Académique Documents
Professionnel Documents
Culture Documents
Process Groups
2
Terminologies
1. Organizational Process Assets (OPA), which contains
historical information of all projects of your organization and
project management policies / templates, are readily
available. PMI advocates constant improvement and
continuous learning from project to project.
2. Enterprise Environment Factors (EEF), which represents
all the factors not in the immediate control of the project, is
something a Project Manager has to live with.
3. Change Requests include Corrective Action, Preventive
Action, Rework and changes that would affect the project
configurations / baselines / plans.
4. Lessons Learned are important outputs.
5. Expert Judgment is the single most important tool and
technique which refers to knowledge gained through
experience and/or studies. If it appears as one of the choices
for an PMP question, it is often the correct answer.
The Project Manager
1. The Project Manager has the responsibility to ensure the
project is completed on time and within budget.
2. The Project Manager should collaborate with stakeholders
throughout the project lifecycle. Plans should be developed in
collaboration with appropriate stakeholders and subject
matter experts.
3. The Project Manager should be proactive in identifying
problems, solving conflicts and looking for changes for the
better. Conflicts should be addressed directly.
4. The Project Manager needs to tailor the PMBOK Guide
Processes to suit the scope and characteristics of individual
projects.
5. The Project Manager must carry out impact analysis should
something unusual happens before asking for changes.
6. The Project Manager may take up a stretch assignment but
should first let management know that they lack the
experience/expertise.
7. The Project Manager should consult sponsors/senior
management when they have to make decisions that are
believed to be out of their assigned authority. However, the
Project Manager to exercise his/her authority to manage
the project as far as he/she can without escalating the
matter to senior management.
8. The Project Manager should not accept request to trim down
the budget (or time) while the scope and time (or budget)
cannot be changed.
Project Management
1. Emphasis is placed on the planning rather than putting out
the fire day in day out. Work should begin after the proper
planning is finished.
2. The Project Management Plan is approved by all designated
stakeholders and is believe to be achievable.
3. All activities, issues and risks should be assigned to
designated project members for handling.
4. Competing constraints are time, cost, scope, quality, risk
and resources. Change in one constrain will affect at least one
other constraints non-linearly, e.g. a reduction in 10% of cost
may affect 90% of the quality.
5. Risk Management is a almost a must for all projects,
project schedule and budget must take risks into
consideration.
6. Always follow the plan-do-check-act cycle.
7. All changes must be handled through the Integrated
Change Control Process, proper approvals must be sought and
changes documented before work begins (except in the case
of implementing workarounds during emergency in which
approval may be sought after the change has been carried
out).
8. Quality is an important consideration which needs constant
improvement (through the control quality / process
improvement).
Others
1. Meetings are used for idea generation, discussion, problem
solving or decision making, not status reporting.
2. Gold-plating is derogatory to PMI.
3. The Project Management Office (PMO) is assumed in most
case.
4. Work performed by resources (including overtime work) must
be compensated. It is NOT recommended to ask resources to
work overtime by sacrificing work-life balance.
5. The goal of negotiation is to create a win-win result
(problem-solving).
6. Sunk cost is not to be considered when deciding when to
terminate a project.
7. Never tolerate sexual discrimination, even if it is customary
in other cultures.
3
Introduction: Essential terms from the PMBOK Guide 5th Edition are
highlighted here. PMP aspirants need to learn these well in order to
successful pass the PMP exam. More information on my PMP
certification exam preparation can be found at my PMP exam and
certification journey here.
PMP Certification Study Notes 2/3 Project Management Processes and Knowledge
Areas
Introduction: This part of PMP exam study notes is based on the 2nd
and 3rd chapter of the PMBOK Guide 5th Edition. It gives an overview of
the 47 processes of project management in the PMBOK
Guide and the process groups. More information on my PMP
certification exam preparation can be found at my PMP exam and
certification journey here.
Web Copy C
Web Coding A C
Introduction: This part of the PMP exam study notes on Project Risk
Management is based on chapter 11 of PMBOK Guide 5th Edition. More
information on my PMP certification exam preparation can be found
at my PMP exam and certification journey here.
Responsibility
in the best interest of the society, public and environment
accept assignments consistent with skills and fulfill
commitments
accept stretch assignment when the assigner is fully aware
of the skill gaps
own error and make corrections
uphold laws and regulations
report illegal/unethical activities substantiated with facts
ask for direction should the decision is beyond assigned
authority
Respect
show respect to others
listen and understand others
conduct in a professional manner, even if not reciprocated
resolve conflicts directly
negotiate in good faith
do not influence others for personal benefits
respect others rights
Fairness
transparency in decision making
be objective
provide equal access to information, equal opportunities
disclose any conflict of interests and refrain from making
decisions in case of conflict of interest
do not deny opportunities base on personal considerations
do not discriminate
apply rules without favoritism or prejudice
Honesty
understand the truth and be truthful
honour commitments
not to deceive others
not engage in dishonest behavior for personal gain / at the
expense of others
111
Summary: Many consider the most difficult part of the PMP exam to be
the calculations and PMP formulas. Luckily PMP calculation is
not quantum physics, you just need to understand and memorize the
following PMP Calculation formulas. Keep calm and study on! (You can
read more about my PMP exam and certification journey here.)
n should
include the
project
manager
<1
behind schedu
Schedule
SPI = EV/PV le
Performanc
= 1 on
e Index EV = Earned Value schedule
(SPI) PV = Planned Value > 1 ahead of
schedule
Cost <1
Performanc CPI = EV/AC Over budget
e Index = 1 On
EV = Earned Value
(CPI) budget
AC = Actual Cost
> 1 Under
budget
Name
(Abbreviati
on) Formula Interpretation
n should
include the
project
manager
sometimes the
term
cumulative
CPI would be
shown, which
actually is the
CPI up to that
moment
Schedule <0
Variance SV = EV PV Behind schedu
(SV) le
EV = Earned Value
= 0 On
PV = Planned Value
schedule
> 0 Ahead of
Name
(Abbreviati
on) Formula Interpretation
n should
include the
project
manager
schedule
<0
Over budget
Cost CV = EV AC
= 0 On
Variance
EV = Earned Value budget
(CV)
AC = Actual Cost > 0 Within
budget
n should
include the
project
manager
have changed
the variance is
Estimate at
EAC = AC + BAC EV caused by a
Completion
one-time event
(EAC) if BAC AC = Actual Cost and is not likely
remains the BAC = Budget at completion to happen
same EV = Earned Value again
n should
include the
project
manager
not accurate
n should
include the
project
manager
n should
include the
project
manager
<0
VAC = BAC EAC Over budget
Variance at = 0 On
Completion BAC = Budget at completion budget
EAC = Estimate at > 0 Under
Completion budget
Name
(Abbreviati
on) Formula Interpretation
n should
include the
project
manager
(O + 4M + P)/6
PERT
Estimation O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
this is a rough
(P O)/6
Standard estimate for the
Deviation O= Optimistic estimate standard
P= Pessimistic estimate deviation
Float/Slack = 0 On
LS ES critical path
Name
(Abbreviati
on) Formula Interpretation
n should
include the
project
manager
LS = Late start
ES = Early start
< 0 Behind
LF EF schedule
LF = Late finish
EF = Early finish
PMP Formulas
Note: Wanna download all PMP Formulas as a printable file for your
PMP Certification exam prep? Please share this post to your social
network first and you will be able to see the download link. Thanks for
helping this PMP website grow!
222
Are You PMP Exam Ready? List of Free PMP Mock Exam Questions w/w Benchmark
One of the most frequent question a PMP aspirant will ask is: am I
PMP exam ready? It is not only a waste of time and money if you
take the actual PMP test questions when you are still not ready yet,
think of the enormous pressure you have to endure sitting 4 hours before
the screen and 15 seconds of blank screen for the result to appear.
How to know if you are ready for the real PMP exam?
Thats why I wrote this post for fellow PMP aspirants. Below is the list of
free/cheap PMP exam questions I have tackled during my preparation for
the PMP PMBOK Guide 5th Edition examination and my first-
time results for those PMP sample exams. Trying the same exam 2 or 3
times is often good for practice, but if you would like to assess whether you
are exam ready, remember to evaluate only with your first-time
results. Though the PMP practice exams listed below are free, the
quality is superb. If you are already well prepared for the PMP exam, you
can just rely on the free resources below to help you pass the PMP
certification without difficulties. All these PMP practice questions /
simulators come with answers and detailed explanations for each mock
exam question. It is highly advisable for PMP Certification
Aspirants to read all the answer explanations for every
PMP mock exam questions (not matter you get the
answer right or wrong) in order to discover any knowledge gaps in
your PMP Exam Prep. Normally PMP Certification Aspirants will only
read the answer explanations for those questions they have got it wrong.
However, reading every answers and explanations for PMP mock exams /
simulators is just like giving you another chance to go over the PMBOK
Guide or other PMP Exam prep guides. This exam prep strategy has
helped me a lot for my passing the PMP Exam in first attempt.
This is the remarks of a reader, Sita Tangirala, PMP, who made use of the
benchmark results to forecast the real PMP Exam results:
In the real PMP Exam taken on 7 Nov, 2013, I passed the PMP exam
and got the following proficiency levels:
Domain Name
Initiation
Planning
Executing
Closing Mod
If you are tight on budget, you may just exploit the above free PMP exam
questions for your exam success!
Hope this resource will help you with your PMP preparation. If
you find PM Exam Simulator suitable and if you enjoy my PMP
articles, please consider buying it though the links on this page. I
will earn a small commission (at NO extra cost to you) to sustain
my website costs. Thank you.
333
However, many project managers may not have done any EVM in their
projects and many of them consider the EVM questions a bit scary. This
post aims to help PMP aspirants to understand easily the
EVM concepts and how to tackle the EVM questions.
Introduction
To arrive at the correct answers for EVM questions, all you need to do in
the PMP Exam is to:
Earned value management (EVM) is used to assess the schedule and cost
performance of a project with EVM, the project manager will know
exactly whether the project is:
Good news here: PMI has simplified PMP EVM calculation to very
ideal situations! You will just need to know the following to get
your PMP EVM questions correct.
EVM is based on monitoring these three aspects along the project in order
to reveal the health of the project with the following indices:
Note both SV and SPI / CV and CPI give similar information on schedule /
budget but the indices will give more insights into the actual performance
with a meaning comparison.
The following will discuss how earned value is measured for project and
work, from simple physical measurements, percentage complete to
weighted milestones. Since the PMP EVM questions cannot describe a
lot of information, the part on earned value measurements will normally be
based on simplified situations like physical measurements or percentage
complete.
It is likely that you will not be tested on the more difficult ways of measuring
earned values. These are included here for your reference only.
In common practices, EVM will also involve plotting the values on a graph
in order to help stakeholders concerned to visualize the progress and the
health of the project. More often than not you will find the EV, AC and PV
plotted on a graph and you will be asked on the interpretation of the graph.
Name
(Abbreviati
on) Formula Interpretation
<1
behind schedu
Schedule
SPI = EV/PV le
Performanc
= 1 on
e Index EV = Earned Value schedule
(SPI) PV = Planned Value > 1 ahead of
schedule
<1
Over budget
= 1 On
budget
> 1 Under
budget
Cost
CPI = EV/AC
Performanc
sometimes the
e Index EV = Earned Value term
(CPI) AC = Actual Cost cumulative
CPI would be
shown, which
actually is the
CPI up to that
moment
Schedule <0
Variance SV = EV PV Behind schedu
(SV) le
Name
(Abbreviati
on) Formula Interpretation
<1
behind schedu
Schedule
SPI = EV/PV le
Performanc
= 1 on
e Index EV = Earned Value schedule
(SPI) PV = Planned Value > 1 ahead of
schedule
= 0 On
EV = Earned Value schedule
PV = Planned Value > 0 Ahead of
schedule
<0
Over budget
Cost CV = EV AC
= 0 On
Variance
EV = Earned Value budget
(CV)
AC = Actual Cost > 0 Within
budget
if the original
Estimate at estimate is
EAC = AC + New ETC
Completion based on wrong
(EAC) if AC = Actual Cost data/assumptio
original is New ETC = New Estimate to ns or
flawed Completion circumstances
have changed
<1
behind schedu
Schedule
SPI = EV/PV le
Performanc
= 1 on
e Index EV = Earned Value schedule
(SPI) PV = Planned Value > 1 ahead of
schedule
one-time event
(EAC) if BAC
and is not likely
remains the AC = Actual Cost
to happen
same BAC = Budget at completion
again
EV = Earned Value
<1
behind schedu
Schedule
SPI = EV/PV le
Performanc
= 1 on
e Index EV = Earned Value schedule
(SPI) PV = Planned Value > 1 ahead of
schedule
Index likely to be
SPI = Schedule Performance used
Index
Estimate to
ETC = EAC -AC
Name
(Abbreviati
on) Formula Interpretation
<1
behind schedu
Schedule
SPI = EV/PV le
Performanc
= 1 on
e Index EV = Earned Value schedule
(SPI) PV = Planned Value > 1 ahead of
schedule
EAC = Estimate at
Completion Completion
AC = Actual Cost
<0
VAC = BAC EAC Over budget
Variance at = 0 On
Completion BAC = Budget at completion budget
EAC = Estimate at > 0 Under
Completion budget
Additional Resources
After understanding the above and memorizing the EVM formulas, PMP
aspirants should be able to answer PMP EVM calculation questions. Now
it is time to test your understanding of EVM calculation by going through
some practice questions at the article tips and skills on how to answer
all PMP EVM questions correctly 20+ practice questions on PMP
EVM are also included to help you hone your EVM skills and all questions
are fully explained.
444
Top Tips for Tackling PMP EVM Questions (20+ Practice Questions Included)
Below you will find 20+ PMP EVM practice questions categorized by
related skills to help you understand what you are required to know in order
to correctly answer all the EVM questions that would appear on the PMP
Exam. Try them and understand thoroughly how to tackle the questions
through the explanations to each question.
You too will be able to get all PMP EVM questions correct. Wish you
PMP success!
The EVM graph questions are one of the easiest questions to answer as
you will only need to understand the meaning of the relative positions of the
AC, PV and EV:
AC vs PV: whether the project is under or over budget (AC >
PV = over budget; AC < PV = under budget)
EV vs PV: whether the project is ahead of or behind schedule
(EV > PV = ahead of schedule; EV < PV = behind
schedule)
For these types of questions, you will simply need to recall the correct EVM
calculation formulas and correctly substitute the values into the formulas
to arrive at the correct answer. Please do make use of the on-screen
calculator / physical calculator provided to do the calculation even if you are
a Maths wizard. It is a pity to lose marks for careless calculation even if you
have selected the correct formula.
Also, most of such simple EVM calculation questions will supply more than
enough information for you to use as a kind of distractor, it is a test of
whether you can select the correct formulas as well as the correct values to
substitute into the formulas.
SV = EV PV
CV = EV AC
SPI = EV/PV
CPI = EV/AC
VAC = BAC EAC
1. A project with Earned Value (EV) = $1000, Actual Cost (AC) =
$800 and Planned Value (PV) = $800. What is the Schedule
Variance (SV)?
A. $200
B. $0
C. -$100
D. -$200
Solution: A
SV = EV PV
SV = $1000 $800 = $200
Note that the Actual Cost (AC) is not used in the calculation.
EAC = BAC/CPI
If we believe the project will continue to spend at the same
rate up to now (e.g. the delay is caused by reasons which is
likely to continue)
EAC = AC + (BAC-EV)
If we believe that future expenditures will occur at the original
forecasted amount (no more delays of the same kind in
future)
EAC = AC + [(BAC-EV)/(SPI*CPI)]
If we believe that both current cost and current schedule
performance will impact future cost performance
EAC = AC + New Estimate
If we believe the original conditions and assumptions are
wrong
2 For the project with Earned Value (EV) = $360, Actual Cost
(AC) = $400 and both Cost Performance Index (CPI) and
Schedule Performance Index (SPI) equal 0.90. The
original project budget is $1,000. Assuming the remaining
work will be impacted by the current cost performance and
current schedule performance, what is the Estimate At
Completion (EAC) of the project?
A. $1,090
B. $1,190
C. $1,290
D. $1,390
Solution: B
As the project will be impacted by the current cost
performance and current schedule performance, the formula
would be:
EAC = AC + [(BAC-EV)/(SPI*CPI)]
EAC = $400 + [($1000 $360) / (0.9 * 0.9)] = $1190
Also, the questions will usually not make use of EVM terms (like Planned
Value, Actual Cost, Earned Value, etc.) but you can easily infer those
values from the descriptions provided. The key to answering wordy
questions correctly is to read the questions carefully and extract useful
information from the questions and write down PV, EV, AC, etc. while you
are reading the questions.
1. For a project with Earned Value (EV) = $300, Actual Cost (AC)
= $350 and Planned Value (PV) = $400. The overall project
budget is $1,000. Assume that you will continue to spend at
the same rate as you are currently spending. What is the
Variance At Completion (VAC)?
A. -$150
B. $150
C. -$167
D. $167
Solution: C
As the project will continue to spend at the same current rate,
the formula to be used would be:
VAC = BAC EAC
EAC = BAC/CPI
CPI = EV/AC
VAC = BAC BAC/(EV/AC) =$1000 $1000/($300/$350) = -
$167
2 For the project with Earned Value (EV) = $300, Actual Cost
(AC) = $250 and Planned Value (PV) = $300. The
original project budget is $1000. Assuming the project will
continue to spend money at the same rate, what is the
Estimate At Completion (EAC) of the project?
A. $833
B. $933
C. $1,000
D. $1,033
Solution: A
As the project will continue to spend at the same current rate,
the formula to be used would be:
EAC = BAC/CPI
CPI = EV/AC
EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833
2 For the project with Earned Value (EV) = $350, Actual Cost
(AC) = $300 and Planned Value (PV) = $400. The
original project budget is $1,000. Assuming the remaining
work will be impacted by the current cost performance and
current schedule performance, what is the Estimate At
Completion (EAC) of the project?
A. $837
B. $937
C. $987
D. $1,280
Solution: B
As the project will be impacted by the current cost
performance and current schedule performance, the formula
would be:
EAC = AC + [(BAC-EV)/(SPI*CPI)]
SPI = EV / PV = $350 / $400 = 0.875
CPI = EV / AC = $350 / $300 = 1.167
EAC = BAC/(EV/AC) = $300 + [($1000 $350) / (0.875 *
1.167)] = $937
555
Of all the PMP Exam Prep references and materials, the glossary is
often overlooked. However, it is an extremely important tool for PMP
Certification Aspirants to assess their readiness for PMP Exam. It is even
better if the glossary is presented in the flashcard format so that PMP
Certification Aspirants will be able to check whether they have correctly
understood all the concepts required for passing the PMP Exam. Below is
the PMP Exam Glossary Flashcard created for you. Do take advantage
of this free tool to assist your PMP Exam preparation (the complete list
of all PMP Glossary articles can be found here)!
(note: you will only need to move the mouse cursor over the
glossary item to read the explanations)
Budget at Completion
(BAC) [Project Cost Management] often used in earned value
management (EVM), it is the total expenditure for the project on
finish.
Sponsor the one who has the authority to authorizes resources and
funding for the project and also helps to promotion and faciliate the project.
Staffing Management Plan [Project Human Resource
Management] (part of the human resource management plan) a
document containing staff acquisitions rules, training, timeline needs, safety
compliance and release criteria of project team members.
Stakeholder [Project Stakeholder Management] any individuals
or organizations who can impact / are impacted by the project outcome.
Stakeholder Analysis [Project Stakeholder Management] a
process to collect stakeholder information (e.g. influence, interests and
power) to understand their importance and impact to the project.
Stakeholder Register [Project Stakeholder Management] a
document recording all stakeholders of the project with required details.
Start Date [Project Schedule Management] the specific date an
activity is scheduled to begin.
Start-to-Finish (SF) [Project Schedule Management] a logical
relationship for two activities in which the predecessor activity must begin
before successor activity ends.
Start-to-Start (SS) [Project Schedule Management] a logical
relationship for two activities in which the predecessor activity must begin
before the successor activity begins.
Statement of Work (SOW) [Project Integration
Management] a document containing the objectives of the project.