ier wave action.
The weight or size of the individual rocks re-
quired to resist displacement by wave action may
be determined theoretically by the methods pre-
sented in the American Society of Civil Engineers
report referred to in the discussion of freeboard re-
quirements [55]. This method is basedon the prem-
ise that the force a wave exerts on riprap rocks on
the face of a dam cannot be greater than that of a
current flowing at the velocity of the water particles
of the wave. These theoretical methods are con-
sistent with the experience and analysis of results
obtained on a large number of earthfill dams by the
Bureau of Reclamation.
The thickness of the rip rap should be sufficient
to accommodate the weight and size of rock nec-
essary to resist wave action. The Bureau of Recla-
mation has found a 3-foot thickness of dumped
rip rap to be generally most economical and satis-
Figure 6-47.-Paved upstream slape af an earthfill dam.
Dam is in excellent condition after 40 years of service. factory for major dams. Lesser thicknesses are used
The structure is McKay Dam on a tributary of the Uma- on low dams or on dike sections where wave action
tilla River in Oregon. 288-D-2878.
will be less severe than on principal structures.
EARTHFILL DAMS
261

Figure 6-48.-Placing riprap an an upstream slape. Meeks Cabin Dam, Wyoming. P415-432-720.

Lesser thicknesses have also been specified for the ment better than boulders and rounded cobbles.
upper slopes of dams whose reservoirs are largely The values given in table 6-9 are for angular quar-
allocated to flood control. This is because of the ried rock. If boulders or rounded cobbles are to be
infrequent and short periods of time that the upper used, as shown on figure 4-1, a thicker layer con-
slopes are subject to wave action. Greater thick- taining larger sizes may be required, or the slope of
nesseshave been specified in caseswhere rock hav- the embankment may need to be made flatter than
ing a low specific gravity (less than 2.50) was used. required for stability so that the boulders and cob-
Table 6-9 shows the recommended thickness and bles stay in place. This is especially true if cobbles
gradation of dumped rock riprap for small dams for of relatively uniform diameter are to be used.
fetch equal to or less than 2.5 miles and greater Table 6-9 is for riprap thickness and gradation
than 2.5 miles, based on theoretical considerations on 3:1 slopes.For 2:1 slopes,a thickness of 36 inches
and the experience and practice of the Bureau of should be used with the gradation corresponding to
Reclamation. a 36-inch thickness in the table.
The shape of the individual rocks or rock frag- A layer, or blanket, of graded gravel should be
ments influences the ability of the rip rap to resist provided underneath the riprap when the com-
displacement by wave action. Angular fragments of pacted material of the underlying earthfill is graded
quarried rock tend to interlock and resist displace- so that wavesmay wash out fines through the voids
262 DESIGN OF SMALL DAMS

spalls or small rock fragments. However, there


should be enough openings in the surface of the
rip rap to allow the water pressure to dissipate with-
out lifting the rocks.
Rock for hand-placed riprap must be of excellent
quality. The thickness of hand-placed rock riprap
should be one-half of the thickness required for
dumped rock riprap, but not less than 12 inches. A
filter blanket should be provided underneath the
riprap if the underlying zone of the earthfill dam
is not gravel.
(e) ConcretePaving.-If a complete history were
gathered concerning the numerous instances where
concrete paving was used for the protection of the
upstream slopes of small dams, the number of fail-
ures would be tremendous. Concrete paving is used
on both earth fill and rockfill dams, although its
performance on rockfill dams (ch. 7) has been much
better. Unfortunately, the fact that some structures
protected with concrete paving have withstood the
Figure 6-49.-Displacement of riprap on a low dike by test of time continues to lead engineers to use this
wave action. 288-D-2936.
type of construction, often without sufficient ref-
erence to other, unsatisfactory performance rec-
in the riprap, resulting in undermining of the ords. A properly designed and constructed concrete
riprap. A blanket is usually not required if the outer paving is never cheap. The uncertainty and com-
zone of the zoned embankment is gravel. Blankets plexity of the forces that may act on a concrete
of crushed rock or natural gravel graded from 3A6 paving make conservative treatment desirable
to 31/2inches with a thickness equal to one-half the wheneverthis type of slope protection is considered.
thickness of the riprap (but not less than 12 inches) The recommendations that follow should provide
have proved satisfactory in practice. The blanket the necessarydegreeof conservatism. But the num-
gradation may be determined more exactly by the ber of situations studied is so limited that there is
filter criteria given in section 6.10(i). An example no assurancethat adequate consideration has been
of a finished rip rap slope is shown on figure 6-50. given to every type of hazard that may be
The structure is Blue Mesa Dam in Colorado. encountered.
The above procedures are generally adequate for Concrete paving slope protection should extend
design of small dams. USBR Design Standards No. from the crest of the daJri to several feet below the
13, chapter 7, gives the current Bureau design cri- minimum water surface. It should terminate on a
teria for dumped riprap slope protection. berm and against.a concrete curb or header, which
(d) Hand-Placed Rock Riprap.-A good example -should extend at least 18 inches below the under-
of hand-placed rock rip rap is shown on figure 6-51. surface of the paving.
This upstream slope protection was in an excellent For dams nearly 50 feet high, a paving-thickness
state of preservation after 36 years of service. Hand- of 8 inches is recommended; for lower dams the
placed riprap consists of stones carefully laid by minimum thickness should be 6 inches. Although
hand in a more or less definite pattern with a min- concrete paving has been constructed in blotks, the
imum amount of voids and with the top surface generally favored method, which has given the best
relatively smooth. Rounded or irregular rocks lay service, is to make the paving monolithic to the
up less satisfactorily and rapidly than rock that is greatest extent possible, and every measure should
roughly square. The flat, stratified rocks should be be taken to prevent accessof water and consequent
placed with their large axes parallel to the slope. development of hydrostatic pressures under the
Joints should be offset as much as possible, and concrete. The good service given by the concrete
openings to the underlying fill should be filled with pavement on the upstream slope of McKay Dam~
EARTHFILL DAMS 263

Table 6-9.-Thickness and gradation limits of riprap on 3:l slopes. For angular quarried rock.

Reservoir Nominal Weight of rock (in pounds) at various percentages (by weight)
fetch, thickness Maximum
mi inches size 40 to 50% 50 to 60 % 20 to 10%

52.5 30 2,500 >1,250 75 to 1,250 t75


>2.5 36 4,500 >2,250 100 to 2,250 < 100
Sand and rock dust shall be less than 5 percent, by weight, of the total riprap material.
The percentage of this size material shall not exceed an amount that will fill the voids between the larger rocks.

(fig. 6-47) is due to the monolithic type of construc- bankment. Normal embankment construction pro-
tion, durability of the concrete, little settlement of cedures are used, with perhaps special care being
the dam or foundation, and pervious nature of the taken to ensure a minimum of embankment con-
underlying fill, which prevents development of hy- solidation and foundation settlement after con-
drostatic uplift pressures even though a minor struction. Soil-cement slope protection used on
amount of cracking has occurred. Cheney Dam in Kansas is shown on figure 6-53.
In contrast with the success of concrete paving The soil-cement is generally placed and com-
at McKay Dam is the experience of the Bureau of pacted in stairstep horizontal layers, as shown on
Reclamation with the concrete paving at Belle figure 6-54. This promotes maximum construction
Fourche Dam. There, monolithic construction was efficiency and operational effectiveness. With typ-
not used. The paving consists of B-inch-thick ical embankment slopes of 2:l and 4:1, a horizontal
blocks, 6 feet 6 inches by 5 feet, placed directly upon layer 8 feet wide will provide minimum protective
the impervious underlying embankment. The con- thicknesses of about 2 and 3l/2 feet respectively,
dition of the paving after 40 years of service is measured normal to the slope. Beginning at the low-
shown on figure 6-52. Considerable maintenance of est layer of soil-cement, each succeeding layer is
the paving has been required through the years; a stepped back a distance equal to the product of the
number of the blocks have been displaced and bro- compacted layer thickness in feet times the em-
ken up by wave action and uplift forces under the bankment slope. For example, if the compacted
slabs. Compared with the general service record of thickness is 6 inches and the slope is 2:1, the step
riprap or with the concrete pavement on McKay back is = 0.5(2) = 1 foot. The usual compacted layer
Dam (fig. 6-47), this slope protection design cannot thickness is 6 inches. Soil-cement layers of this di-
be considered successful. mension can be effectively placed and compacted
If monolithic construction is not possible, ex- with standard highway equipment.
pansion joints should be kept to a minimum and A plating method that forms a single soil-cement
construction joints should be spaced as far apart as layer parallel to the slope is sometimes used in less
possible. The slab should be reinforced with bars critical areas for slope protection.
in both directions, placed at middepth of the slab, If the soil-cement facing does not begin at nat-
and made continuous through the construction ural ground level, the lower portion of the em-
joints. An area of steel in each direction equal to bankment should be on a flatter slope than the
0.5 percent of the area of the concrete is considered portion protected by the soil-cement; or a berm may
good practice. Joints should be sealed with plastic be provided at the lowest elevation of the facing. It
fillers, and subsequent open cracks in the concrete is essential that the soil-cement extend below the
should be grouted or sealed promptly. minimum water level and above the maximum
(f) Soil-Cement.-In recent years, soil-cement water level. The top of the facing should have a
as a facing material for earthfill dams has been freeboard allowance of at least 1.2 times the antic-
found economical where suitable riprap is not avail- ipated maximum wave height, or 5 feet, whichever
able near the site. A reasonably firm foundation is is greater. The edges of the completed soil-cement
preferred so that deformation after placement of layers should not be trimmed because the rounded
soil-cement is not significant; however, no unusual starstep effect helps retard wave runup (fig. 6-53).
design features need be incorporated into the em- Soil-cement can be made with a wide variety of
264 DESIGN OF SMALL DAMS

Figure 6-50.-Completed riprop slope protection on upstreom foce of Blue Meso Dom, Colorodo. P662A-427- 10496NA.

soils. The principal criterion for determining soil for Testing and Materials), AASHTO (American
type is gradation. Coarsesandy or gravelly soils con- Association of State Highway and Transportation
taining about 10 to 25 percent material passing the Officials), or Federal specifications may be used.
No.200 sieve are ideal (American Society for Test- Type 1, or normal portland cement, is most com-
ing and Materials Standard Sieve Series). These monly used becausethe special properties of other
soils can be adequately stabilized with from 3 to 5 types of portland cement are not usually required
sacks of cement per cubic yard of compacted soil- for soil-cement construction [55]. Standard labo-
cement. Standard compaction and placement con- ratory tests are necessaryto verify the acceptability
trol for soil-cement is used; it is described by Holtz of the soil and to determine proper cement content,
and Walker [57]. If the amount of material smaller optimum moisture content, and maximum dry unit
than the No.200 sieve exceeds 35 percent, some weight of the soil-cement.
effort to find a coarsematerial may be justified from After the soil has been classified by sieve anal-
a processing cost standpoint. Soils containing 50 yses and other tests, the required cement content
percent or more material passing the No.200 sieve may be estimated. Moisture unit weight curves are
are not recommendedfor use in their natural state. determined for test mixtures. The estimated cement
Any type of portland cement meeting the re- content and at least four moisture contents are used
quirements of the latest ASTM (American Society to determine the optimum moisture content and
EARTHFILL DAMS 265

Figure 6-53.-Soil-cement paving on the upstream slope


Figure 6.51.-Hand-placed rock riprap on Indian Creek of Cheney Dam, Kansas. The soil-cement is in excellent
Dike. An offstream dike for Strawberry Reservoir, part condition after numerous storms. P835-526-1 0O6NA.
of a transmountain diversion project in Utah.
288-D-2935.
Crest of dom

~ 1:1 ' Surfacing

Riprap,
Upstream sIOpe "'- z

-"::.;,0 ~ ..
c ~/-/.:;,

Lo' ol
Sail cement compacted
to 6. layers
24--' -'\
8 , M;n.--1
~"" ."'- Embankment

Figure 6-54.- Typical section of soil-cement slope pro-


tection. Cheney Dam, Kansas. 288-D-2795.

sion resistance. For most soils, a total required ce-


ment content of 10 to 12 percent by compacted
volume of soil-cement is considered typical.
Compressive strength tests for soil-cement are
considered supplementary to the standard soil-
cement tests. Soil-cement mixtures with a com-
Figure 6.52.-Concrete paving blocks on the upstreom
pressive strength of about 450 lb/in2 or more at 7
slope of Belle Fourche Dam. Note the deteriorated dayswill generally pass the wet-dry and freeze-thaw
condition of this paving after 40 years of service de- tests. Using cement contents of about 10 percent,
spite considerable maintenance. This dam is an earthfill
structure on a tributary of the Belle Fourche River in
7-day compressive strengths of 500 to 1,000 lb/in2
South Dakota. 28B-D-2937. are common with a wide range of soils. Figure 6-55
shows the placement of soil-cement slope protec-
tion at Starvation Dam in Utah.
maximum dry unit weight of the mixture accurately. USBR Design Standards No.13, chapter 17,
A number of test cylinders are prepared, using should be referred to for current criteria and infor-
the estimated cement content and cement contents mation on soil-cement design and construction.
2 percentage points above and below the estimated 6.23. Downstreom Slope Protection.-If the
content. The results of wet-dry, freeze-thaw, downstream zone of an embankment consists of
weight-loss criteria will determine the cement con- rock or cobble fill, no special surface treatment of
tent required. This cement content is then in- the slope is necessary. Downstream slopes of ho-
creased by 2 percentage points for erosion mogeneous dams or dams with outer sand and
resistance. If it is necessaryto use a soil containing gravel zones should be protected against erosion
more than 50 percent fines, the cement content causedby wind and rainfall runoff by a layer of rock,
should be increased by 4 percentage points for ero- cobbles, or sod. Because of the uncertainty of ob-
266 DESIGN OF SMALL DAMS

taining adequate protection by vegetative cover at in the design of earthfill dams. The result is that,
many damsites, especially in arid regions, protec- although the upstream and downstream slopes and
tion by cobbles or rock is preferred and should be the crest of the dam are protected against erosion,
used where the cost is not prohibitive. Layers 24 unsightly gullying occurs at the contact of the em-
inches thick are easier to place, but a 12-inch-thick bankment with earth abutments from which veg-
layer usually affords sufficient protection. etation has been removed during the construction
If grassesare planted, only those suitable for the operations. This gullying occurs especially when the
locality should be selected. Figure 6-56 shows the abutments are steep.
native grassesthat have protected the downstream Gullying most often develops along the contact
slope of the Bureau's Belle Fourche Dam from ero- of the downstream slope with the abutments. How-
sion for 50 years. 'I\vo drainage berms, one of which ever, it can usually be controlled by constructing a
is shown in the photograph, are located on the gutter along the contact. The gutter may be formed
downstream slope of this 115-foot-high dam. Usu- from cobbles or rock used in the downstream sur-
ally, fertilizer and uniform sprinkling of the seeded facing; if the downstream slope is seeded, a con-
areas is necessaryto promote the germination and crete, asphalt, or dry-rock paved gutter should be
to foster the growth of grasses.Appendix G contains provided. The likelihood of gullying of the abut-
sample specifications for placing topsoil, planting ments and gentle slopes of the valley floor caused
seed,and watering the seededarea until completion by runoff from the downstream slope of the dam
of construction. also should be considered; contour ditches or open
6.24. Surface Drainage.-The desirability of drains may be needed to control erosion. Figure 6-
providing facilities to handle surface drainage on 57 shows typical sections of a contour ditch and an
the abutments and valley floor is often overlooked open drain.

Figure 6-55.-Placement of soil-cement slope protection.


Starvation Dam, Utah. P66-418-3549.
EARTHFILL DAMS 267

Figure 6-56.-Downstream slope of Belle Fourche Dam protected by gross.


288-D-2938.

drain discharge away from the downstream toe of


the embankment so that an unsightly boggy area
will not be created. The need for surface drainage
facilities and the most appropriate type for a par-
ticular site can usually best be determined by field
(AI CONTOUR DITCH examination before or during construction.
6.25. Flared Slopes at Abutments.-If neces-
sary, the upstream and downstream slopes of the
embankment may be flared at the abutments to pro-
vide flatter slopes for stability or to control seepage
through a longer contact of the impervious zone of
the dam with the abutment. If the abutment is per-
vious and if a positive cutoff cannot be attained
(8) PAVED DPEN DRAIN
economically, it may be possible to obtain the effect
of an upstream blanket by flaring the embankment.
Figure 6-57.- Typical sections of a contour ditch and an
The design of the transition from normal to flared
open drain. 288-D-2498. slopes is governed largely by the topography of the
site, the length of contact desired, and the desira-
bility of making a gradual transition without abrupt
Attention should also be given to the construc- changes both for ease of construction and for
tion of outfall drains or channels to conduct the toe appearance.

F. DESIGN EXAMPLES OF SMALL EARTHFILL DAMS


6.26. Genera/.-The designs of 29 Bureau of were included to illustrate designs for unusual con-
Reclamation earthfill dams are discussedbriefly in ditions that were not encountered in the construc-
the next section. With only a few exceptions, these tion of any of the smaller dams. All exceptions
dams are less than 50 feet higher than the original chosen, however, are less than 100 feet higher than
streambed, or are dikes of that size constructed in the original streambed.
conjunction with larger dams. The few exceptions These designs include small earthfill dams con-
DESIGN OF SMALL DAMS

strutted by the Bureau of Reclamation since 1930. Soil-cement was used for upstream slope protection
Of these 29 dams, 2 were constructed before 1940, because of the scarcity of good quality rock for rip-
5 in the 1940s, 14 in the 1950s, 5 in the 1960s, rap. The soil-cement was satisfactorily compacted
and 3 in the 1980s. Many minor dikes constructed into lifts thicker than the 6 inches normally con-
in conjunction with storage dams or canal systems sidered standard. The downstream slope was
were omitted because of their similarity to other formed by topsoil that was subsequently seeded for
designs that are shown. slope protection. Because of the extreme depth of
The purpose of these examples is to illustrate alluvial fill, a positive cutoff was uneconomical to
the changes in designs over the years and the va- achieve. Consequently, a sand drain system was in-
riety of designs that were conceived to meet widely stalled at the downstream toe. As shown, a toe drain
varying conditions in foundations and in availabil- was also incorporated into the design.
it,y of construction materials. With few exceptions, (c) Big Sandy Dike.-This dike (fig. 6-60) was
the completed structures have given satisfactory constructed in conjunction with Big Sandy Dam
service. (not shown), a 72-foot-high dam of conventional
Stubblefield Dam has experienced dessication of design with a 3:l upstream slope protected by a 3-
the upper 15 feet of the embankment. Repair is foot-thick layer of rock riprap. The design of the
underway (1986) and will consist of a trench lined upstream slope of the dike represents a departure
with filter fabric and backfilled with pit-run gravel from usual design and was adopted because of the
through the upper part of the embankment. The scarcity and expense of rock for riprap. Note that
reservoir has remained in service even though re- in the surcharge range, the upstream slope of the
stricted to a lower than normal water surface. Love- dike is 8:1, which is the beaching slope of the em-
well Dam has experienced some riprap damage, bankment material. Freeboard above the maximum
which has since been repaired. Several other dams water surface is provided by a 3:l slope, which is
and dikes have been modified to increase their spill- planted to make it erosion resistant to wave splash
way capacity because of revised hydrology or be- and spray to which it will be subjected only rarely.
cause of spillway damage: Big Sandy Dike, This design is suitable for upstream slope protec-
Dickinson Dam, Fruitgrowers Dam, and Tiber tion of a detention dam, provided the maximum
Dike. This amount of repair and modification to water surface will not be attained more than several
this number of dams over the time span involved times during the expected life of the dam.
is considered minor. Even though design and main- (d) Carpinteria Reservoir Dike.-Carpinteria
tenance problems have been minor, the designs are Reservoir is a small equalizing reservoir constructed
not considered unduly conservative. It is believed on a gently sloping sidehill by excavating on the
that a designer of small earthfill dams can gather uphill side and constructing a dike (fig. 6-61) on
valuable ideas from a study of these examples. the downhill side. The concrete lining is provided
6.27. Maximum Sections.-Figures 6-58 to prevent seepage, which would be serious because
through 6-88 show the maximum sections of small of the location of the reservoir with respect to im-
earthfill dams constructed by the Bureau of Rec- proved property. The concrete lining covers all the
lamation. A brief explanation of each of the designs side slopes and the bottom of the reservoir. Figure
follows: 6-62 shows the reservoir lining being constructed.
(a) Amarillo Regulating Reservoir.-This design Because this reservoir is subject to rapid drawdown,
(fig. 6-58) illustrates a small dam embankment to- a gravel drain is placed under the side lining to
gether with an earth lining over the entire reservoir prevent uplift. A pipe drainage system is also pro-
floor to prevent excessive seepage through the floor. vided under the reservoir floor lining.
The earth lining continues up the upstream slope The embankment was constructed of material
of the embankment and is covered by riprap and from the excavation. This soil contained consider-
gravel to protect it from erosion. A toe drain is pro- able rock fragments larger than 5 inches in diam-
vided for drainage. The topsoil protecting the down- eter, and separation was required by the spec-
stream slope came from stripping the structure ifications to obtain an impervious zone that could
area. be compacted satisfactorily. The dumped earth ma-
(b) Cawker City Dike.-Several different design terial zone provided for waste disposal of excess ex-
concepts are illustrated in this example (fig. 6-59). cavation. Oversize rock fragments from the
EARTHFILL DAMS 269

24" R/prap On
12" Gravel blanket
6"Gravel blar lket
MUX. HIS. El. 3660.00- --\ El 3664.00>

ground surface
Earth linlno

Volume=340,000yd3

Figure 6-58.-Amarillo Regulating Reservoir. Located offstream on the Canadian River Aqueduct, Texas (completed 1965).
From 62-D-322.

SO/l-Cement compacted

s toroge: 976.000 acre feet at El /50/ Dike length=l4,96o


top of flood control
WS. El 1488.3 (Wocondo Lake)

Clay, silt and sond A

Volume- 2.505.000yd3

Sond -.iL, Into sondy moteriol

--K-
Assumed formotfon surface

Figure 6-59.-Cawker City Dike. Protecting Cawker City, Kansas, from the waters of Wacondo Lake (constructed 1967).
From 495-D-245.

Crest tl 67690
SeedIng on 12" of topm
i+edmg on I?' of

StrippIng OS drected

Figure 6-60.-Typical section, Big Sandy Dam. Located on Big Sandy Creek, Wyoming (constructed 1950-52). 288-D-2940.
270 DESIGN OF SMALL DAMS

Storage = 40 acre feet r2!.


Max. Operating W.S. ~~2- 1
n:.\-::-r-~--L--dCresf EI.-~82.75 ; PlUS 5 II
Gravel-aro,n ,- / :r- ~.:t s;zes
4"Reinfarced concrete reservoir lining~ cr'~ 1 ' -- -rock fill
/
ClayJ earth
rolledsilt,to sand 8 gravel--
6" layers
material
3
Volume=-38,
700 yd.

Figure 6-61.-Carpinteria Reservoir Dike. Terminal reservoir of a distribution system located near Carpinteria, California
(constructed 1952-53). From 103-D-585.

Figure 6-62.-Construction of concrete lining ot Carpinteria Reservoir. SB-3262-R2.

screening operation were used to construct the of which pass a lA-inch screen with no pieces larger
downstream rockfill toe. than 8 inches. The cutoff wall shown on this section
(e) Carter Lake Dam No. 3.- This dam (fig. 6- is no longer used becauseit is considered unessen-
63) illustrates the design of a zoned embankment tial for structure of this size.
consisting of an earth impervious core and rock (f) Crane Prairie Dam.-The design of this
shells. At this site, there was a limited amount of small dam (fig. 6-64) is conventional. Except for
material for an impervious core, no sand-gravel, but the bottom width of the cutoff trench, the design
a large amount'ofrock that could be quarried. Quar- conforms to the recommendations given in this text.
rying operations were controlled so as to produce (g) Crescent Lake Dam.-This is a typical mod-
the desired amount and gradation of rock frag- ern, small-zoned earthfill dam (fig. 6-65). The large
ments. The rockfill consists of rock with a maxi- pervious shells allow the use of steep slopes on the
mum size of 1 yd3 and sufficient smaller rocks to embankment. Note the key trench and the modi-
fill the voids. The zone of quarry fines, which acts fication to the zone lines near the crest of the dam
as a filter between the rockfill and the impervious to facilitate construction.
core, consists of rock fines not more than 20 percent (h) Dickinson Dam.- This dam (fig. 6-66) is the
EARTHFILL DAMS 271

SfOrOge- 112,200 acre feet Mox. W. S. El. 5763 GreSt El. 5769
Norm. W.S. El. 5759

El. 57353

C Cutoff trench1 LCloy, silt, sand and grave I


compacted to 6 I ifts
Volume=211,8S2 yd3

Figure 6-63.-Carter Lake Dam No. 3. Located on Dry Creek (a tributary of the Big Thompson River), Colorado (constructed
195052). 288-D-2939.

Storage-55,3 00 acre feet -<rest El. 44sqLength-285

,,--N 4430. 0 -24 Riprop


---Waste-C-w

\- 8 Toe droin

VOlURU?r29,700 yd3

Figure 6-64.-Crane Prairie Dam. Located on the Deschutes River, Oregon (constructed 1939-40). From 103-D-581.

C/oy, s//t, sond, ond .4


grovel roiled to 6 loyerz * Crest El 48600, Length-450
Sforoge- 86,000 acre feet
N. b+! s. El. 4847.0+

Or/g/no/ rock, plonk ond crib dam removed-


1 29 c S//t, sond, grovel, cobbles, and boulders compacted
by crawler type trocfor to 18 layers
-A-. Cloy, s/If, sond, grove/ ond cobbles

3
VOlume 16,800 yd

Figure 6-65.-Crescent Lake Dam. Located on Crescent Creek, Oregon (constructed 1954-56). From 103-D-586.
272 DESIGN OF SMALL DAMS

3 R:prop to El 2425
dimrnishing to 24ot Ei 2430 -Crest El 2434, Length-2,275
and above to CP~S++~----...

Storage = 1,00Oocre-feet 0iN W S El 2416 5-


--Seed,ng on IZ~OPSOII-
-fi 2400

Voiume-245,527ydJ

Figure 6-66.-Dickinson Dom. located on the Heart River, North Dakota (constructed 1948-50). From 103-D-584.

modified homogeneous type. The flat slopes at the (fig. 6-69) is higher than those within the scope of
toes of the dam form stabilizing fills, which were this text, it is included herein as an example of a
provided because of the unconsolidated and unce- zoned embankment with a relatively thin imper-
mented foundation material. Note the decrease in vious core and with heavy rockfill supporting zones.
the thickness of riprap near the crest of the dam. The overburden penetrated by the cutoff trench
This was done to decrease the amount of costly consisted of topsoil and sand-gravel. Note the tran-
rock, and in view of the infrequent exposure to wave sition zones between the impervious core and the
action because of the large surcharge head. rockfill zones, and the modifications made to the
(i) Dry Fulls Dam-This design (fig. 6-67) il- zone lines near the crest of the dam to facilitate
lustrates a zoned embankment constructed on a soft construction.
foundation. This dam is unusual in that rock was (1) Lion Luke Dikes.-This is illustrative of a
used to construct the stabilizing fills formed by flat- very small embankment (fig. 6-70) constructed to
tening the slopes of the dam. Usually, rock is too impound a water-supply reservoir. The trench
expensive to be used for this purpose, but in this shown is a relatively deep key extending into glacial
case it was excavated for a canal, which heads at deposits of considerable depth.
the dam. The stability afforded to the section by (m) Lovewell Dam.-Although this dam (fig. 6-
the heavy rock zones permits steep slopes for the 71) is somewhat higher than those within the scope
upper part of the dam. Note the filter zone provided of this text, it is included herein to illustrate the
between the core and the rocktills and the modi- use of stabilizing fills on an extremely soft clay
fications made to the zoning lines near the crest of foundation. Note also how a minimum amount of
the dam to facilitate construction and preserve a riprap is used in this design. The 2O:l slope of the
sufficiently long path of percolation through im- upstream stabilizing fill does not require protection.
pervious material. The 42-foot-wide crest was re- Only a minor amount of erosion is expected on the
quired because this dam is used for a major highway upstream 2.51 slope of the stabilizing fill because
crossing. the extremely short reservoir fetch below elevation
(j) Fruitgrowers Dam.-This is another example 1575.0 will produce little wave action. Minor erosion
of a small earthfill dam (fig. 6-68) whose design of this extensive stabilizing fill will not be of
conforms to modern practices except for the narrow consequence.
bottom width of the cutoff trench. The construction (n) Eklutna Dam.-This dam (fig. 6-72), located
reports note that the bottom width, in general, was in an area of high seismic risk, embodies a large
made 12 to 14 feet to accommodate construction downstream rockfill zone for stability. In addition,
equipment. The cutoff trench was extended to special care was taken to ensure that the cutoff
shale. The spillway was replaced in 1986 because of trench was excavated to firm clayey soil.
damage to the existing spillway and revised hy- (0) Lower Two Medicine Dam.-This dam (fig.
drology. A downstream drainage berm was also 6-73) replaces a previous dam which was overtopped
added to increase both the static and dynamic in 1964. A large concrete overflow section now ad-
stability. equately handles flood flows. The embankment is
(k) Howard Prairie Dam.-Although this dam of standard design except for the riprap and bedding
EARTHFILL DAMS 273

Grand Coulee Equolrzrng Rcservo~r n


Stcroge=/,275,/00acre feet
-_--..

A,, LT"S" o"d of,


objsct!onable rnz

Figure 6-67.-Dry Falls Dam. located near Coulee City, Washington. It forms the south barrier of Grand Coulee Equalizing
Reservoir (constructed 1946-49). From 103-D-583.

9FIne rock or gravel


surfacing 3Crown-----.

ment constructed from


through 1935

-Original ground surface

Volume=l35,5ooyd 3

Figure 6-68.-Fruitgrowers Dam. located on Alfalfa Run Wash in Colorado. Its main water supply is derived from Currant
and Surface creeks (constructed 193839). From 103-D-581.

Storage=62,000acre feetMax wS E, 4533 ,

vo/ume=406,000yd3
..,$ 45 r
Grout holes @ IOcrs

Figure 6-69.-Howard Prairie Dam. Located on Beaver Creek (a tributary of Jenny Creek), Oregon (constructed 1957-59).
From 103-D-587.
274 DESIGN OF SMALL DAMS

Storage = I ,331 acre feei

---Grest El. 34 68, Length- 266

\- Rolled earth materia I

Volume: I, 00CJyd3

Figure 6-70.-lion lake Dikes. Constructed for a water-supply reservoir for Hungry Horse Dam Government Camp, Montana
[constructed 1947). From 103-D-583.

storage = 94,200 acre- feet

Flood control WS, El 1595.3 7~

5Sond and grovel below El 1575

Volume: 3,174,70OYd

Figure 6-71 .-lovewell Dam. located on the Republican River (offstream from White Rock Creek), Kansas (constructed 1954-
57). From 103-D-586.

Sand,gravel and cobbles n &lay, silt, sand and gravel


El. 891.0. length 1750
Storage=197,350 0 ot top of CMax. WS. El. 8
conservation Ms.
6.5

Excavated to firm clayey soil-5 Min.,2oMax.

Figure 6-72.-Eklutno Dam, Alaska. Built to replace a former dam damaged by the 1964 Alaskan earthquake (completed
1965). From 783-D-639.

at the downstream toe for protection against ero- (q) Picaelm North Dam.-This is a detention
sion by anticipated high tailwater. The downstream dam (fig. 6-75) that has no permanent storage pool.
drainage was provided in accordance with section It is constructed on a stratified pervious foundation.
6.10(i). The key trench shown was excavated The impervious zone of the dam was extended to
through weathered, low-density alluvium down to the upstream toe and was made continuous with
firm material. waste placed upstream from the dam to increase
(p) Olympus Dam.-This design (fig. 6-74) is an the path of percolation through the foundation. To
example of an earthfill dam with multiple zones. facilitate the use of available materials from strat-
Note the upstream slope protection; the riprap is ified deposits, the design of the embankment was
used only on the upper portion of the slope where based on the impervious core varying between the
heavy wave action is expected. The lower portion slope limits shown.
of the slope is protected by rock and cobble fill be- (r) Picacho South Dam.-This dam (fig. 6-76) is
cause the water level will rarely be lowered into this also a detention dam with no permanent storage
range. pool. At this site, the foundation was relatively im-
EARTHFILL DAMS 275

Stor oge=/3.500 acre-feet

24Riprop on 12 bedding

between El. 4880 COntOUrS

Figure 6-73.-lower Two Medicine Dam, Montana. This structure replaces a dam that was overtopped in an unprecedented
flood (completed 1967). From 2-D-24.

Lake Estes
-Crest E/
Ei 7481
7481 Length- I, 650 i Eorthl
3001 Concrete I
and ond grovel

,obble fill

Concrete cutoff wall

Figure 6-74.-Olympus Dam. located on the Big Thompson River, Colorado (constructed 1947-49). From 103-D-583.

DetentIon Storage= 790ocre-feet t/ 9941 o-.; 33r , Crest Ef ?942 o, Length I, 600

-Sand and grovel con npOC:ted


by crawler -type tmc Yor

/Juste -

Ciay, s/It, sand ond gravel str /pp/ng


rolled to 6 layers - -

r/olume=148,000yd3

Figure 6-75.-Picacho North Dam. A detention dam located on the North Branch of Picacho Arroyo, New Mexico (constructed
1953-54). From 103-D-586.
276 DESIGN OF SMALL DAMS

pervious; only sufficient pervious material for slope (x) Tiber Dike.-Drawing (A) of figure 6-82
protection of the embankment could be found in shows the maximum section of Tiber Dike, which
the vicinity. A lo-foot-wide sand-gravel-cobble zone is conventional in design. A lo-foot-deep key trench
was specified on both the upstream and down- is excavated into the glacial till foundation, and the
stream slopes to facilitate compaction. Riprap was upstream slope is protected by riprap. Drawing (B)
not considered necessary because the outlet capac- shows modifications made to the dike where the
ity is sufficient to evacuate the reservoir in a few original ground ;s above elevation 2995.0, which is
days. above the top of the irrigation storage at elevation
(s) Pishkun Dikes.-This is an interesting de- 2992.3. Because the slope will be subjected to wave
sign (fig. 6-77) because it illustrates how a 43-foot- action only during a flood, it was decided that ad-
high dam was raised 6 feet, 10 years after comple- equate protection would be provided by a 3-foot-
tion of the initial construction. This embankment thick layer of compacted sand, gravel, and cobbles
is essentially homogeneous; a small downstream (maximum size 10 inches) if the slope were flattened
pervious zone was provided in the original design to 6:l. This modfication was economical because of
to contain the more pervious materials found in the the high cost of riprap. It illustrates design flexi-
borrow pit. Note the sparing use of costly riprap; bility in achieving the most economical structure.
it is provided only in the operating range of the Tiber Dike was raised in 1980-H because of revised
reservoir where wave action will be most severe. hydrology.
(t) Lubbock Regulating Reservoir.-Soil-cement (y) Sheep Creek Barrier Dam.-This dam (fig.
provides the slope protection for this small regu- 6-83) was constructed to form a barrier to flood-
lating reservoir (fig. 6-78) located on the Canadian waters heavily laden with sediment. The sediment
River Aqueduct near Lubbock, Texas. Soil-cement will be deposited in the reservoir area, thus clearing
on an earth lining is also provided to prevent ex- up the stream and helping to reduce the rate of
cessive seepage through the reservoir floor. Topsoil erosion upstream by reducing the hydraulic gra-
to protect the downstream slope came from strip- dient. Because the reservoir pool is designed to fill
ping of the reservoir area. with sediment, no upstream slope protection was
(u) Shadow Mountain Dam.-This dam (fig. 6- provided, and only a minimum key trench was
79) has a pervious glacial foundation. The design constructed.
provides a partial cutoff trench and a flat upstream (z) Wasco Dam.-This dam (figs. 6-84 and 6-85)
slope, which functions as a blanket to reduce see- is used as an example throughout this text. It is not
page, and a drainage blanket in the downstream unusual in design, and it may be considered typical
portion of the dam to control seepage uplift. of small zoned earthfill dams constructed on per-
(v) Soda Lake Dike.-In all respects, this dam vious shallow foundations that can economically be
(fig. 6-80) is well-designed by the standards given cut off by open-trench methods. The cobble and
in this text. The filter zones between the impervious rockfill zones use oversize rock removed from im-
core and the outer rockfill zones were made 12 feet pervious soil and rock fragments from excavations
wide, and the zone lines were modified near the for appurtenant structures. A toe drain was not
crest of the dam to facilitate construction. used in the design because the foundation overbur-
(w) Stubblefield Dam.-This design (fig. 6-81) is den is definitely pervious.
typical of a homogeneous dam modified by a hor- (aa) Ute Dam Dike.-This dike (fig. 6-86) is an
izontal drainage blanket meeting filter require- extension of Ute Dam, which is located on the Ca-
ments. It has a toe drain to lower the phreatic line nadian River in eastern New Mexico. The dike was
in the downstream portion of the embankment. The designed and constructed in the early 1980s, in con-
dumped earth shown outside the 2:l downstream nection with a modification that raised the dam and
slope was for disposal of waste material. It was revised the spillway. The dike is an example of a
thought that disposal of waste material (including zoned section with an inclined filter protecting the
organic material) in this manner not only would impervious zone. This type of filter protection is
flatten the downstream slope, but also would de- typical of current design procedure. The section
velop a vegetative cover that would be adequate for also exhibits the concept of using flat beaching
slope protection. The dam has been modified be- slopes instead of slope protection for wave protec-
cause of dessication (sec. 6.26). tion. On steeper slopes of the dam and transitions
EARTHFILL DAMS 277

,&rest El. 3945.0, Length- 1,680'


cobbles compacted
by crawler-type tractor

Volume=85,940yd3

Figure 6-76.-Picacho South Dam. A detention dam located on the South Branch of Picacho Arroyo, New Mexico (constructed
195354). From 103-D-586.

@-Riprap-. -El. 43800 11940 Enlargement J

Original crest EI 4374.0 Length- 9. 050


Storage = 46,300 acre-feet ,,.- -C/ay,sand, gravel

Clay, sand, gravel


and

Origmal ground surface- .. -Strlpptng

Valume=599,300yd3

Figure 6-77.-Pishkun Dikes. located offstream from the Sun River, Montana (constructed 1930-31). From 103-D-580.

(Gravel surfacing

Max. WS. El. 3282.30


500 acre-feet storage7

Soil-cement facing

Volume=220,000yd3

Figure 6-78.-Lubbock Regulating Reservoir. Located offstream near Lubbock, Texas [completed 1966). From 662-D-409.

Length- 3000
Mar ws El 83670;

Sluiced sand 8 grave/

Valumei67,478y2

Figure 6-79.-Shadow Mountain Dam. Located on the Colorado River, Colorado (constructed 1943-46). From 103-D-582.
278 DESIGN OF SMALL DAMS

Storoge=l0,i50acre-feet Crest El. 1014. 0, Length - 1,750

k---Grout holes @ 10 crs.

Volume=220,000yd3

Figure 6-80.-Sodo Lake Dike. Located offstream from the Columbia River, Washington (constructed 1950-52). From
103-D-584.

Storage=Is,200ocre-feet
Storage=I6,200ocre-1 Length- 15,569
N. WS.
Iv.5 El. 6/29.2-;1
--
24Riprap on
-Dumped earth ma terlal

Vo/ume=826, 796yd3

Figure 6-81.-Stubblefield Dam. Located offstream from the Vermejo River, New Mexico (constructed 1953-54). From
103-D-585.

between the dike and the dam, soil-cement was used weak clay zones are present in the foundation. The
to protect the embankment. The alluvium was rel- upstream berm is provided by waste material from
atively shallow, and an earth cutoff protected by a required excavation. Although somewhat higher (70
downstream filter and extending through the al- to 75 ft) than the standard for a small dam, San
luvium was used as the major seepage control fea- Justo Dike is a, good example of current design
t,ure of the dam foundation. practice.
(bb) Sun Judo D&-This dike (fig. 6-87) is (cc) Calamus Dam.-This dam (fig. 6-88) is lo-
part of an offstream reservoir project located near cated in the sandhills of Nebraska. It was designed
Hollister, California, between the Calaveras and and constructed during the early to mid-1980s. It
San Andreas faults. Design and construction were is not a small dam (about 95 ft high), but is included
accomplished during the mid-1980s. The dike will because it illustrates so many seepage control fea-
almost certainly be shaken one or more times in its tures. It is founded on moderately thick alluvial and
lifetime by a large magnitude earthquake. The sec- eolian deposits of silts and sands that overlay the
tion illustrates a recent typical embankment dam Ogallala Formation. The embankment and foun-
design for an active seismic region. Note the thick dation materials are very erodible and subject to
filters and drains in the inclined and horizontal piping. A total positive cut,off was impossible; there-
drainage layers downstream of the impervious zone. fore, the design concentrated on reducing and con-
Also illustrated is the use of stability berms nec- trolling seepage. An upstream impervious blanket
essary to obtain adequate static stability because and slurry wall were used to reduce seepage. An
EARTHFILL DAMS 279

inclined (chimney drain) and horizontal drainage The Ogallala Formation is a thick, pervious for-
blanket, toe drain, and relief wells were used down- mation that is near the surface across much of the
stream to collect and control the seepage that will midwestern United States and is an important
occur. The slurry wall penetrates to the Ogallala source of water in that area. Its existence precluded
Formation on the right side of the river, but only a positive impervious cutoff.
to a depth of 45 feet on the left side of the river.

Sal

(A) MAXIMUM DIKE SECTION

------Sand,gravel
and cobbles

Remove humus,vegetotion,ond other objectionable material-,----FT-- 12 Horizontal width


Clay,silt,sand
and gravel

(B) FREEBOARD DIKE SECTION

Figure 6-82.--Sections of Tiber Dike. located on the Marios River, Montana (constructed 1953-56). 288-D-2501.

Sloped to drain 3 Selected surfacing


Clay, silt. sand and gravel
Crest El. 5882, Length 720
Ma%. It.9 El. 5878

Miscellaneous material
or sand, gravel and cobbles
Key trench above El. 5855
in abutments only
Volume=70,000yd3

Figure 6-83-Sheep Creek Barrier Dam. A sediment control dam in southern Utah (constructed in 1956). From 788-D- 12.
280 DESIGN OF SMALL DAMS

DIAGRAM FOR CAMBER ON CREST OF DAM

Figure 6-84.-General plan for Wasco Dam. Located on Clear Creek (a tributary of White River), Oregon (completed 1958).
From 350-D-4.
EARTHFILL DAMS 281

5~Oil-OReCtng$r Cnhf

PROFlLE ON E OUTLET WORKS

* 9 .

LCliE or FEFT
RESERVOIR STORAGE ALLOCATlON

Figure 6-85.-Sections for Wasco Dom. located on Clear Creek (a tributary of White River), Oregon (completed 1958).
From 350-D-4.
282 DESIGN OF SMALL DAMS

kc New crest of dike


( Crest of existing dike
New crest of dike. El. 3612

4 gravel surfacing

Existing dike (remo ved)

und surface

ripping as dir ected


t Stripping as directed

-Alluviu of formation

Surface of firm

Impervious material of low plasticity clay and

Silty sand compacted to B-inch lifts by tamping


rollor. SC. CL, SM.

Pervious material of well graded to poorly graded


0
sand, compacted by vibratory compactor in IP-inch
lifts, SP, SW.

Pervious sandstone, cobbles, and gravel compacted


by vibratory compactor in 16-inch lifts.

Figure 6-86.-Dike section of Ute Dom, New Mexico. This structure on the Canadian River was constructed (1982-83)
in conjunction with raising the dam to provide additional storage and flood capacity. 103-D-1832.

ZONES

Figure 6-87.- San J&o Dike. Constructed (1985) in conjunction with Son Juste Dam to form an off-stream reservoir neor
Hollister, California. From 921 -D- 1071.
EARTHFILL DAMS 283

Top of inactive
El 2213.3

eAlluvlum L-r
Slurry trench depth varies

Ogallala on right aide

0 Fine sand containing 20%-50X fines

0 Clean fine sand with less than 10% fines

0 Fine sand containing 10%-20X fines

NOTE: Chimney drain and drainage blanket-processed


and washed asnda and gravels with zero tines

Figure 6-88.-Coiamus Dam. Constructed (1985) on the North Loup River, Nebraska. From 628-D-253.

G. BIBLIOGRAPHY

6.28. Bibliography. mation, 480 pp., U.S. Government Printing Office,


[l] Schuyler, J. D., Reservoirs for Irrigation, John Wiley Washington, D.C., 1981.
and Sons, Inc., New York, NY, 1905. [13] Terzaghi, Karl, and R. B. Peck, Soil Mechanics in En-
[2] Justin, J. D. Earth Dams Projects, John Wiley and gineering Practice, p. 230, John Wiley and Sons, Inc.,
Sons, Inc., New York, NY, 1932. New York, NY, 1948.
[3] Bassel, Burr, Earth Dams, Engineering News Publish- 141 Rice, 0. L., and H. G. Arthur, The Most Recent Meth-
ing Co., New York, NY, 1907. ods Developed to Avoid Piping or Blowouts in Dams,
[4] Justin, J. D., Julian Hinds, and W. P. Creager, Engi- Third Congress on Large Dams, vol. II, Question No. 10,
neering for Dams, John Wiley and Sons, Inc., vol. III, p. R. 49, Stockholm, Sweden, 1948.
675, New York, NY, 1945. 151 Casagrande, Arthur, Seepage Through Dams, Journal
[5] Symposium on Cement and Clay Grouting of Foun- New England Water Works Association, p. 131, June 1937.
dations, Task Committees on Cement and Clay Grout- 161 Taylor, D. W., Fundamentals of Soil Mechanics, p. 156,
ing, ASCE Proceedings, vol. 84, Journal of the Soil John Wiley and Sons, Inc., New York, NY, 1948.
Mechanics and Foundations Division, No. SMl, papers 171 Creager, W. P., J. D. Justin, and Julian Hinds, Engi-
No. 1544 to 1552, February 1958. neering for Dams, John Wiley and Sons, Inc., ~01s. I and
[6] Sherard, J. L., R. J. Woodward, S. F. Gizienski, and W. III, New York, NY, 1945.
A. Clevenger, Earth and Earth-Rock Dams, John Wiley 1.181 Cedergren, H. R., Seepage, Drainage, and Flow Nets, p.
and Sons, Inc., New York, NY, 1963. 110, John Wiley and Sons, Inc., New York, NY, 1967.
[ 71 Pressure Grouting, Bureau of Reclamation, Techni- [19] Justin, J. D., Julian Hinds, and W. P. Creager, Engi-
cal Memorandum No. 646, June 1957. neering for Dams, John Wiley and Sons, Inc., vol. III, p.
[8] Grouts and Drilling Muds in Engineering Practice, 695, New York, NY, 1945.
Symposium organized by the British National Society of [20] Lane, K. S., and P. E. Wohlt, Performance of Sheet
the International Society of Soil Mechanics and Foun- Piling and Blankets for Sealing Missouri River Reser-
dation Engineering, Butterworths, London, 1963. voirs, Proceedings Seventh Congress on Large Dams,
[9] Policy Statements for Grouting, ACER Technical pp. 255-279, 1961.
Memorandum No. 5, Assistant Commissioner-Engineer- [21] Report on Steel Sheet Piling Studies, Soil Mechanics
ing and Research Center, Bureau of Reclamation, 1984. and Materials Division, Canadian Department of Agri-
[lo] Gibbs, H. J., and W. G. Holtz, Research on Deter- culture, Saskatoon, SK, 1951.
mining the Density of Sands by Spoon Penetration Test- [22] Mixed-In-Place Piles, Special Report No. 109, Intru-
ing, Proceedings of the Fourth International Conference sion-Prepakt, Inc., Cleveland, OH, 1968.
on Soil Mechanics and Foundation Engineering, vol. I, [23] Jones, Jack C., Deep Cut-Offs in Pervious Alluvium,
p. 38 (adapted from fig. 7), London, 1957. Combining Slurry Trenches and Grouting, Ninth Con-
[ll] Earth Manual, vol. 2, Test Designations, Bureau of gress on Large Dams, vol. I, p. 509, 1967.
Reclamation, Denver, CO, 1987. [24] Mud Technology Handbook, Baroid Division, National
[12] Ground Water Manual, rev. reprint, Bureau of Recla- Lead Co., Houston, TX, 1965.
DESIGN OF SMALL DAMS

(251 Bibliography on Chemical Grouting, Third Progress ish Method of Analyzing the Stability of Earth Slopes,
Report - Committee on Grouting, ASCE Proceedings, Zkansactions, Second Congress on Large Dams, pt. I of
vol. 92, Journal of the Soil Mechanics and Foundations app. A, vol. IV, p. 540, Washington, D.C., 1936.
Diuision, No. SM6, p. 39, November 1966. [43] Wright, S. G., A Study of Slope Stability and Un-
[26] Bennett, P. T., The Effect of Blankets on Seepage drained Shear Strength of Clay Shales, Ph.D. disser-
Through Pervious Foundations, Transactions ASCE, tation, University of California, Berkeley, 1969.
vol. III, p. 215, 1946. [44] Spencer, E., A Method of Analysis of the Stability of
[27] Terzaghi, Karl, and R. B. Peck, Soil Mechanics in En- Embankments Assuming Parallel Interslice Forces,
gineering Practice, p. 164, John Wiley and Sons, Inc., Geotechnique, pp. 11-26, 1967.
New York, NY, 1967. [45] Chugh, A. K., User Information Manual for Slope Sta-
[28] Cedergren, H. R., Geological Considerations in the De- bility Analysis Program SSTABZ-A Modified Version
sign of Reservoir Seepage Control Systems, Symposium of SSTABl by S. G. Wright, Bureau of Reclamation,
Reservoir Leakage and Ground Water Control, Ass. Eng. Engineering and Research Center, Denver, CO, 1981.
Geol. Nat. Meeting, Seattle, WA, 1968. [46] Cedergren, H. R., Seepage, Drainage, and Flow Nets,
[29] Bertram, G. E., An Experimental Investigation of Pro- John Wiley and Sons, Inc., p. 148, New York, NY, 1967.
tective Filters, Graduate School of Engineering, Har- [47] Algermissen, S. T., Seismic Risk Studies in the United
vard University, Soil Mechanics Series No. 7, January States, Proceedings of the Fourth World Conference on
1940. Earthquake Engineering, Chilean Association for Seis-
[30] Soil Mechanics Fact Finding Survey; Seepage Studies; mology and Earthquake Engineering, Santiago, Chile,
Progress Report, Technical Memorandum No. 175-1, 1969; also reprinted by U.S. Department of Commerce,
U.S. Army Corps of Engineers, Waterways Experiment ESSA, Coast and Geodetic Survey, 20 pp., 1969.
Station, Vicksburg, MS, March 1, 1941. [48] Woodward, Clyde, Sherard and Associates, A Study of
[31] The Use of Laboratory Tests to Develop Design Cri- the Influence of the Earthquake Hazard on the Design
teria for Protective Filters, Earth Laboratory Report of Embankment Dams, report prepared for the state of
No. EM-425, Bureau of Reclamation, June 20, 1955. California Department of Water Resources, July 1966.
[32] Middlebrooks, T. A., and W. H. Jervis, Relief Wells [49] Vibration Effects of Earthquakes on Soils and Foun-
for Dams and Levees, Transactions ASCE, vol. 112, p. dations, STP 450, American Society for Testing and
1321, 1947. Materials, 1969.
[33] Turnbull, W. J., and C. I. Mansur, Relief Well Systems [50] Newmark, N. M., Effects of Earthquakes on Dams and
for Dams and Levees, Ikansactions ASCE, vol. 119, p. Embankments, Geotechnique, vol. XV, No. 2, June 1965.
842, 1954. [51] Seed, H. B., A Method for Earthquake Resistant De-
[34] Mansur, C. I., and R. I. Kaufman, Control of Under- sign of Earth Dams, Journal of the Soil Mechanics and
seepage, Mississippi River Levees, St. Louis District, Foundation Division, ASCE, January 1966.
ASCE Proceedings, vol. 82, Journal of the Soil Mechanics [52] Efficacy of Partial Cutoffs for Controlling Underseep-
and Foundations Division, No. SMl, paper No. 864, Jan- age Beneath Levees, Technical Memorandum No. 3-
uary 1956. 267, U.S. Army Corps of Engineers, Waterways Exper-
[35] Turnbull, W. J., and C. I. Mansur, Underseepage and iment Station, Vicksburg, MS, January 1969.
Its Control - A Symposium, Transactions, ASCE, vol. [53] Wiegel, R. L. (coordinating editor), Earthquake Engi-
126, pt. I, pp. 1,4281,568, 1961. neering, Prentice-Hall, Englewood Cliffs, NJ, 1970.
[36] Clevenger, W. A., Experiences With Loess as a Foun- [54] Gibbs, H. J., Estimating Foundation Settlement by
dation Material, ASCE Proceedings, vol. 82, Journal of One-Dimensional Consolidation Tests, Engineering
the Soil Mechanics and Foundations Division, No. SM3, Monograph No. 13, Bureau of Reclamation, 1953.
paper No. 1025, July 1956. [55] Review of Slope Protection Methods, Subcommittee
[37] Gibbs, J. J., and W. Y. Holland, Engineering and Pe- on Slope Protection, Soil Mechanics and Foundation Di-
trographic Properties of Loessial Soils, Engineering vision, Proceedings ASCE, vol. 74, June 1948.
Monograph No. 28, Bureau of Reclamation, November [56] Slope Protection for Earth Dams, Preliminary Re-
1969. port, US. Army Corps of Engineers, Waterways Exper-
[38] Properties Which Divide Loose and Dense Unce- iment Station, Vicksburg, MS, March 1949.
mented Soils, Earth Laboratory Report No. EM-608 [57] Holtz, W. G., and F. C. Walker, Soil-Cement as Slope
Bureau of Reclamation, January 6, 1961. Protection for Earth Dams, Proceedings of ASCE, Jour-
[39] Terzaghi, Karl, Simple Tests Determine Hydrostatic nal of Soil Mechanics and. Foundation Division, vol. 88,
Uplift, Engineering News-Record, p. 872, June 18, 1936. SM6, pp. 107-134, December 1962.
[40] Timoshenko, S., and J. N. Goodier, Theory of Elas-
ticity, p. 14, McGraw-Hill, New York, NY, 1951. Billig, K., Thixotropic Clay Suspensions and Their
[41] Hilf, J. W., Estimating Construction Pore Pressures Use in Civil Engineering, Civil Engineering and Public
in Rolled Earth Dams, Proceedings of the Second Con- Work Review, p. 1,573, December 1961.
ference on Soil Mechanics and Foundations Engineering,
vol. III, p. 234, Rotterdam, June 1943. DAppalonia, David J., Soil-Bentonite Slurry Trench
[42] May, D. R., Application of the Planimeter to the Swed- Cutoffs, Proceedings of the ASCE, Journal of the Geo-
EARTHFILL DAMS

technical Engineering Division, vol. 106, No. GT4, pp. itors, sec. 18, McGraw-Hill Book Co., New York, NY,
399-417, April 1980. 1969.
Dunnicliff, John, and Don U. Peere, Judgment in Geo- Millet, Richard A., and Jean Yves-Perez, Current USA
technical Engineering - The Professional Legacy of Ralph Practice: Slurry Wall Specifications, Proceedings of the
B. Peck, John Wiley and Sons, Inc., New York, NY, 1984. ASCE, Journal of the Geotechnical Division, vol. 107, No.
GT8, pp. 1,041-1,055, August 1981.
Gardner, W. I., Dams and Reservoirs in Pleistocene-
Eolian Deposit Terrane of Nebraska and Kansas, Sym- Morgenstern, N., and I. Amir-Tahmasseb, The Sta-
posium Reservoir Leakage and Ground Water Control, bility of a Slurry Trench in Cohesionless Soils, Geo-
Ass. Eng. Geol. Nat. Meeting, Seattle, WA, 1968. technique, vol. 15, pp. 387-395, 1965.
Gadsby, J. W., and F. A. Bares, Arrow Project Coffer- Sherard, James L., Statistical Survey of the Dia-
dam, Canadian Geotechnical Journal, vol. 5, No. 3, Au- phragm Wall Applications, Specialty Session No. 14,
gust 1968. Seventh International Conference on Soil Mechanics
and Foundation Engineering, Mexico, 1969.
Gerwick, Ben C., Slurry-Trench Techniques for Dia-
phragm Walls in Deep Foundation Construction, Civil Xanthahos, Petros P., Slurry Walls, McGraw-Hill Book
Engineering, pp, 70-72, December 1967. Co., New York, NY, 1979.
Gibbs, H. J., and C. T. Coffey, Application of Pore Construction of Slurry Trench Cutoff, U.S. Army En-
Pressure Measurements to Shear Strength of Cohesive gineer District, Savannah, Corps of Engineers, Savan-
Soils, Earth Laboratory Report No. EM-761, Bureau of nah, GA, 1968.
Reclamation, June 1969.
Digging a 95-Foot Deep Slurry Trench, Western Con-
Golze, Alfred R., Handbook of Dam Engineering, Van struction, pp. 66-70, November 1966.
Nostrand Reinhold Co., New York, NY, 1977.
Drilling Mud Data Book, Baroid Division, National
Haug, Moir Dee, Optimization of Slurry Trench De- Lead Co., Houston, TX, 1965.
sign, (thesis) University of California, Berkeley, 1980.
Drilling Mud Reference Manual, Baroid Division, Na-
Hirschfeld, Ronald C., and Steve H. Poulos, Embank- tional Lead Co., Houston, TX, 1965.
ment-Dam Engineering, John Wiley and Sons, Inc., New
York, NY, 1973. Earthquake Activity in Western United States, Dams
Branch Report No. DD-8, Bureau of Reclamation, Den-
Kapp, Martin S., Slurry-Trench Construction for ver, CO, April 1968.
Basement Wall of World Trade Center, Civil Engineer-
ing, pp. 36-40, April 1969. Soil-Cement Slope Protection for Earth Dams, Port-
land Cement Assn., Chicago, IL, (undated).
Kulhawy, Fred H., editor, Recent Developments in
Geotechnical Engineering for Hydro Projects, Proceed- Symposium on Earth and Rockfill Dams, ~01s. I and
ings of the Geotechnical Engineering Division at the III, Indian National Society of Soil Mechanics and Foun-
ASCE International Convention, New York, NY, May 11, dation Engineering, 1968.
12, 1981.
Wanapum Hydroelectric Development Final Report,
Lowe, John, Embankment Dams, Handbook of Applied Public Utility District of Grant County, ~01s. I and II,
Hydraulics, 3d ed., C. V. Davis and K. E. Sorensen, ed- Ephrata, WA, 1969.
Chapter 7

Rockf ill Dams


A. GENERAL

7.1. Origin and Usage.-Rockfill dams are while simultaneously placing the embankment. In
generally conceded to have had their origin over 100 addition, uplift pressures and erosion caused by
years ago during the California Gold Rush. From seepage through rockfill material do not generally
the late 1800s to the mid-1930s, many rockfill constitute significant design problems.
dams were constructed. The design and construc- Increasing interest is being shown in using flow-
tion of a number of these dams are described by through rockfill sections in conjunction with di-
Galloway [ 11. version dams to handle sudden floodflows when the
Interest in constructing rockfill dams diminished cost of diversion is high [4, 5, 6, 71. This type of
after the mid-1930s because of the increased costs structure requires that a grid of welded reinforcing
of obtaining and placing large amounts of rockfill rods be placed across the downstream face of the
material; although a number of large rockfill dams dam, below a given elevation, and anchored to the
were constructed in the 1950s [2]. Rockfill dam rockfill so that large flows through the embankment
construction has increased markedly since 1960. do not displace the rock. The rods are usually l/2 to
This is attributed to the use of more remote sites, 3/ inch in diameter and are spaced so that rectangles
more economical quarrying and placing operations, 1 foot vertically by 3 to 4 feet horizontally are
the use of excavated material in random zones, bet- blocked out on the downstream face of the em-
ter design details, more general knowledge con- bankment. This grid is then welded to reinforcing
cerning rockfills, and the recent advent of pumped- rods that are anchored 10 to 15 feet in the rockfill.
storage projects in mountainous terrain. Recent The use of flowthrough rockfill dams presents the
progress in rockfill dams is discussed by Cooke [3]. designer with unique problems concerning the ex-
The excellent performance of an increasing number tent of downstream reinforcing and the ability of
of rockfill dams is another beneficial factor rec- the section to resist overtopping. Therefore, this
ommending their use. type of structure should be designed only by an
Rockfill dams can prove economical when any of experienced design engineer.
the following conditions exist: 7.2. Definition and Types of Rockfill Dams.-
l Large quantities of rock are readily available Rockfill dams have been defined as follows [8, 91:
or will be excavated in connection with the A dam that relies on rock, either dumped in lifts
project, such as from a spillway or tunnel. or compacted in layers,-as a major structural ele-
l Earthfill materials are difficult to obtain or re- ment. An impervious membrane is used as the
quire extensive processing before use. water barrier and can be placed either within the
l Short construction seasons prevail. embankment (internal membrane) or on the up-
l Excessively wet climatic conditions limit the stream slope (external membrane). Various mate-
placement of large quantities of earthfill rials have been used for this membrane including
material. earth materials, concrete, steel, asphaltic concrete,
l The dam is to be raised at a later date. and wood.
Other factors that favor the use of a rockfill dam Rockfill dams may be classified into three groups,
are the ability to place rockfill throughout the win- depending on the location of the membrane: (1)
ter and the possibility of grouting the foundation central core, (2) sloping core, and (3) upstream
membrane, or decked. Each membrane location
Numbers in brackets refer to entries in the bibliography (sec. 7.14). has its advantages and disadvantages, which vary

287
288 DESIGN OF SMALL DAMS

according to the type of membrane, materials avail- ternal) and upstream (external) membranes to
able at the site, and foundation conditions. Central distribute stabilizing reactions against sliding is
and sloping cores, which are internal membranes, shown on figure 7-l.
are generally constructed of impervious earth ma- Upstream membranes have the following
terials. Economic analyses should be made to de- advantages:
termine the type of material to use in constructing l Readily available for inspection and repair.
the membrane, whether it be internal or external. l Can be constructed after completion of the
If an internal membrane is selected, a central ver- rockfill section.
tical core is recommended. This type of core pro- l Foundation grouting can be performed simul-
vides maximum contact pressure with the taneously with rockfill placement.
foundation and requires less strict construction l A larger portion of the dam is available for sta-
control than a sloping core. bility against sliding.
If an external membrane is used, it should be l Can be used as slope protection.
constructed of concrete, asphaltic concrete, or steel. l It is relatively easy to raise the dam at a later
Advantages of the internal membrane include (1) date.
less total area exposed to water, (2) shorter grout l In wet climates, the absence of impervious soil
curtain lengths, and (3) protection from the effects fill simplifies and speeds construction.
of weathering and external damage. The prime dis- If an upstream membrane is used, the reservoir
advantages of an internal membrane are the ina- should be capable of being drawn down to an ele-
bility to place rockfill material without the vation that will permit inspection and repair; tel-
simultaneous placement of impervious core mate- evision cameras or audio devices may be used for
rial and filters, the inaccessibility of the membrane leak detection, and minor repairs may be made by
for damage inspection, the difficulty in correcting divers.
damage should it occur, and the dependenceon a If an earth-core rockfill dam is used, it requires
smaller section of the dam for stability against slid- the use of adequate filters both.upstream and down-
ing. The difference in the abilities of central (in- stream; the filters should satisfy the requirements

(A) UPSTREAM MEMBRANE


P = Resultant water force
f = Friction forces reststIng slldlng

P-

(B 1 CENTRAL MEMBRANE

Figure 7-1 .-Resistance to sliding for embankments. 288-D-2796.


ROCKFILL DAMS 289

listed in section 6.10(i). If adequate earth material processing costs can be extreme. Construction con-
for either the core or the filter is not available at trol costs of the earth-core rockfill dam will also be
the site and separations of impervious material or increased significantly if several filter layers are re-
manufactured filters are required, an earth-core quired to prevent piping.
rockfill dam may be uneconomical because filter

B. FOUNDATION DESIGN
7.3. Foundation Requirements and Treat- dam, foundations are usually grouted. The need for
merit.-The foundation requirements for a rockfill grouting and the extent required should be based
dam are less stringent than those for a concrete on careful study of the site geology, on a visual
gravity dam, but more stringent than those for an examination of the drill cores from the rock foun-
earthfill dam. dation, and on drill-hole water-loss values. If no
Bedrock foundations that are hard and erosion such data are available, it should be assumed that
resistant are the most desirable for rockfill dams. grouting will be required, except where the reservoir
Foundations consisting of river gravels or rock frag- is completely drawn down each year and grouting
ments are acceptable, but the foundation should be requirements can be based on seepage observations
inspected by competent engineers and a positive during the first few years of operation,
cutoff to bedrock should be used. The foundation Cutoff walls excavated to various depths into
should be selected and treated from the viewpoint bedrock are generally used to prevent leakage in the
of providing minimum settlement to the rockfill upper few feet of the foundation, to facilitate grout-
embankment. All materials in cracks, faults, or deep ing operations, to provide a watertight seal with the
pits that may eventually erode into the rockfill, membrane, and to support the downward thrust of
either from the foundation or the abutment, should the membrane. Figures 7-2, 7-3, and 7-4 illustrate
be covered with filters (sec. 6.10(i)) or removed and typical cutoff wall details. Drainage galleries are
backfilled with concrete. For an earth-core rockfill sometimes used in conjunction with cutoff walls to
dam, all joints and cracks beneath the core and the facilitate later grouting and to determine seepage
filters should be cleaned and filled with concrete locations and quantities, but they are not recom-
[lOI. mended for small dams.
The usual method of treating the foundations to Recently [ll], designers have used the doweled
prevent underseepage is cement grouting beneath cutoff slab shown on figure 7-5 in conjunction with
the cutoff; in addition, potential pervious zones up- concrete facings to provide the foundation-
stream from the impervious membrane can be blan- membrane seal. Doweled cutoff slabs have the ad-
keted with impervious material. vantage of not requiring extensive excavations in
The alignment of the dam should be selected so rock, thereby allowing grouting operations to begin
that either minimum embankment volume or min- earlier, speeding completion time, and reducing de-
imum membrane exposure is attained, depending sign costs. Doweled cutoff slabs can be used where
on which criterion is economically more important. the bedrock is sound and few underseepage- prob-
Foundation treatment must be sufficient to sat- lems are expected. When uncertainty concerning
isfy the following criteria: the permeability of upper portions of the founda-
l Minimum leakage tion contact exist, such as for soft rock, a cutoff
l Prevention of piping wall into bedrock can provide increased protection
l Limited settlement and allow an examination of questionable material.
l Sufficient friction development between abut- A minimum width and depth of 3 feet is rec-
ments and foundation to ensure sliding sta- ommended for cutoff walls in sound rock; deeper
bility walls should be used in unsound, broken, or closely
7.4. Membrane Cutoffs.-Of critical impor- jointed rock. The width of the doweled slab should
tance in the functioning of a rockfill dam are the be determined by foundation, construction, or
prevention of seepage beneath the dam and the ef- grouting requirements. In addition to preventing
fecting of a watertight seal between the membrane underseepage, both the cutoff wall and the doweled
and the foundation. To prevent seepage beneath the cutoff slab must be designed to provide adequate
290 DESIGN OF SMALL DAMS

Reinforcement

Pervious zcne

Concrete membrane

Original Oround surface

waterstop

Figure 7-2.-Detail of concrete membrane at cutoff wall. 103-D-1878.

Pervious acne

ease or leveling ccur*e

Asphaltic-concrete membrane

Original QrCud Surface

sumed rock surface


oncrete cutoff wall

-----Grout hole

Figure 7-3.-Detail of asphaltic-concrete membrane at cutoff wall. 103-D- 1879.

Steel plate-,

Original ground surface-~

fill

---Concrete cutoff wall


-Anchor dowel

I--- Grout holes

Figure 7-4.-Detail of steel-plate membrane at cutoff wall. 288-D-2503.


ROCKFILL DAMS 291

Concrete

/I 1 hu+Off (Slab)
Dowel
" ,c hDowe1

Grout line

Figure 7-S-Doweled cutoff slob used with upstream concrete membrane.


288-D-2797.

support for the thrust of the membrane and, in the The cutoff should extend along the entire up-
case of steel membranes, any tension imparted to stream contact between the membrane and the
the cutoff caused by embankment settlement. foundation.

C. EMBANKMENT DESIGN
7.5. Selection of Rock Materials.-A great va- integrate. Igneous, metamorphic, and sedimentary
riety of rock types have been used in the construc- rocks have all been used successfully in embank-
tion of rockfill dams. The types of rock have ranged ment sections, and only general advice can be given
from hard, durable, granite and quartzite to weaker concerning rock types because each damsite pre-
materials, such as graywacke sandstone and slaty sents a unique problem in the use of the nearby
shale. In earlier years, it was thought that only the rock materials. As an aid to the designer, part E of
highest quality rockfill material should be used; chapter 5 gives the classification and engineering
however, with the advent of thinner lifts and more properties of rocks.
efficient compaction techniques, rock having less Results from laboratory tests that measure the
desirable characteristics has become feasible for use abrasion resistance, freeze-thaw characteristics, and
within embankment sections. The use of rock from the percent of water absorption can be used to eval-
excavations for spillways, outlet works, tunnels, and uate the suitability of the rockfill. Results from petro-
other appurtenant structures has reduced the con- graphic analyses can be used to distinguish minerals
struction costs of rockfill dams without impairing known to weather easily, and unconfined or triaxial
the usefulness or stability of embankments. If small compression tests can determine the strength prop-
amounts of the less desirable rock types are avail- erties of the rock. One of the best methods of deter-
able, they can be used in random zones within the mining the resistance of a rock to weathering is simply
embankment; the use of material in random zones to examine its inplace condition; however, this does
is discussed in section 6.18(a). not always indicate how the material will perform
Preferably, rock material should be hard, dura- within the fill. Materials available at the site should
ble, able to withstand disintegration from weath- be examined by constructing test embankments if
ering, and able to resist excessive breakdown from economically possible, especially when the material
quarrying, loading, hauling, and placing operations. properties are questionable. Test fills can determine
(Figure 7-6 shows the granite rockfill on the down- the following items:
stream face of Montgomery Dam.) The rock should Whether or not marginal materials can be used
l

also be free of unstable minerals that would weather How selected embankment materials will per-
l

mechanically or chemically, causing the rock to dis- form during compaction


292 DESIGN OF SMALL DAMS

to the correct size, angular, and quite sound


(G. = 2.87).
3. Amphibolite from Oroville Dam. -A meta-
volcanic rock, rounded to subrounded parti-
cles with some subangular fine-sand particles,
river-dredged material, hard (G. = 2.86 to
2.94).
The gradation curves for the actual rock fill ma-
terial and for the modeled material are shown on
figure 7-7.
Although [14] was primarily concerned with the
use of rock fill material in high dams, the following
general conclusions apply to rockfill dams of all
sizes:
Figure 7-6.-Granite rockfill on downstream face of .Rockfill materials can be successfully modeled
Montgomery Dam, Colorado. CH-520- 150.
so that the strength and deformation charac-
teristics of the actual material can be obtained
.The correct type of compaction equipment for from small-scale tests.
each material .At any given confining pressure, as the particle
.The required number of compaction passesfor size of the specimen increases, the angle of in-
each material ternal friction decreasesa small but significant
.The correct lift thickness for each material amount.
.The necessity for changing the embankment .Rockfill materials composedofwell-graded and
section to accommodate new materials or dif- well-rounded particles are superior to uni-
ferent material properties formly graded angular rockfill materials, es-
As an example, Crisp [12] reports that significant pecially for high dam's.
changeswere proposed in the design of Carters Dam .For any given particle size, as the confining
from results obtained by testing embankment sec- pressure of the sample increases, the angle of
tions of quartzite, phyllite, and argillite. internal friction decreases.
The effect of quarry blasting methods on the gra- Figure 7-8 illustrates the variation of the angle
dation of the rock should also be examined, as well of internal friction with both particle size and con-
as the required extent of quarrying. fining pressure. Although most of the confining
Also of great importance to the design engineer pressures shown are greater than those attained in
selecting the type of rock is the degree to which small dams, the general reduction in friction angle
small-scale triaxial compression tests provide shown on figure 7-8 should be of great interest to
strength parameters applicable to the actual designers.
rockfill. The details of testing and further conclusions
Very limited data are available on this subject; regarding the strength and deformation properties
however, Leps [13] has summarized available data of rock fill materials and the crushing characteris-
and Marachi et al. [14] have examined this problem tics of rock subjected to high confining pressures
by testing 36-, 12-, and 2.8-inch-diameter specimens can be found in [14].
in drained triaxial compression tests using parallel 7.6. Embankment Sections.-Embankment
grain-size curves and identical grain slopes (mod- slopesused for rockfill dams have evolved from very
eling) to examine the effects of grain size on the steep slopes, usually 0.5:1 to 0.75:1 (horizontal to
strength and deformation characteristics of rockfill vertical) on early rock fill dams, to the flatter slopes
material. They also investigated the effect of par- of 1.3:1 to 1.7:1 used today. Earlier rockfill dams
ticle crushing. used upstream membranes exclusively and were
Three types of material were tested as follows: constructed with steep upstream and downstream
1. Argillite from Pyramid Dam. -A fine-grained slopes to minimize the volume of rockfill. Because
sedimentary rock, quarry blasted, angular, these slopeswere considerably steeper than the nat-
with relatively weak particles (GB= 2.67) ural slope of dumped rock, they were stabilized by
2. Crushed basalt. -Quarry blasted and crushed thick zones of crane-placed, dry rubble masonry,
ROCKFILL DAMS 293

US STANDARD SIEVE SlZES

PARTICLE SIZE-INCHES
(A) PYRAMID DAM

S STANDARD SIEVE S,ZES


16

PARTICLE SIZE-INCHES
(6) CRUSHED BASALT

US STANDARD SIEVE SliES

Figure 7-7.-Grain size distribution far modeled rockfill materials.


Adapted from [ 141. 288-D-2798.
294 DESIGN OF SMALL DAMS

55
PYRAMID DAM I

35 2.0 3.0 6.0 IO


0.3 0.6 I.0
MAXIMUM PARTICAL SIZE, INCHES

Figure 7-&--Effect of maximum particle size on the angle of internal friction. Adapted from [ 141.
288-D-2799.
ROCKFILL DAMS 295

which provided the bedding for the upstream slope and a 1.7:1 upstream slope for asphaltic-concrete
protection. The rockfill portions of these dams were facings. Downstream slopes of 1.3:1 to 1.4:1 may be
constructed by dumping the rockfill in thick lifts, used in all cases.
which ranged from 30 to 165 feet. Later designs The upstream and downstream slopes for central
eliminated the rubble masonry on the downstream or sloping earth-core rockfill dams depends on the
slope by flattening it to the angle of repose of the size and soil properties of the earth core, the width
rock, but the very steep upstream slope was re- of filter zones required, type of foundation material,
tained. Because most of the upstream zones were drawdown requirements, construction sequence,
constructed by crane placement of large rocks, the etc., with each site presenting its own unique prob-
cost of the dams continually increased. Gradually, lems. Generally, the upstream and downstream
designers found that it was more economical to use slopes of a typical earth-core rockfill dam are 2:l
slopes approximating the angle of repose of the rock or slightly steeper where all conditions are favor-
material and to eliminate crane placement in favor able, but may be as flat as 4:l (or flatter) for un-
of compacted rockfills. favorable conditions. A typical embankment section
The upstream and downstream slopes of a dam for a central earth-core rockfill dam is shown on
should be based on the type of impervious mem- figure 7-9.
brane and its location. Rockfill dams having central A typical section for a decked (upstream mem-
or sloping cores have slopes ranging from 2:l to 4:l brane) rockfill dam is shown on figure 7-10. The
upstream and downstream-usually tending toward interior section of the decked rockflll dam can be
2:l or slightly steeper when all conditions are fa- divided into three major zones, as shown on figure
vorable. However, dams with upstream membranes 7-10. These zones can be described as follows:
usually have upstream slopes of from 1.3:1 to 1.7:1 Zone C: The larger downstream zone of the dam,
and downstream slopes approximating the natural consisting of the best quality, larger,
slope of the rock. compacted rock; this zone provides high
Most asphaltic-concrete-faced dams have been stability to the section.
constructed with upstream slopes of 1.6:l to 1.7:l Zone B: Rock of lesser quality than zone C, such
tofacilitate construction of the membrane; as that excavated from the spillway;
whereas, most steel- and concrete-faced rockfill used to minimize total dam costs.
dams have slopes of 1.3:l to 1.4:1. A review of avail- Zone A: Well-graded, smaller rock and gravel;
able literature indicates that very few failures have used to provide bedding for the up-
occurred for these slopes. Therefore, small rockfill stream membrane and to retard ex-
dams with good foundations could have 1.3:1 to 1.4:1 treme water losses should the mem-
upstream slopes for concrete and steel membranes, brane crack.

05 required for construction

Slope 2 to 4 I depending on
rock character\stxs

Figure 7-9.-Typical maximum section of on earth-core rockfill dam using a central core. 288-D-2800.
296 DESIGN OF SMALL DAMS

coping wall
v- E Crest of dam

Impervious concret
steel membrane I.

Asphaltlc concr
membrane I 7.1

Natural ground surface

@ Well graded, selected, compacted rock used to provide bearing


support for mem brone

@ Smaller sized rock from quarry and rock of lesser quollty from
foundotlon excavations. compacted to reduce membrane settlement

@ Best quollty, higher strength rock, compacted to provide section stability

Figure 7-10.-Typical maximum section of a decked rockfill dam. 288-D-2801.

In addition to these major zones, a well-graded should provide a smooth uniform bearing surface
sand and gravel base course for the membrane is for the facing, yet be graded to retard large water
sometimes necessary. A thin base course also serves loss should the facing crack.
as a leveling course and provides a good working A base course may not always be necessary, de-
surface. Placement conditions for these three zones pending on the need for a leveling course and on
and the base course are discussed in section 7.7. the gradation of zone A and its ability to withstand
Gradation requirements are difficult to specify raveling during placement of the deck and to with-
because they depend on the type of rock available stand erosion. In any event, the zone immediately
and the quarrying methods used. As with many as- beneath the face slab should provide a good working
pects of dam design, only general rules apply, but surface for equipment and workmen during place-
filter requirements given in section 6.10(i) must be ment of the facing element, and it should resist
satisfied. For decked rockfill dams, zone C of the erosion during surface runoff. The base course ma-
embankment should use the largest and best quality terial should be well-graded, with a maximum size
rock available. Large slabby rocks should not be of 1% inches, 5 to 15 percent passing the No. 100
placed in this fill because they tend to bridge, caus- sieve, and 5 percent or less passing the No. 200
ing large voids that may result in excessive settle- sieve.
ment should the rocks break. If possible, rock in In general, material in zones B and C should
zone C should be well-graded from approximately grade from fine rock upstream to coarse rock down-
1 ft3 to 1 yd3, and the finer fraction of the gradation stream, with the largest and strongest material
should not be sufficient to fill the voids in the com- placed in the lower downstream portions of zone C.
pacted material. Optimally, zone B should be well- Selection of the rock for each zone should be made
graded from a maximum size of about 10 ft3 and at the quarry.
should have a high permeability after compaction. For central earth-core rockfill dams, the larger
Zone A should be well-graded from approximately and stronger rock should be placed in the outer
3 inches down to 5 to 15 percent passing the No. rockfill zones. This rock should grade from fine rock
100 sieve. If a base course is not necessary (as de- next to the filter to coarse rock near the down-
scribed later), the gradation of zone A depends on stream slope.
the type of facing used and its method of construc- The axis of the dam may be either curved (convex
tion. If a base course is not used, zone A material upstream) or straight. A curved axis allows the dam
ROCKFILL DAMS 297

to be compressed as filling occurs; whereas, a imparted compaction energy to the fill, decreased
straight axis has the benefit of easy construction the void space and, thus, reduced embankment set-
layout and less total dam cost. For small dams with tlement. Nevertheless, many of these high lift em-
good foundation and abutment conditions, a bankments have since settled considerably with
straight axis is recommended. For the upstream- concurrent leakage problems. Experience has
membrane rockfill dams, it is also recommended shown that rock material placed in thin layers and
that the layout be such that a minimum area of compacted by vibratory rollers forms a more stable
membrane face be exposed. This expedites face con- mass in which settlement is minimal. For decked
struction, reduces face and cutoff costs, and reduces rockfill dams, the embankment should preferably
the cost of any necessary repairs. be completed before construction of the upstream
Random zones constructed of rock with ques- membrane begins. This reduces the probability of
tionable strength or permeability characteristics serious membrane cracking by allowing initial set-
may also be used within the rockfill embankment tlement to occur.
if the stability of the section is not affected. The Settlement of rockfill material has also been cor-
overriding purpose in the layout of any rockfill sec- related with the application of water; Sowers et al.
tion is to make maximum economic use of the ma- [15] have shown that rockfill material placed dry
terial available at the site. Test embankments can and subsequently wetted may settle appreciably.
be used to determine whether or not materials will Sluicing has long been advocated as a method that
be adequate; these are discussed in section 7.5. ensures that point-to-point bearing occurs between
Crest width should be determined by the type of the larger rocks and that finer materials are washed
membrane used and by its use after construction. into the voids. However, when rockfill material is
The crest should, however, be wide enough to ac- placed in thin lifts and compacted by vibratory roll-
commodate construction of the upstream mem- ers, there appears to be no definite proof that sluic-
brane; a minimum width of 15 to 20 feet is ing operations significantly reduce the total
recommended. Crest camber should be determined settlement, especially for the smaller rockfill dams
by the amount of foundation and embankment set- considered here.
tlement anticipated. Because this is difficult to de- The quantity of sluicing water used has varied
termine, a camber of 1 percent of the embankment extensively, but usually ranges from two to four
height is recommended. A straight-line equation times the volume of rock; dirty rock requires more
may be used to distribute the cambered material on water to wash the fines away. For exceptionally dirty
the crest. Additional considerations concerning rock, segregations may cause a water-saturated
crest details are given in section 6.20. layer of fines to form below the surface of the rock
Freeboard requirements depend on maximum as it is dumped over the edge of the lift and sluiced.
wind velocity, fetch, reservoir operating conditions, The layer will be relatively impermeable and will
spillway capacity, and whether coping walls are hinder or prevent wetting of all parts of the rock
used. If a coping wall like that shown on figure 7- in the lift below the layer of fines. This may be
10 is used to provide wave runup and oversplash corrected by using thicker lifts, which allows in-
protection, the freeboard requirements of the em- creased sluicing time, or possibly by wetting the
bankment may be less than required for a riprapped rockfill before placement. Care should also be taken
earthfill dam (sec. 6.21). If a coping wall is not used, that mud does not form at the toe of the lift as a
the freeboard should be adequate to prevent wave result of sluicing; if mud problems do arise, periodic
runup from flowing over the crest (sec. 6.21). Good removal should be mandatory. Sluicing is usually
results have been obtained with coping walls [ll], done with nozzles having diameters from 2% to 4
and their use is recommended. inches (a typical sluicing operation is shown on fig-
7.7. Placement of Rockfill Materials.-Limit- ure 7-U). Enough sluicing equipment should be
ing settlement is critical in the construction of rock- available to handle maximum rock placing rates;
fill dams because excessive settlement may rupture otherwise, the quantity of rockfill placed may be
the upstream membrane or cause joint separation limited. The sluicing equipment should be mobile.
with subsequent water loss. Early rockfill dams Currently, placing rockfill in thin lifts and com-
were constructed by dumping the rock in high lifts; pacting it with a vibratory roller is the preferred
it was assumed that dropping rock from heights construction method.
298 DESIGN OF SMALL DAMS

, ?
~j;:~;~~
~~.i~ ~
;~""~~

.~z' ,c.~ ? ...""""'if.~/.~.;j;..~.

~~"

Figure 7-11.- Typical rockfill sluicing operation. Montgomery Dam, Colorado (Black and Veatch Engineers photo .
graph). 28B-D-2879.

Figure 7-10 shows a typical decked rockfill dam placement. If a base course is installed under the
section consisting of three zones of material. The deck, it should also be compacted by drawing a
zone C material should be sound, durable rock of smooth-drum vibratory roller up and down its face
high quality dumped in 2- to 4-foot lifts and com- in the same manner described for the face of zone
pacted by a vibratory roller. Zone B material may A. Suggestedgradations for zonesA, B, C, and base
be rock of lesser quality than that in zone C, such course material are discussed in section 7.6.
as spillway excavation or tunnel spoil, and should The size of the vibratory roller for each rockfill
be dumped in 2- to 3-foot lifts and compacted by a zone should be based on the properties of the rock
vibratory roller. Zone A material provides the bear- in that zone and should, preferably, be established
ing surface for the upstream membrane and may be by constructing test embankments. Vibratory roll-
either a processed material or selected material ers weighing from 3 to 10 tons have been the most
from foundation or borrow pit excavations. Zone A widely used for rockfill compaction.
material should be compacted to 12-inch lifts by In a number of concrete- and asphalt-faced rock-
either crawler-type tractors or vibratory rollers; the fill dams [11, 16, 17, 18], the zone A material has
material should be thoroughly wetted before com- been eliminated and only a thin leveling course has
paction. The face of the zone A material should be been applied to the face of zone B. In such cases,
compacted by drawing a smooth-drum vibratory compaction of the leveling course is performed by
roller up and down the face. Generally, the vibrator drawing a smooth-drum vibratory roller up its face.
is turned off for the first two passesto prevent dis- Figure 7-12 shows the maximum section of UDDer

~
ROCKFILL DAMS 299

Working point with camber

Working paint with camber


Spillway crest El. II,

Upstream slope varie Downstream slope above El. 11,705


1.7~1 at no camber es from 1.36~1 ot no comber
1.66~1 at mox combe 1.33~1 at max. camber
Aspholtic concrete
deck 9 inches thl

Intersection of
downstream slope

Theoretical toe line of dam


15:l Slope

Figure 7-1 P.-Maximum section of Upper Blue River Dam, Colorado. (Black and Veatch Engineers drawing). 288-D-2880.

Blue River Dam, in which zone A (zone 2 on the It is the general opinion of many dam designers
fig.) has been eliminated and zone B (zone 1 on the that large downstream zones of quarried rock com-
fig.) has been replaced by zone C. When zone A is pacted in thin lifts provide maximum stability
eliminated, the final upstream surface of zone B against seismic shaking and maximum resistance
may also be finished by pulling the vibratory roller to the flow of large quantities of water through the
up its face. The advice of an experienced dam de- section should cracking occur. Thus, it is recom-
signer should be obtained before zone A is mended that where seismic activity is expected,
eliminated. decked rockfill dams containing large downstream
For central earth-core rockfill dams, such as that zones of compacted rockfill be used. The rockfill
shown on figure 7-9, the upstream and downstream should, preferably, be well-graded, angular rock
rockfills should be compacted in 2- to 4-foot lifts fragments of high strength and durability. To ac-
by vibratory compactors to provide the most stable commodate the larger downstream zones, it is rec-
section possible. The fill should be thoroughly wet- ommended that where questionable earthquake
ted to facilitate compaction. Sluicing operations conditions are encountered, the downstream slope
used with this type dam require that great care be of the decked rockfill be flattened to 1.7:1 in all
taken to ensure that filters are not clogged or im- cases. The upstream slope of the embankment
pervious material washed away. The filter material should also be flattened if additional conservative
should be compacted to 12-inch lifts either by design measures are warranted.
crawler-type equipment or vibratory rollers. The The foundation of the dam should, preferably,
width of the filter zones should be sufficient to ac- be firm rock; however, free-draining foundations
commodate placing and compacting equipment. (cobbles, boulders, rock fragments, etc.) may be
7.8. Seismic Design.-For areas of low seismic used if their unit weight is similar to that of the
activity, the designs recommended herein should be rockfill material and they are approved by a com-
adequate. The determination of potential earth- petent dam designer. Trench-type foundation cut-
quake activity within a given region can be made offs are also recommended. In addition, it may be
from a seismic risk map like that on figure 6-44 or desirable to provide a thicker zone A (fig. 7-10) be-
by consultation with a seismologist or engineering neath the membrane, to require better quality rock
geologist. If the damsite lies within a zone of high for zone B, and to reduce the lift thickness to a
seismic activity, an experienced dam designer maximum of 3 feet within zone C. Still another pre-
should be consulted. caution would be using a thicker membrane on the
300 DESIGN OF SMALL DAMS

upstream slope and, in the case of a concrete mem- for design within earthquake regions, and an au-
brane, placing reinforcing in each face. thority in this field should be consulted when se-
It should be noted that there are no exact rules rious seismic conditions exist.

D. MEMBRANE DESIGN

7.9. Impervious Central Core.-A typical The foundation and abutments against which the
earth-core rockfill section using a central imper- core rests should be carefully treated to prevent
vious earth core is shown on figure 7-9. Internal piping. Joints, cracks, fissures, and shear zones
membranes of concrete, asphalt, and steel are not should be cleaned out to firm material and filled
recommended because of the inability to inspect or with concrete or grouted. Vertical faces, overhangs,
repair them. The rockfill zones of the central core and large rock protrusions should be flattened to
dam are discussed in sections 7.5, 7.6 and 7.7. The slopes not steeper than 0.5:1, horizontal to vertical,
upstream rockfill material should be of sufficient by excavation or concrete placement [lo]. A trench-
size and quality to satisfy the riprap requirements type concrete cutoff wall may be necessary with cen-
discussed in section 6.22(c); however, riprap bed- tral impervious earth cores when foundation grout-
ding requirements need not be met. ing is required and the upper zone of rock is closely
Earth-core rockfill dams are economical where fractured, weathered, soft, etc.
site conditions suggest the use of rockfill, but pre- The freeboard requirements are the same as
clude the use of a decked rockfill structure. This those for earthfill dams discussed in section 6.21.
can be the case where the upstream abutments show 7.10. Reinforced Concrete.-More rockfill
highly weathered rock to great depths and thus dams have been faced with conventionally placed
present questionable cutoff conditions for an up- reinforced concrete than with any other type of im-
stream membrane, or where the higher elevations pervious membrane. In most cases, these facings
of the abutments are covered with deep layers of have performed well for correctly compacted rockfill
overburden and preclude the economical installa- embankments; leakage has been within acceptable
tion of a positive trench-type cutoff for the decked limits, and repairs have been minor. Slab thickness
rockfill. and reinforcing requirements have usually been de-
The impervious material used in the core should termined by experience or precedent to satisfy the
be similar to the material used for earthfill cores, following criteria:
as discussed in chapter 6. The material should be l Low permeability
placed at or near optimum moisture content in l Sufficient strength to bridge subsided areas of
about g-inch lifts and should be compacted to 95 the face
to 100 percent standard laboratory unit weight2 by l High resistance to weathering
a tamping roller. The plasticity index of the ma- l Sufficient flexibility to tolerate small embank-
terial should be sufficient to allow the core to de- ment settlement
form without cracking. Specifications for this type Compacted rockfill dams have considerably re-
of placement are given in appendix G. duced embankment settlement, and the use of a
Filter zones should be adequate to prevent piping well-compacted facing layer, which acts as a con-
of impervious material during steady-state or rapid tinuous, firm bedding surface for the concrete face,
drawdown conditions, and it is recommended that has reduced the bridging requirements of the face.
the filter criteria in section 6.10(i) be met. Multiple For a small dam on a stable foundation, a rein-
filters may be required if gradation differences be- forced concrete slab with a minimum thickness of
tween the core and rockfill materials are large. Fig- 8 inches is recommended. The concrete should be
ure 7-13 shows the placement of fine and coarse dense, durable, weather resistant, and have low
filter material for the 55-foot-high New Exchequer permeability (concrete mix designs are discussed in
Saddle Dike in California. app. F). If foundation settlement could occur, or if
other factors such as earthquake conditions exist,
Standard laboratory compaction as defined by the Bureau of
it would be wise to increase the membrane thick-
Reclamation. ness. The amount of steel reinforcing should meet
ROCKFILL DAMS 301

Figure 7-13.-Placement af fine and coarse filter material. For the 55-foot-high New Exchequer
Saddle Dike, California. {Tudor Engineering Co. photograph). 288-D-2881.

the generally accepted requirements, 0.5 percent of slab shown on figure 7-5 has demonstrated its ad-
the concrete area. The reinforcing should be placed equacy and economy [11]; whereas, in closely
both horizontally and vertically in a single layer in jointed, weathered rock, or rock of questionable
the center of the slab. quality, a cutoff wall should be used. Waterstops
Becauseof the low reservoir head and the small should be used between the cutoff and the facing.
amount of settlement expected, horizontal or ver- Becauseconcrete facings provide little resistance
tical expansion joints are normally not required in to wave runup, increased freeboard is required to
the reinforced concrete facings for low dams. Ver- prevent wave runup and oversplash. Coping or par-
tical joints may be required to compensate for hor- apet walls similar to that shown on figure 7-10 may
izontal expansion on low dams of considerable be used to reduce the height of embankment re-
length and are often used to facilitate construction quired for freeboard purposes. These walls should
of the face. Polyvinyl chloride or rubber waterstops be constructed as integral continuations of the con-
should be used to ensure impermeability along the crete face and reinforced accordingly. Coping walls
joints. work well. Cooke [11] reports that in one case,walls
The type of cutoff between the concrete facing 10 feet high have stored water to 8 feet without
and the foundation depends on the quality .of rock harmful effects; although this procedure is not rec-
encountered. For sound rock, the doweled cutoff ommended for the types of structures considered
302 DESIGN OF SMALL DAMS

here. When coping walls are used for runup and rockfill section at Upper Blue River Dam before
oversplash protection, freeboard requirements of asphalt membrane placement.
the embankment can be less than those for an A penetration coat should be applied to the base
earthfill dam (sec. 6.21). The design top of the rock- course surface before asphalt membrane placement
fill should be above the maximum water surface. to bind and stabilize it. The weight of the paving
The height of the coping wall can be determined machine may still gouge the base course, and hand
either by precedent or the designers experience. placement of asphalt in the gouged surfaces may be
The spillway should be designed so that its capacity required.
increases rapidly as the reservoir surface begins to The recommended asphaltic-concrete membrane
encroach on the coping walls. thickness is between 4 and 12 inches, depending on
Concrete has generally been placed by the same the hydraulic head. It should be applied by a stan-
slip-forming process used in road construction, but dard road paver in one to three approximately equal
in some cases shotcrete has been used effectively. lifts, depending on the total thickness [19]. Figure
Figure 7-14 shows the placement of concrete by the 7-17 shows placement of an asphaltic-concrete layer
use of slip-forms on the upstream slope of New at, Montgomery Dam in Colorado. A seal coat is
Exchequer Dam in California, and figure 7-15 shows desirable on the finished surface of the membrane.
shotcreting at Taum Sauk Dam near St. Louis, Mis- The seal coat waterproofs the facing and provides
souri. Placement of the concrete membrane should increased durability. Each layer is placed in strips
not begin until the entire embankment has been 10 to 12 feet wide and constructed at right angles
placed; this allows maximum construction settle- to the axis of the dam. Paving is placed on the
ment and reduces the possibility of cracking and upslope pass only, and the machine is returned to
excess leakage. If concurrent slab placement is nec- the bottom and reloaded for each strip. If sufficient,
essary to complete the job on time, an experienced asphaltic material is not available for each strip,
dam designer should be consulted. Concrete over- reloading must be performed on the upstream face;
runs could occur as a result of the voids in the facing a single paving machine should be capable of plac-
layer and should be accounted for in estimating the ing between 25 and 35 tons of asphaltic concrete
quantities. per hour. Rolling operations should be performed
7.11. Asphahic Concrete.-The second most shortly after placing. Smooth-wheel rollers, either
common facing for rockfill dams is asphaltic con- the vibratory or standard tandem type, can be used
crete. Asphaltic concrete provides more flexibility for lift compaction.
and can thus tolerate larger settlements than rein- Lifts should be compacted to a minimum of 97
forced concrete facings. It offers an economical al- percent of standard laboratory density. Construc-
ternative to concrete and has proved dependable tion control can be effected by taking core samples
when correctly constructed. The recommended up- from the asphalt face at random locations and per-
stream slope for asphaltic-concrete-faced rockfill forming asphalt content, unit weight, stability, and
dams is 1.7:l or flatter, as shown on figure 7-10. The permeability tests.
zone A material should provide a well-graded, free- Effecting tight joints between adjacent strips of
draining rock layer to eliminate uplift pressures in the facing is important to the imperviousness of the
case of rapid drawdown. Yet it should also provide membrane. Transverse joints in the strips should
sufficient resistance to limit water velocities and be kept to a minimum and should be hot joints, if
prevent piping if a crack forms in the membrane. possible. Cold joints, either between parallel strips
The gradation of the zone A material should be or transversely on a single strip, should be treated
smaller than the zone B material. A base course as follows:
with a minimum thickness of 6 inches should be 1. Apply a tack coat of asphaltic cement, the
provided beneath the asphalt as a leveling course, same type used in the mix.
working surface, and smooth base surface for as- 2. Place the asphaltic concrete, overlapping the
phalt placement. The base course should consist of joint 3 to 6 inches.
well-graded material from a maximum size of about 3 Reheat the joint with an infrared heater,
1 to 2 inches to 5 to 7 percent passing the NO. 200 avoiding open flames.
sieve. The base course should be well compacted by 4. Compact the joint by rolling, immediately
a vibratory roller. Figure 7-16 shows the completed after reheating.
ROCKFILL DAMS 303

Figure 7-14.-Placement of concrete by the use of slip torms. On the upstream slope of New
Exchequer Dam, California. (Tudor Engineering Co. photograph). 288-D-2882.

When one lift is placed on top of another, the .Impervious


parallel joints in the strips of the top lift should be .Does not creep
offset 3 or 4 feet from the joints of the bottom strip. .Resists weathering
The foundation cutoff used with asphalt facings Material found within an economical hauling
must promote easy placement of the asphalt lift at distance of the dam should be used in the asphaltic
the contact with the foundation. A trench-type cut- concrete if possible. A number of different materials
off wall similar to that shown on figure 7-3 is rec- and gradations ranging from silty sand [20] to
ommended. The cutoff used at Montgomery Dam graded gravel [17] have been used to construct ad-
is shown on figure 7-18; the 12-inch-diameter drain equate upstream facings. Clay fines should not be
wasusedto reduceuplift pressure during drawdown. permitted in mixes because the clay tends to ball
The cutoff used at Upper Blue River Dam is visible during the drying process and to crush when com-
at the left edge of figure 7-16. pacted, thereby leaving dry material exposedto the
The upstream asphaltic membrane should be reservoir water.
constructed so that it is: The gradation limits of the material used for the
.Durable asphaltic-concrete facing at Montgomery Dam are
.Flexible shown in table 7-1.
DESIGN OF SMALL DAMS

figure 7-15.-Placement af shatcrete on the upstream face of Taum Sauk Dam, Missouri.
(Union Electric Co. photograph). 288-D-2883.

Table 7-1.-Gradations of asphaltic-concrete aggregates.Agge- of the asphaltic concrete, thereby increasing its life
gate specified and that used for the asphaltic-concrete facing
at Montgomery Dam. expectancy.
The tests that may be performed to evaluate the
materials and the different mixes are:
Sieve designation 1. Sieve analysis and specific gravity test
Percent passing by weight
square openings 2. Immersion-compression test
(U.S. standard sieves) Specifications Job mixl 3. Unconfined-compression test
4. Sustained-load test
11/2inch 100 100
5. Permeability test
34 inch 80-95 86.4
6. Wave-action test
1/2inch 71-89 76.5
Tests 1 through 5 are similar to those described
No.4 55-75 58.7
in ASTM Standards, part II. Test 6, concerning the
No.10 40-60 46.5
effect of wave action, is described in [20, 21, 22];
No.40 22-36 30.0
this test was developed by the Bureau of Recla-
No.80 14-26 19.2
mation to simulate wave effects on asphaltic-
No.200 7-15 12.8
1Average gradation of material used in construction.
concrete facings and has proved useful in helping
to select the correct mix proportions.
Special tests that can be performed are:
Tests should be performed using various grada- 1. Slope-flow test
tions, compressive efforts, percent asphaltic ce- 2. Coefficient of expansion test
ment, and percent lime to determine the mix that 3. Flexural strength test
has the maximum unit weight and best satisfies the 4. Effect of reservoir ice test
above criteria. In certain cases,1 to 3 percent lime All of the above tests, both standard and special,
has been shown to reduce the underwater expansion were performed by the Bureau of Reclamation to
ROCKFILL DAMS 305

Figure 7-16.-Completed rockfill embonkment ot Upper Blue River Dam, Colorado, before membrane placement.
(Dept. of Public Utilities, Colorado Springs, Colorado, photograph). 288-D-2884.

determine the proper type of asphaltic cement and (d) Solubility in carbon
the correct percentage to be used at ~ontgomery tetrachloride min. 99.5%
Dam [21]. These tests led to a mix design incor- (testedper ASTM D 165)
porating 8.5 percent asphaltic cement. The speci- (e) Softeningpoint (ring and
fications for the asphaltic cement used at ball method) min. 125oF
~ontgomery Dam are reprinted below: (testedper ASTM D 36)
(f) Spot test (per paragraph 3 of AASHTO
"All asphalt for use in the asphaltic concrete Specifications T 102) negative
shall be uniform in character, shall not foam when (g) Results of tests made on residues after thin-
heated to 350 oF,and shall conform to the following film overn heating, per test method No. Calif.
specifications and requirements; 337-A, January 3, 1956, of the Division of
(a) Penetration (testedper ASTM D 5) Highways, Department of Public Works,
(1) At 77 oF,100grams,5 seconds 50-60 State of California, shall conform to the fol-
(2) At 32 oF,200 grams,60 seconds min. 12 lowing as compared with like tests made on
(b) Ductility at 77 oF,5 cm/min min.140 cm the identical material before such heating.
(testedper ASTM D 113) Such method shall be considered to be a part
(c) Flash point (Clevelandopen cup) min. 450 oF hereof, provided that in lieu of the pertinent
(testedper ASTM D 92) AASHTO Specifications there shall be used
306 DESIGN OF SMALL DAMS

Figure 7-17.-Placing asphaltic concrete on the face of Montgomery Dam, Colorado.


CH-520-81.

Original ground surface 10'-0" Min. radius


/

-~ ---

Surfaces thoroughly cleaned and

specially
'I
v
2
'L
I
Thoroughly compacted /
backfill .:1
/
Rock surfoce
'Theoretical heel
3'-0" Min., 8'-0" Max.~ Min.

~ ~ ~~/:e..~"fh~am Open Jto R. C. Po drain


Reinf. steel--. Variable
Pour against undisturbed ~ , " ~
face of excavation = ---""" -1-6 ~.. 2t" Dia. grout pipes embedded in cutoff
~ 3'-0 Mln,t4- at approx. 8" ctrs.

~ Grout holes

Figure 7-18.-Foundation cutoff used at Montgomery Dam, Colorado. 288-D-2802.


ROCKFILL DAMS 307

the ASTM Specifications referred to in this ?gble 7-2.-Results of tests on asphaltic concrete. Montgomery
item plus ASTM D 6 and E 11. The contrac- Dam and Cawker City Dike.-.---
tor shall cause the producer of the asphalt to
Percent of result before heating
supply the engineer, as required, with data or
curves showing the relation between temper- Test Montgomery Cawker City
ature and viscosity representative of the as- Dam Protective Dike
phalt as furnished for the work.
Penetration, at 77 F,
The results of the tests specified above are shown retained, minimum 65 55
in table 7-2. Penetration, at 32 F,
A very low air-void content resulting from proper retained, minimum 70 45
mix design and compaction is required to obtain Ductility, at 77 F,
durable facings; however, a low air-void ratio cannot retained, minimum 80 30
be obtained by simply adding more asphalt cement. Increase in softening
Air-void ratios of 1 percent are commonly obtained, point, minimum 10 15
and the maximum air-void ratio allowed in the con- Loss in weight,
struction of an asphalt facing should be 5 percent. maximum 0.3 0.3
Experience has indicated that densely graded ag- The percentages for Gawker City Dike were added for comparison with
gregates with ample filler (minus No. 200), correctly those used for Montgomery Dam.
proportioned with a 50 to 60 penetration, paving-
grade asphalt cement produces a very workable, rel- criteria besides precedent are applicable, and the
atively easily compacted hot mix at about 300 F. available literature should be consulted for a com-
The thicker films of asphalt cement obtained with plete review of the practices used [18, 23, 24, 251.
a rich mix of slightly harder 50 to 60 asphalt ce- Figure 7-20 shows the upstream face of the Bu-
ment, as compared with an 85 to 100 or 100 to 150 reau of Reclamations El Vado Dam where the steel
penetration asphalt cement, can be expected to in- plate is in excellent condition after 45 years of
crease watertightness, stability, and durability. The service.
completed asphaltic-concrete facing at Upper Blue Steel-faced dams can be rapidly constructed and
River Dam is shown on figure 7-19. should be capable of tolerating greater embankment
Parapet walls should be used with asphaltic-con- movements than either concrete or asphalt-faced
Crete facings in lieu of increasing the height of the dams. The most prominent disadvantage to steel
dam to retard wave runup and oversplash. Galva- facings is the possibility of corrosion reducing their
nized corrugated metal has been used for a number economic life, although this can be effectively con-
of small dams [ 17,211 and appears to be performing trolled by cathodic protection on both faces of the
well; figure 7-19 shows the parapet wall at Upper plate. Experience with the few existing steel-faced
Blue River Dam. When parapet walls are used to dams strongly indicates that corrosion failure of the
protect against wave runup and oversplash, the free- plate is remote, and that for practical purposes, the
board heights of the embankment may be reduced facing can be assumed to be permanent if proper
from those heights required for earthfill dams (sec. maintenance is provided.
6.21); however, the embankment crest must be Steel-faced dams have generally been con-
above maximum water surface. Wall heights can be structed with upstream slopes from 1.3:l to 1.7:1.
determined by precedent or design experience. For rockfill dams, the upstream and downstream
For further information on asphalt facings, the slopes need not be flatter than the natural slope of
reader should consult the references at the end of the material, which is generally from 1.3:1 to 1.4:1.
this chapter. Specifications for materials used to The steeper slopes lead to reduced costs, but
manufacture asphaltic concrete are subject to slightly increased face construction difficulties.
change, and the literature should be consulted. The portion of the embankment on which the
7.12. Steel.-Steel facings have been used on steel plate bears (zone A on fig. 7-10) should, in
relatively few dams throughout the world, but their general, be constructed of well-graded, pervious
satisfactory performance on these few dams illus- gravel to provide a uniform bearing surface for the
trates clearly that they should be given serious eco- steel facing. Anchor rods should extend from the
nomic consideration by dam designers. Few design facing plates into the embankment to prevent uplift
308 DESIGN OF SMALL DAMS

Figure 7-19.-Completed asphaltic-concrete facing at Upper Blue River Dam, Colorado. (Dept. of Public Utilities,
Colorado Springs, Colorado, photograph). 288-D-2885.

or loosening of the face as a result of embankment have varied considerably; large plates are more dif-
settlement or wave action. 1\vo methods of an- ficult to handle and appear to provide little advan-
choring the faceplate to the embankment have been tage over smaller plates.
used. The first method requires that the steel plate The foundation cutoff used should be the trench-
be constructed on a scaffolding grid that is raised type cutoff wall shown on figure 7-4. It should be
a few feet off the face of the dam; bedding material designedto withstand the tension causedby settle-
is then placed between the facing and the embank- ment and stresses imposed by any differential face
ment either after the plate construction is com- movement adjacent to the cutoff. Coping walls
pleted or concurrently with its construction up the should be used to retard oversplash. Freeboard re-
face. The second method requires that anchor bar quirements are similar to those for a concrete-faced
holes be dug in the completed faceplate bedding rockfill dam (sec. 7.10).
material, and the anchor bars grouted in with con- Expansion joints are usually V -shaped metal
crete. The first method provides more ade{Juate strips placed perpendicular to the axis of the dam
plate anchoring, but the seco~'d method is less and extending from the crest to the cutoff; the V-
costly. strips may have their raised portion placed on either
The steel plates should have a thickness of 14to the front or back of the steel face. Design details
3/8inch, depending on the assumed magnitude of used for El Vado Dam in New Mexico, Rio Lagartijo
the movements of the dam. All joints and seams Dike in Venezuela, and Sirinumu Dam in New
should have a continuous fillet weld, and nuts used Guinea are shown on figures 7-21, 7-22, and 7-23,
on alignment or anchor bolts should be welded to respectively.
the plate on all sides to prevent leakage. Plate sizes 7.13. Timber Planking.-Timber planking has
ROCKFILL DAMS 309

Figure 7-20.-Steel facing on the upstream slope of El Vado Dam, New Mexico.
The facing is in excellent condition after 45 years of service. 288-D-2886.

been used as a temporary type of membrane, but is construction are the danger of loss by fire at low
not recommended for general use, even though it is water and the relatively short life of timber con-
often the most inexpensive type of membrane to struction when alternately exposed to wetting and
construct. The principal objections to this type of drying.
310 DESIGN OF SMALL DAMS

Steel porapet
203 ~+-251.8~-a-/

-----_-
ill' In 8" layers7

(A)
-I Grout Holes 5' c.to c
I

dT=hr I" Cable

Concrete
1" 0 Bars posts
-(I II
lal?rrS~-+l I. I

(D)

Figure 7-21 .-Details of steel membrane used at El Vado Dam, New Mexico. 288-D-2703.
ROCKFILL DAMS 311

graded and compacted rock

Rock
A

4 L4 plates @ 8,0,, w,th % space between p_) 4

329%
Steel-plate Faclng~Portlon of Plan

, T cut from 4 Wf

ixpansion Joint

C
8 X 8 X 4

Plate 48 X % X 80

Continuous weld \

. Anchor
tiorlzontal Jomt
E F

Figure 7-22.-Details of steel membrane used at Rio Lagartijo Dike, Venezuela.


Adapted from (24). 288-D-2804.
312 DESIGN OF SMALL DAMS

M S. face plate
1 15r R L 1752.50
p I sq.7 ,,
Shop wel
Field we

kfill (50% 5 15 no

rockfill L-12Sq. 4
18 n-l,
6) TYPICAL ANCHOR BOLT
STEEL FACE PLATE
Assumed found&Ion --

TYPICAL SECTION THROUGH DAM

(with nuts) at 2ctrs.

TYPICAL EXPANSION JOINT


STEEL FACE PLATE

Field butt weld, ~ /Field seal weld

TYPICAL ELASTIC PIPE JOINT AND


EMBEDMENT OF STEEL FACE PLATE
IN CUTOFF WALL
TYPICAL HORIZONTAL BUTT JOINT
STEEL FACE PLATE

Figure 7-23.-Details of steel membrane used at Sirinumu Dam, New Guinea. Adapted
from (251. 288-D-2805.

E. BIBLIOGRAPHY

7.14. Bibliography. [7] Shand, N., and P. J. N. Pells, Experience in the Design
[l] Galloway, J.D., The Design of Rockfill Darns, Zkans- and Construction of Reinforced Rockfill Dams, Tenth
actions, AXE, No. 104, pt. 2, p. 1, 1939. International Congress on Large Dams, Montreal,
[2] Symposium on Rockfill Dams, Transactions, ASCE, pp. 270-317, 1970.
vol. 125, pt. 2, 1960. [8] Pinkerton, I. L., and R. J. Paton, Design and Con-
[3] Cooke, Barry .J., Progress in Rockfill Dams, Journal struction of Geehi Dam, Journal of the Inst. of Civil
of Geotechnical Engineers, ASCE, vol. 110, No. 10, Engineers, Autstralia, March 1968.
pp. 1,383-1,414, October 1984. [9] Mitchell, W. R., J. Fidler, and M. D. Fitzpatrick,
[4] Fenton, J. D., Hydraulic and Stability Analysis of Rowallan and Parangana Rockfill Dams, Journal of
Rockfill Dams, Department of Civil Engineering, Uni- the Inst. of Civil Engineers, Australia, October-November
versity of Melbourne, July 1968. 1968.
[5] Marsal, R. ,I., Large Scale Testing of Rockfill Mate- [lo] Bureau of Reclamation, Design Standard No. 13, Chap-
rials, Jourml of the Soil Mechanics and Foundations ter 3, Foundation Surface Treatment.
Division, ASCE, vol. 93, No. SM2, March 1967. [ll] Steele, I. C., and J. B. Cooke, Concrete-Face Rock-Fill
IS] Porkin, A. K., D. H. Trollope, and J. D. Lawson, Rock- Dams, Handbook of Applied Hydraulics, C. V. Davis and
fill Structures Subject to Water Flow, paper No. 4973, K. E. Sorensen editors, 3rd ed., McGraw-Hill, New York,
Journal of the Soil Mechanics and Foundations Division, NY, 1969.
ASCE, November 1966. [ 121 Crisp, R. L., Design, Construction, and Instrumenta-
ROCKFILL DAMS 313

tion of Carters Rockfill Dam, Paper presented at US- Elsden, O., H. G. Keefe, and A. W. Bishop, Embank-
COLD-CNC/ICOLD meeting, Vancouver, B.C., October ment Dams, Hydroelectric Engineering Practice, 2d ed.,
1966. ch. IX, vol. 1, Glasgow, 1964.
[ 131 Leps, T. M., Review of Shearing Strength of Rockfill,
Journal of the Soil Mechanics and Foundations Division, Fumagelli, Emanuele, Tests on Cohesionless Materials
ASCE, Vol. 96, No. SM4, pp. 1,159-1,170, 1970. for Rockfill Dams, Journal of the Soil Mechanics and
[ 141 Marachi, N. Dean, Clarence Chan, and H. Bolton Seed, Foundations Division, ASCE, vol. 95, No. SMl, pp. 313-
Journal of the Soil Mechanics and Foundation Division, 330, January 1969.
ASCE, January 1972.
[15] Sowers, G. F., R. C. Williams, and J. S. Wallace, Com- Giudici, Sergio, Rockfill Structures Subject to Water
pressibility of Broken Rock and the Settlement of Rock- Flow, Discussion of Proceedings, paper No. 4973, Jour-
fills, Proceedings, Sixth Int. Conf. Soil Mechanics and nal of the Soil Mechanics and Foundations Division,
Foundations, vol. 2, Montreal, 1965. ASCE, vol. 93, No. SM3, pp. 329-337, September 1967.
[16] Scheidenhelm, F. W., J. B. Snethlage, and A. N. Van-
derlip, Montgomery Dam-Rock Fill with Asphaltic Kjoernsli, B., and I. Torblaa, Asphalt on Earth and
Concrete Deck, Transactions, ASCE, vol. 125, pt. 2, Rockfill Dams, Publication No. 48, Norwegian Geo-
1960. technical Institute, Oslo, 1966.
[ 17) Proudfit, D. P., Asphaltic Concrete Facing for a Rock-
Mann, J.N., Aspects of Rockfill Selection, Placement
Fill Dam, Civil Engineering, March 1968.
and Sluicing in the Construction of Moondarra Dam,
[18] Sherard, J. L., R. J. Woodard, S. F. Gizienski, and W.
Journal of the Inst. of Engineers, Australia, April-May
A. Clevenger, Earth and Earth-Rock Dams, John
1963.
Wiley and Sons, Inc., New York, NY, 1963.
1191 Bunn, R. A. , Asphaltic Concrete Membranes in Em- Oliver, H., Through and Overflow Rockfill Dams-
bankment Dams, Water Power and Dam Construction, New Design Techniques, Proceedings, Inst. Civil En-
January 1983. gineers, paper No. 7012, 1967.
[20] Mix Design Investigations of Asphaltic Concrete for
Dam Facing-Glen Elder Dam, Bureau of Reclamation, Robeson, F. A., and R. L. Crisp, Rockfill Design-Cart-
Chemical Engineering Laboratory Report No. ChE-42, ers Dam, Prvceedings, Journal of the Construction Di-
February 18, 1965. uision, ASCE, vol. 92, No. C03, September 1966.
[21] Laboratory Investigation of Asphaltic Concrete, Mon-
togomery Dam, Colorado, Proceedings, Association of Reid, H. I., Steel Plates with Welded cJoints Seal Rock-
Asphalt Paving Technologists, 1958. fill Dam, Engineering News-Record, vol. 108, p. 761.
[22] Mix Design Investigation of Asphaltic Concrete for
Facing Downs Protective Dike, Bureau of Reclamation, Rowe, P. W., The Stress-Dilatancy Relation for Static
Chemical Engineering Laboratory Report No. ChE-66, Equilibrium of an Assembly of Particles in Contact,
December 29, 1966. Proceedings, Royal Society, series A, vol. 269, No. 1339,
[23] Hovey, 0. E., Steel Dams, American Institute of Steel October 9, 1962.
Construction, p. 79, New York, NY, 1935.
Terzaghi, K., and R. B. Peck, Soil Mechanics in En-
[24] Sherard, J. L., A Steel Faced Rockfill Dam, Coil En-
gineering Practice, 2d ed., art. 62, John Wiley and Sons,
gineering, vol. 29, No. 10, pp. 698-701, October 1959.
Inc., New York, NY, 1967.
[25] Fraser, J. B., A Steel-Faced Rockfill Dam for Papua,
Civil Engineering Transactions, Institution of Engineers, Seger, C. P., Steel Used Extensively in Building El
vol. CE4, No. 1, pp. 35-48, Australia, March 1962. Vado Dam, Engineering News-Record, vol. 115, p. 211.
Asbeck, Baron W. F. van, Bitumen in Hydraulic En-
Wesley, L. D., Settlement of Embankment Materials
gineering, vol. 11, Elsevier, London, 1964.
in Earth and Rockfill Dams,New Zealand Engineering,
pp. 179-187, May 15, 1967.
Bertram, G. E., Rockfill Compaction by Vibratory
Rollers, Proceedings, 2d Pan-American Conference on Wilkins, J. K., Rockfill Structures Subject to Water
Soil Mechanics, Brazil, 1963. Flow, Discussion of Proceedings, paper No. 4973, Jvur-
nal of the Soil Mechanics and Foundations Division,
Davis, R. E., Tests on Models of Sariyar Rockfill Dam, ASCE, vol. 93, No. SM 3, p. 177, May 1967.
Report to International Engineering Co., Berkeley, CA,
July 1949. Wilkins, J. K., Decked Rockfill Dams, Journal Inst.
of Engineers, Australia, April 1968.
Ellsperman, L. M., and F. C. Walker, Factors Affecting
the Use of Asphaltic Diaphragms in Earth and Rockfill Abrasive Rock, Asphalt Facing for Water Supply
Dams in the Western United States, Seventh Inter- Dam, Engineering News-Record, p. 44, November 15,
national Congress on Large Dams, Rome, Italy, 1961. 1956.
314 DESIGN OF SMALL DAMS

Asphalt on Earth- and Rock-Fill Dams, Norwegian Bitumen or Other Materials, Seventh International
Geotechnical Institute, Publication No. 48, Oslo, 1962. Congress on Large Dams, vol. IV, Rome, Italy, 1961.

Asphalt Deck is Dams Watertight Layer, Engineering Question 31 - High Rockfill Dams, Eighth Interna-
News-Record, p. 36, December 5, 1957. tional Congress on Large Dams, vol. III, 1964.

Question 27 - Sealing of Earth and Rockfill Dams with

Vous aimerez peut-être aussi