Académique Documents
Professionnel Documents
Culture Documents
REVISION HISTORY
TABLE OF CONTENTS
1.0 INTRODUCTION..............................................................................................4
1.1 PURPOSE...........................................................................................................4
1.2 SCOPE...............................................................................................................4
1.3 GENERAL DESCRIPTION..................................................................................4
1.4 VALIDATION PLAN...........................................................................................4
2.0 OVERVIEW........................................................................................................5
3.0 OPERATIONAL REQUIREMENTS...............................................................6
3.1 CAPACITY.........................................................................................................6
3.2 PROCESS REQUIREMENTS...............................................................................6
3.3 PROCESS CONTROL.........................................................................................7
3.4 FUNCTIONS.......................................................................................................7
3.5 DATA AND SECURITY.....................................................................................14
3.6 ENVIRONMENT...............................................................................................18
4.0 CONSTRAINTS...............................................................................................19
4.1 MECHANICAL.................................................................................................19
4.2 MILESTONES AND TIMELINES.......................................................................20
4.3 EQUIPMENT CONSTRAINTS...........................................................................21
4.4 COMPATIBILITY AND SUPPORT.....................................................................22
4.5 AVAILABILITY................................................................................................23
4.6 PROCEDURAL CONSTRAINTS.........................................................................24
4.7 MAINTENANCE...............................................................................................25
5.0 LIFE-CYCLE....................................................................................................27
5.1 DEVELOPMENT...............................................................................................27
5.2 TESTING..........................................................................................................27
5.3 DELIVERY.......................................................................................................27
5.4 SUPPORT.........................................................................................................29
6.0 GLOSSARY......................................................................................................31
7.0 REFERENCES.................................................................................................32
8.0 APPROVAL.......................................................................................................33
9.0 ATTACHMENTS..............................................................................................34
Project No.:
Insert the unique project number associated with this particular URS.
Document No.:
Insert the Document Identification Number and Revision.
Document Description:
Insert description of document, e.g. GRANULATOR URS Template, JETT Example
User Requirements Specification.
1.0 INTRODUCTION
Note: Insert your own description and introduction. You may wish to include
your own requirements and specifics to allow the inexperienced reader,
contractors, and suppliers adequate explanation to understand the scope of the
equipment.
1.1 Purpose
This document was generated under the authority of the
___________________ Company for the purpose of specifying the user
requirement for an automated granulation system. The system shall be
used to perform a wet high shear granulation step in which active and/or
inactive pharmaceutical ingredients are combined with granulation fluid.
1.2 Scope
This user requirement specification will be recognized as an integral part
of the procurement agreement with the selected equipment vendor. The
equipment supplier or vendor will abide by the information and
conditions set forth by this document as well as the standard purchasing
term and conditions of the ____________________ Company.
2.0 OVERVIEW
This document encompasses the normal range of equipment operations. This
section should be expanded to provide a high level description of the system
explaining why it is required and what is required of it. Include the background,
key objectives and benefits, main functions and interfaces, applicable GxP
requirements, and other applicable regulations. Obviously, technology
improvements and new applications may require deviation from this template.
3.4 Functions
3.4.1 Operation
The operational requirements for this granulation system include
the following:
3.4.1.2 The system shall have a manual mode, which will allow
the operator control of all of the major functions of the
equipment.
3.4.2 Hand-Wash
Notes: E-Stop alarms shall take action immediately to stop the equipment.
The operator shall be required to acknowledge the alarm before the alarm can be
reset and the machine restarted.
Cycle-Stop alarms shall take action at the end of a rotation cycle to stop the
equipment. The operator shall be required to acknowledge the alarm before the
alarm can be reset and the machine restarted.
The list of critical alarms in the table is not intended to be a comprehensive list
of all alarms for the system. A complete alarm list will be developed and
included in the Functional Specification document. The equipment vendor is to
submit the complete alarm list and differentiate between critical and non-critical
alarms.
Table 3.5.3.4.3
Reference Unit(s) of
Parameter Format
Number measurement
Maintenance, etc.)
Loading/Unloading Valve
3.5.3.4.3.6
Controls and indications
3.5.3.4.3.7 Alarms and Warnings.
System Status (e.g. off,
3.5.3.4.3.8 on, standby states,
etc.).
Phase Logic commands
3.5.3.4.3.9
per ISA/ANSI S88.01
(Start, Stop, Hold,
3.5.3.4.3.10 Restart, Abort, Reset,
Pause, Resume)
3.6 Environment
Details of the physical environment in which the granulator will be
operated are presented below.
3.6.1 Layout
4.0 CONSTRAINTS
4.1 Mechanical
4.2.3 The User shall review, comment and/or approve, and return the
Functional and Design Specification to the Supplier within
_____ weeks of receipt from the Supplier.
4.3.2.2.1 Minimum: C.
4.3.2.2.2 Maximum: C.
4.4.3 Utilities
The User shall ensure that the following utilities are available
and that the utility supply lines and piping are terminated with
fittings or connections, which are compatible with those
described on the Customer Connection Drawings.
4.4.3.1.1 Electricity
4.5 Availability
Equipment availability based on anticipated usage is listed below.
4.6.1.1 All piping welds and product contact welds shall meet
ASME and 3A specification requirements.
For example:
The noise level generated during operation of the
[equipment/system] will not exceed 85 dB from 3 feet away.
For example:
4.6.5 Containment
4.6.6 Labeling
All equipment and control wiring shall be labeled and identified.
4.7 Maintenance
The expected hardware and software maintenance support including
ease of maintenance, expansion capability (software only), likely
enhancements (software only) expected lifetime and long-term support
are described below.
5.0 LIFE-CYCLE
5.1 Development
This section lists the requirement for vendor involvement in the
equipment supply and includes testing, delivery, and support.
5.1.1 The Supplier shall provide a Quality and Project Plan as part of
their proposal. The Supplier shall have a quality system in place.
Internal quality procedures shall be available for the Users
review.
5.1.2 The Supplier shall provide a Project Manager for the project to
provide a single communication point with the User.
5.2 Testing
This section describes the Supplier testing requirements and should
reference the Validation Test Plan, Factory Acceptance Test, special
tests, etc.
5.2.1 In order to verify system performance, the User shall witness the
execution of the Factory Acceptance Test (FAT) procedures. The
Supplier shall notify the User _____ weeks in advance of the
start of this test.
5.2.2 The FAT Specification shall be submitted to the User for review
and approval prior to execution. A minimum of _____ weeks
shall be allowed for the User to review and to comment and/or
approve the FAT Specification.
5.3 Delivery
This section lists the delivery requirements of the equipment.
5.3.1.1 Documentation
OIP Configuration Printout and Disk File XXX Program Development format
5.4 Support
The following support activities are required after acceptance. The
paragraphs outlined below provide the areas of consideration.
5.4.2 Training
5.4.3.1 Post start-up shall consist of monthly User site visits for
a period of _____ months after the completion of
commissioning activities.
6.0 GLOSSARY
If necessary, attach a glossary, which includes definitions of terms that may be
unfamiliar to the Supplier or terminology that may have meanings specific to
entries on this User Requirements Check sheet.
For example (example list is not intended to be complete):
Acronym Definition
C Degrees Celsius
BL Biohazard Level
CFR Code of Federal Regulations
DB Decibels
EMI Electro-Magnetic Interference
Ft Feet
GUI Graphic User Interface
HMI Human Machine Interface
HVAC Heating, Ventilation, and Air Conditioning
ISO International Organization for Standardization
JETT Joint Equipment Transition Team
LEL Lower Explosion Limit
OIP Operator Interface Panel
RFI Radio Frequency Interference
URS User Requirement Specification
IBC Intermediate Bulk Container
Granulation The process of creating granules. The powder morphology is
modified through the use of either a liquid that causes particles to
bind through capillary forces or dry compaction forces. The
process will result in one or more of the following powder
properties: enhanced flow; increased compressibility;
densification; alteration of physical appearance to more spherical,
uniform, or larger particles; and/or enhanced hydrophilic surface
properties. (SUPAC IR/MR: US FDA, Jan. 1999.)
Wet High-Shear Wet high-shear granulator subclasses are primarily distinguished
Granulator by the geometric positioning of the primary impellers; impellers
can be top, bottom, or side driven.
7.0 REFERENCES
A list of references that were used in preparing this document or that provided
additional details is shown below.
8.0 APPROVAL
This document has been reviewed by the User Project Manager and approved for use by the
Supplier.
This document has been reviewed by the User Quality Assurance Group and approved for
use by the Supplier.
This document has been reviewed by the Supplier Project Manager and approved for use by
the Supplier Project Team.
Other approvals as necessary may be included, such as the Technical Services Groups,
User Groups, Engineering, etc. as required.
9.0ATTACHMENTS